ML21099A093
ML21099A093 | |
Person / Time | |
---|---|
Site: | Oconee, Mcguire, Catawba, McGuire |
Issue date: | 04/09/2021 |
From: | Jannette Worosilo NRC/RGN-II/DRP/RPB1 |
To: | Jared Nadel NRC/RGN-II/DRP/RPB1 |
References | |
Download: ML21099A093 (2) | |
Category:Meeting Summary
MONTHYEARML24242A3242024-08-30030 August 2024
[Table view]Duke Energy Carolinas - Catawba 2A EDG Regulatory Conference Meeting Summary - August 7, 2024 ML24124A0342024-05-0101 May 2024 Summary of Public Meeting Concerning Annual Assessment of Catawba Nuclear Station Units 1 and 2, McGuire Nuclear Station Units 1 and 2, Oconee Nuclear Station Units 1, 2, and 3, Brunswick Steam Electric Plant Units 1 and 2, Shearon Harris ML24071A1692024-03-15015 March 2024 February 2024 Subsequent License Renewal Public Draft Environmental Impact Statement Meetings-Memo ML24071A1702024-03-15015 March 2024 February 2024 Oconee Draft EIS Public Meetings - Summary ML23118A2852023-05-0202 May 2023 Public Meeting Summary - 2022 Annual Assessment Meeting Regarding Catawba Nuclear Station, McGuire Nuclear and Oconee Nuclear Station ML22335A4012022-12-15015 December 2022 Summary of December 8, 2022, Public Meeting with Duke Energy Carolinas, LLC, Regarding Pre-Application Meeting to Discuss Proposed License Amendment Request to Revise TS 3.7.11 Control Room Area Chilled Water System (Cracws) ML22340A6662022-12-0808 December 2022 Summary of November 30, 2022, Public Meeting with Duke Energy Carolinas, LLC for McGuire Nuclear Station, Units 1 & 2 Proposed LAR to Adopt TSTF-505, Rev. 2 and 10 CFR 50.69 Risk-Informed Categorization and Treatment of Structures, Systems ML22200A0772022-08-0808 August 2022 SLRA - Summary of July 14, 2022 and July 28, 2022 Public Meetings ML22193A0182022-07-18018 July 2022 SLRA - Summary of June 30, 2022 Public Meeting ML22129A0062022-05-10010 May 2022 Summary of April 20, 2022, Meeting with Duke Energy Progress, LLC, to Discuss Proposed License Amendment Request to Revise Reactor Coolant System Pressure Isolation Valve Operational Leakage Surveillance Requirement Frequency (L-2022-LRM 00 ML22130A0122022-05-0404 May 2022 SLRA - Summary of April 28, 2022 Public Meeting ML22124A2052022-05-0404 May 2022 Summary of May 4, 2022, Clarification Call with Duke Energy Carolinas, LLC, Application to Revise TS 3.7.7, Low Pressure Service Water (LPSW) System ML22075A2042022-04-0505 April 2022 SLRA - Summary of March 7, 2022 Public Meeting ML22094A1112022-04-0404 April 2022 Public Meeting Summary 2021 Annual Assessment Meeting Catawba Dockets Nos. 50-413 and 50-414; McGuire No. 50-369 and 50-370; Oconee. 50-269, 50-270, and 50-287 ML22084A6142022-04-0404 April 2022 SLRA - Summary of March 16, 2022 (Closed Public Meeting) ML22063A1162022-03-0808 March 2022 SLRA - Summary of Public Meeting Dated February 17, 2022 ML21341A5542021-12-29029 December 2021 Summary of November 29, 2021, Meeting with Duke Energy Progress, LLC and Duke Energy Carolinas, LLC to Discuss a Planned License Amendment Request to Relocate ML21348A5452021-12-14014 December 2021 December 13, 2021, Clarification Call Summary Use of an Alternative to the ASME Code Case N-853 Acceptance Criteria ML21342A0902021-12-14014 December 2021 Summary of December 7, 2021, Public Meeting with Duke Energy Carolinas, LLC, Regarding Pre-Application Meeting to Discuss Reactor Vessel Closure Head Nozzle Repair for Catawba Nuclear Station, Unit 2 ML21279A1542021-11-0808 November 2021 August 25, 2021, Oconee Nuclear Station, Units 1, 2, and 3 Subsequent License Renewal Application Public Environmental Scoping Meeting Summary Memo ML21236A2832021-09-22022 September 2021 Summary of August 30, 2021, Public Meeting with Duke Energy Carolinas, LLC, Regarding Pre-Application Meeting to Discuss Moderator Temperature Coefficient Methodology Revision ML21279A1192021-08-25025 August 2021 August 25, 2021, Oconee Nuclear Station, Units 1, 2, and 3 Subsequent License Renewal Application Public Environmental Scoping Meeting Summary ML21195A2692021-07-14014 July 2021 Meeting Summary: Pre-Submittal Meeting for the Oconee Subsequent License Renewal Application (EPID Number: L-2020-RNW-0028) (Docket Numbers: 50 269, 50-270, and 50-287) - Memo ML21195A2712021-07-14014 July 2021 Meeting Summary: Pre-Submittal Meeting for the Oconee Subsequent License Renewal Application (EPID Number: L-2020-RNW-0028) (Docket Numbers: 50 269, 50-270, and 50-287) - Summary ML21133A0042021-05-26026 May 2021 Summary of Conference Call Regarding the Spring 2021 Steam Generator Tube Inspections (Epid: L-2021-Nfo-0004) ML21102A0612021-04-27027 April 2021 April 14, 2021, Meeting Summary Regarding Pre-Application Meeting to Discuss Proposed Relief Request Related to Code Case N-853 ML21116A0662021-04-22022 April 2021 C2R24 Relief Request Pre-Submittal Slides Call 2 ML21099A0932021-04-0909 April 2021 Public Meeting Summary - 2020 Annual Assessment Meeting Regarding Catawba, McGuire, and Oconee Nuclear Stations ML20266G2192020-11-0303 November 2020 Regulatory Audit Report Regarding License Amendment Request to Revise the Licensing Basis for High Energy Line Breaks Outside of the Containment Building ML20141L4172020-05-20020 May 2020 EOC Public Meeting Summary ML19331A8062020-01-29029 January 2020 Summary of November 13, 2019 Closed Meeting with Duke Energy Carolinas, LLC and Duke Energy Progress, LLC, to Discuss Security-Related Information for Its Licensed Facilities ML19331A5202019-12-12012 December 2019 Summary of Meeting with Duke Energy Carolinas, LLC to Discuss Submitted License Amendment Request for Oconee Nuclear Station, Units 1, 2, and 3 Regarding High Energy Line Break Licensing Basis ML19220A6702019-08-26026 August 2019 Summary of August 7, 2019, Meeting with Duke Energy Progress, LLC and Duke Energy Carolinas, LLC to Discuss a Proposed License Amendment Request for a Common Emergency Plan ML19207A0172019-07-30030 July 2019 Summary of Meeting with Duke Energy Carolinas, LLC to Discuss Proposed License Amendment Request for Oconee Nuclear Station, Units 1, 2, and 3 Regarding High Energy Line Break Licensing Basis ML19102A3352019-04-12012 April 2019 Public Meeting Summary - Oconee Nuclear Station Docket Nos. 50-269, 50-270, and 50-287 ML19087A0622019-04-11011 April 2019 Summary of March 25, 2019, Public Teleconference with Duke Energy to Discuss the Request for Additional Information Response Regarding the Proposed Alternative to the Depth Sizing Qualification Requirement (Duke Energy Fleet Relief Request ML19088A1362019-03-29029 March 2019 Public Meeting Summary ML18250A0952018-09-20020 September 2018 Summary of August 29, 2018, Licensing Meeting with Duke Energy to Discuss a Planned License Amendment Request to Revise TS 4.2.2, Control Rod Assemblies to Permit Operation with One Less than the Required Number ML18227B2122018-09-0505 September 2018 Summary of August 1, 2018, Meeting with Duke Energy Carolinas, LLC to Discuss Proposed License Amendment Request for Oconee Nuclear Station, Units 1, 2, and 3 Regarding Tornado Mitigation Licensing Basis ML18183A4502018-07-16016 July 2018 Summary of June 11, 2018, Licensing Meeting with Duke Energy to Discuss a Planned License Amendment Request to Remove Containment Valve Injection Water from Specified Containment Isolation Valves ML18134A2292018-05-14014 May 2018 Summary of April 26, 2018, Public Teleconference with Duke Energy Carolinas, LLC to Discuss Proposed License Amendment and 3 Regarding Technical Specification 3.8.1 ML17293A0232018-05-0404 May 2018 Summary of 9/20/17, Meeting with Duke Energy to Discuss LAR to Extend Completion Time for an Inoperable Emergency Diesel Generator and Electrical Alignments for Shared Systems for Catawba and McGuire (CAC Nos. MF9667-74; Epids L-2017-LLA-02 ML18117A2212018-04-27027 April 2018 Summary of Public Meeting with Catawba Nuclear Station Concerning Annual Assessment of Units 1 and 2 for Period of January 01, 2017 - December 21, 2017 ML18089A0532018-03-30030 March 2018 Summary of Public Meeting with McGuire Nuclear Station ML18082A1082018-03-29029 March 2018 Summary of February 28, 2018, Meeting with Duke Energy Carolinas, LLC to Discuss Proposed LAR Regarding Tornado Mitigation Licensing Basis ML18082A0582018-03-23023 March 2018 Summary of Meeting with Oconee Nuclear Station to Discuss Annual Assessment of Oconee for the Period of January 01, 2017 - December 31, 2017 ML17179A3472017-07-18018 July 2017 Summary of Meeting with Duke Energy Carolinas, LLC to Discuss Proposed License Amendment Request for Oconee Nuclear Station, Units 1, 2, and 3 Regarding Thermal Margin for the Standby Shutdown Facility ML17110A1862017-04-20020 April 2017 Summary of Public Meeting - McGuire, Units 1 and 2 to Discuss Concerning Annual Assessment ML17107A0642017-04-17017 April 2017 Summary of Public Meeting with Catawba, Units 1 and 2 ML17103A0292017-04-13013 April 2017 Summary of Meeting to Provide Opportunities to Discuss Annual Assessment of Oconee Nuclear Station Units 1, 2 and 3 2024-08-30 Category:Memoranda MONTHYEARML24122C6932024-05-0101 May 2024
[Table view]Referral of Petition to Intervene and Request for Hearing Re Subsequent License Renewal Application from Duke Energy Carolinas, LLC for Oconee Units 1, 2 & 3 ML24124A0342024-05-0101 May 2024 Summary of Public Meeting Concerning Annual Assessment of Catawba Nuclear Station Units 1 and 2, McGuire Nuclear Station Units 1 and 2, Oconee Nuclear Station Units 1, 2, and 3, Brunswick Steam Electric Plant Units 1 and 2, Shearon Harris ML24071A1692024-03-15015 March 2024 February 2024 Subsequent License Renewal Public Draft Environmental Impact Statement Meetings-Memo ML24047A2092024-02-22022 February 2024 Calendar Year 2023 Baseline Inspection Completion ML23118A2852023-05-0202 May 2023 Public Meeting Summary - 2022 Annual Assessment Meeting Regarding Catawba Nuclear Station, McGuire Nuclear and Oconee Nuclear Station ML22300A0742023-01-11011 January 2023 Final Environmental Assessment and Finding of No Significant Impact for the Duke Energys Updated Decommissioning Funding Plans Submitted in Accordance with 10 CFR 72.30(C) for Catawba Nuclear Station Independent Spent Fuel Storage Installat ML22299A1052023-01-11011 January 2023 Memo to File - McGuire Final EA 2017+19+21 ML22299A0482023-01-11011 January 2023 Final Environmental Assessment and Finding of No Significant Impact for the Duke Energy’S Updated Decommissioning Funding Plans Submitted in Accordance with 10 CFR 72.30(C) for Oconee Nuclear Station Independent Spent Fuel Storage Installat ML22349A1482022-12-19019 December 2022 Transmittal Letter for Oconee SE for SLRA Review ML22193A2542022-08-0505 August 2022 SLRA - Audit Report ML22111A3142022-05-0202 May 2022 Limited Aging Management Audit Plan Regarding the Subsequent License Renewal Application Review ML22084A6142022-04-0404 April 2022 SLRA - Summary of March 16, 2022 (Closed Public Meeting) ML22024A1392022-03-11011 March 2022 SLRA - Request for Withholding Information ML21347A0102021-12-20020 December 2021 Proposed Alternative to Implement ASME Code Case OMN-26 ML21279A1542021-11-0808 November 2021 August 25, 2021, Oconee Nuclear Station, Units 1, 2, and 3 Subsequent License Renewal Application Public Environmental Scoping Meeting Summary Memo ML21064A3502021-07-26026 July 2021 OEDO-21-00048 - Oconee Nuclear Station, Units 1, 2, and 3 - Response Memorandum ML21195A2692021-07-14014 July 2021 Meeting Summary: Pre-Submittal Meeting for the Oconee Subsequent License Renewal Application (EPID Number: L-2020-RNW-0028) (Docket Numbers: 50 269, 50-270, and 50-287) - Memo ML21056A5502021-04-22022 April 2021 Memo to File - Ea/Fonsi for McGuire DFP ML21055A8672021-04-22022 April 2021 Memo to File: Final Ea/Fonsi of Independent Spent Fuel Storage Facilities Decommissioning Funding Plans Related to Oconee ML21099A0932021-04-0909 April 2021 Public Meeting Summary - 2020 Annual Assessment Meeting Regarding Catawba, McGuire, and Oconee Nuclear Stations ML20357B1332020-12-30030 December 2020 Transmittal Memo - Delivery of Partial Deliverable Associated with the Trace Code Maintenance, Plant Model Maintenance, and Plant Model Development to Support Licensing Actions and Emergent Technical Issues User Need ML20141L4172020-05-20020 May 2020 EOC Public Meeting Summary ML20036E3902020-02-11011 February 2020 Regulatory Audit in Support of Review of License Amendment Request to Revise the Licensing Basis for High Energy Line Breaks Outside of the Containment Building ML19102A3352019-04-12012 April 2019 Public Meeting Summary - Oconee Nuclear Station Docket Nos. 50-269, 50-270, and 50-287 ML19098B4482019-04-0808 April 2019 Public Meeting Summary ML19088A1362019-03-29029 March 2019 Public Meeting Summary ML19037A0052019-02-0808 February 2019 Regulatory Audit in Support of Review of License Amendment Request No. 2018-02 ML18226A2152019-01-22022 January 2019 Response to Task Interface Agreement 2014-04, Adequacy of the Oconee Nuclear Station Design and Licensing Bases for Degraded Voltage Protection (TAC Nos. MF4622, MF4623, and MF4624; EPID L-2014-LRA-0003) ML20052D9362018-07-0303 July 2018 Response to Nrg Request for Additional Information (RAI) Regarding NAC Magnastor Cask Loaded to Incorrect Helium Backfill Density ML18117A2212018-04-27027 April 2018 Summary of Public Meeting with Catawba Nuclear Station Concerning Annual Assessment of Units 1 and 2 for Period of January 01, 2017 - December 21, 2017 ML18089A0532018-03-30030 March 2018 Summary of Public Meeting with McGuire Nuclear Station ML18082A0582018-03-23023 March 2018 Summary of Meeting with Oconee Nuclear Station to Discuss Annual Assessment of Oconee for the Period of January 01, 2017 - December 31, 2017 ML18032A4612018-03-0505 March 2018 Regulatory Audit in Support of Review of License Amendment Request No. 2017-03 ML18004A0122018-01-0404 January 2018 Regulatory Audit in Support of Review of Proposed Alternative (CAC Nos. MF7365, MF7366 and MF7367; EPID No. L-2016-LLR-001) ML17264A0312017-09-29029 September 2017 Draft Response to Task Interface Agreement 2014-05 to Licensee Oconee Design Analysis for Single Failure/Integration of Class 1E Direct Current Control Cabling in Raceways with High Energy Power Cabling ML17202U7312017-07-25025 July 2017 Regulatory Audit in Support of License Amendment Request No. 2015-03 ML17151A3372017-06-0202 June 2017 Recommendation for Non-Acceptance with Opportunity to Supplement of McGuire Nuclear Station Units 1 and 2 Technical Specifications Completion Time Extension Request for Failure to Supply Information (CACs MF9673, MF9674) ML17110A1862017-04-20020 April 2017 Summary of Public Meeting - McGuire, Units 1 and 2 to Discuss Concerning Annual Assessment ML17107A0642017-04-17017 April 2017 Summary of Public Meeting with Catawba, Units 1 and 2 ML17103A0292017-04-13013 April 2017 Summary of Meeting to Provide Opportunities to Discuss Annual Assessment of Oconee Nuclear Station Units 1, 2 and 3 ML16111B2472016-04-28028 April 2016 Request for Additional Information Re. License Amendment Request to Revise TS 5.5.2 Containment Leakage Rate Testing Program ML16088A2052016-03-28028 March 2016 Enclosure 1 - (72.30 DFP Reviews to Be Completed 2015) - Memo T Bowers from s Ruffin, Technial Assistance Requests - Review 2015 Tri-Annual Decommissioning Funding Plans for Multiple Independent Spent Fuel Storage Installations ML16088A2042016-03-28028 March 2016 Memo T Bowers from s Ruffin, Technical Assistance Requests - Review 2015 Tri-Annual Decommissioning Funding Plans for Multiple Independent Spent Fuel Storage Installations W/ Encl 2 (Template) ML16082A0682016-03-21021 March 2016 Summary of Meeting with the Public Concerning the Annual Assessment of McGuire Nuclear Station, Units 1 and 2 ML16081A3352016-03-17017 March 2016 Summary of Meeting with Public Concerning Annual Assessment of Catawba Nuclear Station, Units 1 and 2 ML15253A4032016-03-11011 March 2016 Recommendation for Dispositioning Proposed Generic Issue on the Effects of Downstream Dam Failures on Nuclear Power Plants ML16061A5652016-03-0909 March 2016 Request for Additional Information for Relief Request 14-ON-001, Letdown Cooler Nozzle Welds ML16056A5832016-02-26026 February 2016 and 3, Draft Request for Additional Information License Amendment Request to Adopt Emergency Action Level Scheme Based on NEI 99-01 Rev.6 ML16021A3452016-01-29029 January 2016 Draft Request for Additional Information License Amendment to Add High Flux Trip for 3 Reactor Coolant Pump Operation ML15364A3802016-01-0808 January 2016 Draft Request for Additional Information Relief Request ON-GRR-01 2024-05-01 |
Text
April 09, 2021 MEMORANDUM TO: Jared Nadel, Acting Chief Reactor Projects Branch 1 Division of Reactor Projects FROM: Jannette Worosilo, Senior Project Engineer /RA/
Reactor Projects Branch 1 Division of Reactor Projects
SUBJECT:
PUBLIC MEETING
SUMMARY
- 2020 ANNUAL ASSESSMENT MEETING REGARDING CATAWBA NUCLEAR STATION DOCKET NOS. 50-413 AND 50-414; MCGUIRE NUCLEAR STATION NOS. 50-369 AND 50-370; OCONEE NUCLEAR STATION NOS. 50-269, 50-270, AND 50-287 On April 1, 2021, Nuclear Regulatory Commission (NRC) staff held a virtual public meeting concerning the annual assessment of Catawba Nuclear Station Units 1 and 2; McGuire Nuclear Station Units 1 and 2; and Oconee Nuclear Station Units 1, 2, and 3. The purpose of the virtual meeting session was to provide opportunities to discuss the annual assessment of Catawba Nuclear Station Units 1 and 2; McGuire Nuclear Station Units 1 and 2; and Oconee Nuclear Station Units 1, 2, and 3 for the period of January 1, 2020 - December 31, 2020, with the public.
In response to the COVID-19 coronavirus and updated Federal Government guidance on travel and social distancing, the meeting was held remotely through Microsoft Teams application. The following documents related to the meeting are available in ADAMS: Meeting Notice (ML21090A151), Assessment Meeting Presentation (ML21089A173).
The meeting was conducted from 5:00 PM to 6:00 PM local time. There were 29 attendees, which consisted of representatives from the NRC, Duke Energy, and members of the public. Due to the nature of the meeting, no official list of attendees is included. NRC staff were available for questions following each presentation. There was minimal interaction with the public, consistent with the normal meetings conducted near the stations.
Docket Nos.: 50-413 and 50-414; 50-369 and 50-370; 50-269, 50-270, and 50-287 License No.: NPF-35 and NPF-52; NPF-9 and NPF-17; DPR-38, DPR-47, and DPR-55 CONTACT: Jannette Worosilo, RII/DRP/RPB1 404-997-4485
ML21099A093 SUNSI X Non-Sensitive X Publicly Available X
Review Sensitive Non-Publicly Available RII/DRP/ RPB1 OFFICE NAME J. Worosilo DATE 4/6/2021