Letter Sequence Request |
|---|
|
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance...
- Supplement, Supplement, Supplement, Supplement
Results
- Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval
Other: ML040650206, ML040910016, ML041310015, ML041310029, ML041310206, ML041700505, ML041700523, ML041700550, ML041700572, ML041950508, ML041980222, ML042010388, ML042240255, ML042390497, ML042580327, ML042820624, ML042920201, ML042990519, ML043000040, ML050310428, ML050320137, ML051180046, ML051180464, ML051250308, ML051400190, ML051460418, ML052140646, ML052170406, ML052210484, ML052220070, ML052630075, ML053050358, ML060410288, ML060450582, ML060950060, ML061110094, ML061110102, ML061110126, ML061140182, ML061140209, ML061140322, ML061140352, ML061730464, ML091540582, ML091870509, ML11171A037, ML11171A038, ML11308A018
|
MONTHYEARML0336503552003-12-31031 December 2003 Forthcoming License Renewal Meeting Between the U.S. NRC Staff and the Nuclear Energy Institutes (Neis) License Renewal Working Group; Carolina Power and Light Company (Cp&L), for the H.B. Robinson Steam Electric Plant Project stage: Meeting ML0405102412004-02-19019 February 2004 January 28, 2004 Meeting Follow-Up - Additional Information Project stage: Meeting ML0406502062004-03-0404 March 2004 Determination of Acceptability and Sufficiency for Docketing and Opportunity for a Hearing Regarding the Application from Tennesssee Valley Authority for Renewal of the Operating Licenses for Browns Ferry, Units 1, 2 & 3 Project stage: Other ML0409100162004-03-31031 March 2004 Review Schedule for Application for Renewal of the Operating Licenses for the Browns Ferry Nuclear Plant, Units 1, 2 and 3 Project stage: Other ML0413100152004-05-0404 May 2004 Summary of Telephone Conferences on April 7, 2004, Between the U.S. Nuclear Regulatory Commission and the Tennessee Valley Authority Concerning Activities on Browns Ferry Nuclear Plant Units 1, 2 and 3, License Renewal Application Project stage: Other ML0413100292004-05-0606 May 2004 & 03/31/2004 Summary of Telephone Conferences with Tennesssee Valley Authority Concerning Activities on Browns Ferry Nuclear Plant, Units 1, 2 & 3 LRA Project stage: Other ML0413102062004-05-10010 May 2004 Summary of Telephone Conferences with Tennessee Valley Authority Concerning Activities on Browns Ferry Nuclear Plant, Units 1, 2 and 3, License Renewal Application Project stage: Other ML0414604202004-05-25025 May 2004 Revision of Schedule for Conduct of Review of Browns Ferry Nuclear Plant, Units 1, 2, and 3 License Renewal Application Project stage: Approval ML0419501002004-06-10010 June 2004 Audit and Review Plan for Plant Aging Management Programs and Reviews - Browns Ferry Nuclear Plant, Units 1, 2 and 3 Project stage: Request ML0417005502004-06-15015 June 2004 Summary of Telephone Conference with the Tennessee Valley Authority Regarding Activities on Browns Ferry Nuclear Plant, Units 1, 2 and 3, License Renewal Application Project stage: Other ML0417005232004-06-16016 June 2004 Summary of Telephone Conference Between the U.S. Nuclear Regulatory Commission and the Tennessee Valley Authority Concerning Activities on Browns Ferry Nuclear Plant, Units 1, 2 and 3, License Renewal Application Project stage: Other ML0417005052004-06-16016 June 2004 Summary of Telephone Conference with Tennessee Valley Authority Concerning Activities on Browns Ferry Nuclear Plant, Units 1, 2 and 3, License Renewal Application Project stage: Other ML0417005722004-06-18018 June 2004 Summary of Telephone Conference with Tennessee Valley Authority Regarding Activities on Browns Ferry Nuclear Plant, Units 1, 2 and 3, License Renewal Application Project stage: Other ML0417600762004-06-23023 June 2004 Request for Additional Information for the Review of the Browns Ferry Nuclear Plant, Units 1, 2 and 3 License Renewal Application Project stage: RAI ML0418101682004-06-28028 June 2004 Summary of Telephone Conference on May 27, 2004, Between the U.S. NRC and the Tennessee Valley Authority Concerning Draft Requests for Additional Information on Browns Ferry Nuclear Plant, Units 1, 2 and 3 LRA Project stage: Draft RAI ML0419802222004-07-0909 July 2004 Technical Specification 436 - Increased Main Steam Isolation Valve Leakage Rate Limits and Exemption from 10CFR50, Appendix J Project stage: Other ML0419505082004-07-10010 July 2004 Summary of Telephone Conference on June 16, 2004, Between the NRC & TVA Concerning Browns Ferry Nuclear Plant, Units 1, 2 and 3 License Renewal Application Project stage: Other ML0420103882004-07-19019 July 2004 Summary of Telephone Conference with Tennessee Valley Authority Concerning Activities on Browns Ferry Nuclear Plant, Units 1, 2 and 3 License Renewal Application Project stage: Other ML0421104852004-07-28028 July 2004 Summary of Telephone Conference Held on July 1, 2004, Between NRC and TVA Concerning Draft Requests for Additional Information (D-RAI) on Browns Ferry Nuclear Plant Units 1, 2,& 3 Project stage: Draft RAI ML0421201862004-07-30030 July 2004 Request for Additional Information for the Review of the Browns Ferry Nuclear Plant, Units 1, 2 and 3 License Renewal Application Project stage: RAI ML0422402552004-08-10010 August 2004 Audit and Review Plan for Plant Aging Management Reviews and Programs at the Browns Ferry Nuclear Power Plants, Units 1, 2 and 3 Project stage: Other ML0423904972004-08-23023 August 2004 Summary of Telephone Conference Held on July 28, 2004, Between the U.S. Nuclear Regulatory Commission and the Tennessee Valley Authority Concerning Browns Ferry Nuclear Plant, Units 1 and 2 and 3, License Renewal Application. Project stage: Other ML0423605902004-08-23023 August 2004 Request for Additional Information for the Review of the Browns Ferry Nuclear Plant, Units 1, 2 and 3, License Renewal Application Project stage: RAI ML0423607622004-08-23023 August 2004 Request for Additional Information for the Review of the Browns Ferry Nuclear Plant, Units 1, 2 and 3, License Renewal Application Project stage: RAI ML0424005502004-08-26026 August 2004 Summary of Telephone Conference Held on July 27, 2004, Between U.S. Nuclear Regulatory Commission & Tennessee Valley Authority Concerning Draft Requests for Additional Information on Browns Ferry Nuclear Plant, Units 1, 2 & 3, License Renew Project stage: Draft RAI ML0424502112004-08-31031 August 2004 Summary of Telephone Conference Held on July 12, 2004, Between the U.S. Nuclear Regulatory Commission (NRC) and the Tennessee Valley Authority (TVA) Concerning Requests for Additional Information (RAI) on Browns Ferry Nuclear Plant, Unts 1, Project stage: RAI ML0424502602004-08-31031 August 2004 Request for Additional Information for the Review of the Browns Ferry Nuclear Plant, Units 1, 2 and 3 License Renewal Application Project stage: RAI ML0425203742004-09-0303 September 2004 (BFN) - Units 1, 2, and 3 License Renewal Application - NRC Scoping and Screening Audit - Request for Additional Information Project stage: Request ML0426005222004-09-16016 September 2004 Summary of Telephone Conference Held on August 19, 2004, Between the U.S. Nuclear Regulatory Commission and the Tennessee Valley Authority Concerning Draft Requests for Additional Information on Browns Ferry Nuclear Plant, Units 1, 2 & 3 Lr Project stage: Draft RAI ML0425803272004-09-16016 September 2004 Audit Trip Report Regarding the Tennessee Valley Authority License Renewal Application for Browns Ferry Nuclear Plant, Units 1, 2 and 3 Dated December 31, 2003 Project stage: Other ML0427502592004-09-30030 September 2004 License Renewal Application Response to NRC Request for Additional Information (RAI) Project stage: Response to RAI ML0428206242004-10-0707 October 2004 License Renewal Application - Notification of Change of TVA License Renewal Project Manager Project stage: Other ML0428704222004-10-0808 October 2004 License Renewal Application - Response to NRC Request for Additional Information Related to Aging of Mechanical Systems During the Extended Outage Project stage: Response to RAI ML0428600662004-10-0808 October 2004 Request for Additional Information for the Review of the Browns Ferry Nuclear Plant, Units 1, 2 and 3 License Renewal Application (RAI 2.3.2-2.3.3) Project stage: RAI ML0428704282004-10-0808 October 2004 (BFN) - Units 1, 2, and 3 License Renewal Application - Response to NRC Request for Additional Information Developed During the License Renewal Audit Inspections for Comparison to Generic Aging Lessons Learned Project stage: Response to RAI ML0428600152004-10-0808 October 2004 Request for Additional Information for the Review of the Browns Ferry Nuclear Plant, Units 1, 2 and 3 License Renewal Application (2.3 Rx Systems) Project stage: RAI ML0428601332004-10-12012 October 2004 Request for Additional Information for the Review of the Browns Ferry Nuclear Plant, Units 1, 2 and 3, License Renewal Application (Aux System\\Rai 3.3) Project stage: RAI ML0429202012004-10-15015 October 2004 Summary of Telephone Conference Call Held on September 15, 2004, Between the U.S. Nuclear Regulatory Commission and the Tennessee Valley Authority Concerning Browns Ferry Nuclear Plant, Units 1, 2 and 3, License Renewal Application Project stage: Other ML0429304712004-10-18018 October 2004 License Renewal Application - Response to NRC Request for Additional Information (RAI) Project stage: Response to RAI ML0429309312004-10-19019 October 2004 Units 1, 2, and 3 License Renewal Application Response to NRC Request for Additional Information Project stage: Response to RAI ML0429905192004-10-21021 October 2004 Summary of Telephone Conference Held on September 22, 2004, Between the U.S. Nuclear Regulatory Commission and the Tennessee Valley Authority Concerning Browns Ferry Nuclear Plant, Units 1, 2 and 3, LRA Project stage: Other ML0430000402004-10-22022 October 2004 Summary of Telephone Conference with Tennessee Valley Authority Concerning Browns Ferry Nuclear Plant, Units 1, 2 and 3 License Renewal Application Project stage: Other ML0430001492004-10-25025 October 2004 (BFN) Units 1, 2, and 3 License Renewal Application - Appendix F - Request for Additional Information (RAI) Project stage: Request ML0430304342004-10-28028 October 2004 Units 1, 2, and 3 License Renewal Application Fire Protection Section Verbal Request on October 20, 2004 - Response to NRC Request for Additional Information Project stage: Response to RAI ML0430604922004-11-0101 November 2004 Request for Additional Information for the Review of the Browns Ferry Nuclear Plant, Units 1, 2 and 3, License Renewal Applicaiton Project stage: RAI ML0431005882004-11-0303 November 2004 (Ban) - Units 1, 2, and 3 License Renewal Application - Reactor Systems Section 2.3.1, 2.3.2, and 2.3.3 - Response to Request for Additional Information Project stage: Response to RAI ML0430905452004-11-0303 November 2004 License Renewal Application, Heating, Ventilation and Cooling (HVAC) Systems Sections 2.3.2 and 2.3.3, Request for Additional Information (RAI) Project stage: Request ML0430903432004-11-0303 November 2004 License Renewal Application Auxiliary Systems Section 3.3 Response to NRC Request for Additional Information Project stage: Response to RAI ML0430905772004-11-0404 November 2004 Request for Additional Information for the Review of the Browns Ferry Nuclear Plant, Units 1, 2 and 3, LRA (TAC Nos. MC1704, MC1705 and MC1706.) Project stage: RAI ML0430905732004-11-0404 November 2004 Request for Additional Information for the Review of the Browns Ferry Nuclear Plant, Units 1, 2 and 3, LRA Project stage: RAI 2004-05-04
[Table View] |
Text
December 3, 2004 10 CFR 54 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Mail Stop: OWFN P1-35 Washington, D.C. 20555-0001 Gentlemen:
In the Matter of
) Docket Nos. 50-259 Tennessee Valley Authority
) 50-260 50-296 BROWNS FERRY NUCLEAR PLANT (BFN) - UNITS 1, 2, AND 3 LICENSE RENEWAL APPLICATION - HEATING, VENTILATION, AND COOLING (HVAC) SYSTEMS SECTIONS 2.3.2 AND 2.3.3 - FOLLOWUP REQUEST FOR ADDITONAL INFORMATION (RAI) (TAC NOS. MC1704, MC1705, AND MC1706)
By letter dated December 31, 2003, TVA submitted, for NRC review, an application pursuant to 10 CFR 54, to renew the operating licenses for the Browns Ferry Nuclear Plant, Units 1, 2, and 3. As part of the review of TVAs license renewal application, the NRC staff made a request for additional information (RAI) relating to the aging management of Sections 2.3.2 and 2.3.3 of the License Renewal Application. By letter dated November 3, 2004, TVA responded to the additional information requested by the NRC relating to the HVAC Sections 2.3.2 and 2.3.3. The NRC reviewed these RAI responses and determined further clarification was required. This followup NRC RAI was discussed with the TVA staff in a telephone discussion with the NRC on November 9, 2004.
U.S. Nuclear Regulatory Commission Page 2 December 3, 2004 The enclosure to this letter contains the specific NRC requests for additional information and the corresponding TVA response.
If you have any questions regarding this information, please contact Ken Brune, Browns Ferry License Renewal Project Manager, at (423) 751-8421.
I declare under penalty of perjury that the foregoing is true and correct. Executed on this 3rd day of December, 2004.
Sincerely, Original signed by:
T. E. Abney Manager of Licensing and Industry Affairs
Enclosure:
cc: See page 3
U.S. Nuclear Regulatory Commission Page 3 December 3, 2004 Enclosure cc (Enclosure):
State Health Officer Alabama Department of Public Health RSA Tower - Administration Suite 1552 P.O. Box 303017 Montgomery, Alabama 36130-3017 Chairman Limestone County Commission 310 West Washington Street Athens, Alabama 35611 (Via NRC Electronic Distribution)
Enclosure cc (Enclosure):
U.S. Nuclear Regulatory Commission Region II Sam Nunn Atlanta Federal Center 61 Forsyth Street, SW, Suite 23T85 Atlanta, Georgia 30303-8931 Mr. Stephen J. Cahill, Branch Chief U.S. Nuclear Regulatory Commission Region II Sam Nunn Atlanta Federal Center 61 Forsyth Street, SW, Suite 23T85 Atlanta, Georgia 30303-8931 NRC Senior Resident Inspector Browns Ferry Nuclear Plant 10833 Shaw Road Athens, Alabama 35611-6970 NRC Unit 1 Restart Senior Resident Inspector Browns Ferry Nuclear Plant 10833 Shaw Road Athens, Alabama 35611-6970 cc: continued page 4
U.S. Nuclear Regulatory Commission Page 4 December 3, 2004 cc: (Enclosure)
Margaret Chernoff, Project Manager U.S. Nuclear Regulatory Commission (MS 08G9)
One White Flint, North 11555 Rockville Pike Rockville, Maryland 20852-2739 Eva A. Brown, Project Manager U.S. Nuclear Regulatory Commission (MS 08G9)
One White Flint, North 11555 Rockville Pike Rockville, Maryland 20852-2739 Yoira K. Diaz-Sanabria, Project Manager U.S. Nuclear Regulatory Commission (MS 011F1)
One White Flint, North 11555 Rockville Pike Rockville, Maryland 20852-2739 Ramachandran Subbaratnama, Project Manager U.S. Nuclear Regulatory Commission (MS 011F1)
One White Flint, North 11555 Rockville Pike Rockville, Maryland 20852-2739
U.S. Nuclear Regulatory Commission Page 5 December 3, 2004 GLS:BAB Enclosure cc (Enclosure):
A. S. Bhatnagar, LP 6-C K. A. Brune, LP 4F-C J. C. Fornicola, LP 6A-C D. F. Helms, LP 6A-C F. C. Mashburn, BR 4X-C R. G. Jones, NAB 1A-BFN K. L. Krueger, POB 2C-BFN R. F. Marks, Jr., PAB 1A-BFN J. R. Rupert, NAB 1F-BFN K. W. Singer, LP 6A-C M. D. Skaggs, PAB 1E-BFN E. J. Vigluicci, ET 11A-K NSRB Support, LP 5M-C EDMS, WT CA-K s://Licensing/Lic/BFN LR Sections 2.3.2 and 2.3.3 HVAC Followup RAI TVA Response Letter.doc
ENCLOSURE TENNESSEE VALLEY AUTHORITY BROWNS FERRY NUCLEAR PLANT (BFN)
UNITS 1, 2, AND 3 LICENSE RENEWAL APPLICATION (LRA),
RESPONSE TO NRC FOLLOWUP REQUEST FOR ADDITIONAL INFORMATION (RAI), RELATED TO HEATING VENTILATION AND COOLING (HVAC) SYSTEMS SECTION 2.3.2 AND 2.3.3 (SEE ATTACHED)
E-1 TENNESSEE VALLEY AUTHORITY BROWNS FERRY NUCLEAR PLANT (BFN)
UNITS 1, 2, AND 3 LICENSE RENEWAL APPLICATION (LRA),
RESPONSE TO NRC FOLLOWUP REQUEST FOR ADDITIONAL INFORMATION (RAI), RELATED TO HEATING VENTILATION AND COOLING (HVAC) SYSTEMS SECTION 2.3.2 AND 2.3.3 By letter dated December 31, 2003, TVA submitted, for NRC review, an application pursuant to 10 CFR 54, to renew the operating licenses for the Browns Ferry Nuclear Plant, Units 1, 2, and 3. As part of the review of TVAs license renewal application, the NRC staff made a request for additional information (RAI) relating to the aging management of Sections 2.3.2 and 2.3.3 of the License Renewal Application. By letter dated November 3, 2004, TVA responded to the additional information requested by the NRC relating to the HVAC Sections 2.3.2 and 2.3.3. The NRC reviewed these RAI responses and determined further clarification was required. This followup NRC RAI was discussed with the TVA staff in a telephone discussion with the NRC on November 9, 2004.
NRC Request for Additional Information for Section 2.3.5 LRA Section 2.3.5 should be revised to add the following subcomponent Categories:
Ductwork - Air conditioning unit Housings (RAI 2.3.2.1-1, RBVS),
Damper housings (RAI 2.3.2.1-1, RBVS and (RAI 2.3.2.2-1, SGTS),
Screens and Plenums (RAI 2.3.3.8-1, VS, and (RAI 2.3.3.9-1, HVACS)
Fire Dampers - Fire Damper Housings (RAI 2.3.3.8-1 and RAI 2.3.3.9-1)
Heat Exchanger - Cooling Coil Housings ((RAI 2.3.2.1-1, RBVS and RAI 2.3.3.9-1, HVACS)
Add Category "Valves" and add subcategory Valve Bodies (RAI 2.3.2.1-1, RBVS and RAI 2.3.3.9-1, HVACS)
TVA Response to Request for Additional Information by NRC for Section 2.3.5 The following changes apply to Section 2.3.5:
E-2 Under the heading Ductwork:
- Replace "Air Conditioning Unit (ACU)" with "Air Conditioning Unit (ACU) Housings"
- Replace "Air Handling Unit (AHU)" with "Air Handling Unit (AHU) Housings"
- Replace "Dampers (BKD), (BLD), (FCO), (TCO), (XFD), or (DMP)" with "Damper (BKD), (BLD), (FCO), (TCO), (XFD), or (DMP) Housings"
- Add "Screens" Replace the heading "Fire Dampers" with "Fire Damper Housings" Under the heading Heat Exchanger:
- "Replace Cooling Coil (CCL)" with "Cooling Coil (CCL)
Housing" At the end of Section 2.3.5 add "When valves are listed in Tables in Section 2.3 the portion of the valve that is in scope is the body."
NRC Request for Additional Information for Section 2.3.3.9-1 LRA Section 3.5.2.1.2 is meant for Reactor Building. However, TVA response for RAI 2.3.3.9-1 states that "Structural sealants (such as those required to maintain the control room envelope (at positive pressure with respect to the adjacent areas) or secondary containment (at negative pressure with respect to the adjacent areas) are contained in Section 3.5.2.1.2 and in component type "Compression Joints and Seals" and in component type "Caulking and Sealants" in Table 3.5.2.2." Clarify whether control room envelope is within the reactor building.
If not, provide the proper reference Section and Table number where main control room envelope sealants are described. Also, clarify that structural sealants maintain the control room envelope at positive pressure and secondary containment at negative pressure with respect to the adjacent areas.
E-3 TVA Response to Request for Additional Information by NRC for Section 2.3.3.9-1 The Control Room is part of the Reactor Building per License Renewal Application Section 2.4.2.1. The structure sealants are used to maintain the control room envelope at a positive pressure and the secondary containment at a negative pressure.