IR 05000334/2022004

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000334/2022004 and 05000412/2022004
ML23040A089
Person / Time
Site: Beaver Valley
Issue date: 02/09/2023
From: Matt Young
Division of Operating Reactors
To: Blair B
Energy Harbor Nuclear Corp
References
IR 2022004
Download: ML23040A089 (1)


Text

February 9, 2023

SUBJECT:

BEAVER VALLEY POWER STATION, UNITS 1 AND 2 - INTEGRATED INSPECTION REPORT 05000334/2022004 AND 05000412/2022004

Dear Barry Blair:

On December 31, 2022, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Beaver Valley Power Station, Units 1 and 2. On January 12, 2023, the NRC inspectors discussed the results of this inspection with you and other members of your staff.

The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Matt R. Young, Chief Projects Branch 2 Division of Operating Reactor Safety

Docket Nos. 05000334 and 05000412 License Nos. DPR-66 and NPF-73

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000334 and 05000412

License Numbers:

DPR-66 and NPF-73

Report Numbers:

05000334/2022004 and 05000412/2022004

Enterprise Identifier: I-2022-004-0031

Licensee:

Energy Harbor Nuclear Corporation

Facility:

Beaver Valley Power Station, Units 1 and 2

Location:

Shippingport, PA 15077

Inspection Dates:

October 1, 2022 to December 31, 2022

Inspectors:

G. Eatmon, Senior Resident Inspector

B. Edwards, Health Physicist

E. Eve, Senior Reactor Inspector

R. Rolph, Resident Inspector

B. Towne, Senior Resident Inspector

S. Wilson, Senior Health Physicist

Approved By:

Matt R. Young, Chief

Projects Branch 2

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Beaver Valley Power Station, Units 1 and 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

PLANT STATUS

Unit 1 began the inspection period at rated thermal power. Unit 1 was shutdown on October 9, 2022, for a refueling outage. Unit 1 was returned to rated thermal power on November 24, 2022, and remained at or near rated thermal power for the remainder of the inspection period.

Unit 2 operated at or near rated thermal power for the entire inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Impending Severe Weather Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the readiness for seasonal extreme weather conditions prior to the onset of very cold temperatures for the Units 1 and 2 refueling water storage tanks, the intake structure, and the alternate intake structure during the week of December 19, 2022.

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (2 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Unit 1, residual heat removal system train 'A' and 'B' during lowered reactor coolant system inventory, October 13, 2022
(2) Unit 1, 'A' and 'B' trains of auxiliary feedwater system, December 13, 2022

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (2 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Unit 1, primary auxiliary building 768' and 752' and fire compartments, fire areas 1PFP-AXLB-768, 1PFP-ALXB-752, 1-PA-1C and 1-PA-1A, October 12, 2022
(2) Unit 1, safeguards during 1R28 refueling outage and associated hot work, October 28, 2022

71111.08P - Inservice Inspection Activities (PWR) PWR Inservice Inspection Activities Sample (IP Section 03.01)

(1) The inspectors verified that the Unit 1 reactor coolant system boundary, steam generator tubes, reactor vessel internals, risk significant piping system boundaries, and containment boundary are appropriately monitored for degradation and that repairs and replacements were appropriately fabricated, examined and accepted by reviewing the following activities from October 17 to October 31, 2022:

03.01.a - Nondestructive Examination (NDE) and Welding Activities

  • Direct observation of ultrasonic testing of safety injection system weld, SI-262-1502-Q1, NDE Report No.: UT-22-1020
  • Direct observation of liquid penetrant testing of recirculation spray pump 2A welded attachment weld, RS-P-2A-A-7, NDE Report No.: PT-22-1001
  • Remote observation of visual and ultrasonic testing examination of baffle former bolts per MRP-227 and MRP-228, CR-2022-08109
  • Record review of reactor vessel lower head bare metal visual inspection of nozzles per American Society of Mechanical Engineers Code Case N-722, NDE Report No.: VT-22-1030
  • Record review of visual examination of pressurizer lower instrument nozzles in response to insulation impact, CR-2022-07981 and NDE Report no.: BOP-VT-22-015

03.01.b - Pressurized-Water Reactor Vessel Upper Head Penetration Examination Activities

  • Record review of reactor head penetration 47 visual re-examination, NDE Report No.: BOP-VT-22-012

03.01.c - Pressurized-Water Reactor Boric Acid Corrosion Control Activities

  • CR-2019-10355, evaluation for active boric acid leakage past threaded cap of 4-way fitting downstream of 1QS-88 ( (1QS-P-1A) bearing water supply isolation valve)
  • CR-2022-07894, evaluation for active boric acid leak was identified on RV-1DA-101, thermal relief valve for containment penetration # 38
  • CR-2022-07908, corrective actions associated with dry boric acid identified on MOV-1RC-535, pressurizer power operated relief valve isolation motor operated valve 03.01.d - Pressurized-Water Reactor Steam Generator Tube Examination Activities
  • Video review of 1A secondary side visual examinations

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control room during the planned shutdown of Unit 1 for refueling outage 1R28 on October 8-9, 2022.

71111.12 - Maintenance Effectiveness

Quality Control (IP Section 03.02) (2 Samples)

The inspectors evaluated the effectiveness of maintenance and quality control activities to ensure the following structures, systems, and components remain capable of performing its intended function:

(1) Unit 1, recirculation spray diaphragm as-found weld inspection of the 'A' and 'C' heat exchangers, October 16, 2022; and as-left weld inspection, October 22, 2022
(2) Unit 1, 480 volt stub bus supply breaker (9P16) failed to trip when signal received, December 9, 2022

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (6 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Unit 2, elevated risk for planned power reduction for maintenance that removed all the moisture separator reheaters from service, October 3, 2022
(2) Unit 1, elevated risk due to 'B' loop cold leg isolation valve, MOV-1RC-593, bound and will not open to isolate the loop for a planned steam generator inspection during the refueling outage, October 10, 2022
(3) Unit 2, elevated risk due to a heavy load lift on reactor coolant filter in the auxiliary building, October 31, 2022
(4) Unit 1, component misposition event de-energized vital bus 2 while the unit was in no mode, November 1, 2022
(5) Unit 1, emergent work on the 'A' steam generator throttle valve, MOV-1FW-151E, from the 'B' train auxiliary feedwater header would not open in Mode 3, November 16, 2022
(6) Unit 1, emergent work on 1A feedwater pump due to loss of oil. Loss of pump would result in 50 percent power limit during the week of December 12, 2022

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (4 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) Unit 2, service water pump 21C high shaft inner column water pressure due to outer shaft leakage, September 16, 2022
(2) Unit 2, service water train 'B' due to leak on the containment air recirculation cooling coil supply line, October 9, 2022
(3) Unit 1, eleven feet of pressurizer circumferential insulation slid 18 inches down tank while being removed for inspection during 1R28, resting on various pressurizer nozzles causing physical observable deflection to five nozzles, October 21, 2022
(4) Unit 2, terry turbine steam isolation valve slow stroke closed, December 1, 2022

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (2 Samples)

The inspectors evaluated the following temporary or permanent modifications:

(1) Unit 1, permanent modification of tubing downstream of 1RC-272 support relocation in Engineering Change Package 22-1073-001
(2) Unit 1, replacement of Flowserve double disk gate valve wedge pin and threaded stem to upper wedge connection in the low head safety injection to reactor coolant system cold leg motor operated valve, MOV-1SI-890C, and reuse existing lower wedge, October 12, 2022

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (6 Samples)

The inspectors evaluated the following post-maintenance testing activities to verify system operability and/or functionality:

(1) Unit 1, static test of MOV-1SI-890C valve operator, low head safety injection to reactor cooling system cold leg, after anchor darling gate valve wedge pin and stem replacement, October 12, 2022
(2) Unit 1, relay trip checks associated with safety-related electrical bus AE outage, October 23, 2022
(3) Unit 1, emergency diesel generator 1-1 surveillance to verify operation of breaker 4KV-1AE-1E9, the incoming supply breaker from 1-1 emergency diesel generator to

'AE' emergency switch gear, after a ground was identified, October 25, 2022

(4) Unit 1, emergency diesel generator 1-2, after replacing two air start valves and an oil change, November 1, 2022
(5) Unit 1, 'B' motor driven auxiliary feedwater pump following bearing inspection, November 5, 2022
(6) Unit 2, emergency diesel generator 2-1, after rebuilding temperature control valve, EDG-RS-201, that caused excess condensation in the engine intercooler, December 1, 2022

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated Unit 1 refueling outage 1R28 activities from October 9 to November 19, 2022.

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance testing activities to verify system operability and/or functionality:

Surveillance Tests (other) (IP Section 03.01) (1 Sample)

(1) Unit 2, 2SIS-P21A, "Low Head Safety Injection Pump Test," Revision 33, November 1, 2022

Containment Isolation Valve Testing (IP Section 03.01) (1 Sample)

(1) Unit 1, leak test on 1X-89, "Condenser Air Ejector Discharge to Containment," October 13,

RADIATION SAFETY

71124.01 - Radiological Hazard Assessment and Exposure Controls

Radiological Hazard Assessment (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated how the licensee identifies the magnitude and extent of radiation levels and the concentrations and quantities of radioactive materials and how the licensee assesses radiological hazards.

Instructions to Workers (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated how the licensee instructs workers on plant-related radiological hazards and the radiation protection requirements intended to protect workers from those hazards.

Contamination and Radioactive Material Control (IP Section 03.03) (2 Samples)

The inspectors observed/evaluated the following licensee processes for monitoring and controlling contamination and radioactive material:

(1) Workers exiting the radiologically controlled area at Unit 1 during a refueling outage
(2) Evaluated how radiation protection personnel supported removal of an injured worker from Unit 1 containment building

Radiological Hazards Control and Work Coverage (IP Section 03.04) (4 Samples)

(1) Nozzle dam insertion for Unit 1 B steam generator under Radiation Work Permit Number 122-4017
(2) Insert removal for Unit 1 B steam generator under Radiation Work Permit Number 122-4017
(3) Removal of robot from Unit 1 C steam generator under Radiation Work Permit Number 122-4017
(4) Removal of seal package from Unit 1 B reactor coolant pump under Radiation Work Permit Number 122-4025

High Radiation Area and Very High Radiation Area Controls (IP Section 03.05) (3 Samples)

The inspectors evaluated licensee controls of the following High Radiation Areas and Very High Radiation Areas:

(1) Units 1 and 2 high radiation area key storage, controls, and inventory system
(2) Unit 1 reactor head stand locked high radiation area controls
(3) Unit 1 B steam generator cubicle

Radiation Worker Performance and Radiation Protection Technician Proficiency (IP Section 03.06) (1 Sample)

(1) The inspectors evaluated radiation worker and radiation protection technician performance as it pertains to radiation protection requirements.

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification

The inspectors verified licensee performance indicators submittals listed below:

BI01: Reactor Coolant System (RCS) Specific Activity Sample (IP Section 02.10)===

(1) Unit 1, October 1, 2021 through September 30, 2022
(2) Unit 2, October 1, 2021 through September 30, 2022

BI02: RCS Leak Rate Sample (IP Section 02.11) (2 Samples)

(1) Unit 1, October 1, 2021 through September 30, 2022
(2) Unit 2, October 1, 2021 through September 30, 2022

OR01: Occupational Exposure Control Effectiveness Sample (IP Section 02.15) (1 Sample)

(1) October 1, 2021 through October 1, 2022

PR01: Radiological Effluent Technical Specifications/Offsite Dose Calculation Manual Radiological Effluent Occurrences (RETS/ODCM) Radiological Effluent Occurrences Sample (IP Section 02.16) (1 Sample)

(1) October 1, 2021 through October 1, 2022

71152A - Annual Follow-up Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) The inspectors conducted an in-depth review of the corrective actions for multiple check source failures in Unit 2.

71152S - Semiannual Trend Problem Identification and Resolution Semiannual Trend Review (Section 03.02)

(1) The inspectors reviewed the licensees risk assessment practices for emergent maintenance for potential adverse trends that might be indicative of a more significant safety issue.

INSPECTION RESULTS

Observation: Annual Review of Risk Challenge Review Boards for Emergent Maintenance 71152S Inspectors investigated a potential adverse trend in risk assessment for emergent maintenance. Inspectors found that the licensee began performing inter-disciplinary risk challenge meetings for emergent maintenance following consecutive Unit 2 reactor trips in the fall of 2021 and multiple Unit 1 reactor trips in the spring of 2022. The inspectors determined that, in most cases, the risk associated with emergent maintenance was appropriately evaluated by licensee staff and mitigating actions were effectively implemented.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On January 12, 2023, the inspectors presented the integrated inspection results to Barry Blair, Site Vice President, and other members of the licensee staff.
  • On October 27, 2022, the inspectors presented the inservice inspection activities inspection results to Steve Sawtschenko, Manager, Regulatory Compliance and Emergency Preparedness, and other members of the licensee staff.
  • On October 20, 2022, the inspectors presented the radiation protection radiological hazards and control inspection results to Bob Kristophel, General Plant Manager, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.01

Corrective Action

Documents

CR 2021-00999

Alternate Intake Structure Furnace Power Supply Handle

Not Functioning

2/16/2021

CR 2021-01421

Alternate Intake Furnace Won't Fire

03/02/2021

CR 2021-06940

Damaged Insulation

09/15/2021

CR 2021-09607

Permanent Structure Instead of Temporary Tents

2/20/2021

CR 2021-9611

Temporary Heathers Not Ready

2/20/2021

Procedures

1/2-ADM-2029

Temporary Configuration Control

1/2OST-45.1

Extreme Cold Weather Protection Verification

71111.04

Drawings

RM-0018A

Flow Diagram Feed Water

RM-0410-001

Piping and Instrumentation Diagram Residual Heat Removal

System

71111.05

Fire Plans

1PFP-AXLB-752

Auxiliary Building General Area Fire Compartment 1-PA-1C

1PFP-AXLB-768

Auxiliary Building General Area Fire Compartment 1-PA-1A

1PFP-SFGB-722

Safeguards Area Fire Compartment 1-PT-1

1PFP-SFGB-735-

AUX

AUX FW & QS Pumps Fire Compartment 1-QP-1

1PFP-SFGB-735-

EAST

East Cable Vault Fire Compartment 1-CV-2

1PFP-SFGB-735-

WEST

West Cable Vault Fire Compartment 1-CV-1

71111.11Q Procedures

1OM-52.4.R.1.F

Station Shutdown from 100 Percent Power to Mode 5

71111.12

Corrective Action

Documents

CR 2021-03368

CR 2022-08268

Work Orders

WO 200835699

WO 200835967

71111.13

Corrective Action

Documents

CR 2022-07619

CR 2022-07805

CR 2022-08294

CR 2022-08786

CR 2022-09477

Procedures

1/2-ADM-0819

Handling of NUREG 0612 Heavy Loads

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

1OM-

53C.4.1.38.1B

Loss of Vital Bus II

1OST-24,9

Turbine-Driven AFW Pump (1FW-P-2) Operability Test

01/05/2022

1OST-24.1

SG Aux Feed Pumps Throttle Valve Stroke From Control

Room

10/26/2018

2OM-26.4.S

Isolation of Turbine Moisture Separator Reheat Section

NOP-OP-1007-01

Risk Management Plan

71111.15

Calibration

Records

Calculation Package, "Beaver Valley SW Branch Line N-513

Evaluation," Structural Integrity Associates, Inc.

10/09/2022

Corrective Action

Documents

CR 2021-01889

CR 2021-04525

CR 2022-06668

CR 2022-06851

09/08/2022

CR 2022-07059

09/16/2022

CR 2022-07530

10/07/2022

CR 2022-07555

10/09/2022

CR 2022-07981

CR 2022-08953

Engineering

Evaluations

EER 601376944

Engineering Evaluation Request for Flaw and Wall Thinning

10/08/2022

EER 601377626

Evaluate Long Term Operation of 2SWS-P21C

10/13/2022

Engineering

Evaluation

Request

601003686

IST Pre-Conditioning Evaluation

Miscellaneous

N-513-4

American Society of Mechanical Engineers Evaluation

Criteria for Temporary Acceptance of Flaw in Moderate

Energy Class 2 or 3 Piping

05/07/2014

71111.18

Corrective Action

Documents

CR 2022-00451

CR 2022-07671

CR 2022-07981

Engineering

Changes

ECP-22-1073-001 Tubing Downstream of 1RC-272 Support Relocation

Engineering

Engineering

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Evaluations

Evaluation

Request

601378751

Procedures

LTR-CECO-22-

096

Evaluation of Beaver Valley Unit 1 Bent Pressurizer

Instrumentation Nozzles

PERP-001312

Part Equivalent Replacement Package for Anchor Daring

Gate Valve Wedge Pin Material Upgrade

10/12/2022

TP16-1-112

Recommendations to Resolve Flowserve 10CFR Part 21

Notification Affecting Anchor Daring Double Disk Gate Valve

Wedge Pin Failures

71111.19

Corrective Action

Documents

CR 2022-08069

CR 2022-08383

CR 2022-09133

Miscellaneous

NORM-WM-

4006A

Conduct of Maintenance Handbook

Procedures

1OM-36.4.AR

Clearing and Returning to Service Emergency 4KV Bus 1AE

1OST-24,3

Motor Driven Auxiliary Feed Pump Test [1FW-P-38]

1OST-36.2

Diesel Generator No. 2 Monthly Test

2OST-36.1

Emergency Diesel Generator Monthly Test

LUC PAF-22-

06145, 1OST-

36.1

Diesel Generator No. 1 Monthly Test

10/24/2022

Work Orders

WO200844687

71111.20

Procedures

1OM-52.4.B

Load Following

1OST-47.2B

Containment Closeout Inspection

1RST02,1

Initial Approach to Critically After Refueling, Issue 1

71111.22

Procedures

Inservice Testing (IST) Program for Pumps and Valves,

Issue 4

1OST-47.152

Type C Test - Penetration #89 (Main Condenser Ejector

Vent)

2OST-11.1

Low Head Safety Injection Pump Test

71151

Corrective Action

Documents

CR 2022-04716

71152A

Corrective Action

CR 2019-03658

2MSS-RQ101A Abnormal High Reading

04/18/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Documents

CR 2021-04027

2MSS-RQ101B Alert Alarm

05/18/2021

CR 2022-03110

2MSS-DAU102A Failed Source Check

04/07/2022

CR 2022-06046

Failed Check Source on 2MSS-RQ101B

08/05/2022

CR 2022-06704

2MSS-RQ101B Failed Check Source

08/31/2022

CR 2022-06760

Evaluate Extent of Condition for Radiation Monitor Check

Source Degradation

09/02/2022

CR 2022-06936

2MSS-RQ101C Main Steam Line Monitor Check Source

Failure

09/12/2022

CR 2022-08430

Equipment Reliability Issue - Unit 2 Cs-137 Radiation

Monitor Calibration Sources