ML060390411
ML060390411 | |
Person / Time | |
---|---|
Site: | Indian Point |
Issue date: | 02/07/2006 |
From: | Brian Mcdermott Reactor Projects Branch 2 |
To: | Dacimo F Entergy Nuclear Operations |
McDermott, B J, RGN-I/DRP/610-337-5233 | |
References | |
FOIA/PA-2016-0148 IR-05-005 | |
Download: ML060390411 (49) | |
See also: IR 05000247/2005005
Text
February 7, 2006
Mr. Fred R. Dacimo
Site Vice President
Entergy Nuclear Operations, Inc.
Indian Point Energy Center
295 Broadway, Suite 1
P.O. Box 249
Buchanan, NY 10511-0249
SUBJECT: INDIAN POINT NUCLEAR GENERATING UNIT 2 - NRC INTEGRATED
INSPECTION REPORT NO. 05000247/2005005
Dear Mr. Dacimo:
On December 31, 2005, the U.S. Nuclear Regulatory Commission (NRC) completed an
inspection at the Indian Point Nuclear Generating Unit 2 (IP2). The enclosed integrated
inspection report documents the inspection findings, which were discussed on
January 11, 2006, with Mr. Paul Rubin and other members of your staff.
The inspection examined activities conducted under your license as they relate to safety and
compliance with the Commissions rules and regulations, and with the conditions of your
license. Within these areas, the inspection consisted of a selected examination of procedures
and representative records, observations of activities, and interviews with personnel.
Based on the results of the inspection, six findings were identified. Four of these findings were
determined to be violations of NRC requirements, including one finding that was determined to
be a Severity Level IV violation. However, because of the very low safety significance, and
because they were entered into your corrective action program, the NRC is treating these four
findings as non-cited violations (NCVs) consistent with Section VI.A of the NRC Enforcement
Policy. If you contest the NCVs in this report, you should provide a response within 30 days of
the date of this inspection report, with the basis for your denial, to the Nuclear Regulatory
Commission, ATTN: Document Control Desk, Washington, D.C. 20555-0001; with copies to the
Regional Administrator, Region I; the Director, Office of Enforcement; and the NRC Senior
Resident Inspector at Indian Point 2.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its
enclosure will be available electronically for public inspection in the NRC Public Document
Room or from the Publicly Available Records (PARS) component of the NRCs document
Mr. Fred R. Dacimo 2
system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-
rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Brian J. McDermott, Chief
Projects Branch 2
Division of Reactor Projects
Docket No. 50-247
License No. DPR-26
Enclosure: Inspection Report No. 05000247/2005005
w/Attachment: Supplemental Information
G. J. Taylor, Chief Executive Officer, Entergy Operations
M. R. Kansler, President, Entergy Nuclear Operations Inc. (ENO)
J. T. Herron, Senior Vice President and Chief Operations Officer (ENO)
C. Schwarz, Vice President, Operations Support (ENO)
P. Rubin, General Manager Operations (ENO)
O. Limpias, Vice President, Engineering (ENO)
J. McCann, Director, Licensing (ENO)
C. D. Faison, Manager, Licensing (ENO)
M. J. Colomb, Director of Oversight (ENO)
J. Comiotes, Director, Nuclear Safety Assurance (ENO)
P. Conroy, Manager, Licensing (ENO)
T. C. McCullough, Assistant General Counsel, Entergy Nuclear Operations, Inc.
P. R. Smith, President, New York State Energy, Research and Development Authority
P. Eddy, Electric Division, New York State Department of Public Service
C. Donaldson, Esquire, Assistant Attorney General, New York Department of Law
Mayor, Village of Buchanan
J. G. Testa, Mayor, City of Peekskill
R. Albanese, Four County Coordinator
S. Lousteau, Treasury Department, Entergy Services, Inc.
Chairman, Standing Committee on Energy, NYS Assembly
Chairman, Standing Committee on Environmental Conservation, NYS Assembly
Chairman, Committee on Corporations, Authorities, and Commissions
M. Slobodien, Director, Emergency Planning
B. Brandenburg, Assistant General Counsel
Assemblywoman Sandra Galef, NYS Assembly
County Clerk, Westchester County Legislature
A. Spano, Westchester County Executive
R. Bondi, Putnam County Executive
C. Vanderhoef, Rockland County Executive
E. A. Diana, Orange County Executive
T. Judson, Central NY Citizens Awareness Network
Mr. Fred R. Dacimo 3
M. Elie, Citizens Awareness Network
D. Lochbaum, Nuclear Safety Engineer, Union of Concerned Scientists
Public Citizen's Critical Mass Energy Project
M. Mariotte, Nuclear Information & Resources Service
F. Zalcman, Pace Law School, Energy Project
L. Puglisi, Supervisor, Town of Cortlandt
Congresswoman Sue W. Kelly
Congresswoman Nita Lowey
Senator Hillary Rodham Clinton
Senator Charles Schumer
J. Riccio, Greenpeace
A. Matthiessen, Executive Director, Riverkeeper, Inc.
M. Kaplowitz, Chairman of County Environment & Health Committee
A. Reynolds, Environmental Advocates
M. Jacobs, Director, Longview School
D. Katz, Executive Director, Citizens Awareness Network
P. Leventhal, The Nuclear Control Institute
K. Coplan, Pace Environmental Litigation Clinic
W. DiProfio, PWR SRC Consultant
D. C. Poole, PWR SRC Consultant
W. Russell, PWR SRC Consultant
W. Little, Associate Attorney, NYSDEC
R. Christman, Manager Training and Development
Mr. Fred R. Dacimo 4
Distribution w/encl: (via E-mail)
S. Collins, RA
M. Dapas, DRA
S. Lee, RI OEDO
R. Laufer, NRR
P. Tam, PM (backup)
B. McDermott, DRP
D. Jackson, DRP
C. Long, DRP
M. Cox, DRP, Senior Resident Inspector - Indian Point 2
G. Bowman, DRP, Resident Inspector - Indian Point 2
R. Martin, DRP, Resident OA
Region I Docket Room (w/concurrences)
ROPreports@nrc.gov
DOCUMENT NAME:E:\Filenet\ML060390411.wpd
SISP REVIEW COMPLETE ________DEJ________ (Reviewers initials)
After declaring this document "An Official Agency Record" it will be released to the Public.
To receive a copy of this document, indicate in the box: "C" = Copy without
attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy
OFFICE RI/DRP RI/DRP RI/DRP
NAME MCox/DEJ for DJackson/DEJ BMcDermott/BJM
DATE 02/07 /06 02/07/06 02/07/06
OFFICIAL RECORD COPY
U.S. NUCLEAR REGULATORY COMMISSION
REGION I
Docket No. 50-247
License No. DPR-26
Report No. 05000247/2005005
Licensee: Entergy Nuclear Northeast
Facility: Indian Point Nuclear Generating Unit 2
Location: 295 Broadway, Suite 3
Buchanan, NY 10511-0308
Dates: October 1, 2005 - December 31, 2005
Inspectors: M. Cox, Senior Resident Inspector, IP2
T. Hipschman, Senior Resident Inspector, IP3
G. Bowman, Resident Inspector, IP2
C. Long, Acting Resident Inspector, IP2
S. Barr, Senior Operations Engineer, Region I
T. Fish, Senior Operations Engineer, Region I
R. Fuhrmeister, Senior Project Engineer, Region I
D. Jackson, Senior Project Engineer, Region I
R. Kahler, Senior Emergency Preparedness Specialist, NSIR
J. Noggle, Senior Health Physicist, Region I
D. Silk, Senior Emergency Preparedness Inspector, Region I
D. Johnson, Reactor Inspector, Region I
T. Sicola, Reactor Inspector, Region I
Approved by: Brian J. McDermott, Chief
Projects Branch 2
Division of Reactor Projects
i Enclosure
TABLE OF CONTENTS
SUMMARY OF FINDINGS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . iii
Summary of Plant Status . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
REACTOR SAFETY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
1R01 Adverse Weather . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
1R04 Equipment Alignment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
1R05 Fire Protection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
1R06 Flood Protection Measures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
1R07 Heat Sink Performance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
1R11 Operator Requalification Inspection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
1R12 Maintenance Effectiveness . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
1R13 Maintenance Risk Assessments and Emergent Work Control . . . . . . . . . . . . . . 9
1R14 Personnel Performance During Non-routine Plant Evolutions and Events . . . 13
1R15 Operability Evaluations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
1R16 Operator Workarounds . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
1R19 Post-Maintenance Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
1R22 Surveillance Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
1R23 Temporary Plant Modifications . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
1EP2 Alert and Notification System Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17
1EP3 Emergency Response Organization (ERO) Augmentation Testing . . . . . . . . . 17
1EP4 Emergency Action Level (EAL) and Emergency Plan Changes . . . . . . . . . . . 18
1EP5 Correction of Emergency Preparedness Weaknesses and Deficiencies . . . . . 20
1EP6 Drill Evaluation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20
4. OTHER ACTIVITIES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21
4OA1 Performance Indicator Verification . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21
4OA2 Identification and Resolution of Problems . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22
4OA4 Cross-Cutting Aspects of Findings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27
4OA6 Meetings, including Exit . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27
ATTACHMENT: SUPPLEMENTAL INFORMATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27
KEY POINTS OF CONTACT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . A-1
LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED . . . . . . . . . . . . . . . . . . . . . . . . . . . A-2
LIST OF DOCUMENTS REVIEWED . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . A-2
LIST OF ACRONYMS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . A-11
ii Enclosure
SUMMARY OF FINDINGS
IR 05000247/2005005; 10/01/2005 - 12/31/2005; Indian Point Nuclear Generating Unit 2;
Maintenance Rule; Maintenance Risk Assessment and Emergent Work; Emergency Planning;
Problem Identification and Resolution.
The report covers a 3-month period of inspection by resident inspectors, 8 regional inspectors,
and one inspector from the NRCs Office of Nuclear Security and Incident Response. Six
findings were identified, four of which were non-cited violations (NCVs), including one that was
determined to be a Severity Level IV violation. The significance of most findings is indicated by
their color (Green, White, Yellow, Red) using Inspection Manual Chapter (IMC) 0609,
Significance Determination Process, (SDP). Findings for which the SDP does not apply may
be Green or be assigned a severity level after NRC management reviews. The NRCs program
for overseeing the safe operation of commercial nuclear power reactors is described in
NUREG-1649, Reactor Oversight Process, Revision 3, dated July 2000.
A. NRC Identified and Self-Revealing Findings
Cornerstone: Mitigating Systems
- Green
This finding greater than minor because it is associated with the Mitigating
Systems cornerstone attribute of Equipment Performance, and affected the
cornerstone objective of ensuring the availability, reliability, and capability of
systems that respond to initiating events to prevent undesirable consequences.
Specifically, the reliability of the control rod drive mechanism fans, which are
to cool the control rod drive mechanisms during normal operation and
are used in emergency operating procedures to prevent void formation in the
reactor head region during natural circulation cool down, was adversely affected.
This finding is of very low safety significance because while equipment reliability
was degraded, there was no actual loss of function
. (Section 1R12)
- Green. The NRC identified a Green NCV of Technical Specification 5.4.1
. Specifically,
iii Enclosure
. Entergy entered this issue into the
corrective action program and took action to revise their work control procedure
to modify their definition of emergency work.
This finding greater than minor, because if left uncorrected it would become a
more significant safety concern. Failure to complete required prior to
work on safety-related equipment could impact the operability of risk-significant
components.
This finding is of very low
safety significance, because the safety-related work performed without an
approved evaluation did not result in the actual loss of safety function of a
system and did not impact fire, flooding, seismic, or severe weather initiating
events.
(Section 1R13)
Cornerstone: Barrier Integrity
- Green. The NRC identified a Green NCV of 10 CFR 50, Appendix B, Criterion V,
Instructions, Procedures, and Drawings,
to FCV-447, the safety-related
feedwater flow control valve to the 24 steam generator. Specifically, while
implementing a modification to grind material from the valve actuator cap screw
heads, maintenance personnel removed more material than allowed by the
modification package.
Entergy entered
this issue into the corrective action program and completed an operability
assessment to show that remained operable.
This finding is greater than minor because it is associated with the Barrier
Integrity cornerstone attribute of Barrier Performance, and affected the
cornerstone objective of ensuring the availability and reliability of components
used for containment isolation. Improper implementation of this modification
could have resulted in the inability of this valve to perform its safety function.
This finding is of very low safety significance because while the modification was
incorrectly implemented, subsequent analysis showed that the valve remained
(Section 1R13)
iv Enclosure
Cornerstone: Emergency Preparedness
This finding is greater than minor because it is associated with the Emergency
Preparedness cornerstone attribute of Facilities and Equipment, and affected the
cornerstone objective of ensuring that the licensee is capable of implementing
adequate measures to protect the health and safety of the public in the event of
a radiological emergency. The deficiency is not greater than Green because it
did not result in the Risk-Significant Planning Standard Function being lost or
degraded. Section 4.4 of Manual Chapter 0609, Appendix B, provides examples
for use in assessing emergency preparedness related findings. One example of
a Green finding states, The EAL classification process would not declare any
Alert or Notification of Unusual Event that should be declared. Since the
declaration of an UE based on low service water bay level could have been
missed or delayed, this finding was considered consistent with the example
provided and was therefore determined to be of very low safety significance
(Green). Because this issue is of very low safety significance and has been
entered into Entergys corrective action program, it is being treated as an NCV.
(Section 1EP4)
- Green. The inspectors identified a Green finding for a failure to implement timely
corrective actions for multiple frame relay system problems dating back to 2003.
Specifically, for issues related to the reliability of the frame relay system,
adequate actions to prevent recurrence were not implemented in a timely
manner. Entergys corrective actions in response to the August 2005 frame
relay failures resulted in a more thorough assessment of this issue and
reasonable actions to prevent recurrence.
This finding was determined to be more than minor because it is associated with
the Emergency Preparedness cornerstone attribute of Facilities and Equipment.
It affected the cornerstone objective of ensuring that the licensee is capable of
implementing adequate measures to protect the health and safety of the public in
the event of a radiological emergency. This finding is not suitable for
Significance Determination Process evaluation but has been reviewed by NRC
management and is determined to be a finding of very low safety significance.
This issue is not greater than Green, because of the short periods that the frame
relay system was unavailable and, because the alert and notification system
design included a secondary method (i.e., back-up radio system) to actuate the
sirens. (Section 4AO2)
v Enclosure
- Severity Level IV. A Severity Level IV violation of 10 CFR 50.72(b)(3)(xiii) was
identified for not formally reporting a siren system problem that occurred on
August 5, 2005. The inspectors noted that the duration of the siren system
problem was short, the NRC was informally notified, the process for back-up
route alerting was available, and the capability to actuate the sirens via a manual
siren initiation method was not lost. Subsequent to this event, Entergy
implemented corrective actions to formalize the manual siren system actuation
method. Notwithstanding these circumstances, a formal notification to the NRC
was required, because the normal processes for actuation of the sirens were not
available and Entergy did not have formal procedures for, and had limited
experience with, method.
This deficiency was evaluated using the traditional enforcement process since
the failure to make a required report could adversely impact the NRCs ability to
carry out its regulatory mission.
(Section 4OA2)
B. Licensee Identified Violations.
None.
vi Enclosure
Report Details
Summary of Plant Status
Indian Point 2 (IP2) began the inspection period at full power and operated at or near full power
until December 22. On December 22, power was reduced to approximately 3 percent and the
main turbine was taken off-line to repack FCV-447, the feedwater regulating valve to the 24
steam generator (S/G). Work was completed and the plant was returned to full power on
December 23. The plant remained at full power for the remainder of the inspection period.
1. REACTOR SAFETY
Cornerstones: Initiating Events, Mitigating Systems, Barrier Integrity
1R01 Adverse Weather
a. Inspection Scope (71111.01 - 1 sample of system-related weather preparations)
The inspectors reviewed Entergys administrative controls and implementation of a
maintenance program to ensure adequate protection of safety-related water sources
from freezing conditions. These systems were selected because their safety-related
functions could be affected by adverse weather. Specifically, the inspectors reviewed
Entergys strategy for coping with cold weather effects on the condensate storage tank
(CST), the primary water storage tank (PWST), and the refueling water storage tank
(RWST). The inspectors also reviewed work orders (WOs) and condition reports (CRs)
associated with these external tanks which had the potential to impact cold weather
performance. In addition, the inspectors walked down the accessible areas of piping
and instrumentation to evaluate the insulation and heat tracing material condition. The
specific information reviewed is listed in the attachment. Cumulatively, this inspection of
selected tanks and support systems constituted one inspection sample.
b. Findings
No findings of significance were identified.
1R04 Equipment Alignment
.1 Partial System Walkdown
a. Inspection Scope (71111.04Q - 3 samples)
The inspectors performed three partial system walkdowns to verify the operability of
redundant or diverse trains and components during periods of system train unavailability
or following periods of maintenance. The inspectors referenced the system procedures
and drawings in order to verify that the alignment of the available train was proper to
support its required safety functions. The inspectors also reviewed applicable CRs and
WOs to assure that Entergy had identified and properly addressed equipment
discrepancies that could potentially impair the capability of the available train.
Enclosure
2
Referenced documents are listed in the attachment at the end of this report. The
following system walkdowns were counted as inspection samples:
- Gas Turbine (GT) 3 with GT-1 Out of Service for Preventative Maintenance
- 22 and 23 Auxiliary Boiler Feed Pumps (ABFP) with the 21 ABFP Out of Service
for Maintenance
- Emergency Diesel Generators 21, 22, and 23 Following Periodic Testing
b. Findings
No findings of significance were identified.
.2 Full Equipment Alignment
a. Inspection Scope (71111.04S - 1 sample)
The inspectors performed an extensive walkdown of the component cooling water
(CCW) system. The inspectors walked down the system using 2-PT-Q90, Component
Cooling Water System Quarterly Alignment Verification, Revision 0, and the system
flow diagrams. The inspectors verified that all accessible system components were in
the proper position and verified that any discrepancies were properly documented.
Additionally, the inspectors evaluated the physical condition of the equipment during the
walkdown and reviewed open CRs and WOs to evaluate if any had the potential to
impact system operability. This system walkdown was considered one inspection
sample.
b. Findings
No findings of significance were identified.
1R05 Fire Protection
a. Inspection Scope (71111.05Q - 6 samples)
The inspectors toured areas that were identified as important to plant safety and risk
significance. The inspectors consulted the Indian Point 2 Individual Plant Examination
for External Events (IPEEE), Section 4.0, Internal Fires Analysis, and the top risk-
significant fire zones in Table 4.6-2, Summary of Core Damage Frequency
Contributions from Fire Zones. The objective of this inspection was to determine if
Entergy had adequately controlled combustibles and ignition sources within the plant,
effectively maintained fire detection and suppression capability, and had adequately
established compensatory measures for degraded fire protection equipment. The
inspectors evaluated conditions related to: (1) control of transient combustibles and
ignition sources; (2) the material condition, operational status, and operational lineup of
fire protection systems, equipment, and features; (3) the fire barriers used to prevent fire
damage or fire propagation; (4) compensatory measures for out-of-service, degraded, or
inoperable fire protection equipment were implemented in accordance with Entergys fire
Enclosure
3
plan. Reference material used by the inspectors to determine the acceptability of the
observed conditions in the fire zones are referenced in the attachment at the end of this
report. The following areas were counted as inspection samples:
- Zone 11
- Zones 5, 6, 7
- Zone 14
- Zones 9, 12A, 13A
- Zones 19, 20, 45A
- Zone 1
b. Findings
No findings of significance were identified.
1R06 Flood Protection Measures
a. Inspection Scope (71111.06 - 1 internal flooding sample)
The inspectors reviewed Entergys internal flood analysis, flood mitigation procedures,
and design features to verify that they were consistent with IP2's design
requirements. The inspectors walked down the emergency diesel generator (EDG)
building and evaluated the condition and adequacy of mitigation equipment to assess
whether flood protection design features were adequate. This walkdown constituted one
inspection sample.
The inspectors reviewed Entergys flood mitigation procedures. In addition, the
inspectors reviewed the corrective action program (CAP) to determine if there was any
history of flood problems in this area. The specific information reviewed is referenced in
the attachment at the end of this report.
b. Findings
Introduction: The inspectors identified an Unresolved Item (URI) associated with the
potential vulnerability of the normal and emergency 480 VAC vital alternating current
(AC) power sources to flooding in the EDG building. Approximately 30 to 50 oil
absorbing pads of varying sizes were found on the floor underneath all three EDGs.
During a flooding event, these pads could be swept into the five building drainage
sumps, preventing water from being drained from the building.
Discussion: On November 29, 2005, the inspectors reviewed the internal flood
protection measures for the EDG building. All three 480 VAC EDGs are located in this
building in a common area separated by installed fire barrier walls. The EDGs are
approximately five feet above the concrete floor of the building and access to the EDGs
is afforded by metal grate flooring. The major sources of potential flooding for the space
are fire protection piping and the essential service water (ESW) system piping in the
building. The building is designed such that water drains toward five shallow sumps that
Enclosure
4
are connected to a common 12-inch-diameter drain line that discharges to the site
drainage system. Each sump has two 3-inch-diameter openings that have backwater
ball check valves to prevent back-leakage into the EDG building. Inspectors observed
between 30 and 50 oil absorbent pads on the concrete floor underneath the EDGs.
These pads were not fixed to the floor by any means, and would be free to migrate to
the building sumps along with water during a flooding event. The pads were of sufficient
size to effectively block the 3-inch holes in each of the building sumps as water level
rises in the building. The IPEEE credits the building drains being sufficiently sized to
prevent significant accumulation of water due to a break of fire protection piping in the
room. This assumes that the function of these drains is not impeded by foreign material
blockage. In addition, both the IPEEE and the IP2 Probabilistic Safety Assessment
(PSA) state that a break of an ESW line is bounded by the fact that the EDGs are
cooled by ESW and would be the only equipment negatively impacted by the flooding,
and that this occurrence is analyzed by the total loss of service water event. There are
inconsistencies between the IPEEE, dated 1995, and the PSA, which was completed in
the 1998 time frame. The PSA does not account for the fire protection header as being
a potential source of flooding for the EDG building, whereas the IPEEE does. Both
analyses credit open ventilation louvers along the building north wall at grade level to
drain water if the buildings installed drain capacity is insufficient. However, during the
winter months these louvers are maintained shut. In addition, the IPEEE mentions an
EDG building flood alarm in the control room and specific isolation procedures in the
event of flooding. Neither the alarm, nor the specific isolation procedures, currently
exist. Finally, the inspectors identified that 480 VAC normal feeder breaker control
power exists in each EDG control cabinet. Flood water that reaches the bottom of the
EDG control cabinets due to insufficient building drain capacity, and can not be relieved
through closed building doors and closed ventilation louvers, could potentially render all
three EDGs unavailable and trip the normal feeder breakers to all 480 VAC vital AC
buses. In response to the , Entergy removed the oil absorbent
pads from the EDG building and entered the issue into the corrective action
program (CR-IP2-05-4868). This issue will be treated as a URI pending additional
licensee evaluation and inspector review of the potential impact of flooding in the EDG
building on the normal and emergency vital AC power sources:
URI 05000247/2005005-01, Emergency Diesel Generator Building Flood Mitigation
Capability.
1R07 Heat Sink Performance
a. Inspection Scope (71111.07 - 1 sample)
The inspectors performed a review of the instrument air closed cooling water (IACCW)
heat exchangers to verify that Entergy was monitoring performance on a continuing
basis and to ensure that any potential deficiencies which could mask degraded
performance were identified. The inspectors reviewed the design basis documents and
Final Safety Analysis Report (FSAR) to validate that testing acceptance criteria were
appropriate. The inspectors also reviewed the latest inspection reports for both the 21
and 22 IACCW heat exchangers, evaluated the results of eddy current testing, and
Enclosure
5
ensured that the appropriate tube plugging criteria were used. In addition, the
inspectors verified that Entergy was maintaining their commitments from Generic Letter 89-13 concerning heat exchanger inspection and testing. The inspection of the IACCW
heat exchangers constituted one inspection sample.
b. Findings
No findings of significance were identified.
1R11 Operator Requalification Inspection
.1 Resident Inspector Quarterly Review
a. Inspection Scope (71111.11Q - 2 samples)
On November 30, 2005, the inspectors observed an Emergency Plan drill
implementation by licensed operators in the simulator. The inspectors reviewed the
simulator scenario performed as a part of the overall drill to determine if the scenario
contained: (1) clear event descriptions with realistic initial conditions, (2) clear start and
end points, (3) clear descriptions of visible plant symptoms for the crew to recognize,
and (4) clear expectations of operator actions in response to abnormal conditions. The
scenario involved a simulated reactor coolant system leak, small break loss of coolant
accident, large break loss of coolant accident, and a loss of emergency coolant
recirculation capability.
During the simulator exercise, the inspectors evaluated the teams performance for: (1)
clarity and formality of communications, (2) correct use and implementation of
emergency operating procedures (EOPs) and abnormal operating procedures (AOPs),
(3) operators ability to properly interpret and verify alarms, (4) operators ability to
classify events in a timely fashion, and (4) operators ability to take timely actions in a
safe direction based on transient conditions. In addition, the inspectors evaluated the
control room supervisors ability to exercise effective oversight and control of the crews
actions during the exercise.
On December 1, 2005, the inspectors observed in-plant training of 2-AOP-SSD-1,
Control Room Inaccessibility Safe Shutdown Control. The training involved rotating
three groups of licensed operators between the primary auxiliary building, auxiliary
feedwater pump building, and turbine hall to walk-through the complex procedure. The
instructors were knowledgeable and asked probing questions of the students throughout
the training. Actions in the procedures were simulated as actual performance was not
possible due to plant operation.
The simulator scenario observation was counted as one inspection sample, and the
observation of the walk through training was counted as a second inspection sample.
b. Findings
Enclosure
6
No findings of significance were identified.
.2 Annual Review of Operating Test and Comprehensive Written Exam Results
a. Inspection Scope (71111.11B - 1 sample)
On December 19, 2005, the inspector conducted an in-office review of licensee annual
operating test results and comprehensive written exam results for 2005, constituting one
inspection sample. The inspection assessed whether pass rates were consistent with
the guidance of NRC Manual Chapter 0609, Appendix I, Operator Requalification
Human Performance Significance Determination Process (SDP). The inspector verified
that:
- Crew failure rate was less than 20%. (Crew failure rate was 0%.)
- Individual failure rate on the dynamic simulator test was less than or equal to
20%. (Individual failure rate was 0%.)
- Individual failure rate on the walk-through test was less than or equal to 20%.
(Individual failure rate was 2%.)
- Individual failure rate on the comprehensive written exam was less than or equal
to 20%. (Individual failure rate was 11%.)
- Overall pass rate among individuals for all portions of the exam was greater than
or equal to 75%. (Overall pass rate was 87%.)
b. Findings
No findings of significance were identified.
1R12 Maintenance Effectiveness
.1 Maintenance Rule Implementation - Quarterly
a. Inspection Scope (71111.12Q - 3 samples)
The inspectors also reviewed WOs, and associated post-maintenance test activities to
assess whether: (1) the effect of maintenance work in the plant had been adequately
Enclosure
7
addressed by control room personnel, (2) work planning was adequate for the
maintenance performed, (3) the acceptance criteria were clear and adequately
demonstrated operational readiness consistent with design and licensing documents,
and (4) the equipment was effectively returned to service. Referenced documents are
listed in the Supplemental Information attachment at the end of this report. The below-
listed systems maintenance activities were observed and/or evaluated. Each system
review constituted one inspection sample.
- Control Rod Drive Mechanism Fans
- 480 VAC Circuit Breakers
- CCW System
b. Findings
Introduction: The inspectors identified a Green finding in that Entergy failed to maintain
adequate design control of the control rod drive mechanism (CRDM) fans. This directly
resulted in loss of lubrication and failure of the 23 CRDM fan.
Description: On June 2, 2005, the 23 CRDM fan failed during operation. These fans
are used to remove the heat generated by the CRDMs when the plant is at power.
Restrictions are placed on plant operation and additional actions by operators are
required if more than one fan is out of service. The CRDM fans are also used in the
EOPs to facilitate natural circulation cooldown of the plant by preventing void formation
in the reactor head region. Alternate mitigation strategies are available to the operators
in the event the fans are unavailable, however, this complicates and slows down the
cooldown process.
Entergys failure analysis for the 23 CRDM fan determined that the failure was due to a
lack of grease in a motor bearing. It was further determined that the fan motor bearings
were not built in accordance with design change package MSAP-00-00524-FFX. This
design change, which installed a more robust bearing design, was implemented in 2000
to improve CRDM fan reliability and recover the system from Maintenance Rule (a)(1)
status. The original motor design used light duty ball bearings, while the upgraded
design used heavier duty bearings with a thrust bearing at one end. The thrust bearing
required the installation of shields to ensure it could run for a 24 month cycle without
additional grease. The shields in the 23 CRDM fan had not been properly installed,
which ultimately resulted in bearing seizure due to lack of lubrication.
The inspectors also noted that following a failure of the 24 CRDM fan in April 2005 from
an unrelated cause, Entergy identified that the spare motor was not properly configured.
The companys investigation determined that there was an error in the purchase order
for fans installed in the November 2004 plant outage, and Entergy could not be certain
of the configuration of any of the installed motors.
. Entergy entered this issue into the corrective action program (CR-
IP2-05-2210) and has taken actions to ensure that the deficiency will be corrected
during the upcoming refueling outage.
Enclosure
8
Analysis: The inspectors determined that the failure to maintain design control of the
CRDM fans was a performance deficiency since it was the direct result of errors in
Entergys procurement process. This issue directly resulted in the failure of the 23
CRDM fan. It is reasonable that Entergy could have recognized and prevented this
problem. Traditional enforcement does not apply since there were no actual safety
consequences or potential for impacting the NRCs regulatory function, and the finding
was not the result of any willful violation of NRC requirements or Entergys procedures.
This finding is greater than minor since it is associated with the Design Control attribute
of the Mitigating Systems cornerstone objective to ensure availability, reliability, and
capability of systems that respond to initiating events to prevent undesirable
consequences. This finding was evaluated using Phase 1 of Inspection Manual Chapter
(IMC) 0609, Appendix A, Significance Determination of Reactor Inspection Findings for
At-Power Situations. The finding is of very low safety significance since the
performance deficiency does not represent an actual loss of function and did not
screen as risk-significant due to seismic, flooding, or severe weather initiating events.
was out of service, the other three fans were available to perform the
necessary system functions.
Enforcement: No violation of regulatory requirements occurred since the design control
issues involved the non-safety-related CRDM fans which are outside the scope of 10
CFR 50, Appendix B, Quality Assurance Criteria for Nuclear Power Plants and Fuel
Reprocessing Plants. This finding is identified as FIN 05000247/2005005-02, Failure
to Maintain Design Control of Control Rod Drive Mechanism Fans.
.2 Maintenance Rule Implementation - Biennial
a. Inspection Scope (71111.12B - 4 samples)
The inspector conducted a review of the periodic evaluation of implementation of the
Maintenance Rule as required by 10 CFR 50.65(a)(3) for IP2. The evaluation covered a
period from April 2003 to April 2005. The purpose of this review was to ensure that IP2
established appropriate goals, and effectively assessed system performance and
preventive maintenance activities. The inspector verified that the evaluation was
completed within the required time period and that industry operating experience was
utilized, where applicable. Additionally, the inspector verified that Indian Point
appropriately balanced equipment reliability and availability and made adjustments when
appropriate.
The inspector selected a sample of four risk-significant systems to verify that: (1) the
structures, systems, and components were properly characterized; (2) goals and
performance criteria were appropriate; (3) corrective action plans were adequate; and
(4) performance was being effectively monitored in accordance with station procedure
ENN-DC-121, Maintenance Rule. The following systems were selected for detailed
review and constituted four inspection samples:
Enclosure
9
- Auxiliary Feedwater System
- Chemical and Volume Control System
- Control Rod Drives
- Gas Turbines
These systems were either in (a)(1) status, had been in (a)(1) status at some time
during the assessment period, or had experienced degraded performance. The
inspector reviewed corrective action documents for malfunctions and failures of these
systems to determine if: (1) system failures had been correctly categorized as functional
failures, and (2) system performance was adequately monitored to determine if
classifying a system as (a)(1) was appropriate.
The inspector interviewed the maintenance rule coordinator and system engineers,
reviewed documentation for applicable systems, and reviewed a sample of condition
reports. The documents that were reviewed are listed in the attachment to this report.
b. Findings
No findings of significance were identified.
1R13 Maintenance Risk Assessments and Emergent Work Control
a. Inspection Scope (71111.13 - 4 samples)
The inspectors observed selected portions of routinely scheduled and emergent
maintenance work activities to assess Entergys risk management in accordance with 10
CFR 50.65(a)(4). The inspectors verified that Entergy took the necessary steps to plan
and control emergent work activities, to minimize the probability of initiating events, and
to maintain the functional capability of mitigating systems. The inspectors observed
and/or discussed risk management actions with maintenance and operations personnel.
The following emergent work activities were observed, and constituted four inspection
samples:
- WO IP2-05-25862, Replacement of the 22 S/G High Steam Flow SI Initiation
Bistable
- CR IP2-05-4759, PCV-455C Low Nitrogen Pressure Alarms
- WO IP2-01-23320, Lighting Bus 22/23 Tie Breaker Maintenance
- FCV-447 Packing Leakage Corrective Actions
Introduction: The inspectors identified a Green non-cited violation (NCV) in that
modification documents and procedures were not followed while implementing a
temporary modification to the 24 S/G feedwater regulating valve, FCV-447. This was
determined to be a violation of 10 CFR 50, Appendix B, Criterion V, Instructions,
Procedures and Drawings.
Enclosure
10
Description: On September 27, 2005, a modification was performed on FCV-447 in
which the cap screws holding the valve actuator onto the valve body were ground down
at an angle to allow clearance between the cap screws and the packing gland follower.
This valve is a safety-related component required for isolation of one of the four
feedwater lines following a feed or steam line break inside the containment to minimize
peak containment pressure. The additional clearance was required to allow further
packing adjustments to prevent feedwater/steam leakage through the valves packing.
The temporary alteration package, TA-05-2-107, specified that the maximum thickness
removed was to be three-eighths of an inch, which would leave a minimum of three-
eighths of an inch of the cap screw head remaining. The supporting calculation to
assure structural integrity following this modification also assumed the cap screw
thickness to be three-eighths of an inch following the grinding.
The inspectors reviewed Entergys analysis to show that the structural integrity of the
cap screws would be maintained, and completed a walkdown of the valve to ensure the
modification had been properly implemented. The inspectors identified that more
material had been ground from the cap screws than allowed by the analysis. The
inspectors also found that Entergys structural integrity evaluation failed to consider
seismic stresses. Based on the inspectors observations, Entergy declared the valve
inoperable and entered a 72 hour8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> action statement as required by Technical
Specifications. Entergy entered this issue into the corrective action program (CR-IP2-
05-4615) and completed an additional evaluation which showed that the actuator cap
screws on FCV-447 would remain operable under design conditions in the as-left
condition. Following this evaluation, Entergy exited the 72 hour8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> action statement.
Analysis: The inspectors determined that this is a performance deficiency since Entergy
exceeded the grinding depth as specified in the alteration package and failed to identify
this condition. It is reasonable that Entergy could have recognized and prevented this
problem. Traditional enforcement does not apply since there were no actual safety
consequences or potential for impacting the NRCs regulatory function and the finding
was not the result of any willful violation of NRC requirements or Entergys procedures.
This finding is greater than minor, because it was associated with the Barrier Integrity
cornerstone attribute of Human Performance, and affected the cornerstone objective of
ensuring the containment would remain functional to protect the public from radionuclide
releases caused by accidents or events. This finding was evaluated using Phase 1 of
IMC 0609, Appendix A, Significance Determination of Reactor Inspection Findings for
At-Power Situations, and is of very low safety significance since the work performed on
FCV-447 did not result in an actual loss of its safety function.
This finding is also related to the cross-cutting area of Human Performance in that
maintenance personnel failed to implement the modification as specified in the
temporary alteration package. This error was not identified by the maintenance workers
or engineering personnel upon completion of the modification. (Section 4OA4).
Enforcement: 10 CFR 50, Appendix B, Criterion V states, in part, that activities affecting
quality shall be prescribed by procedures and shall be accomplished in accordance with
these procedures. Contrary to this, Entergy failed to implement the modification of FCV-
Enclosure
11
447 as prescribed by the modification requirements. Because this failure to follow
modification requirements for the valve is of very low safety significance and has been
entered into Entergys corrective actions program (CR-IP2-2005-4615) this violation is
being treated as an NCV, consistent with Section VI.A of the NRC Enforcement Policy:
NCV 05000247/2005005-03, Failure to Follow Procedural Requirements During
Modification of a Safety-Related Valve.
2. Introduction: The inspectors identified a Green NCV of Technical Specification (TS)
5.4.1, Administrative Controls - Procedures, because Indian Points work management
procedure inappropriately allowed actions to be implemented to perform a modification
on a safety-related component before the modification package was issued.
Description: The inspectors reviewed procedure IP-SMM-WM-100, Work Management
Process. This procedure, which is specific to Indian Point, defines emergency work, in
part, as: Actions required to prevent a real or potential plant transient or forced
shutdown. TS 5.4.1 requires Indian Point to establish, implement, and maintain those
procedures discussed in Appendix A of Regulatory Guide (RG) 1.33, Quality Assurance
Program Requirements (Operation). RG 1.33 states that maintenance which can affect
the performance of safety-related equipment should be properly preplanned and
performed in accordance with written procedures, documented instructions, or drawings
appropriate to the circumstances.
Entergys work management procedure provided steps to bypass the established work
control process in order to prevent a forced shutdown of the plant based on the
procedural definition of emergency work. 10 CFR 50.54(x) allows licensees to take
actions that depart from a Technical Specification requirement in an emergency, when
that action is immediately needed to protect public health and safety, and there is no
immediately apparent action consistent with the Technical Specifications which can
provide adequate or equivalent protection. The inspectors determined that Entergys
definition of emergency work, specifically work to prevent a forced shutdown,
.
Therefore, there was no valid basis to bypass the established work control process, as
required by TS 5.4.1, to prevent forced shutdowns or plant transients. In addition, the
inspectors noted that EN-WM-100, Work Request Generation, Screening and
Classification, the Entergy fleet-wide governing document for the site specific work
control procedure, did not classify work to prevent a forced shutdown as emergency
work. The inspectors determined that Indian Points work management procedure
inappropriately allowed maintenance which could result in a shutdown or transient to be
declared emergency work thus allowing the required work controls process to be
bypassed.
On September 27, 2005, and again on November 8, 2005, Entergy modified capscrews
on a safety related valve (FCV-447), using the work management procedures allowance
for emergency work. Entergys decision to use this process was based on the
assumption that prompt action was required to prevent excessive damage to the
packing, which would make future packing adjustments unsuccessful and leave valve
Enclosure
12
re-packing or leak repair as the only viable maintenance alternatives. The declaration of
emergency work allowed the maintenance to be performed prior to completion of work
procedures, a modification package, and the associated engineering analysis.
In response to the inspectors concerns,
Additionally, procedure IP-SMM-WM-100 was
revised to prevent the declaration of emergency work for issues which could result in a
plant shutdown or transient. Entergy also completed an engineering analysis to show
that FCV-447 would still be able to perform its safety function.
Analysis: The inspectors determined that Indian Points development of a procedure
actions contrary to the plants Technical Specifications is a performance
deficiency and directly resulted in actions to commence modifications on a safety-
related component before evaluation was completed. It is reasonable that
Entergy could have recognized and prevented this problem. Traditional enforcement
does not apply because there were no actual safety consequences or potential for
impacting the NRCs regulatory function, and the finding was not the result of any willful
violation of NRC requirements or Entergy procedures. This finding is greater than
minor, because if left uncorrected, the issue could become a more significant safety
concern. This finding was evaluated using Phase 1 of IMC 0609, Appendix A,
Significance Determination of Reactor Inspection Findings for At-Power Situations.
The inspectors determined that the violation of TS 5.4.1 is of very low safety significance
since the work performed on FCV-447 did not result in the actual loss of safety function
of a system and did not impact fire, flooding, seismic, or severe weather initiating
events.
This finding is associated with the Human Performance cross-cutting area in that the
decision to implement the modification to FCV-447 without an adequate evaluation was
based on inappropriate procedural guidance (see Section 4OA4).
Enforcement: TS 5.4.1 requires that written procedures be established, implemented,
and maintained covering the activities recommended in RG 1.33. RG 1.33 states that
maintenance which can affect the performance of safety-related equipment should be
properly preplanned and performed in accordance with written procedures, documented
instructions, or drawings appropriate to the circumstances. Contrary to the above,
Entergy developed a site work control procedure which allowed a modification to be
performed on an in-service safety-related component prior to the modification
documents being completed and formalized. Because this violation is of very low safety
significance
, it is being treated as an NCV consistent with Section VI.A.1 of the NRC
Enforcement Policy: NCV 05000247/2005005-04, Inadequate Procedure for Control
of Work on Safety-Related Components.
Enclosure
13
November 17, 2005
- On December 22, 2005, the inspectors monitored Entergys actions to reduce
reactor power to approximately 3 percent and take the turbine off-line to repack
FCV-447. The inspectors reviewed Entergys procedures for plant shutdown and
observed the evolution in the control room. The inspectors also observed
important activities associate with the power ascension following completion of
the maintenance. A list of documents reviewed is included in the attachment to
this report.
b. Findings
No findings of significance were identified.
Enclosure
14
1R15 Operability Evaluations
a. Inspection Scope (71111.15 - 5 samples)
The inspectors selected operability evaluations that Entergy had generated that
warranted review on the basis of potential risk significance. The selected samples are
addressed in the CRs listed below. The inspectors assessed the accuracy of the
evaluations, the use and control of compensatory measures, if needed, and compliance
with the TSs. The inspectors review included a verification that the operability
evaluations were made as specified by procedure ENN-OP-104, Operability
Determinations. The technical adequacy of the evaluations was reviewed and
compared to the TSs, Technical Requirements Manual (TRM), FSAR, and associated
design basis documents. The operability evaluations that were inspected constituted
five inspection samples.
- CR IP2-05-4246, Operations with the Low Feed Flow Bypass Isolation Valves
Open
- CR IP2-05-4414, Failure of FCV-1176 (EDG Service Water Outlet Valve) to
Close Following Surveillance Testing
- CR IP2-05-4642, EDG Fuel Oil Inventory
- CR-IP2-05-4792, Identification of a Gas Void Between the Outlet of the 21
Residual Heat Removal Heat Exchanger and Valve HCV-638
- CR IP2-05-4841, Cable Separation Issues Identified During Walkdowns Outside
Containment
b. Findings
No findings of significance were identified.
1R16 Operator Workarounds
a. Inspection Scope (71111.16 - 2 samples)
The inspectors reviewed the operator workaround associated with failure of a power
supply for Control Room alarm panel AS-1. The inspectors reviewed the individual
alarms lost, impact on plant operation, and the compensatory measures established by
Entergy. The inspectors evaluated these measures to ensure they were appropriately
scoped within Entergys operator burdens program and that the required actions could
feasibly be performed by the operations staff. This operator workaround review
constitutes one inspection sample.
The inspectors also focused on the operator workaround associated with one
pressurizer spray valve (PCV-455A) being isolated. The inspectors verified that the
Operational Decision Making Process was followed for this issue, and that appropriate
compensatory actions were taken. The inspectors used OAP-45, Operator Burden
Program, and EN-OP-111, Operational Decision Making Issue Process, to evaluate
plant deficiencies and their effects on plant operation.
Enclosure
15
The sample related to operation with PCV-455A isolated was originally documented in
Inspection Report 05000247/2005-04. However, due to an oversight, it was not counted
as a completed sample. It is being documented again in this report to correct the error.
b. Findings
No findings of significance were identified.
1R19 Post-Maintenance Testing
a. Inspection Scope (71111.19 - 8 samples)
The inspector reviewed post-maintenance test (PMT) procedures and associated testing
activities to assess whether: (1) the effect of testing in the plant was adequately
addressed by control room personnel; (2) testing was adequate for the maintenance
WO performed; (3) the acceptance criteria was clear and adequately demonstrated
operational readiness consistent with design and licensing documents; (4) test
instrumentation had current calibrations, range, and accuracy for the application; and
(5) test equipment was removed following testing.
The selected testing activities involved components that were risk-significant as
identified in the IP2 Individual Plant Examination (IPE). The regulatory references for
the inspection included TSs and 10 CFR 50, Appendix B, Criterion XIV, Inspection,
Test, and Operating Status. The following testing activities were evaluated, and
constituted eight inspection samples:
- WO IP2-05-2522, Containment Sump Stop Valve 885B Following Mechanical
Interlock Replacement
- WO IP2-05-26316, 21 CCP Following Internal Valve Replacements Due to Flow
Oscillation
- WO IP2-05-27328, PWT Following On-Line Leak Repair of PCV-1135, the 22
S/G Atmospheric Dump Valve
- WO IP2-05-28030, 23 Station Battery Following Replacement of Cell 3 Due to
Low Cell Voltage
- WO IP2-05-20640, 21 CCW Pump Following a Planned Component
Maintenance Outage Period
- WO IP2-05-21932, 24 Service Water Pump (SWP) Following a Planned
Component Maintenance Outage Period
- WO IP2-04-12427, 25 SWP Following a Planned Component Maintenance
Outage Period
- WO IP2-05-26680, PWT for 3M Oil and Filter Change on 23 EDG Starting Air
Compressor
b. Findings
No findings of significance were identified.
Enclosure
16
1R22 Surveillance Testing
a. Inspection Scope (71111.22 - 5 samples)
The inspectors reviewed surveillance test procedures and observed testing activities to
assess whether: (1) the test preconditioned the component tested; (2) the effect of the
testing was adequately addressed in the control room; (3) the acceptance criteria
demonstrated operational readiness consistent with design calculations and licensing
documents; (4) the test equipment range and accuracy were adequate and the
equipment was properly calibrated; (5) the test was performed per the procedure; (6)
test equipment was removed following testing; and (7) the test discrepancies were
appropriately evaluated. The surveillance tests observed were based on risk-significant
components as identified in the IP2 IPE. The regulatory requirements that provided the
acceptance criteria for this review were 10 CFR 50, Appendix B, Criterion V,
Instructions, Procedures, and Drawings; Criterion XIV, Inspection, Test, and
Operating Status; Criterion XI, Test Control; and TS 6.8.1.a. The following test
activities were reviewed and constituted five inspection samples:
- 2PT-Q29B, 22 Safety Injection Pump Quarterly Test, Revision 15
- 2PI-3Y2A, 23 Auxiliary Boiler Feed Pump Suction and Discharge Inservice
Inspection Pressure Test, Revision 4
- 2PT-Q27A, 21 Auxiliary Boiler Feed Pump Quarterly Test, Revision 12
- 2PT-SA067, Main Turbine Stop and Control Valves, Revision 1
- 2PT-M21A, Emergency Diesel Generator 21 Load Test, Revision 11
b. Findings
No findings of significance were identified.
1R23 Temporary Plant Modifications
a. Inspection Scope (71111.23 - 2 samples)
The inspectors reviewed two temporary modifications, that constituted two inspection
samples, to ensure that the effects on plant operation were well understood and to
ensure that no unintended, adverse consequences would result from the modification.
The inspectors evaluated the modification documentation for accuracy and
completeness, the basis for the modification, and any associated procedures or
changes to procedures to control the temporary modification operation. The following
temporary modifications were reviewed:
- WO IP2-05-27331, On-line Leak Repair of PCV-1135, 22 S/G Atmospheric
Dump Valve
- TA-05-2-039, Removal and Installation of SWN-840 Actuator on 22 CCW Heat
Exchanger Valve SWN-35-1
Enclosure
17
b. Findings
No findings of significance were identified.
Cornerstone: Emergency Preparedness
1EP2 Alert and Notification System Testing
a. Inspection Scope (71114.02 - 1 Sample)
An onsite review of Entergys alert and notification system (ANS) was conducted to
ensure prompt notification of the public for taking protective actions. During the
inspection at Indian Point, the inspectors reviewed the test and maintenance
documentation for the siren system. Distribution records were sampled pertaining to the
tone alert radio portion of the ANS. CRs generated as a result of siren testing were
reviewed for causes, trends, and corrective actions. The inspectors interviewed
personnel responsible for the alert and notification program. The inspection was
conducted in accordance with NRC Inspection Procedure 71114, Attachment 02.
Planning standard 10 CFR 50.47(b)(5) and the related requirements of 10 CFR 50,
Appendix E were used as reference criteria.
b. Findings
No findings of significance were identified.
1EP3 Emergency Response Organization (ERO) Augmentation Testing
a. Inspection Scope (71114.03 - 1 Sample)
A review of Indian Points ERO augmentation staffing requirements and the process for
notifying the ERO was conducted to ensure the readiness of key staff for responding to
an event and to ensure timely facility activation. The inspectors reviewed procedures
and CRs associated with the ERO notification system and process. The inspectors
interviewed personnel responsible for the ERO augmentation process. The inspection
was conducted in accordance with NRC Inspection Procedure 71114, Attachment 03.
Planning standard 10 CFR 50.47(b)(2) and related requirements of 10 CFR 50,
Appendix E were used as reference criteria.
b. Findings
No findings of significance were identified.
Enclosure
18
1EP4 Emergency Action Level (EAL) and Emergency Plan Changes
.1 EAL Review
a. Inspection Scope
The inspectors reviewed changes to Entergys EALs to ensure that the changes did not
decrease the effectiveness of the Emergency Plan. The inspectors reviewed Entergy
procedures to determine if an EAL scheme had been changed in a manner that
decreased its effectiveness such that the EALs may not produce the appropriate
emergency classification. The inspectors verified that the EAL scheme continued to
meet the planning standard.
b. Findings
Introduction: The inspectors identified a Green NCV associated with emergency
planning standard 10 CFR 50.47(b)(4). The inspectors determined that a performance
deficiency existed in that inadequate indications were available for operators to
determine if a threshold for an unusual event (UE), based on service water bay level,
had been met. This issue did not result in the loss or degradation of a risk significant
planning standard based on the inspectors assessment of the criteria in NRC Manual
Chapter 0609, Appendix B, Emergency Preparedness Significance Determination
Process.
Description: A combination of low tides and debris on the intake structure trash bars
resulted in a low service water bay level at the Indian Point Unit 3 (IP3) intake structure
between November 23 to November 25, 2005. Operators were alerted to this condition
due to the occasional trips of the non-safety related screen wash pumps. EAL 8.4.3
requires the declaration of a UE if service water bay level drops to 4 feet 5 inches below
mean sea level. In response to the low water conditions, the operators improvised a
means to measure the service water bay level and determined that the UE criteria had
not been met. The inspectors discussed the availability of instrumentation for
assessment of the UE entry criteria with IP operations and emergency planning staff,
reviewed relevant plant procedures, and performed a walkdown of the intake structure.
The inspectors determined that Entergy had no established means of indication or
instrumentation for operators to assess the service water bay level and evaluate the
associated entry criteria of EAL 8.4.3. Upon further review,
Analysis: The performance deficiency is that no established means of indication or
procedures were readily available for operators to determine if the service water bay
level met the threshold declaration of an UE described in EAL 8.4.3. The failure to
provide adequate indication for assessment of EAL entry criteria could impact the timely
declaration of an emergency and is contrary to 10 CFR 50.54(q) and 50.47(b)(4). This
finding is greater than minor because it was associated with the Emergency
Enclosure
19
Preparedness (EP) cornerstone attribute of Facilities and Equipment, and affected the
cornerstone objective of ensuring that a licensee is capable of implementing adequate
measures to protect the health and safety of the public in the event of a radiological
emergency. This finding was evaluated using Inspection Manual Chapter 0609,
Appendix B, Emergency Preparedness Significance Determination Process, Sheet 1,
Failure to Comply. This finding is associated with a failure to meet or implement a
regulatory requirement. The deficiency is not greater than Green because it did not
result in the Risk-Significant Planning Standard Function being lost or degraded.
Section 4.4 of Manual Chapter 0609, Appendix B, provides examples for use in
assessing emergency preparedness related findings. One example of a Green finding
states, The EAL classification process would not declare any Alert or Notification of
Unusual Event that should be declared. Since the declaration of an UE based on low
service water bay level could have been missed or delayed, this finding was considered
consistent with the example provided and was therefore determined to be of very low
safety significance (Green).
Enforcement: 10 CFR 50.54(q) requires that the facility licensee follow and maintain in
effect emergency plans which meet the standards in 10 CFR 50.47(b). 10 CFR
50.47(b)(4) requires, in part, that emergency response plans include a standard
emergency classification and action level scheme, the bases of which include facility
system and effluent parameters. The emergency classification and action level scheme
is required to be used by the nuclear facility licensee, and State and local response
plans rely on information provided by facility licensees for determinations of minimum
initial offsite response measures. Contrary to the above, prior to November 2005,
Entergy did not have adequate means of indication or procedures to support an EAL
classification based on service water bay intake level. Entergy entered this issue into its
CAP as CR-IP3-2005-5380 and installed temporary level indication pending the
development of permanent corrective actions. Because this issue is of very low safety
significance and has been entered into Entergy's CAP, it is being treated as an NCV
consistent with Section VI.A.1 of the NRC Enforcement Policy: NCV 05000247/2005-
05-05, Inadequate Equipment to Assess Threshold for Emergency Action Level
8.4.3.
.2 Emergency Plan Change Review
a. Inspection Scope
Prior to this inspection, the NRC had received and acknowledged the changes made to
the Indian Point Emergency Plan and implementing procedures. These changes were
made in accordance with 10 CFR 50.54(q), which Entergy had determined did not result
in a decrease in effectiveness to the Plan and concluded that the changes continued to
meet the requirements of 10 CFR 50.47(b) and Appendix E of 10 CFR 50. During this
inspection, the inspectors conducted a sampling review of the changes which could
potentially result in a decrease in effectiveness. This review does not constitute an
approval of the changes and, as such, the changes are subject to future NRC
inspection. The inspection was conducted in accordance with NRC Inspection
Enclosure
20
Procedure 71114, Attachment 4. The requirements in 10 CFR 50.54(q) were used as
reference criteria.
b. Findings
No findings of significance were identified.
1EP5 Correction of Emergency Preparedness Weaknesses and Deficiencies
a. Inspection Scope (71114.05 - 1 Sample)
The inspectors reviewed CRs initiated by Indian Point from drills, self-assessments, and
audits, and the associated corrective actions to determine the significance of the issues
and to determine if repeat problems were occurring. A list of the CRs reviewed are
contained in the attachment to this report. Also, the 2004 and 2005 audit reports were
reviewed to assess Indian Points ability to identify issues, assess repetitive issues, and
evaluate the effectiveness of corrective actions through their independent audit process.
This inspection was conducted according to NRC Inspection Procedure 71114,
Attachment 05. Planning standard 10 CFR 50.47(b)(14) and the related requirements of
10 CFR 50, Appendix E were used as reference criteria.
b. Findings
No findings of significance were identified.
1EP6 Drill Evaluation
a. Inspection Scope
The inspectors observed an EP drill conducted on November 30. The inspectors used
NRC Inspection Procedure 71114.06, Drill Evaluation, as guidance and criteria for
evaluation of the drill. The drill consisted of an Emergency Notification Siren test and
Emergency Response Organization Drill. The inspectors observed the drill and
conducted reviews from the Indian Point Emergency Operations Facility (EOF). The
inspectors focused the reviews on the identification of weaknesses and deficiencies in
the classification and notification timeliness and quality and accountability of essential
personnel during the drill. The inspectors were briefed on Entergys critique results and
compared the NRC-identified weaknesses and deficiencies to those identified by
Entergy to ensure that problem areas were properly identified. Inspection of this EP Drill
constitutes one inspection sample.
b. Findings
No findings of significance were identified.
Enclosure
21
4. OTHER ACTIVITIES
4OA1 Performance Indicator Verification
.1 Occupational Exposure Control Effectiveness
a. Inspection Scope (71151 - 1 sample)
The inspector reviewed implementation of Entergys Occupational Exposure Control
Effectiveness Performance Indicator (PI) Program. Specifically, the inspector reviewed
CRs, and radiological controlled area dosimeter exit logs for the past four calendar
quarters. These records were reviewed for occurrences involving locked high radiation
areas, very high radiation areas, and unplanned exposures against the criteria specified
in Nuclear Energy Institute (NEI) 99-02, Regulatory Assessment Performance Indicator
Guideline, Revision 2, to verify that all occurrences that met the NEI criteria were
identified and reported as performance indicators. This inspection activity represents
the completion of one sample relative to this inspection area, completing the annual
inspection requirement.
b. Findings
No findings of significance were identified.
.2 RETS/ODCM Radiological Effluent Occurrences
a. Inspection Scope (71122.01 - 1 Sample)
The inspector reviewed a listing of relevant effluent release reports for the past four
calendar quarters, for issues related to the public radiation safety PI, which measures
radiological effluent release occurrences per site that exceed 1.5 mrem/quarter whole
body or 5.0 mrem/quarter organ dose for liquid effluents, 5 mrad/quarter gamma air
dose, 10 mrad/quarter beta air dose, and 7.5 mrads/quarter for organ dose for gaseous
effluents. This inspection activity represents the completion of one sample relative to
this inspection area, completing the annual inspection requirement.
The inspector reviewed the following documents to ensure Entergy met all requirements
of the performance indicator:
- monthly projected dose assessment results due to radioactive liquid and
gaseous effluent releases;
- quarterly projected dose assessment results due to radioactive liquid and
gaseous effluent releases; and
- dose assessment procedures.
b. Findings
No findings of significance were identified.
Enclosure
22
a. Inspection Scope (71151 - 3 Samples)
The inspectors reviewed Entergys procedure for developing the data for the EP PIs
which are: (1) Drill and Exercise Performance (DEP), (2) ERO Drill Participation, and
(3) ANS Reliability. The inspectors also reviewed Entergys drill and exercise reports,
training records, and ANS testing data to verify the accuracy of the reported data. Data
generated since the June 2004 EP PI verification was reviewed during this inspection.
Therefore, data submitted from the second quarter of 2004 through the end of the third
quarter of 2005 were reviewed. The review was conducted in accordance with NRC
Inspection Procedure 71151. The acceptance criteria used for the review were 10 CFR
50.9 and NEI 99-02, Revision 3, Regulation Assessment Performance Indicator
Guideline.
d. Findings
No findings of significance were identified.
4OA2 Identification and Resolution of Problems
.1 Daily Review
a. Inspection Scope (71152)
As required by Inspection Procedure 71152, Identification and Resolution of Problems,
and in order to help identify repetitive failures or specific human performance issues for
follow-up, the inspectors screened all items entered into Entergys corrective action
program. This review was accomplished by reviewing copies each condition report
(CR).
b. Findings
No findings of significance were identified.
.2 Semi-annual Trend Review
a. Inspection Scope (71152 - 1 sample)
The inspectors performed a semi-annual review to identify trends that might indicate the
existence of a more significant safety issue. The inspectors included in this review
repetitive or closely related issues that may have been documented by Entergy outside
of the normal CAP, such as trend reports, PIs, major equipment problem lists,
maintenance rework lists, departmental challenges, system health reports, maintenance
rule assessments, and maintenance and CAP backlogs.
Enclosure
23
The inspectors reviewed Entergys CAP database during 2005 in order to assess the
total number and significance of CRs written in various subject areas such as equipment
or processes, and to discern any notable trends in these areas. The CRs entered into
the CAP in all quarters included those written as a result of NRC findings. This semi-
annual review represented one inspection sample.
b. Findings
No findings of significance were identified.
.3 Identification and Resolution of Problems - Emergency Preparedness
a. Inspection Scope (71152 - 2 samples)
The inspectors reviewed Entergys corrective actions for recent problems associated
with components used to actuate the siren system. These problems included
malfunctions of the frame relay telephone network that connects the county actuation
points with the siren system (primary actuation method) and problems associated with
the radio system (back-up actuation method). The inspectors reviewed CR evaluations
and associated root or apparent cause reports, and interviewed licensee and contractor
personnel responsible for maintenance of the siren system and the corrective action
program. The inspection was conducted per NRC Inspection Procedure 71152. The
applicable emergency preparedness planning standards, 10 CFR 50.47(b) and the
requirements of 10 CFR 50 Appendix E were used as reference criteria.
Introduction: The inspectors identified a Green finding for a failure to implement timely
corrective actions for multiple frame relay system problems.
Description: While reviewing documentation pertaining to an August 5, 2005, frame
relay problem, the inspectors noted nine condition reports referenced in Entergys higher
tier apparent cause (CR-IP2-2005-3345) for various frame relay problems dating back to
September 23, 2003. Following the inspection, Entergy identified an additional 13 CRs
pertaining to frame relay issues, the oldest going back to March 21, 2003. The
inspectors found that the evaluation and corrective actions described in CR IP2-2005-
3345 following the August 5, 2005, frame relay system failure to be appropriate.
Entergys corrective action program, as described in procedure, EN-LI-102, Corrective
Action Process, Revision 3, groups CRs into significance categories. Category C and
D issues can be closed by fixing the immediate problem or by confirming that the
condition has been corrected. Category B CRs require an apparent cause evaluation be
conducted to address the apparent causes for the failures. The inspectors noted that
the nine frame relays system CRs, referenced in CR-IP2-2005-3345, had been
characterized as Category C or D. The inspectors also noted that Entergy had not
performed any type of apparent cause evaluation to identify the underlying causes
and to prevent recurrence of these repeat unplanned frame relay system outages.
Enclosure
24
Entergy disagreed with the characterization of this finding and stated that the frame
relay system availability had improved during the period and also that there was no
identified connection between the frame relay problems dating back to 2003 and the
corrective actions identified in the recent apparent cause evaluation (CR IP2-2005-
3345). The inspectors considered this information and concluded that Entergy should
have acted in a more timely manner to identify and correct the underlying causal factors
that led to the earlier frame relay system outages. The failure to implement a timely and
thorough evaluation of these failures adversely impacted the reliability of the frame relay
system.
Analysis: The performance deficiency involved the failure to implement timely corrective
actions to prevent repeat unplanned failures of the frame relay system. This finding was
determined to be more than minor because the finding is associated with the EP
cornerstone attribute of Facilities and Equipment (alert and notification system
availability). It affected the cornerstone objective of ensuring that Entergy is capable of
implementing adequate measures to protect the health and safety of the public in the
event of a radiological emergency. This finding is not suitable for Significance
Determination Process evaluation but has been reviewed by NRC management and is
determined to be a finding of very low safety significance. This issue is not greater than
Green because of the short periods that the frame relay system was unavailable and
because the ANS design included a secondary method (i.e., back-up radio system).
This finding was associated with the Problem Identification and Resolution cross-cutting
area because it was related to Entergys failure to implement timely corrective actions
for reliability issues with the frame relay system.
Enforcement: No violation of regulatory requirements occurred. This finding of very low
significance was entered into Entergys corrective action process (CR-IP2-2005-4475).
FIN 05000247/2005-05-06; Inadequate Corrective Actions for Frame Relay System
Problems.
Introduction: An NCV of 10 CFR 50.72(b)(3)(xiii) was identified for not formally reporting
a siren system problem that occurred on August 5, 2005.
Description: At about 0830 on August 5, 2005, Entergy identified a frame relay system
problem that prevented use of the primary siren system actuation method from the
Putnam County warning point. Entergy contacted the vendor to correct this condition.
At about 1200, Entergy noted that the frame relay system, used to provide the primary
siren system actuation method for all four counties located in the Indian Point
emergency planning zone, was out of service. Entergy again contacted the vendor to
effect repairs and learned that the entire frame relay system had been inoperable since
approximately 0901. Entergy checked the back-up radio activation system for each of
the four counties at about 1200 and identified that the radio activation system for
Westchester County was non-functional. The back-up radio system for the remaining
three counties had remained functional. The frame relay system for all four counties
was restored at about 1435 and the back-up radio system for Westchester County was
restored by 1820. The inspectors determined that the primary and back-up systems
Enclosure
25
relied upon to actuate the sirens in Westchester County had been non-functional from
about 0900 to 1435 (approximately five and one-half hours).
Entergy reported that the counties were informed regarding the above actuation system
problems and the NRC was also informally notified regarding the above actuation
system problems. The inspectors questioned why Entergy did not formally report the
problem associated with actuation of the Westchester County sirens per 10 CFR 50.72.
Entergy indicated that formal reporting of this problem was not required since manual
actuation from the Indian Point emergency operations facility was available to actuate
the sirens upon a request by the County. The inspectors reviewed the procedures,
protocols, and practices that would have been relied upon to implement this alternate
manual siren actuation method at the time of the loss of the normal and back-up siren
actuation methods for Westchester County and noted that they were not described in
any formal procedure or documentation. The inspectors also questioned how Entergy
had practiced or demonstrated the manual notification method and were informed that
the manual actuation method was attempted during a practice exercise in 2004.
Entergy documented (CR IP2-2005-3245) several problems associated with the manual
activation method including the lack of formal guidance and protocol for Indian Point and
County emergency response staff. Subsequent to this event, Entergy implemented
appropriate corrective actions to address the identified manual actuation system
problems.
The inspectors reviewed the process for manual actuation of the sirens and considered
that successful actuation would have involved a series of tasks including identification of
an actuation problem and effective interaction with county representatives to obtain
direction and permission to actuate the sirens. The inspectors reviewed NUREG-1022
which provided guidance for reportabilty under 10 CFR 50.72, and noted that Entergy
could refrain from reporting emergency notification system problems based upon, the
existence of procedures or practices to compensate for the lost emergency sirens. The
inspectors determined that Entergy should have reported the Westchester County siren
system actuation problem per 10 CFR 50.72 based on the lack of formal procedures for
using the manual actuation method and also based on the limited experience and
practices where Entergy had demonstrated use of this method. Entergy disagreed with
this conclusion and indicated that the manual actuation method should be considered a
practice as described in NUREG-1022. The inspectors, in coordination with specialists
from the Office of Nuclear Reactor Regulation and from the Office of Nuclear Security
and Incident Response, reviewed Entergys position and concluded that Entergy should
have formally reported the siren system problem for the Westchester County sirens per
Analysis: The performance deficiency involved the failure to formally notify the NRC
regarding a siren system actuation problem as required by 10 CFR 50.72. This
deficiency was evaluated using the traditional enforcement process since the failure to
make a required report could adversely impact the NRCs ability to carry out its
regulatory mission.
Enclosure
26
While reviewing this finding, the inspectors considered the short duration of the siren
system problem, the fact that the NRC was informally notified, that back-up route
alerting was available, and also that the capability to actuate the sirens via the manual
siren initiation method was not lost. The inspectors also noted that subsequent to this
event Entergy implemented corrective actions to formalize the manual siren system
actuation method as described in CR IP2-2005-3245. The inspectors considered the
above and evaluated the severity of this violation using the criteria contained in
Supplement I - Reactor Operations and Section VI.A.1 of the NRCs Enforcement Policy
and determined that this finding met the criteria for disposition as a non-cited violation.
Enforcement: 10 CFR 50.72(b)(3)(xiii) requires that problems associated with operation
of the off-site notification system be reported to the NRC. Contrary to the above, on
August 5, 2005, Entergy did not formally report a problem that affected the primary and
back-up actuation systems for the sirens located in Westchester County. This is a
violation of 10 CFR 50.72(b)(3)(xiii). Because this finding met the criteria contained in
Section VI.A.1 of the NRCs Enforcement Policy, it is being dispositioned as a non-cited
violation. NCV 05000247/2005-05-07; Failure to Make a 10 CFR 50.72(b)(3)(xiii)
Notification.
.4 PI&R Annual Sample - Fire Brigade
a. Inspection Scope (71152 - 1 sample)
The inspector reviewed CRs pertaining to the fire brigade which were generated during
calender year 2005. The inspector also reviewed procedures controlling fire brigade
activities, reviewed fire brigade drill reports and attendance sheets, and discussed fire
brigade performance with the Site Fire Protection Engineer to determine whether
Entergy was identifying areas for improvement and entering them into the corrective
action program.
b. Findings and Observations
No findings were identified. During calender year 2005, Indian Point generated 65 CRs
related to fire brigade activities. Issues included equipment, manning, drill response
times, and access through locked doors on-site, among others. Fire brigade response
times were noted to be outside the administrative requirements on several drills, from
several areas both within and outside the protected area. Fire protection personnel are
monitoring response times for each brigade member, and recording both the response
time and the area of the plant from which the individual responded. This effort was
intended to continue through the end of the year when results were to be evaluated for
additional enhancements. Actions taken to date include having operators outside the
protected area taking logs remain in direct contact with the control room, providing a
company vehicle to operators leaving the protected area on assigned duties, and having
the brigade member pre-stage personnel protective equipment near the security access
point. Assigned fire brigade members are prohibited from attending training outside the
protected area.
Enclosure
27
Several instances were identified where fire brigade members were unable to enter
areas of the facility to respond to alarms due to locked doors. This delayed response to
smoke detector alarms on more than one occasion. When problems were identified,
actions were taken to provide appropriate keys or keycards to the brigade. In the event
of an actual fire, the brigade could use the available forcible entry tools to gain access.
On those occasions where deficiencies were identified with regard to fire brigade
equipment, actions were implemented to restore the inventory and condition of
equipment to that required.
4OA4 Cross-Cutting Aspects of Findings
Section 1R13 describes a finding related to improper implementation of a temporary
alteration on a safety-related component that had a cross-cutting aspect in the area of
human performance. Specifically, maintenance personnel exceeded the maximum
allowable material removal allowed by the modification package while grinding the cap
screw heads on FCV-447.
Section 1R13 describes a finding related to a work control procedure which
inappropriately allowed a modification to be implemented on a safety-related component
prior to the completion of an adequate evaluation. This finding had a cross-cutting
aspect in the area of human performance because the decision to implement the
modification was based on inappropriate procedural guidance.
Section 4AO2 describes a finding related to Entergys failure to take timely corrective
actions for a series of problems with the frame relay portion of the alert and notification
system. This finding had a cross-cutting aspect in the area of problem identification and
resolution because Entergy properly evaluate a problem with the ANS system, and as a
result did not take timely and effective corrective actions.
4OA6 Meetings, including Exit
Exit Meeting Summary
On January 11, 2006, the inspectors presented the inspection results to Mr. P. Rubin
and other Entergy staff members, who acknowledged the inspection results presented.
The inspectors asked Entergy what materials examined during the inspection should be
considered proprietary. No proprietary information is presented in this report.
ATTACHMENT: SUPPLEMENTAL INFORMATION
Enclosure
A-1
SUPPLEMENTAL INFORMATION
KEY POINTS OF CONTACT
Licensee Personnel
F. Dacimo Site Vice President
P. Rubin Plant Manager
J. Comiotes Director, Nuclear Safety Assurance
A. Vitale Site Operations Manager
T. Barry Security Manager
P. Conroy Manager, Licensing
R. DeCensi Technical Support Manager
F. Inzirillo Emergency Planning Manager
S. Petrosi Manager, Design Engineering
J. Ventosa Engineering Manager
C. Wend Radiation Protection Manager
T. Orlando Systems Engineering Manager
D. Mayer Unit 1 Project Manager
G. Hinrichs Project manager
J. Tuohy Manager, Cable Separation Program Improvements
J. Baker Shift Manager
P. Studley Shift Manager
H. Santis Project Construction Manager
G. Schwartz ISFSI Project Manager
G. Dean Assistant Operations Manager - Training
R. Drake Supervisor, Mechanical Design Engineering
V. Andreozzi Systems Engineering Electrical Systems Supervisor
D. Gately Assistant Radiation Protection Superintendent
M. Sicard I&C Superintendent
L. Lee Systems Engineering Primary Systems Supervisor
J. Raffaele Supervisor, Electrical Design Engineering
E. Anderson Lead Engineer, Cable Separation Program Improvements
T. Beasley System Engineer
C. Bergeren In-Service Testing Engineer
J, Bretti System Engineer
T. Chan System Engineer
G. Dahl Technical Specialist, Licensing
R. Daley System Engineer
T. Foley System Engineer
D. Friedle System Engineer
M. Johnson System Engineer
T. Jones Nuclear Safety/Licensing Specialist, Licensing
T. Lowe System Engineer
W. Mahlmeister Technical Lead, Cable Separation Program Improvements
B. Meek System Engineer
P. Peloquin Project Engineer
Attachment
A-2
B. Rokes Licensing Engineer
J. Skonieczny Project Engineer
D. Smith Scheduling and Work Order Coordinator
A. Stewart Licensing
R. Sutton System Engineer
S. Wilkie System Engineer
LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED
Opened
05000247/2005005-01 URI Emergency Diesel Generator Building Flooding
(Section 1R06)
Opened and Closed
05000247/2005005-02 FIN Failure to Maintain Design Control of Control Rod
Drive Mechanism Fans (Section 1R12)05000247/2005005-03 NCV Failure to Follow Procedural Requirements During
Modification of a Safety-Related Valve (Section
1R13)05000247/2005005-04 NCV Inadequate Procedure for Control of Work on
Safety-Related Components (Section 1R13)05000247/2005005-05 NCV Inadequate Equipment to Assess Threshold for
Emergency Action Level 8.4.3. (Section 1EP4)05000247/2005005-06 FIN Inadequate Corrective Actions for Frame Relay
System Problems05000247/2005005-07 NCV Failure to Make a 10 CFR 50.72(b)(3)(xiii)
Notification
LIST OF DOCUMENTS REVIEWED
Section 1R01: Adverse Weather Protection
Procedures
OAP-008, Severe Weather Preparations, Revision 0
2-SOP-20.2, Condensate System Operation, Revision 40
2-SOP-11.5, Space Heating and Winterization, Revision 31
OAP-048, Seasonal Weather Preparations, Revision 2
Attachment
A-3
SOP-30.1, Electric Heat Trace System, Revision 24
Condition Reports
IP2-03-02655 IP2-04-06749 IP2-05-04130
IP2-04-06700 IP2-05-00378 IP2-05-04667
Work Orders
IP2-03-20868 IP2-03-21069 IP2-04-24084
IP2-03-21054 IP2-03-21591 IP2-04-24091
Section 1R04: Equipment Alignment
Procedures
2-AOP-CCW-1, Loss of Component Cooling Water, Revision 1
2-COL-27.3.1, Diesel Generators, Revision 25
2-SOP-4.1.2, Component Cooling System Operation, Revision 29
2-COL-31.3, Gas Turbine 3, Revision 6
Condition Reports
IP2-04-00213 IP2-04-01706 IP2-05-01179
IP2-04-01328 IP2-05-00541
Drawings
9321-F-2028-36, Jacket Water to Diesel Generators, Revision 1
9321-H-2029-49, Starting Air to Diesel Generators, Revision 11
9321-F-2030-39, Fuel Oil to Diesel Generators, Revision 39
302775-04, Fuel Oil System Flow Diagram
304122-05, Fuel Forwarding System Flow Diagram
UFSAR Figure 9.3-1, Auxiliary Coolant System - Flow Diagram Sheet 1, Revision 17B
UFSAR Figure 9.3-1, Auxiliary Coolant System - Flow Diagram Sheet 2, Revision 17B
UFSAR Figure 9.3-1, Auxiliary Coolant System - Flow Diagram Sheet 3, Revision 1
Miscellaneous
CCWS DBD, Design Bases Document for the Component Cooling Water System, Revision 0
Section 1R05: Fire Protection
Procedures
PFP-207, General Floor Plan - Primary Auxiliary Building, Revision 0
Attachment
A-4
PFP-209, Component Cooling Pump Room - Primary Auxiliary Building, Revision 0
PFP-255D, Boiler Feed Pumps - Turbine Building, Revision 0
PFP-252, Cable Spreading Room - Control Building, Revision 0
PFP-211, General Floor Plan - Primary Auxiliary Building, Revision 0
Section 1R06: Flood Protection Measures
Condition Reports
IP2-03-04868 IP2-05-00543 IP2-05-04686
Miscellaneous
IPEEE (1995) Section 5, Internal Flooding
IP2 PSA Section 4.7, Internal Flooding Analysis
Section 1R07: Heat Sink Performance
Calculations
PGI-00089-00, 22 Instrument Air Closed Cooling Heat Exchanger Performance, Revision 0
PGI-00090-00, 21 Instrument Air Closed Cooling Heat Exchanger Performance, Revision 0
Condition Reports
Heat Exchanger Test Reports
Report 21-87, Eddy Current Inspection Results for 21 Instrument Air Closed Cooling Heat
Exchanger, June 8, 2004
Report 21-106, Eddy Current Inspection Results for 22 Instrument Air Closed Cooling Heat
Exchanger, February 14, 2005
SE-330, Attachment III, Heat Exchanger Inspection Report for 22 Instrument Air Closed
Cooling Water Heat Exchanger, February 14, 2005
Miscellaneous
Indian Point Response to Generic Letter 89-13, Service Water System Problems Affecting
Safety-Related Equipment, February 2, 1990
Indian Point 2 Maintenance Rule Basis Document - Instrument Air Closed Cooling Water
Work Orders
IP2-03-11687
Attachment
A-5
Section 1R11: Operator Requalification
Miscellaneous
Lesson Plan IP2LPLORAOP003, Safe Shutdown/ Control Room Inaccessibility Review and
Drill
Section 1R12: Maintenance Effectiveness
Maintenance Rule (A)(1) Evaluations
Maintenance Rule Action Plan, Gas Turbine Reliability, Revision 6
Maintenance Rule Action Plan, Control Room HVAC System
Maintenance Rule Action Plan, Component Cooling Water System
Maintenance Rule Action Plan, Vapor Containment System, July 2005
Maintenance Rule Action Plan, Rod Control System
Maintenance Rule Action Plan, CVCS System, June 2005
Maintenance Rule Action Plan, IP2 and IP3 Structural Monitoring Program
Maintenance Rule Basis Documents
Maintenance Rule SSC Basis Document:: Auxiliary Feedwater System, Revision 4
Maintenance Rule SSC Basis Document:: Chemical and Volume Control System, Revision 2
Maintenance Rule SSC Basis Document:: Nuclear Instrumentation System
Maintenance Rule SSC Basis Document:: Control Rod Drive System
Maintenance Rule SSC Basis Document:: 345 kV Electrical System
Maintenance Rule SSC Basis Document:: Emergency Lighting System
Maintenance Rule SSC Basis Document:: Heating, Ventilation, and Air Conditioning, Revision 2
Maintenance Rule SSC Basis Document:: Control Rod Drive Fans, Revision 2
Maintenance Rule SSC Basis Document:: Component Cooling Water System, Revision
Administrative Documents
ENN-DC-121, Maintenance Rule, Revision 2
ENN-DC-171, Maintenance Rule Monitoring, Revision 2
ENN-DC-172, Maintenance Rule (a)(3) Periodic Assessment, Revision 0
ENN-MS-S-008, ENN Engineering Standard - Action Plans, Revision 0
IP3-LO-2005-00208, Maintenance Rule Periodic Assessment, June 2005
IP-SMM-WM-100, Work Control Process, Revision 4
Condition Reports
IP2-03-06179 IP2-04-03669 IP2-05-00794
IP2-03-07485 IP2-04-04366 IP2-05-01101
IP2-04-02334 IP2-05-00211 IP2-05-01350
IP2-04-02668 IP2-05-00212 IP2-05-01402
IP2-04-02668 IP2-05-00568 IP2-05-01662
Attachment
A-6
IP2-05-01691 IP2-05-02210 IP2-05-03670
IP2-05-01691 IP2-05-02717 IP2-05-04580
IP2-05-01884 IP2-05-02729 IP2-05-04704
IP2-05-01908 IP2-05-03018 IP2-05-04744
IP2-05-01944 IP2-05-03206
Miscellaneous
ES-0.2 Deviation, Natural Circulation Cooldown, Revision 17
Indian Point Energy Center Maintenance Rule Program Quarterly Report second Quarter 2005
Shulz Electric Motor Failure Report, Q-9993
Maintenance Rule Expert Panel Meeting #2005-03 Minutes, May 9, 2005
Maintenance Rule Expert Panel Meeting #2005-04 Minutes, May 23, 2005
IPEC Maintenance Rule Program Quarterly Report, First Quarter 2005
IPEC Maintenance Rule Program Quarterly Report, Second Quarter 2005
IPEC Maintenance Rule Program Quarterly Report, Fourth Quarter 2005
Top Ten Technical Issue - IPEC NI System Reliability, Revision 5, May 2005
Top Ten Equipment Reliability Action Plan - Control Rod Drive System
Performance Criteria/Goal Evaluation - 345 kV System
System Health Reports
Auxiliary Feedwater System Health Report, Third Quarter 2005
CVCS System Health Report, Third Quarter 2005
Control Rod Drive Annual System Health Report, 2004
345 kV Annual System Health Report, 2004
Control Room HVAC System Health Report, Third Quarter 2005
Component Cooling Water System, First Quarter 2004
Component Cooling Water System, Second Quarter 2004
Component Cooling Water System, Fourth Quarter 2004
Component Cooling Water System, Second Quarter 2005
Component Cooling Water System, Third Quarter 2005
HVAC Annual Report, June 2004 to June 2005
Section 1R13: Maintenance Risk Assessment and Emergent Work Control
Work Orders
Calculations
1487203-C-003, Assessment of Actuator Bolting with Shaved Cap Screw Heads
IP3-Calc-FW-02760, Allowable Margin for Cap Screw Grinding
FPX-00281-00, Nitrogen Supply Capacity Requirement of an Accumulator for Power-Operated
Relief Valves PCV-455C and PCV456, Revision 0
Attachment
A-7
Condition Reports:
IP2-05-03847 IP2-05-04544 IP2-05-04671
IP2-05-04137 IP2-05-04615 IP2-05-04926
IP2-05-04354 IP2-05-04666 IP2-05-04979
IP2-05-04408
Miscellaneous
Operators Daily Risk Report 10/28/05
IEEE Standard C37.106-2003, Guide for Abnormal Frequency Protection for Power Generating
Plants
Westinghouse I.L. 14429-A, Instructions of A/200 Series Mechanical Interlocks
Regulatory Guide 1.33, Quality Assurance Program Requirements, Revision 2
TA-05-2-107, Grind the socket head cap screws to facilitate packing adjustment
Procedures
2-ARP-SKF, Bearing Monitor, Revision 23
EN-WM-100, Work Request Generation, Screening and Classification, Revision 0
0-VLV-416-AOV, Copes-Vulcan Steam Generator Feedwater Regulating Valve Maintenance,
Revision 1
Drawings
A225103-08, Logic Diagram Steam Generator Trip Signals
D252556-4, Flow & Pressure Channel 1 (SG #22)
Section 1R14: Non-Routine Events
Procedures
2-TOP-006, Permanent Tave Increase to 565F, Revision 0
OAP-030, Infrequently Performed Tests and Evolutions, Revision 0
2-POP-1.3, Plant Startup, Mode 2 to Mode 1, Revision 69
2-POP-3.1, Plant Shutdown, Mode 1 to Mode 3, Revision 47
2-SOP-26.4, Turbine Generator Startup, Synchronizing, Voltage Control and Shutdown,
Revision 48
2-ARP-SCF, Condensate and Boiler Feed, Revision 35
2-ARP-SAF, Reactor Coolant System, Revision 34
Miscellaneous
IP-EP-AD13 Attachment 2, EAL Technical Bases, Revision 2
Operator Logs November 30, 2005
Operator Logs December 22-23, 2005
Attachment
A-8
Section 1R15: Operability Evaluations
Calculations
IP-CALC-05-00951, Evaluation of an Increase in SG Feedwater Regulating Valve Stroke Time
Revision 0
CN-CRA-02-38, Indian Point 2 Steamline Break Inside Containment with Feedwater Valve
Failure, Revision 0
CN-CRA-03-20, Indian Point 2 Steamline Break Inside Containment Analysis for Stretch Power
Uprate, Revision 0`
Condition Reports
IP2-04-01075 IP2-05-04246 IP2-05-04642
IP2-04-06818 IP2-05-04414 IP2-05-04792
IP2-04-06837
Drawings
A235296, Flow Diagram - Safety Injection System, Revision 65
B206909-5, Inservice Inspection Isometric of Safety Injection Line 361 - Inside Containment
(Sheet 1 of 2) (RHR Return), November 21, 1975
D252680, EDGs Jacket Water and Lube Oil Coolers Cooling Water System, Revision 4
Miscellaneous
10 CFR 50.59 Evaluation EVL-IP2-05-26384, Operation of Feedwater Bypass BFD-90 Series
and 417L Series Valves at Stretch Uprate Power, Revision 0
UFSAR Section 14.2.5, Rupture of a Steam Pipe, Revision 17
IP2-RPT-05-00112, Outside VC Cable Tray Walkdown Summary
Procedures
2-PT-M108, RHR/SI System Venting, Revision 2
2-PT-Q013, Inservice Valve Tests, Revision 36
Work Orders
Section 1R19: Post Maintenance Testing
Condition Reports
IP2-03-05294 IP2-05-04125 IP2-05-04138
IP2-04-06150 IP2-05-04137 IP2-05-04795
Attachment
A-9
Work Orders
IP2-04-12427 IP2-05-02522 IP2-05-25316
IP2-04-35956 IP2-05-20640 IP2-05-26680
IP2-05-02517 IP2-05-21932 IP2-05-27328
IP2-05-02521
Drawings
IP2-S-000221-01, RHR Pump Suction from Containment Pump Vaive-MOV 885A
9321-F-3006-92, Single Line Diagram 480V MCC 26A and 26B
Miscellaneous
IEEE Std 43-2000, Recommended Practice for Testing Insulation Resistance of Rotating
Machinery
Procedures
2-PT-Q013-DS249, Valve PCV1135 IST Data Sheet, Revision 24
2-PT-Q026D, 24 Service Water Pump, Revision 8
2-PT-Q030A, 21 Component Cooling Water Pump, Revision 12
BAT-C-001-A, Replacement of Battery Cells, Revision 8
PT-A35C, 23 Station Battery Intercell Resistance Checks, Revision 1
PT-Q17E, Alternate Safe Shutdown Supply Verification to 24 SWP, Revision 8
PMP-006-CVCS, Replacement of Fluid Cylinder Valves - Union QX-300 Charging Pump,
Revision 6
PT-Q33A, 21 Charging Pump, Revision 9
PT-Q68A, 21 Charging Pump Check Valves, Revision 3
2-PT-Q026E, 25 Service Water Pump, Revision 9
2-PT-Q013, Inservice Valve Tests, Revision 36
Section 1R22: Surveillance Testing
Procedures
2-PT-SA067, Main Turbine Stop and Control Valves, Revision 1
2-PT-M021A, Emergency Diesel Generator 21 Load Test, Revision 14
2-SOP-27.3.1.1, 21 Emergency Diesel Generator Manual Operation, Revision 13
PI-3Y2A, Inservice Inspection Pressure Tests - 23 AFP Suction & Discharge, Revision 1
Condition Reports
IP2-05-04504
Attachment
A-10
Drawings
UFSAR Figure 10.2-7, Flow Diagram Boiler Feedwater
Section 1R23: Temporary Alterations
Calculations
IP-CALC-05-1032, Evaluation of Leak Repair Injection for PCV-1135, 22 S/G Atmospheric
Relief, Revision 0
Condition Reports
Engineering Requests
IP2-05-27331-RS, Leak Repair on PCV-1135 Lubricator Nipple,
Procedures
0-LKR-401-GEN, Temporary On-Line Leak Repairs, Revision 0
ENN-ME-S-001, Attachment 7.3, Leak Repair Evaluation, Revision 0
Miscellaneous
10 CFR 50.59 Screening for PCV-1135 Leak Repair
Work Orders
Section 1EP4: Emergency Action Level (EAL) and Emergency Plan Changes
Procedures
IPEC-EP-AD-13, IPEC Emergency Plan Administrative Procedures, Revision 2
3-ARP-012, Panel SJF - Cooling Water and Air, Revision 44
3-AOP-SW-1, Service Water Malfunction, Revision 1
3-ARP-049, Panel Local - Intake Structure, Revision 1
Drawings
9321-F-20015, Screenwash Pump
9321-F-10113-8, Intake Structure Top Slab Plan
9321-F-10143-7, Intake Structure Miscellaneous Steel Details
Attachment
A-11
Condition Reports
IP3-05-05375 IP3-05-05388 IP3-05-05401
IP3-05-05380 IP3-05-05389
Calcalations
IP3-CALC-SWS-03622, Service Water Header Pressure
Section 4OA1: Performance Indicator Verification
Condition Reports
Section 4OA2: Problem Identification and Resolution
Procedures
IPEC Operations Night Orders, December 6, 2005
IP-SMM-TQ-122, Fire Protection Training Program, Revision 1
IP-SMM-DC-901, IPEC Fire Protection Program Plan, Revision 2
OAP-001, Conduct of Operations, Revision 8
OASL-15.21, Shift Manning Requirements, Revision 5
OASL-15.22, Fire Brigade Requirements, Revision 7
Condition Reports
IP2-2005-00429 IP2-2005-03999 IP3-2005-02763
IP2-2005-00530 IP2-2005-04033 IP3-2005-02776
IP2-2005-00584 IP2-2005-04257 IP3-2005-02912
IP2-2005-00808 IP2-2005-04282 IP3-2005-03081
IP2-2005-01763 IP2-2005-04546 IP3-2005-03882
IP2-2005-02555 IP2-2005-04606 IP3-2005-04138
IP2-2005-02700 IP2-2005-04760 IP3-2005-05047
IP2-2005-03308 IP3-2005-00471 IP3-2005-05060
IP2-2005-03319 IP3-2005-00675 IP3-2005-05231
IP2-2005-03354 IP3-2005-00744 IP3-2005-05620
IP2-2005-03448
Miscellaneous
Standing Order 05-02
Temporary Procedure Change 03-0229
LIST OF ACRONYMS
ABFP Auxiliary Boiler Feedwater Pump
ADAMS Agencywide Document Management System
AOP Abnormal Operating Procedure
CAP Corrective Action Program
Attachment
A-12
CCP Coolant Charging Pump
CCW Component Cooling Water
CFR Code of Federal Regulations
CR Condition Report
CRDM Control Rod Drive Mechanism
CST Condensate Storage Tank
EDG Emergency Diesel Generator
EOP Emergency Operating Procedure
ESW Emergency Service Water
FSAR Final Safety Analysis Report
GT Gas Turbine
IACCW Instrument Air Closed Cooling Water
IMC Inspection Manual Chapter
IP2 Indian Point 2
IP3 Indian Point 3
IPE Individual Plant Examination
IPEEE Individual Plant Examination of External Events
MR Maintenance Rule
NCV Non-Cited Violation
NEI Nuclear Energy Institute
NRC Nuclear Regulatory Commission
PARS Publically Available Records System
PI Performance Indicator
PSA Probabilistic Safety Assessement
PWST Primary Water Storage Tank
PWT Post Work Test
RG Regulatory Guide
RWP Radiation Work Permit
RWST Refueling Water Storage Tank
SDP Significance Determination Process
SFP Spent Fuel Pool
S/G Steam Generator
SI Safety Injection
SWP Service Water Pump
Tave Average Coolant Temperature
TRM Technical Requirements Manual
TS Technical Specification
URI Unresolved Item
WO Work Order
Attachment