Letter Sequence Meeting |
---|
|
|
MONTHYEARML21208A2802021-08-0505 August 2021 Federal Register Notice: Oconee Nuclear Station, Units 1, 2, and 3 - Notice of Intent to Conduct Scoping Process and Prepare an Environmental Impact Statement Project stage: Other ML21208A4102021-08-0505 August 2021 Letter to Steven M. Snider, Site Vice President, Oconee Nuclear Station - Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping Process Project stage: Other ML21263A0312021-09-21021 September 2021 License Renewal Regulatory Audit Regarding the Environmental Review of the Subsequent License Renewal Application Project stage: Approval ML21279A1032021-11-0808 November 2021 August 25, 2021, Oconee Nuclear Station, Units 1, 2, and 3 Subsequent License Renewal Application Public Environmental Scoping Meeting Transcript Project stage: Meeting ML21279A1542021-11-0808 November 2021 August 25, 2021, Oconee Nuclear Station, Units 1, 2, and 3 Subsequent License Renewal Application Public Environmental Scoping Meeting Summary Memo Project stage: Meeting ML21323A1152021-11-23023 November 2021 Subsequent License Renewal Environmental Review Requests for Additional and Subsequent Information - Enclosure Project stage: Other ML21323A1132021-11-23023 November 2021 Subsequent License Renewal Environmental Review Requests for Additional and Subsequent Information - Letter Project stage: Other ML21335A2852021-12-0202 December 2021 Subsequent License Renewal Environmental Review Requests for Additional and Subsequent Information - Supplemental Letter Project stage: Other ML21357A0692022-01-10010 January 2022 Issuance of Environmental Scoping Summary Report Associated with the U.S. Nuclear Regulatory Commission Staff'S Review of the Oconee Nuclear Station Project stage: Approval ML22055A5332022-02-24024 February 2022 Commission Memorandum and Order (CLI-22-03) Project stage: Request ML22055A5272022-02-24024 February 2022 Commission Memorandum and Order (CLI-22-03) Project stage: Request L-2022-031, Annual Radioactive Effluent Release Report2022-03-0101 March 2022 Annual Radioactive Effluent Release Report Project stage: Request L-2022-076, Subsequent License Renewal Application - Appendix E Environmental Report Supplement 22022-06-0909 June 2022 Subsequent License Renewal Application - Appendix E Environmental Report Supplement 2 Project stage: Supplement RA-22-0285, Subsequent License Renewal - Appendix E Environmental Report Supplement 22022-11-0707 November 2022 Subsequent License Renewal - Appendix E Environmental Report Supplement 2 Project stage: Supplement ML22321A3232022-11-18018 November 2022 License Renewal Regulatory Audit Regarding the Environmental Review of the Subsequent License Renewal Application Supplement Project stage: Approval ML23031A1932023-02-0101 February 2023 Summary of the Environmental Remote Audit Related to the Review of the Subsequent License Renewal Application Project stage: Approval ML23031A1992023-02-0101 February 2023 Nd 4 Environmental Remote Audit Requests for Confirmation of Information Project stage: Other ML23075A0732023-04-0505 April 2023 License Renewal Regulatory Audit Regarding the Environmental Review of the Subsequent License Renewal Application Supplement (EPID Number L-2021-SLE-0002) Project stage: Approval ML23132A2392023-06-0101 June 2023 Summary of the April 2023 Remote Environmental Audit Related to the Review of the Subsequent License Renewal Application Project stage: Approval ML23145A2602023-06-0505 June 2023 Revision of Schedule for the Environmental Review of the Turkey Point Nuclear Generating Station, Units 3 and 4, Subsequent License Renewal Application (EPID Number: L-2021-SLE-0002) (Docket Numbers: 50-250 and 50-251) Project stage: Approval ML23199A2482023-09-0505 September 2023 Ltr to Florida Power and Light Co - Turkey Point Nuclear Generating Units 3 and 4 - Notice of Availability of Draft Site-Specific Environmental Impact Statement for Subsequent License Renewal Project stage: Draft Other ML23199A2352023-09-0505 September 2023 Letter to EPA-Turkey Point Nuclear Generating Station, Units 3 and 4 - Notice of Availability of Draft Site-Specific Environmental Impact Statement for Subsequent License Renewal Project stage: Draft Other ML23269A1102023-10-0606 October 2023 Letter to Steven Snider-Revised Schedule for the Environmental Review of the Oconee Nuclear Station, Unit 1, 2, and 3, Subsequent License Renewal Application Project stage: Approval ML23321A0472023-12-20020 December 2023 Letter to Rod L. Penfield - Perry Nuclear Power Plant, Unit 1 - License Renewal Regulatory Audit Regarding the Environmental Review of the License Renewal Application Project stage: Approval 2022-02-24
[Table View] |
Text
November 2, 2021 MEMORANDUM TO: Robert B. Elliott, Chief Environmental Review License Renewal Branch Division of Rulemaking, Environmental, and Financial Support Office of Nuclear Material Safety and Safeguards Signed by Rakovan FROM: Lance J. Rakovan, Senior Project Manager on 11/02/21 Environmental Review License Renewal Branch Division of Rulemaking, Environmental, and Financial Support Office of Nuclear Material Safety and Safeguards
SUBJECT:
MEETING
SUMMARY
- PUBLIC SCOPING MEETING FOR THE ENVIRONMENTAL REVIEW OF THE SUBSEQUENT LICENSE RENEWAL APPLICATION FOR OCONEE NUCLEAR STATION, UNITS 1, 2 AND 3 (EPID NO.: L-2021-SLE-0002)
On August 25, 2021, the U.S. Nuclear Regulatory Commission (NRC) staff conducted a scoping meeting to gather information necessary to prepare an environmental impact statement to evaluate the environmental impacts for the subsequent license renewal of the operating licenses for Oconee Nuclear Station, Units 1, 2 and 3. Enclosed is the meeting summary.
If you have any questions or comments, please contact me via e-mail at Lance.Rakovan@nrc.gov.
Docket Nos. 50-269, 50-270 and 50-287
Enclosures:
- 1. Meeting Summary
- 2. List of Attendees
- 3. NRC slide presentation
- 4. Meeting transcript cc: w/enclosures:
see next page CONTACT: Lance J. Rakovan, NMSS/REFS 301-415-2589
ML21279A154 OFFICE NE/PM:ELRB:REFS LA:REFS/ERMB BC:ELRB:REFS NE/PM:ELRB:REFS NAME LRakovan SFigueroa RElliott LRakovan DATE 10/20/2021 10/21/2021 11/02/2021 11/02/2021