10 CFR 54 June 15, 2005 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Mail Stop: OWFN P1-35 Washington, D.C. 20555-0001 Gentlemen:

In the Matter of

)

Docket Nos. 50-259 Tennessee Valley Authority

)

50-260 50-296 BROWNS FERRY NUCLEAR PLANT (BFN) - UNITS 1, 2, AND 3 -

LICENSE RENEWAL APPLICATION (LRA) - RESPONSE TO NRC REQUEST FOR ADDITIONAL INFORMATION ON CLARIFICATION FOR ITEM 2 OF RAI 2.3-2 AND RAI 2.3-3 (TAC NOS. MC1704, MC1705, AND MC1706)

By letter dated December 31, 2003, TVA submitted, for NRC review, an application pursuant to 10 CFR 54, to renew the operating licenses for the Browns Ferry Nuclear Plant, Units 1, 2, and 3. As part of its review of TVAs LRA, the NRC staff, through informal requests on March 21 and 22, 2005, identified additional information needed for clarification for Item 2 of RAI 2.3-2 and follow-up to RAI 2.4-14. By letter dated May 18, 2005 (Reference 1), TVA provided the additional information on clarification for Item 2 of RAI 2.3-2 and follow-up to RAI 2.4-14.

After review of this response, the NRC staff, through an informal request on June 2, 2005, requested that "Follow-up to RAI 2.4-14" be changed to "RAI 2.3-3" since this question and response was directly related to Section 2.3 of the LRA, "Scoping and Screening Results: Mechanical Systems.

U.S. Nuclear Regulatory Commission Page 2 June 15, 2005 The following changes to the May 18, 2005, TVA response address the NRCs request of June 2:

On the cover page of the letter, change Follow-up to RAI 2.4-14 to RAI 2.3-3 in two places.

On the cover page for Enclosure 1, change Follow-up to RAI 2.4-14 to RAI 2.3-3.

On page E-1, change Follow-up to RAI 2.4-14 to RAI 2.3-3 in three places.

On page E-2, change Follow-up to RAI 2.4-14 to RAI 2.3-3.

If you have any questions regarding this information, please contact Ken Brune, Browns Ferry License Renewal Project Manager, at (423) 751-8421.

I declare under penalty of perjury that the foregoing is true and correct. Executed on this 15th day of June, 2005.

Sincerely, Original signed by:

William D. Crouch Acting Manager of Licensing and Industry Affairs

Enclosure:

cc: See page 3 REFERENCES

1. T. E. Abney (TVA) to NRC letter dated May 18, 2005:

BROWNS FERRY NUCLEAR PLANT (BFN) - UNITS 1, 2, AND 3 -

LICENSE RENEWAL APPLICATION (LRA) - RESPONSE TO NRC REQUEST FOR ADDITIONAL INFORMATION ON CLARIFICATION OF ITEM 2 OF RAI 2.3-2 AND FOLLOW-UP TO RAI 2.4-14 (TAC NOS. MC1704, MC1705, AND MC1706)

U.S. Nuclear Regulatory Commission Page 3 June 15, 2005 Enclosure cc (Enclosure):

State Health Officer Alabama Department of Public Health RSA Tower - Administration Suite 1552 P.O. Box 303017 Montgomery, Alabama 36130-3017 Chairman Limestone County Commission 310 West Washington Street Athens, Alabama 35611 (Via NRC Electronic Distribution)

Enclosure cc (Enclosure):

U.S. Nuclear Regulatory Commission Region II Sam Nunn Atlanta Federal Center 61 Forsyth Street, SW, Suite 23T85 Atlanta, Georgia 30303-8931 Mr. Stephen J. Cahill, Branch Chief U.S. Nuclear Regulatory Commission Region II Sam Nunn Atlanta Federal Center 61 Forsyth Street, SW, Suite 23T85 Atlanta, Georgia 30303-8931 NRC Senior Resident Inspector Browns Ferry Nuclear Plant 10833 Shaw Road Athens, Alabama 35611-6970 NRC Unit 1 Restart Senior Resident Inspector Browns Ferry Nuclear Plant 10833 Shaw Road Athens, Alabama 35611-6970 cc: continued page 4

U.S. Nuclear Regulatory Commission Page 4 June 15, 2005 cc (Enclosure):

Margaret Chernoff, Project Manager U.S. Nuclear Regulatory Commission (MS 08G9)

One White Flint, North 11555 Rockville Pike Rockville, Maryland 20852-2739 Eva A. Brown, Project Manager U.S. Nuclear Regulatory Commission (MS 08G9)

One White Flint, North 11555 Rockville Pike Rockville, Maryland 20852-2739 Yoira K. Diaz-Sanabria, Project Manager U.S. Nuclear Regulatory Commission (MS 011F1)

One White Flint, North 11555 Rockville Pike Rockville, Maryland 20852-2739 Ramachandran Subbaratnam, Project Manager U.S. Nuclear Regulatory Commission (MS 011F1)

One White Flint, North 11555 Rockville Pike Rockville, Maryland 20852-2739

U.S. Nuclear Regulatory Commission Page 5 June 15, 2005 JEM:TLE:BAB Enclosure cc (Enclosure):

B. M. Aukland, POB 2C-BFN A. S. Bhatnagar, LP 6-C K. A. Brune, LP 4F-C J. C. Fornicola, LP 6A-C R. G. Jones, NAB 1A-BFN R. F. Marks, Jr., PAB 1A-BFN F. C. Mashburn, BR 4X-C N. M. Moon, LP 6A-C J. R. Rupert, NAB 1F-BFN K. W. Singer, LP 6A-C M. D. Skaggs, PAB 1E-BFN E. J. Vigluicci, ET 11A-K NSRB Support, LP 5M-C EDMS, WT CA-K s://Licensing/Lic/BFN LR Renumbering of RAI.doc