June 20, 2006 LICENSEE: DUKE POWER COMPANY LLC (DUKE)

FACILITY: OCONEE NUCLEAR STATION, UNITS 1, 2, AND 3 (OCONEE)

SUBJECT:

SUMMARY

OF MAY 25, 2006, MEETING TO DISCUSS NEW LICENSE AMENDMENT REQUEST (LAR) FOR DIGITAL REACTOR PROTECTIVE SYSTEM (RPS) AND ENGINEERED SAFEGUARDS PROTECTIVE SYSTEM (ESPS)

On May 25, 2006, the Nuclear Regulatory Commission (NRC) met with Duke (the licensee) to discuss the contents of a new LAR for the Oconee RPS/ESPS. Enclosure 1 is a list of the attendees. Enclosure 2 is the handouts provided by the licensee during the meeting.

The licensee is preparing a new LAR for the digital RPS/ESPS in case the licensee decides to withdraw the February 14, 2005, LAR (the original LAR). If the licensee does withdraw the original LAR, it foresees submitting a new LAR in Fall 2006 to support implementation of the digital RPS/ESPS in Fall 2007. The NRC staff stated that it could complete its review in about a year if the quality of the new LAR, and the quality in the design and implementation of the digital RPS/ESPS, is acceptable. The NRC staff stated that it would conduct an acceptance review of the new LAR. The acceptance review would take about 1 to 2 months and would determine if the completeness and quality of the new LAR were sufficient for the NRC to conduct its review.

The NRC staff provided several examples of unacceptable quality in the original LAR. The licensee agreed to address each of these examples and to take corrective action on any programmatic issues that may result from the examples in order to improve the quality of the submittal and the design.

The licensee stated that the new LAR will include a commitment to provide a diverse, automatic actuation of high-pressure injection. The new LAR will also include responses to the requests for additional information that the NRC staff generated from its review of the original LAR. The licensee stated that all the vendor documents that will be submitted in support of the new LAR will have received an owner-acceptance review by the licensee prior to being submitted to the NRC.

Duke The licensee handed out an outline of two relief requests that it intends to submit. The licensee and the NRC staff agreed to discuss these two relief requests at a later time.

/RA/

Leonard N. Olshan, Project Manager Plant Licensing Branch II-1 Division of Operator Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-269, 50-270, and 50-287

Enclosures:

1. List of Attendees
2. Licensees Handouts

Duke June 20, 2006 The licensee handed out an outline of two relief requests that it intends to submit. The licensee and the NRC staff agreed to discuss these two relief requests at a later time.

/RA/

Leonard N. Olshan, Project Manager Plant Licensing Branch II-1 Division of Operator Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-269, 50-270, and 50-287

Enclosures:

1. List of Attendees
2. Licensees Handouts DISTRIBUTION:

Public RidsRgn2MailCenter(MErnstes) EEagle, NRR LPL 2-1 r/f JNakoski, NRR RJervey, NRR RidsNrrDorlLplc(EMarinos) R. Jasinski, NRR EImbro, NRR RidsNrrPM LOlshan SLee, EDO Region II CMiller, NRR RidsNrrLAMOBrien WKemper, NRR YHsii, NRR RidsOgcRp MWaterman, NRR NCarte, NRR RidsAcrsAcnwMailCenter PLoeser, NRR AHowe, NRR PRebstock, NRR ADAMS Accession No. ML061530315 Enclosure 2: ML061530466 Package: ML061530328 NRR-058 Office NRR/LPL2-1/PM NRR/LPL2-1/LA NRR/LPL2-1/BC Name LOlshan:sxd6 MOBrien EMarinos Date 06/19/06 06/19/06 06/20/06 OFFICAL RECORD ONLY

MEETING ATTENDEES MEETING TO DISCUSS NEW LAR FOR DIGITAL RPS/ESPS MAY 25, 2006 NRC DUKE W. Kemper B. Shingleton M. Waterman R. Gill P. Loeser J. Fuller P. Rebstock J. Nakoski OTHER Y. Hsii N. Carte C. Brinkman, Westinghouse E. Eagle A. Harris, Nuclear Energy Institute R. Jervey E. Imbro A. Howe E. Marinos C. Miller L. Olshan ENCLOSURE 1

Oconee Nuclear Station, Units 1, 2, and 3 cc:

Ms. Lisa F. Vaughn Mr. R. L. Gill, Jr.

Duke Power Company LLC Manager - Nuclear Regulatory 526 South Church Street Issues and Industry Affairs P. O. Box 1006 Duke Power Company LLC Mail Code EC07H 526 S. Church St.

Charlotte, North Carolina 28201-1006 Mail Stop EC05P Charlotte, NC 28202 Manager, LIS NUS Corporation Division of Radiation Protection 2650 McCormick Dr., 3rd Floor NC Dept of Environment, Health, & Natural Clearwater, FL 34619-1035 Resources 3825 Barrett Dr.

Senior Resident Inspector Raleigh, NC 27609-7721 U.S. Nuclear Regulatory Commission 7812B Rochester Highway Mr. Peter R. Harden, IV Seneca, SC 29672 VP-Customer Relations and Sales Westinghouse Electric Company Mr. Henry Porter, Director 6000 Fairview Road Division of Radioactive Waste Management 12th Floor Bureau of Land and Waste Management Charlotte, NC 28210 Dept. of Health and Env. Control 2600 Bull St. Mr. Henry Barron Columbia, SC 29201-1708 Group Vice President, Nuclear Generation and Chief Nuclear Officer Mr. Michael A. Schoppman P.O. Box 1006-EC07H Framatome ANP Charlotte, NC 28201-1006 1911 North Ft. Myer Dr.

Suite 705 Rosslyn, VA 22209 Mr. B. G. Davenport Regulatory Compliance Manager Oconee Nuclear Site Duke Energy Corporation ON03RC 7800 Rochester Highway Seneca, SC 29672 Ms. Karen E. Long Assistant Attorney General NC Department of Justice P.O. Box 629 Raleigh, NC 27602