ML030560426

From kanterella
Jump to navigation Jump to search
IR 05000346-02-008, on 05/15-08/09/2002, Firstenergy Nuclear Operating Company, Davis-Besse Nuclear Power Station, Augmented Insepection Team Follow-up Special Inspection, Preliminary Significance Assessment
ML030560426
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 02/25/2003
From: Dyer J
Division of Nuclear Materials Safety III
To: Myers L
FirstEnergy Nuclear Operating Co
References
EA-03-025, FOIA/PA-2005-0261 IR-02-008
Download: ML030560426 (46)


See also: IR 05000346/2002008

Text

February 25, 2003

EA-03-025

Mr. Lew Myers

Chief Operating Officer

FirstEnergy Nuclear Operating Company

Davis-Besse Nuclear Power Station

5501 North State Route 2

Oak Harbor, OH 43449-9760

SUBJECT: DAVIS-BESSE CONTROL ROD DRIVE MECHANISM PENETRATION

CRACKING AND REACTOR PRESSURE VESSEL HEAD DEGRADATION

PRELIMINARY SIGNIFICANCE ASSESSMENT

(REPORT NO. 50-346/2002-08(DRS))

Dear Mr. Myers:

On February 16, 2002, the Davis-Besse Nuclear Power Station was shut down for refueling and

inspection of control rod drive mechanism reactor pressure vessel head penetration nozzles.

Your staff discovered that Nozzles Nos. 1, 2, and 3 were leaking through axial cracks, and

discovered that Nozzle No. 2 had begun to develop a circumferential crack. During repair of

Nozzle No. 3 on March 5 and 6, 2002, it became loose in the reactor pressure vessel head.

Subsequent investigation revealed that a cavity had formed adjacent to Nozzle No. 3 in the

thick low-alloy steel portion of the reactor pressure vessel head, leaving only a thin stainless

steel clad material as the reactor coolant pressure boundary over an area of approximately

20 square-inches. A similar but much smaller cavity was subsequently identified at the location

of the leaking crack in Nozzle No. 2. Your staffs root cause analysis report concluded that the

axial crack in Nozzle No. 3 had likely been leaking for a period of six to eight years.

On March 12, 2002, the NRC dispatched an Augmented Inspection Team (AIT) to the

Davis-Besse site in accordance with NRC Management Directive 8.3, NRC Incident

Investigation Program. The AIT was chartered to determine the facts and circumstances

related to the significant degradation of the reactor pressure vessel head discovered by your

staff. The AIT results were summarized for you and your staff during a public exit meeting on

April 5, 2002, and the AIT report was issued on May 3, 2002. Subsequently, on May 15, 2002,

the NRC began a special AIT Follow-up inspection focused on the results documented in the

AIT report. The NRC completed this inspection and summarized the results of the inspection

for you and your staff on August 9, 2002. The AIT Follow-up report was issued on

October 2, 2002.

The performance deficiency associated with the AIT Follow-up inspection findings was your

failure to properly implement the boric acid control and the corrective action programs, which

allowed reactor coolant system (RCS) pressure boundary leakage to occur undetected for a

prolonged period of time resulting in reactor pressure vessel head degradation and control rod

drive nozzle circumferential cracking. This letter presents the results of the NRCs preliminary

significance determination for this performance deficiency.

L. Myers -2-

On March 27, 2002, you provided a schedule for your evaluation of the safety significance of

the reactor pressure vessel head degradation. Your evaluation was completed and submitted

to the NRC on April 8, 2002, and supplemented with additional information on June 12, July 12

and 20, and November 18, 2002. The NRC assessment of the significance of this performance

deficiency considered the information you have provided.

As discussed in detail in the enclosure, the significance of this performance deficiency was

assessed using the NRC Significance Determination Process. The performance deficiency

resulted in an increase in the risk of reactor core damage through a loss of coolant accident

caused by either a rupture in the exposed cladding in the reactor pressure vessel head cavity or

a control rod drive mechanism nozzle ejection due to a circumferential crack. The result of our

significance analysis of the as-found reactor pressure vessel head cavity and potential for larger

cavity growth indicate that the significance is in the Red range (change in core damage

frequency > 10-4 per reactor-year). The result of our significance analysis of the as-found

circumferential crack and potential for crack growth indicate that the significance is in the

Yellow to Red range (change in core damage frequency in the range of low 10-5 to low 10-4 per

reactor-year). Consequently, the NRC has preliminarily determined that the performance

deficiency resulting in the reactor pressure vessel head degradation and control rod drive

mechanism nozzle cracking has high safety significance in the Red range.

Be advised that this significance assessment is preliminary. The final significance assessment

will include consideration of any further information or perspectives you provide that may

warrant reconsideration of the methodology or assumptions used during the preliminary

significance assessment.

Before we make a final decision on the significance of this performance deficiency, we are

providing you another opportunity to present to the NRC any further perspectives on the facts

and assumptions used by the NRC to arrive at its preliminary significance determination at a

Regulatory Conference or by a written submittal. Any perspectives you provide should be

limited to the significance assessment, and should not discuss the apparent violations, their root

causes or your corrective actions.

If you choose to request a Regulatory Conference, it should be held within 30 days of the

receipt of this letter and we encourage you to submit supporting documentation at least one

week prior to the conference in an effort to make the conference more efficient and effective. If

a Regulatory Conference is held, it will be open for public observation. If you decide to submit a

written response, such submittal should be sent to the NRC within 30 days of the receipt of this

letter.

Please contact Christine Lipa at 630-829-9619 within 10 business days of your receipt of this

letter to notify the NRC of your intentions. If we have not heard from you within 10 days, we will

finalize our significance determination and you will be advised by separate correspondence of

the results of our deliberations on this matter.

Completing the significance determination for this performance deficiency is one input into the

NRCs final decision on enforcement action. Another critical input will be the results of the

ongoing investigation by the NRCs Office of Investigations.

L. Myers -3-

In accordance with 10 CFR 2.790 of the NRCs Rules of Practice, a copy of this letter

and its enclosures will be available electronically for public inspection in the NRC Public

Document Room or from the Publicly Available Records (PARS) component of NRCs

document system (ADAMS). ADAMS is accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html.

Sincerely,

/RA/

J. E. Dyer

Regional Administrator

Enclosure: Significance Determination Process and

Enforcement Review Panel Worksheet for SDP-Related

Findings: Davis-Besse Degraded Reactor Head

Docket No. 50-346

License No. NPF-3

See attached distribution list

cc w/encl:

Plant Manager

Manager - Regulatory Affairs

M. OReilly, FirstEnergy

State Liaison Officer, State of Ohio

R. Owen, Ohio Department of Health

Ohio Public Utilities Commission

C. Emahiser, Ottawa County Sheriff

J. P. Greer, Director, Emergency

Management Agency

S. Isenberg, President, Lucas County

Board of Commissioners

J. Telb, Lucas County Sheriff

B. Halsey, Director, Emergency

Management Agency

G. Adams, Village Administrator, Genoa

The Honorable Robert Purney

The Honorable Lowell C. Krumnow

The Honorable Joseph Verkin

The Honorable Thomas Leaser

The Honorable Jack Ford

The Honorable Thomas Brown

The Honorable Joe Ihnat

President, Ottawa County Board of Commissioners

INPO

D. Lochbaum, Union of Concerned Scientists

Distribution w/encl:

ADAMS (PARS)

W. Kane, DEDR

J. Craig, OEDO

J. Dyer, RIII

S. Collins, NRR

G. Caputo, OI

H. Bell, OIG

F. Congel, OE

J. Grobe, RIII

R. Paul, OI:RIII

L. Chandler, OGC

W. Dean, NRR

J. Luehman, OE

D. Dambly, OGC

C. Lipa, RIII

H. Nieh, OEDO

J. Ulie, OI:RIII

C. Weil, RIII

D. Nelson, OE

L. Dudes, NRR

L. Myers -3-

In accordance with 10 CFR 2.790 of the NRCs Rules of Practice, a copy of this letter

and its enclosures will be available electronically for public inspection in the NRC Public

Document Room or from the Publicly Available Records (PARS) component of NRCs

document system (ADAMS). ADAMS is accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html.

Sincerely,

J. E. Dyer

Regional Administrator

Enclosure: Significance Determination Process and

Enforcement Review Panel Worksheet for SDP-Related

Findings: Davis-Besse Degraded Reactor Head

Docket No. 50-346

License No. NPF-3

See attached distribution list

C:\ORPCheckout\FileNET\ML030560426.wpd

OFFICE RIII OGC OE NRR RIII

NAME JGrobe:klg DDambly FCongel SCollins JDyer

/RA/ J.Grobe /RA/ J.Grobe /RA/ J.Grobe

per telecon per telecon per telecon

w/Dambly w/Luehman w/Borchardt

DATE 02/20/03 02/20/03 02/20/03 02/20/03 02/24/03

OFFICIAL RECORD COPY

Significance Determination Process (SDP) and Enforcement Review Panel

Worksheet for SDP-Related Findings

Davis-Besse Degraded Reactor Head

Panel Date: February 6, 2003

Cornerstone Affected and Proposed Preliminary Results:

Initiating Events & Barrier Integrity Cornerstones:

  • Red Finding
  • Specific Violations and Severity Level to be determined following completion of OI

investigation

Licensee: FirstEnergy Nuclear Operating Company

Facility/Location: Davis-Besse Nuclear Power Station / Oak Harbor, OH

Docket No: 05000346

License No: DPR-25

Inspection Report No: 50-346/2002-008

Date of Exit Meeting: August 9, 2002

Issue Sponsor : Jack Grobe

Meeting Members:

Issue Sponsor  : Jack Grobe

Technical Spokesperson(s)  : Sonia Burgess / Steve Long

Program Spokesperson  : Cindy Carpenter / Mike Johnson

OE Representative  : Jim Luehman

CONTENTS

A. Brief Description of Issue . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2

B. Statement of the Performance Deficiencies . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2

C. Significance Determination Basis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2

1. Reactor Inspection for IE, MS, BI Cornerstones . . . . . . . . . . . . . . . . . . . . . 2

a. Phase 1 Screening Logic, Results and Assumptions . . . . . . . . . . . 2

b. Phase 2 Risk Evaluation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2

c. Phase 3 Risk Evaluation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3

Analysis of the RPV Head Cavity . . . . . . . . . . . . . . . . . . . . . . . . . . 4

Analysis of CRDM Circumferential Cracking . . . . . . . . . . . . . . . . . 6

Potential Risk Contribution due to Large Early Release Frequency

(LERF) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7

Potential Risk Contribution due to External Events . . . . . . . . . . . . 7

Conclusion . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7

2. All Other Inspection Findings (not IE, MS, BI cornerstones) . . . . . . . . . . . 8

D. Proposed Enforcement. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8

E. Determination of Follow-up Review . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8

SDP Worksheets . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9

Attachment 1 Insights from Regulatory Guide (RG) 1.174 to Confirm Risk Characterization

Attachment 2 TIA 2002-01, Response to Request for Technical Assistance - Risk

Assessment of Davis-Besse Reactor Head Degradation

1

A. Brief Description of Issue

During an inspection of the control rod drive mechanism (CRDM) nozzles in February and

March 2002, the licensee discovered three nozzles (Nos. 1, 2 and 3) which contained through-wall

axial cracks, and that Nozzle No. 2 had developed a small circumferential crack. During repair of

Nozzle No. 3, it became loose in the reactor pressure vessel (RPV) head. Subsequent

investigation revealed that a cavity had formed around Nozzle No. 3 in the 6.63 inch-thick low-alloy

steel portion of the RPV head, leaving only the stainless steel clad material (measuring 0.202 to

0.314 inches-thick) as the reactor coolant pressure boundary over an area of approximately 20

square-inches. A similar but much smaller cavity was subsequently identified at the location of the

through-wall crack in Nozzle No. 2. The licensees root cause analysis report concluded that the

through-wall axial crack in Nozzle No. 3 had most probably been leaking for a period of 6 to 8

years before detection in February 2002.

B. Statement of the Performance Deficiencies

The performance deficiency associated with this finding was the licensees failure to properly

implement the boric acid control and the corrective action programs, which allowed reactor coolant

system (RCS) pressure boundary leakage to occur undetected for a prolonged period of time

resulting in reactor pressure vessel head degradation and CRDM nozzle circumferential cracking.

C. Significance Determination Basis

1. Reactor Inspection for Initiating Event (IE), Mitigating Systems (MS), Barrier

Integrity (BI) Cornerstones

a. Phase 1 Screening Logic, Results and Assumptions

In accordance with Manual Chapter (MC) 0612, the inspectors determined

that the issue was more than minor in safety significance because if left

uncorrected, the circumferential cracking and boric acid corrosion would

become a more significant safety concern. The resulting circumferential

cracking and cavity represent a significant loss of the design basis barrier

integrity and could be reasonably viewed as a precursor to a significant

event.

In accordance with MC 0609, Appendix A, the inspectors conducted a SDP

Phase 1 screening and determined that the finding degraded both the

Initiating Event and Barrier Integrity Cornerstones. The through-wall CRDM

axial cracks and developing circumferential cracks, and the RPV wastage

compromised the reactor coolant pressure boundary and resulted in an

increase in the likelihood of a loss of coolant accident (LOCA).

b. Phase 2 Risk Evaluation

Internal Initiating Events

Assumptions:

During March 2002, the region performed a Phase 2 risk assessment using

the Revision 0 unbenchmarked Davis-Besse SDP worksheets and

determined that the issue could be characterized as a Yellow when

increasing the LOCA initiating event likelihood one order of magnitude, or a

2

Red when increasing the LOCA initiating event likelihood two orders of

magnitude. The regional Senior Reactor Analyst later performed an

evaluation of the issue using the benchmarked Revision 1 SDP worksheets

(issued in February 2003) and determined that the color characterization of

the finding did not change.

SDP Worksheet Results (Initial Results...see Attached Worksheets)

SLOCA -Small LOCA

SLOCA (2 or 1) + EIHP (5) = 7 or 6

SLOCA (2 or 1) + HPR (3) = 5 or 4

SLOCA (2 or 1) + PCS (2) + AFW (5) + EIHP (2) = 11 or 10

SLOCA (2 or 1) + PCS (2) + AFW (2) + FB (2) = 11 or 10

MLOCA - Medium LOCA

MLOCA (3 or 2) + LPR (3) = 6 or 5

MLOCA (3 or 2) + LPI (3) = 6 or 5

MLOCA (3 or 2) + EIHP (3) = 6 or 5

LLOCA - Large LOCA

LLOCA (4 or 3) + LPI (3) = 7 or 6

LLOCA (4 or 3) +LPR (2) = 6 or 5

Based on the Phase 2 SDP results, this issue is considered to be of high

safety significance, potentially RED (change in Core Damage Frequency

( CDF) >10-4 per Reactor Year (RY)), when the LOCA initiating event

frequency is increased two orders of magnitude.

c. Phase 3 Risk Evaluation

The Phase 3 risk evaluation was performed as an outcome risk analysis that

focused on two LOCA initiation scenarios:

  • the as-found cavity and the potential for cavity growth, and
  • the as-found circumferential crack and the potential for crack growth

Other potential outcomes from the licensees performance deficiency were

not evaluated. What follows are summaries from the Phase 3 analysis

documented in the attached Response to Request for Technical

Assistance-Risk Assessment of Davis-Besse Reactor Head Degradation

(TIA 2002-01) (Attachment B).

In response to TIA 2002-01, NRR performed a Phase 3 assessment of the

risk associated with the CRDM nozzle cracking and the resulting wastage

cavity in the Davis-Besse RPV head. Early in the analysis, it was

determined that a medium or large LOCA would have resulted from the

failure of the reactor coolant system (RCS) pressure boundary; therefore,

attempts were made to determine the increase in the medium and large

LOCA frequencies that could be attributed to the licensees performance

deficiency.

3

Analysis of the RPV Head Cavity

The NRC and the licensee used a traditional material and engineering

modeling approach to evaluate the RPV cavity. Both the staffs and

licensees analyses for the failure pressure of the modeled cavity resulted in

estimates in excess of 7000 psig. Both of the respective uncertainty

analyses indicated that the probability for rupture of the modeled cavity due

to pressure transients was very low (i.e., CDF<10-6/RY).

However, it is important to note that the Phase 3 analyses for this modeling

of the as-found condition highlighted significant unanalyzed parameters for

which we have insufficient knowledge to appropriately apply to the risk

analysis:

  • Flaws in clad material. The clad material was treated in the model as

if it was a plate of uniform thickness with uniform stress-strain. The

clad was neither designed nor acceptance tested to serve as a

structural element of the vessel design, so it may contain structurally

significant flaws that are not represented in the analysis.

Consideration of the size distribution of flaws and the probability of

one occurring in an area of exposed clad could change the risk

result, but without doing a flaw analysis in a quantitative manner, it is

not possible to conclude whether there is a predominance of large

flaws which would increase the risk by lowering burst pressures of

small cavities or a predominance of small flaws which would

decrease the overall risk by introducing a substantial probability that

the clad would leak and be detected before the exposed area

became large enough to rupture. In the limited consideration of

cavities no larger than the one found at Davis-Besse, the occurrence

of flaws is most likely to increase the contribution to the overall risk.

Engineering evaluations of the as-found cladding material and the

effects of flaws on clad strength are in progress, but are not available

at this time for this SDP preliminary risk assessment.

  • Clad material was weld applied with thickness and material

variations. The corrosion resistant cladding on the interior of the

head was applied by a combination of an automatic and manual

welding process. The welding process results in a somewhat

non-uniform layer of clad as evidenced by clad thickness

measurements in the degraded area ranging from 0.202 inches to

0.314 inches. While the clad thickness is not uniform,

measurements indicate that the nominal design thickness of 0.187

inches was achieved. Weld material by its nature may also contain

small discontinuities and inclusions resulting in localized variations in

mechanical properties. These variations in thickness and

mechanical properties challenge the ability to precisely predict the

point at which the clad would have failed.

  • Crack in clad material. An additional challenge to predicting cladding

failure is the identification of a slight distortion or bulging of the

as-found cladding material and the development of a series of small

cracks on the outer surface of the clad in the distorted area.

4

Engineering evaluations of the cracks are in progress, but are not

available at this time for this SDP preliminary risk assessment.

  • Corrosion mechanism not clearly understood. The corrosion

phenomena that produced the cavity are not understood well enough

to specify the rates of corrosion or the cavity shapes that could have

occurred, or whether there is corrosion rate dependence on leak rate

or a limit on the size of the cavity that can result.

  • Corrosion rates not known. Based primarily on the observed levels

of boric acid particles in the containment atmosphere, the licensees

root cause analysis report speculates that the cavity found in the

RPV head grew at an average rate of 2-inches/year over the 4-year

period of the last two operating cycles. The available evidence to

support this is certainly not conclusive, and other interpretations are

also reasonable. Corrosion rates for aqueous boric acid solutions in

a variety of physical situations are provided in the Electric Power

Research Institute Boric Acid Corrosion Guidebook. The closest

situation covered by the Guidebook appears to be the tests where an

aqueous solution of boric acid flowed across a low-alloy steel surface

that was heated to 600°F, which resulted in corrosion rates as high

as 7-inches/year. It seems reasonable to consider the possibility that

the last stages of cavity growth on the Davis-Besse RPV head may

have experienced a 7-inch/year corrosion rate. It is not known at this

time which case or what intermediate corrosion rate value is more

likely.

  • The possibility of additional wastage creating a larger cavity. This

analysis is the most difficult to perform since the available data

provided limited opportunities for quantifying results. However, the

results of the analyses that were performed indicated that the

potential growth of wastage cavities beyond the as-found condition

was possible. At the most-rapid growth rates, an additional 1 to 2

years of operation would enlarge the cavity sufficiently to allow

rupture at expected pressures, depending on cavity shape.

Alternatively, at the average corrosion rate estimated by the licensee,

an additional 4 to 7 years of operation would be required. It is also

important to note that there are some reasons to suspect that the

physical processes that developed the as-found cavity may become

self-limiting at some cavity size, so that it may not even be possible

to develop a cavity that is large enough to burst at expected

pressures with leakage rates limited by the plant's technical

specifications. Alternatively, modest enlargement of the as-found

cavity could have completely exposed Nozzle No. 11, potentially

introducing additional failure mechanisms and additional

opportunities for discovering the cavity before failure occurred.

In conclusion, although the results of the initial Phase 3 modeling of the

as-found cavity suggest that the risk due to potential rupture may be low

(i.e., CDF<10-6/RY), there exists significant unanalyzed parameters in

which we have insufficient knowledge at this time to evaluate and quantify

the risk. However, given the breadth and amount of unanalyzed

parameters, there is great potential for the risk to be substantially higher

5

than that quantified for the modeled cavity. Therefore, it is not prudent for

the significance determination to disregard this potential due to the staffs

inability to quantify it with existing knowledge in a Phase 3 analysis. For that

reason, the results of the Phase 2 analysis are used for this part of the

significance assessment.

The Phase 2 process calls for the use of either one or two orders of

magnitude increase in the LOCA frequency. Increasing the MLOCA and

LLOCA frequency by two orders of magnitude would produce a Red

significance level, through the SDP counting rule, and was determined to be

appropriate given the significant unanalyzed parameters. Therefore, using

the insights of the Phase 3 assessment and the results of the Phase 2

worksheets, a reasonable characterization of the RPV head cavity risk is in

the RED range ( CDF>10-4/RY).

Analysis of CRDM Circumferential Cracking

The Possibility of Nozzle Ejection due to Circumferential Cracking

The licensee's performance deficiency resulted in prolonged, undetected

leakage of boric acid onto the reactor head through axial cracks in several

control rod drive mechanism nozzles. This increased the probability for a

LOCA because the external surfaces of the leaking nozzles could develop

circumferential cracks which could grow large enough over time that a

nozzle could break above the weld and be ejected from the head.

In fact, two nozzles were developing wastage cavities and one of those two

nozzles also was developing a circumferential crack. Thus, analyses

restricted to the risk associated with the as-found dimensions of one cavity

do not necessarily provide a full perspective on the risk associated with the

licensee's performance deficiencies.

The circumferential cracking analysis indicated that there was sufficient time

during the estimated 6 to 8 years that Nozzle No. 3 was leaking for a

circumferential crack to develop and grow large enough to cause the nozzle

to be ejected. Neither the actual stress levels in Nozzle No. 3 nor the

cracking rate as a function of stress for the material used to fabricate the

nozzle is known; however, because the same material cracked in a greater

fraction of the nozzles at Davis-Besse and appears to have leaked earlier in

the plant's life than at Oconee 3, it is inferred that the residual stress levels

must be relatively high at Davis-Besse. Because the material has cracked

more rapidly than other operating Babcock and Wilcox plants, the analysis

also used a range of cracking rates indicative of the worst heat of material in

the available laboratory data. While conservative, these assumptions are

not necessarily bounding, so the results should be used as an indication of

what the risk may be, based on what we know today. The results are about

3 x 10-2/RY for the increase in the LOCA frequency and about 8 x 10-5/RY for

the corresponding increase in CDF with a range from low 10-5/RY to low

10-4/RY .

6

Potential Risk Contribution due to Large Early Release Frequency (LERF)

Davis-Besse has a large dry type containment. This containment type

typically has a relatively small probability for early failure following a core

damage accident caused by a LOCA. The Davis-Besse Individual Plant

Evaluation estimates the conditional containment failure probability as 0.006.

Values less than 0.1 will not affect the color assignment in an SDP analysis,

because the color thresholds for increases in LERF are a factor of 0.1 times

the thresholds for the increases in CDF.

To date, no information has been reported that indicates the Davis-Besse

containment is degraded to the point that its probability for early failure

following a medium or large LOCA is significantly increased. If the

significance determination for the nozzle leaks is based only on the risk

associated with nozzle ejection due to circumferential cracking, then an

increase in containment failure probability to a value of at least 0.13 would

be needed to increase the significance from greater than 8x10-5/RY based

on CDF to greater than 1x10-4/RY based on LERF. The value of 0.13

represents an increase by about a factor of 20 over the value derived in the

Davis-Besse Individual Plant Examination.

Potential Risk Contribution due to External Events

Further expenditure of resources to analyze the external event contribution

was not warranted since the internal risk contribution alone was

characterized as RED.

Conclusion

In summary, the risk assessment indicates that there are several combinations of

factors that plausibly represent conditions resulting from the performance deficiency

at Davis-Besse and lead to CDF>10-4/RY (RED range).

  • The results of the initial Phase 3 modeling of the as-found cavity suggest

that the risk due to potential rupture may be low (i.e., CDF<10-6/RY);

however, there exist significant unanalyzed parameters where we have

insufficient knowledge at this time to evaluate and quantify the risk. Given

the breadth and amount of unanalyzed parameters, the risk is clearly higher

than that quantified for the modeled cavity and justifies increasing the

initiating event frequency of MLOCA and LLOCA two orders of magnitude in

the SDP Phase 2 worksheets to properly characterize the significance of this

issue. Using the insights of the Phase 3 risk assessment and the results of

the Phase 2 SDP worksheets, a reasonable significance characterization of

the cavity is in the RED range using the counting rule for the MLOCA and

LLOCA accident sequences.

  • Circumferential cracking analysis indicated that there was sufficient time

during the estimated 6 to 8 years that Nozzle No. 3 was leaking for a

circumferential crack to develop and grow large enough to cause the nozzle

to be ejected. The CDF due to the increase LOCA frequency is in the

range of 10-5/RY to 10-4/RY, YELLOW to RED.

7

In addition to these risk insights, additional perspective on the RPV head

degradation can be gained from reviewing the key principles enumerated in

Regulatory Guide 1.174. It is included as Attachment A to further demonstrate the

high significance of this performance deficiency and can be used as a confirmation

of the risk characterization outcome.

2. All Other Inspection Findings (not IE, MS, BI Cornerstones)

No other inspection findings were identified.

D. Proposed Enforcement.

a. Regulatory requirement not met.

NRC Inspection Report No. 50-346/02-08(DRS) contains several unresolved

items that remain under consideration for enforcement action.

b. Proposed citation.

Enforcement is pending contingent on the results of the ongoing OI

investigation into these matters.

c. Historical precedent.

None.

E. Determination of Follow-up Review

It is proposed that NRR, OE and OGC review final determination letter before

issuance.

8

Table 3.3 SDP Worksheet for Davis-Besse Nuclear Power Station, Unit 1 Small LOCA (SLOCA)

Estimated Frequency (Table 1 Row) III Exposure Time >30 days Table 1 Result (circle): C- B or A

when increasing IE frequency

Safety Functions Needed: Full Creditable Mitigation Capability for Each Safety Function:

Power Conversion System (PCS) 1/2 Feedwater trains with 1/3 condensate trains (operator action = 2) (1)

Secondary Heat Removal (AFW) 1/1 MDAFW trains (1 train) (2) or 1/2 TDAFW train (2 ASD trains) or 1/1 SUFPs (operator

action = 1) (3)

Primary Heat Removal, Feed/Bleed 1/1 PORV or 1/2 PSVs (operator action = 2) (4)

(FB)

High Pressure Injection (EIHP) 1/2 HPI pumps (1 multi-train system) or 2/2 Makeup pump trains requiring operator

action (5) but limited by hardware (1 train)

High Pressure Injection (EIHP2) 2/2 Makeup pump trains requiring operator action (5) but limited by hardware (1 train)

High Pressure Recirculation (HPR) 1/2 HPI trains taking suction from 1/2 LPI trains through LPI HX (operator action = 3) (6)

Circle Affected Functions Recovery Remaining Mitigation Capability Rating for Each Sequence

of Affected Sequence Color

Failed

Train

0 SLOCA (2 or 1) + EIHP (5) = 7 or 6

1 SLOCA - EIHP (3,6)

0 SLOCA (2 or 1) + HPR (3) = 5 or 4

2 SLOCA - HPR (2,5,8)

0 SLOCA (2 or 1) + PCS (2) + AFW (5) + EIHP2 (2) = 11 or 10

3 SLOCA - PCS - AFW - EIHP2 (9)

9

0 SLOCA (2 or 1) + PCS (2) + AFW (5) + FB (2) = 11or 10

4 SLOCA - PCS - AFW - FB (10)

Identify any operator recovery actions that are credited to directly restore the degraded equipment or initiating event:

If operator actions are required to credit placing mitigation equipment in service or for recovery actions, such credit should be given only if the following criteria are met: 1) sufficient

time is available to implement these actions, 2) environmental conditions allow access where needed, 3) procedures exist, 4) training is conducted on the existing procedures under

conditions similar to the scenario assumed, and 5) any equipment needed to complete these actions is available and ready for use.

Notes:

  • The PCS should initially operate automatically. The operator needs to make sure that PCS continues to operate. This may

include manually taking control of the PCS to prevent over cooling. The IPE does not document how this operator action is

modeled.

  • The HEP for operator failure to initiate MDAFW is 2.7E-3. (Event QHAMDFPE.)
  • The utility commented that start up feedwater pump should be credited, and provided a HEP of 7.5E-2. (Event FHASUFPE.)
  • The human error for initiation of HPI cooling is 1.5E-2. (Event UHAMUHPE.)
  • A credit of 3 should be given to the operator action. The HEP for operator failure to align makeup system to full flow is 1.E-3.

(Event UHAMUINE.)

  • The HEP for operator failure to establish HPR is 2.9E-3.

10

Table 3.5 SDP Worksheet for Davis-Besse Nuclear Power Station, Unit 1 Medium LOCA (MLOCA)

Estimated Frequency (Table 1 Row) IV Exposure Time >30 days Table 1 Result (circle): D - C or B

when increasing IE frequency

Safety Functions Needed: Full Creditable Mitigation Capability for Each Safety Function:

Early Inventory, HP Injection 1/2 HPI trains (1 multi-train systems)

(EIHP)

Low Pressure Injection (LPI) 1/2 LPI train (1 multi-train system)

Low Pressure Recirculation 1/2 LPI train taking suction from sump (operator action = 3) (1)

(LPR)

Circle Affected Functions Recovery of Remaining Mitigation Capability Rating for Each Affected Sequence

Failed Train Sequence Color

0 MLOCA (3 or 2) + LPR (3) = 6 or 5

1 MLOCA - LPR (2)

0 MLOCA (3 or 2) + LPI (3) = 6 or 5

2 MLOCA - LPI (3)

0 MLOCA (3 or 2) + EIHP (3) = 6 or 5

3. MLOCA - EIHP (4)

Identify any operator recovery actions that are credited to directly restore the degraded equipment or initiating event:

If operator actions are required to credit placing mitigation equipment in service or for recovery actions, such credit should be given only if the following criteria are met: 1) sufficient

time is available to implement these actions, 2) environmental conditions allow access where needed, 3) procedures exist, 4) training is conducted on the existing procedures under

conditions similar to the scenario assumed, and 5) any equipment needed to complete these actions is available and ready for use.

Note:

  • The HEP for operator failure to initiate LPR is 3.8E-3. (Event XHALPRME.)

11

Table 3.6 SDP Worksheet for Davis-Besse Nuclear Power Station, Unit 1 Large LOCA (LLOCA)

Estimated Frequency (Table 1 Row) V Exposure Time >30 days Table 1 Result (circle): E- D or C

when increasing IE frequency

Safety Functions Needed: Full Creditable Mitigation Capability for each Safety Function:

Low Pressure Injection (LPI) 1/2 LPI train (1 multi-train system)

Low Pressure Recirculation (LPR) 1/2 LPI train taking suction from sump (operator action = 2) (1)

Circle Affected Functions Recovery of Remaining Mitigation Capability Rating for Each Sequence

Failed Train Affected Sequence Color

0 LLOCA (4 or 3) + LPI (3) = 7 or 6

1 LLOCA - LPI (3)

0 LLOCA (4 or 3) + LPR (2) = 6 or 5

2 LLOCA - LPR (2)

Identify any operator recovery actions that are credited to directly restore the degraded equipment or initiating event:

If operator actions are required to credit placing mitigation equipment in service or for recovery actions, such credit should be given only if the following criteria are met: 1) sufficient

time is available to implement these actions, 2) environmental conditions allow access where needed, 3) procedures exist, 4) training is conducted on the existing procedures under

conditions similar to the scenario assumed, and 5) any equipment needed to complete these actions is available and ready for use.

Note:

  • The HEP for operator failure to initiate LPR is 6.3E-3. (Event XHALPRAE.)

12

Davis-Besse SERP Attachment 1

Using the Principles from RG 1.174 to Confirm the High Safety Significance Risk

Characterization

Because the staff recognizes substantial vulnerabilities in purely risk-based decision

processes, Regulatory Guide (RG) 1.174 was developed to provide a risk-informed

decision-making process that integrates numerical risk estimates with other deterministic

information for evaluating permanent changes to the licensing basis for nuclear power

facilities. Consideration of the other key principles enumerated in RG 1.174 provides

additional insights and confirmation that the Davis-Besse RPV head degradation

represents a finding of high safety significance. These are applied with some translation

from a process for prior approval of a regulatory change to the ROP for post-facto

evaluation of an unintended occurrence.

Principle 1 - Regulations are met: In this case, regulations apparently were not met in

more than one respect. Clearly, pressure boundary leakage* occurred, although none is

permitted by technical specifications, but, pressure boundary leakage occurs occasionally

in plants without unacceptably poor licensee performance. The highly significant aspect of

this leakage at Davis-Besse was the extended period over which it was allowed to persist,

and the extent of the damage that it created to a safety-significant structure. That damage

is contrary to the general design criteria (GDC) requirements in the regulations, in

particular, the requirement that the RCS be inspected and maintained in a condition that

has an extremely low probability of abnormal leakage or gross failure.

Principle 2 - Defense-in-depth is maintained: In this case, no physical barrier was

breached, although one physical barrier was nearly eliminated. The physical effect on the

part of the barrier that is credited in the plants design-basis appears to be more

appropriately addressed in the next principle with respect to safety margins. However, the

defense-in-depth principle applies to processes as well as barriers. The processes of

design, fabrication, pre-service testing, operation within limits, maintenance and in-service

inspection are intended to provide assurance through redundancy of the adequacy of the

RCS pressure boundary for the life of the plant. In that context, failures of the maintenance

and inspection aspects of the licensees performance were sufficient to defeat the design

feature. Based on the licensees analysis of the root cause, if the head had been

maintained in a clean state or the inspections had been performed for leaking nozzles in a

complete manner, the cavity would have been discovered before it reached a threatening

size. This is a performance deficiency that degraded the level of defense in depth.

Principle 3 - Sufficient safety margins are maintained: In this case, the design margin

for the strength of the reactor pressure vessel head is provided solely by the carbon steel

forging; the strength of the clad material was not credited in the design process.

Therefore, safety margins were not maintained during this degradation event.

Principle 4 - The risk is low: The results of the initial Phase 3 modeling of the as-found

cavity suggest that the risk due to potential rupture may be low (i.e., <10-6); however, there

Pressure boundary leakage is defined in Technical Specifications to be leakage through

a non-isolatable flaw in a reactor coolant system component body, pipe wall or vessel wall

(except flaws in steam generator tubes, where leakage is limited by separate specifications). It

does not include leakage through bolted connections or valves.

1

exists significant unanalyzed parameters where we have insufficient knowledge at this time

to evaluate and quantify the risk. Given the breadth and amount of unanalyzed

parameters, the risk is clearly higher than that quantified for the modeled cavity. Also, the

circumferential cracking analysis indicated that there was sufficient time during the

estimated 6 to 8 years that nozzle No. 3 was leaking for a circumferential crack to develop

and grow large enough to cause the nozzle to be ejected. The change in CDF due to the

increase LOCA frequency is in the 10-5/RY range.

Principle 5 - The impact of the situation was monitored with strategies sufficient to

assure adequate performance: In this case, the licensee was unaware of the leaks in the

CRDM nozzles and of the possibility for corrosion of the low alloy steel during operation. In

addition, dispositions of several noted abnormal conditions were inappropriately based on

false assumptions about the locations of leaks and the possibilities of nozzle cracking and

head wastage. The licensees performance provided no basis for assuring that the

degradation would be adequately managed or even discovered prior to pressure boundary

rupture.

In summary, the licensees performance was inconsistent in some manner with all of the

principles that are used in conjunction with low risk to find that an action or design change

is acceptable.

2

Davis-Besse SERP Attachment 2

December 6, 2002

MEMORANDUM TO: John A. Grobe, Chair

Davis-Besse Reactor Oversight Panel

Region III

FROM: Ledyard B. Marsh, Deputy Director /RA/

Division of Licensing and Project Management

Office of Nuclear Reactor Regulation

SUBJECT: RESPONSE TO REQUEST FOR TECHNICAL ASSISTANCE - RISK

ASSESSMENT OF DAVIS-BESSE REACTOR HEAD DEGRADATION

(TIA 2002-01)

In response to your request dated May 3, 2002, we have performed an assessment of the risk

associated with the control rod drive mechanism nozzle leakage and the resulting wastage cavity

in the Davis-Besse reactor pressure vessel head. The phenomena that produced the cavity were

not expected and are still not completely understood. Our analysis attempts to assemble the

available information and quantify the risk associated with the deficiencies in the licensees

performance that allowed these conditions to occur. Where the quantification of some risk

elements would be too uncertain, our analysis attempts to explore the implications of the plausible

ranges for parameters, rather than to focus on a single value.

As requested in your memorandum, our analysis used insights from ongoing Office of Research

(RES) activities to evaluate aspects of the degradation beyond your specific questions related to

the as-found condition. These analyses include the possibility of additional wastage creating a

larger cavity and the possibility of nozzle ejection due to circumferential cracking. Because the

wastage mechanism is not well understood, and because probabilistic risk assessments typically

do not address long-term degradation phenomena, we found that the available tools were not

sufficient to quantify the risk from additional wastage. The insights we did obtain are included in

our response to you because they provide additional perspective beyond what would be reached

by focusing solely on the probability of rupture for a cavity. As more information becomes

available from ongoing studies, it may be possible to derive additional insights and reach a

consensus on the methods best suited to the analysis of the wastage issue. At this time, the

results of our analysis of the potential for rupture due to cavity enlargement are too uncertain to be

added directly to the other parts of the analysis, but the results of the circumferential cracking

analysis are suitable for supporting the Significance Determination Process (SDP).

CONTACT: Steve Long, SPSB/DSSA/NRR

301-425-1077

J. A. Grobe

Also, as you requested, we have provided a discussion of the potential for using the principles for

integrated, risk-informed decision making (from Regulatory Guide (RG) 1.174) as a basis for

augmenting the risk analysis to determine the appropriate agency response. Based on the results

of our review, we believe the licensees performance was inconsistent in some manner with all four

principles that are used in conjunction with low risk to find that an action or design change is

acceptable.

Since two of the three degradation sequences studied could not be placed unambiguously into a

single SDP color range, and since other considerations (such as RG 1.174 safety principles) may

be relevant to the SDP and Enforcement Review Panel (SERP) deliberations, we have not

provided an overall SDP color for this performance deficiency. The selection of an appropriate

SDP color for use with the Action Matrix is a SERP responsibility. We conclude that the attached

information should be considered in the SDP color determination.

Our risk assessment and discussion of the use of the other risk-informing principles are provided

in Attachments A and B, respectively. Our responses to your specific requests are provided

below:

1. Develop an estimate of the increase in loss-of-coolant (LOCA) initiating event likelihoods

given the as-found condition of the reactor head.

Both the staffs and licensee's analyses for the failure pressure of the as-found cavity

resulted in estimates in excess of 7000 psig. Both of the respective uncertainty analyses

indicate that the probability for rupture due to pressure transients is very low. The staffs

analysis indicates that this probability is below 7 x 10-8/reactor-year. The licensee's

analytical approach, updated by the staff to reflect its latest failure pressure criterion,

results in a value below 1 x 10-4/reactor-year. The large numerical difference is an artifact

of the different approaches taken for the two analyses. It is inconsequential for purposes

of reaching a significance determination. Refer to pages 2 through 6 of Attachment A for

the supporting analyses.

It is important to note that these analyses treat the clad material as if it is a plate of uniform

thickness with uniform stress-strain properties obtained from small clad samples. The clad

was neither designed nor acceptance tested to serve as a structural element of the vessel

design, so it may contain structurally significant flaws that are not represented in the

analysis. The presence of large flaws could result in rupture at lower pressure and thus

increase these probabilities. Alternatively, the presence of small flaws could result in leaks

and cavity detection before the exposed area of clad has become large enough to rupture.

Therefore, it is not known whether inclusion of pre-existing flaws in the analysis would

increase or decrease risk until a quantitative analysis is performed with an appropriate flaw

size distribution.

2. Estimate the likelihood of an anticipated transient without scram (ATWS) as a

consequence of the LOCA, or if engineering review indicated that a reactor vessel head

LOCA will not cause an ATWS, then provide a justification for why further evaluation is not

warranted.

2

J. A. Grobe

The RELAP computer code was used to perform integrated thermal-hydraulic and reactivity

analysis for a spectrum of LOCA sizes with the break location on the reactor vessel head.

The results indicated that, for all LOCA sizes, the void formation due to boiling of the

coolant in the reactor would have a sufficient effect on the reactivity to stop the nuclear

fission chain reaction. When cool water from the emergency core cooling system is

injected into the core and the boiling stopped, the concentration of boron required to be in

the injection water is sufficient to maintain the shutdown condition.

3. Evaluate the change in core damage frequency ( CDF), the conditional core damage

probability (CCDP) and the change in large early release frequency (LERF) risk due to the

degradation of the vessel head.

The change in core damage frequency is obtained by multiplying the change in the LOCA

frequency by the CCDP for the appropriate LOCA size. The licensee provided an

evaluation of a medium LOCA CCDP to make it specific to the size of the as-found cavity,

with a resulting probability of 2.91 x 10-3. Multiplying the staffs update for the licensee's

estimated contribution to the LOCA frequency for the as-found cavity would produce CDF

contributions of less than 3 x 10-7/reactor-year. Estimates of CDF based on the staffs

results for cavity failure probabilities at various pressures were not calculated because the

licensee's approach produced larger results that were still in the lowest risk category for the

SDP process. The staffs analysis also considered the results of GSI-191 concerning the

potential for emergency core cooling system (ECCS) sump clogging. See pages 12

through 18 in Attachment A for a description of our supporting analyses.

The conditional containment early failure probability for these LOCAs is estimated to be

about 0.006. Because the numerical thresholds for the LERF color categories are a factor

of 0.1 times the numerical thresholds for the corresponding CDF categories, the LERF

increase for this performance deficiency will not be as significant as the CDF increase for

purposes of establishing the risk significance.

4. Utilize risk insights from ongoing RES activities, which may be evaluating other accident

aspects for the reactor head degradation.

The licensee's performance deficiencies resulted in prolonged, undetected leakage of boric

acid onto the reactor head through axial cracks in multiple control rod drive mechanism

nozzles. This increased the probability for a LOCA by two mechanisms:

a) After they became wet, the external surfaces of the leaking nozzles could develop

circumferential cracks which could grow large enough over time that a nozzle could

break above the weld and be ejected from the head.

b) A cavity could develop due to corrosion wastage of the low-alloy steel portion of the

reactor vessel head and grow large enough over time that the clad exposed

beneath the cavity could rupture during normal operation or anticipated pressure

transients.

3

J. A. Grobe

In fact, two nozzles were developing wastage cavities and one of those two nozzles also

was found to be developing a circumferential crack. Thus, analyses restricted to the risk

associated with the as-found dimensions of one cavity do not necessarily provide an

adequate perspective on the risk associated with the licensees performance deficiencies.

The analyses we provide on pages 6 through12 of Attachment A use results of ongoing

RES studies to gain additional insights and useful perspectives on these two sources of

risk. Because there is much that is not known about the phenomena and the probabilistic

aspects of these two degradation mechanisms, some of our analyses attempt to define

logical limits to the possible ranges of results.

The results of our analyses for circumferential cracking indicate that there was sufficient

time during the estimated 6-8 years that Nozzle #3 was leaking for a circumferential crack

to develop and grow large enough to cause the nozzle to be ejected. We do not know the

actual stress levels in Nozzle #3 nor the cracking rate as a function of stress for the

material used to fabricate the nozzle. However, because the same material cracked in a

greater fraction of the nozzles at Davis-Besse and appears to have leaked earlier in the

plants life than at Oconee 3, we infer that the residual stress levels must be relatively high

at Davis-Besse. Because the material has cracked more rapidly than other operating

Babcock and Wilcox plants, we also used a range of cracking rates indicative of the worst

heat of material in the available laboratory data. These assumptions, are not necessarily

bounding. So, the results should be used as an indication of what the risk may be, based

on what we know today. The results are about 3 x 10-2/reactor-year for increase in the

LOCA frequency and about 8 x 10-5/reactor year for the corresponding increase in CDF.

This result alone, puts the CDF increase in the 10-5/RY range, with uncertainty from as

high as the low 10-4/RY range to the low 10-5/RY range.

Analysis of the risk associated with the potential growth of wastage cavities beyond the

as-found condition is difficult. Typical risk assessment approaches would explore

variations in corrosion rates, leak rates, time available, cavity shapes, clad strength, clad

flaw densities and size distributions to estimate the change in LOCA frequency associated

with the finding of reactor vessel head damage. However, there is little information that

can be used to quantify the probability distributions for many of the important variables in

this case. Thus, we were unable to reach a consensus for a probabilistic treatment of the

time available for wastage to occur. Therefore, even very precise probabilistic analyses of

the physical cracking and corrosion phenomena would leave the analysis incomplete. The

results of our partial analysis in this area are provided with the recognition that they do not

quantify the risk increase due to potential for cavity growth to a different size before

discovery. Although the results of this part of the assessment cannot be directly added to

the results of the more definitive parts, they do provide additional information that can be

used to assess qualitatively the adequacy of the definitive parts for determining the overall

risk significance.

The results of our analyses for potential growth of wastage cavities beyond the as-found

condition indicate that it was possible. At the most-rapid growth rates indicated to be

possible by the results of laboratory experiments involving solid boric acid crystals on wet,

4

J. A. Grobe

heated steel, an additional 1 to 2 years of operation would enlarge the cavity sufficiently to

allow rupture, depending on cavity shape. Alternatively, at the

average corrosion rate estimated by the licensee, an additional 4 to 7 years of operation

would be required. It is also important to note that there are some reasons to suspect that

the physical processes that developed the as-found cavity may become self-limiting at

some cavity size, so that it may not even be possible to develop a cavity that is large

enough to burst with leakage rates limited by the plants technical specifications.

Alternatively, modest enlargement of the as-found cavity could have completely exposed

Nozzle #11, potentially introducing additional failure mechanisms and additional

opportunities for discovering the cavity before failure occurred. Thus, this part of the

analysis is unusually difficult and the available data provide limited opportunities for

quantifying results. However, we believe that the potential for a larger cavity to have

formed is an essential consideration for assessing the significance of these findings.

5. Evaluate the licensees deterministic and risk-based assessments to determine if their

bases for an increase in CDF of 1 E-5 is valid.

The licensees risk assessment was based on a deterministic analysis of the failure

pressure for the as-found cavity, a choice for a mathematical formula that was assumed to

represent the probability distribution for failures at other pressures, and an assessment of

the plants historical frequency of reactor coolant system (RCS) pressure transients. These

were mathematically combined to produce an estimated frequency that the RCS would

attain a pressure that would have caused the as-found cavity to fail.

We reviewed the licensees analysis and re-evaluated the results of that approach using

newer information and a correction to the calculation process. The licensees analysis

started with an estimated cavity rupture pressure of 5600 psig. This pressure value was

developed using a finite element, elastic-plastic numerical model and a criterion for

deciding when the results of the model indicated that conditions had been reached that

correspond to failure of the physical material. When some physical testing data was used

to tune this model, a better estimate of the failure pressure was possible. Based on

additional work by the licensees contractors and RES contractors, we currently estimate

the failure pressure to be about 7980 psig. We also reviewed the licensees estimates for

frequencies of RCS pressure transients and found them to be reasonably consistent with

expectations and available reports of transient events. In reevaluating the licensees LOCA

frequency calculation using the updated rupture pressure result, we noted that the logic in

the licensees approach represented pressure transients that begin at zero pressure, rather

than at normal operating pressure. This "over-counts" the probability that the cavity would

fail at normal operating pressure by a factor equal to the sum of the frequencies of the

transients in each of the "bins" used to group the pressure transients within pressure

ranges. Using the licensees choice of a log-normal distribution for the failure pressure with

the new median failure pressure estimate and the corrected process for combining the

failure probabilities with the pressure transient frequencies, the CDF result was greatly

reduced to about 3 x 10-7/reactor-year. Because this was already below the threshold of

10-6/RY, we did not continue to apply corrections that would have the effect of further

reducing the result.

5

J. A. Grobe

Two undermining aspects of this analysis should be considered in any application of this

result. First, the analysis does not consider the probability that a structurally significant flaw

in the clad material could be present in the exposed clad area. The potential effects of

flaws have been discussed in our response to Item 1 and will not be repeated here.

Second, the use of a log-normal distribution to represent a probability of failure at

pressures around 2200 psig is essentially meaningless for a median pressure as far from

that value as the 7980 psig is in this case. The result of this analysis is essentially an

artifact of the choice of the log-normal function to represent the probability distribution. To

obtain a numerical result that can be reliably related to physical reality, it would be

necessary to conduct a better probabilistic analysis that explicitly uses a clad flaw size

distribution derived from data on real clad layers.

In conclusion, although the results of our analyses suggest that the risk due to potential rupture of

the as-found cavity may be very low (i.e., <10-6/RY), the analysis uncertainty is large, since the

analysis used a simplistic model that treated the cladding as a plate and the effects of flaws in the

clad material were not considered. We believe that this result alone does not provide an adequate

representation of the risk associated with the licensees performance deficiencies which allowed

that cavity to develop. Our analyses of the potential for circumferential cracking and nozzle

ejection indicate that the risk from that phenomenon is in the range from 10-5/RY to 10-4/RY. Our

analyses of the potential for further cavity growth leading to rupture of the underlying clad were

unable to quantify the additional risk. Thus, it is not known whether the total risk attributable to

these deficiencies exceeds 10-4/RY. From a public safety standpoint, we believe it is prudent to

respond to the broader implications rather than to rely on the low risk level indicated by the narrow

perspective of the analysis for the as-found condition, alone.

In addition to the assessment described above and detailed in Attachment A, which evaluated the

risk based on available information, NRR also has evaluated its analysis and decision making

process used related to the delay in the CRDM inspection at Davis-Besse. This staff evaluation of

the Davis-Besse response to NRC Bulletin 2001-01 was forwarded to the licensee by letter dated

December 3, 2002, and is in ADAMS at ML023300539. Also, for completeness, a senior staff

member provided comments regarding his concurrence on the product provided to the Division of

Licensing Project Management. The staff reviewed the staff members comments and have not

included them in this transmittal because the comments serve to reinforce the fact made in the

analysis that there is considerable uncertainty in the analysis.

Attachments: As stated

cc w/atts: W. Lanning, RGN- I

C. Casto, RGN-II

D. Chamberlain, RGN-IV

6

Risk Assessment and Insights in Support of Phase 3 Risk

Significance Determination for the Control Rod Drive Mechanism (CRDM)

Nozzle Cracking and Associated Reactor Pressure Vessel (RPV) Head

Wastage Event at the Davis-Besse Nuclear Power Station

During an inspection of the CRDM nozzles in the spring of 2002, the licensee discovered three

nozzles were leaking through axial cracks, and that one of the leaking nozzles had begun to

develop a circumferential crack. During repair of another one of the leaking nozzles, it became

loose in the RPV head. Subsequent investigation revealed that a cavity had formed around that

nozzle in the low-alloy steel portion of the RPV head, leaving only the stainless steel clad material

as the reactor coolant pressure boundary over an area of approximately 20 square-inches. In their

root cause analysis report, the licensee concluded that the axial crack in the affected nozzle had

most probably been leaking for a period of 6 to 8 years before detection. A similar but much

smaller cavity was subsequently identified at the location of the leaking crack in another of the

degraded nozzles.

The purpose of this analysis is to assess the degree of risk associated with the deficiencies in the

licensees performance which allowed these conditions to occur. The analysis attempts to quantify

the risk to the extent practicable with the limited data available and the limited understanding of the

phenomena involved. Where a consensus could not be reached on an approach to quantify some

risk elements, this analysis attempts to develop a broad perspective and obtain useful insights

relevant to the unquantified parts. Those insights are provided to serve as qualifiers to the

incomplete risk total developed from those elements that we were able to quantify.

Statement of the licensee performance deficiency :

The licensee failed to properly implement a boric acid wastage prevention program, which allowed

reactor coolant system (RCS) pressure boundary leakage to occur undetected for a prolonged

period of time. Also, the licensee failed to implement an inspection program for the detection of

reactor coolant pressure boundary leakage that adequately addressed RCS degradation

mechanisms that industry experience had indicated were applicable to the Davis-Besse plant. In

addition, the licensee failed to implement an adequate corrective action program to properly

disposition anomalous indications in plant data and correct their causes.

Accident sequences that contribute increased risk:

The licensees failure to detect the leakage from CRDM nozzles for an extended period of time

could have lead to the failure of the reactor coolant pressure boundary by three mechanisms:

1. The section of clad that was exposed by wastage of the RPV head could have

failed if the cavity had formed at a weaker point in the clad or the reactor had

experienced a transient condition that caused the pressure in the RCS to exceed its

normal pressure of operation.

Attachment A

1

2. The wastage cavity could have grown larger before discovery, allowing it to fail at a

lower RCS pressure, including normal RCS operating pressure.

3. The extended period of exposure of the outside of the CRDM nozzles to RCS

coolant could have allowed the formation and growth of a circumferential crack

sufficiently large to cause the nozzle to fail and be ejected from the RPV head.

In each of these three cases, a loss-of-coolant accident (LOCA) would have resulted from the

failure of the RCS pressure boundary. In cases 1 and 3, the LOCA would have been in the

"medium" range, requiring both high-and low-pressure emergency core cooling system (ECCS)

equipment to prevent reactor core damage. For case 2, the size of an unflawed clad area that

must be exposed in order to fail at normal operating pressure creating a LOCA is in the "large"

category, but still within the design limits of the ECCS system. LOCAs in the "large" range require

operation of core flood tanks and the low pressure ECCS pumps to prevent core damage.

The probability that the ECCS would fail to prevent core damage was calculated previously for

both of these LOCA sizes in the Davis-Besse individual plant examination. What remains to be

assessed for this analysis is the increase in the LOCA frequencies of medium and large LOCAs

that can be attributed to the licensees performance deficiencies. When combined with the

conditional core damage probabilities (CCDPs) for the appropriate size LOCAs, the estimated

changes in the frequencies produce estimates for the increase in core damage frequency

attributable to the performance deficiency.

Probability of burst during reactor operation for the as-found cavity:

The cavity as found at Davis-Besse did not burst during operation. However, during the period of

its exposure, the RCS pressures did not significantly exceed the normal operating pressure of

2185 psig. Operational experience at Davis-Besse and other plants indicates that there is a

modest frequency of transient events that cause the RCS pressure to temporarily increase.

Therefore, part of the risk assessment process is to determine the probability that the RCS

pressure could have reached a value sufficient to burst the cavity.

The power operated relief valves and safety valves (SVs) located on the pressurizer actuate at

high pressure to limit RCS pressure increases. The SVs at Davis-Besse limit RCS pressure to

2550 psig for design-basis accidents. The licensee has provided a table of the number of times

the Davis-Besse RCS has reached various pressure levels above its normal operating value.

None of these pressure transients has reached the SV setpoint at Davis-Besse. However, other

plants have experienced pressure transients that actuated their pressurizer SVs. Davis-Besse

provided an estimate of the frequency of reaching the SV setpoint, using the number of years of

operation and a Bayesian statistical process. That estimate appears to be reasonable and slightly

conservative in comparison with the statistics available for the operational transients at other

plants.

For the RCS pressure to increase beyond the SV setpoint, an operational event that is more

severe than the plant is designed to handle would need to occur. Previous probabilistic analyses

have identified an event that has these characteristics, a total loss of feedwater with failure of the

control rods to insert and stop the nuclear chain reaction in the reactor core. These types of

2

events are called anticipated transient without scram (ATWS) events. The frequency estimated for

this type of event is less than 1 x 10-5/RY in probabilistic risk assessments (PRAs).

On the basis of these considerations, the frequencies used in this analysis for reaching various

pressure levels in the Davis-Besse RCS are listed in Table 1.

Table 1. Frequency of Operation within Specific RCS Pressure Ranges at Davis-Besse

RCS Pressure Frequency of Occurrence Frequency of Exceeding Range Base

2185 psig 1.0 [during operation] 1.0 [during operation]

2250-2300 psig 0.254/reactor-year 0.95/reactor-year

2300-2350 psig 0.508/reactor-year 0.698/reactor-year

2350-2400 psig 0.127/reactor-year 0.190/reactor-year

2400-2450 psig 0.0635/reactor-year 0.063/reactor-year

2450-2550 psig 0.0317/reactor-year 0.0317/reactor-year

>2550 psig <0.00001/reactor-year < 0.00001/reactor-year

The Oak Ridge National Laboratory (ORNL) has estimated the failure pressure for the as-found

cavity to be 7,353 psig (reference 1). This is intended to be a conservative estimate, based on

minimum strength properties of the type of material used to form the clad, an intentional

over-estimate of the exposed clad area, and a uniform clad thickness that was the minimum value

initially reported by the licensee under the cavity, 0.240 inch. (More recent measurements have

decreased the minimum thickness to about 0.20 inch, but the average is about 0.25 inch.) The

failure pressure was estimated from the results of a nonlinear, finite-strain, elastic-plastic,

finite-element model that was tuned to the results of a set of 9 physical burst tests conducted

under the sponsorship of the American Society of Mechanical Engineers (ASME) Pressure Vessel

Research Committee Subcommittee on Effective Utilization of Yield Strength in 1972 (reference 2).

The pressure at which this model reached instability was increased by a factor of 1.1 to estimate

the median failure pressure for the cavity.

ORNL also used the variability in the results of those 9 tests to estimate the uncertainty in their

estimate of the failure pressure for the physical conditions assumed in their analysis. A cavity clad

burst pressure as low as 5900 psig would be within the variability exhibited by the burst tests.

However, it is not credible that a reactor could achieve this pressure, because other components

are expected to fail at lower pressures and stop the pressure increase at a lower value.

Extrapolation of the variability in the burst tests to estimate probabilities of failure at lower RCS

pressures depends on the subjective selection of a mathematical relationship. ORNL evaluated

several mathematical functions, and found six that are consistent with the spread in the burst test

data. Using all six distributions, the average probability of cavity failure at normal operating

pressure is estimated to be 6.9 x 10-8, and the probability at the safety valve setpoint pressure is

estimated to be 3.6 x 10-7. As will be shown later in this analysis, probability values that are low,

produce core damage frequency contributions ( CDFs) that are well below the threshold of 1 x

10-6/RY used in the setdown pool (SDP). Likewise, the frequency of an ATWS event at < x 1

0-5/RY is too low to produce a CDF above that threshold by creating pressures with higher failure

probabilities.

Therefore, the ORNL analysis establishes a definitive significance result for the as-found cavity,

with one caveat: the effects of defects in the clad material were not considered in the analysis.

3

The ORNL probabilistic analyses are based on the variability in the results of the ASME tests for 9

disks fabricated from plate material. The floor of the cavity is modeled as a uniformly thick plate of

material with uniform properties. However, the remaining clad at the bottom of the cavity in the

Davis-Besse RPV head is not plate material; it is a weld overlay that was not fabricated or

acceptance tested to serve as a pressure boundary. There is some probability that the clad could

be weakened by incomplete fusion between some of the sequentially applied strips of weld metal.

From a risk perspective, the potential occurrence of flaws in the cladding does not necessarily

increase the risk. If small flaws are more prevalent than large flaws, then it is conceivable that

they could enhance the probability that the initial failure is a detectable leak, rather than a gross

rupture of the exposed clad material. That effect would reduce the probability of burst and lower

the risk. Alternatively, if large flaws are more prevalent, they could increase the probability of

rupture at realistic RCS pressures and thus increase the risk above the values estimated for failure

of the as-found cavity in this analysis. Some data have been produced on the frequency of

occurrence and size distribution of flaws RPV clad. Application of that data would be the logical

next step if there is a need to improve this analysis.

The licensee submitted a risk analysis (references 3,4,5) based on the average thickness of the

clad under the cavity (0.297 inch) and an estimated exposed clad area of 20.5 square inches. The

numerical model reached instability at a pressure of 7219 psig. Using the ORNL relationship

between the pressure of numerical instability and the physical failure pressure, the projected

median failure pressure would be 7982 psig.

The licensees analysis used a log-normal distribution for the probability of failure as a function

of pressure:

f = { ln(P/Pm) / C } where: f = probability that failure occurs at pressure P(psig)

PM= median pressure capability (psig)

P = pressure capability variable (psig)

C = composite logarithmic standard deviation for

randomness

= gaussian cumulative distribution function

The licensee chose a value of 0.33 for c from references 6 and 7. This is composed of

coefficients of variation as follows:

0.1 for the coefficient of variation for plastic collapse for semi-ellipsoidal heads;

0.29 for the coefficient of variation of the yield strength of stainless steel at 605 oF;

0.11 for the coefficient of variation for buckling capacity developed from the test results.

C is calculated as the square root of the sum of the squares of these constituent values.

Values of C in the cited references ranged from 0.06 to 0.39, so the licensees choice is near the

conservative end of the range.

Reproducing the licensees approach to the uncertainty with the updated estimate of 7941 psig for

the median cavity failure pressure (reference 5), the probabilities for rupture at the pressures of

interest are given in Table 2.

4

Table 2. Probability for As-Found Cavity Rupture as a Function of Pressure, Using

Licensees Variability Assumptions

RCS Pressure Probability of Failure

< 2185 psig 4.32 x 10-5

< 2250 psig 6.23 x 10-5

< 2275 psig 7.13 x 10-5

< 2325 psig 9.29 x 10-4

< 2375 psig 1.20 x 10-4

< 2425 psig 1.53 x 10-4

< 2475 psig 1.94 x 10-4

< 2525 psig 2.44 x 10-4

< 3000 psig 1.51 x 10-3

< 3500 psig 6.24 x 10-3

< 4000 psig 1.81 x 10-2

< 4500 psig 4.12 x 10-2

A finite probability of failure at 2185 psig, despite the fact that the cavity survived normal operation

at that pressure for a significant period, could be attributed conceptually to the probability that the

clad material has a small random probability for being substantially weaker at the location of the

cavity. However, the extrapolation of the uncertainty in the failure pressure from over 7000 psi to

about 2000 psi goes far beyond the range of the data to which these mathematical functions have

been fitted. Therefore, it is unrealistic to expect this mathematical function to produce accurate

probability estimates in this case.

To probabilistically combine the frequencies of pressures in the RCS with the probabilities for

failure at the various pressures, it is necessary to consider that the RCS was maintained at

approximately 2185 psig for the entire year of operation, plus it had some probabilities of

exceeding that pressure by the specified amounts for a short period at some time during the year.

So, the probability for failure at 2185 psig is used directly as part of the failure probability for the

as-found cavity, because it is assumed that the cavity experienced that pressure in its as-found

condition with a probability of one. For the probability of failure during pressure transients, it is

necessary to account for the fact that the cavity did not fail at normal operating pressure, so the

probability of failure at 2185 psig is subtracted from the probabilities for failure at the midpoints of

the other pressure ranges and the differences are multiplied by the frequencies of pressure

transients within those ranges. For pressure transients up to the safety valve setpoints, the result

is 9.7 x 10-5/RY. About 45 percent of this value comes from the probability for rupture at normal

operating pressure.

As can be seen from the probabilities for cavity rupture at pressures between the safety valve

setpoints and 4500 psig, those probabilities would not add significantly to this result when

multiplied by the frequencies below 1 x 10-5/RY for ATWS events that would be capable of

attaining those pressures.

The 55 percent of the rupture probability that comes from pressure transients was calculated as if

the cavity existed at its as-found size for a whole year. It would be necessary to reduce that

portion of the probability to reflect the fact that the cavity was growing during operation, and thus

5

was stronger for most of the year prior to its discovery. The magnitude of that adjustment

depends on the cavity growth rate, which will be addressed in the next section of this analysis.

However, as will be shown in a later section of this analysis, the unadjusted probability estimate,

when multiplied by the conditional core damage probability for a LOCA of the size of the exposed

clad area, will result in a core damage frequency increase below the 10-6/RY threshold.

Therefore, additional probability reduction factors will not be addressed in this analysis.

In summary, the estimated rupture pressure for the as-found cavity exceeds 7000 psig in both the

Nuclear Regulatory Commissions (NRC's) and licensee's analyses. The uncertainties considered

in these analyses are not large enough to produce a significant probability that the cavity would

rupture at RCS pressures below the safety valve setpoints. A potentially significant unanalyzed

factor is the probability for flaws in the clad to produce failure at lower pressures. It is not known

whether this factor would increase or decrease the overall risk.

Probability that the cavity could grow large enough to burst before discovery:

For the cavity to have grown to a different size by the time it was discovered, one or more things

would have had to occur differently from what actually did occur in the past, which caused the

cavity to reach a particular size and to be discovered on a particular date. Risk assessment

techniques are intended to explore the effects of plausible variations in what did happen to

understand what might have happened and what the probabilities were for different outcomes.

Typical risk assessment approaches would explore variations in corrosion rates, leak rates, time

available, cavity shapes, clad strength, and flaw sizes and densities in clad material to estimate the

change in LOCA fervency associated with the finding of reactor vessel head damage.

However, this case is somewhat atypical and more complicated to analyze. It was the initial

discovery of a different phenomenon (circumferential cracks in CRDM nozzles) at a different plant

(Oconee unit 3) that caused the inspection at Davis-Besse which led to discovery of the cavity that

is the subject of this analysis. Thus, this case involves the actions of other licensees and the NRC

staff to limit the period in which degradation was allowed to occur, whereas a more typical

significance determination would only need to assess the potential for variations in the actions of

the licensee that is the subject of the finding.

Complete assessment of all potential variables would be required to establish the precise level of

risk increase. However, it typically is infeasible to produce a complete risk analysis. Typically,

analysts attempt to identify the parameters that have the most substantial effects on the results

and evaluate those, while simply showing the others to be unimportant to the results. An analysis

that fails to evaluate a parameter that can substantially alter the results is too incomplete to be

used as a basis for a regulatory decision. When limitations in available information and/or

analytical capabilities make it infeasible to produce an analysis complete enough to support its

purpose, it is the responsibility of the analyst to make that clear.

Unfortunately in this case, there is little information that can be used to quantify the probabilities

for many of the important variables. The timing of the formation of the cavity actually found at

Davis-Besse is not definitively established by the available information. The actual rate of reactor

coolant leakage into the cavity is not known as a function of time. The corrosion phenomena that

produced the cavity are not understood well enough to specify the rates of corrosion or the shapes

6

that could have occurred, or even whether there is dependence on leak rate or a limit on the size

of the cavity that can result. In addition, because the crack growth appears to depend on the time

that the plant was running at power, and the cavity growth appears to require the reactor coolant

system to be pressurized and hot, the size of the cavity eventually discovered appears to depend

on the operating history of the plant at times even

before the licensees performance deficiency occurred. Thus, the risk is sensitive to the

relationship between the plants total operating history and the timing of the cavity discovery. That

relationship introduces some possibilities that are particularly difficult to analyze in this case. What

if the discovery of circumferential nozzle cracks at Oconee unit 3 had occurred at a later date?

What if the history of operation of Davis-Besse had provided more opportunity for crack and cavity

growth before February 2002? We were unable to reach a consensus with our NRC colleagues

on a relevant and appropriate probabilistic approach for addressing the time parameter intrinsic to

these questions. However, the relative timing of the discovery in the context of the unmonitored

progression of the plants degradation appears to have the potential to substantially affect the

results of the analysis. Therefore, even very precise probabilistic analyses of the physical cracking

and corrosion phenomena would leave the risk analysis incomplete.

The following analysis is provided with the recognition that it cannot be complete enough to

quantify the risk increase definitively due to potential for cavity growth to the point that the

underlying clad material ruptures. It attempts to identify the important parameters and to provide

information that plausibly limits the applicable range of variation for their values in this case. It

does not attempt to estimate the range of risk results that those variations could produce.

Although the results of this part of the assessment cannot be directly added to the quantitative risk

results from the other parts, they do provide additional information that can be used to qualitatively

assess the adequacy of the quantified parts for determining the overall risk significance. As more

information becomes available from ongoing studies, it may be possible to derive additional

insights and reach consensus on methods to assess this contribution to the risk.

Cavity size needed to fail during normal operation:

Based on the analyses provided by the Office of Nuclear Regulatory Research (reference 9), a

cavity would have to grow to cover an area of approximately 330 square-inches in order to rupture

at normal operating pressures, assuming a shape similar to that of the as-found cavity. This would

require growth by about 15 inches in the longest cavity dimension. If the cavity grew into a more

rounded shape, it might fail under normal operating pressures with an area of about 250 square

inches. That shape would require approximately 7 inches of additional cavity growth, assuming

growth occurred uniformly in the down-hill and side-hill directions, but not the up-hill direction.

Because none of the corrosion experiments in the literature formed large cavities, there is some

potential for unknown factors to limit the corrosion process such that cavity growth stops at some

maximum size. If such a size limit exists, then the probability that the cavity could rupture may be

substantially reduced. However, there currently is no data useful for quantifying that potential so

that it can be included in this analysis.

7

Cavity growth rate :

Based primarily on the observed levels of boric acid particles in the containment atmosphere, the

licensees Root Cause Analysis Report speculates that the cavity found in the RPV head grew at an

average rate of 2-inches/year over the 4-year period of the last two operating cycles.

This appears to be a reasonable interpretation, but the available evidence is certainly not

conclusive, and other interpretations are also reasonable. The licensees report also states that, by

making a "bounding assumption" that there was a linear rate of increase over time for the

cavity growth rate, "the maximum corrosion rate near the end of cycle 13 would be about 4.0

inches/year." However, no basis is provided to support the assertion that a linear increase with

time is physically bounding or otherwise supported by the available information.

There are multiple reasons to suspect that the cavity growth rate did not increase at a linear rate (or

less) for a period of 4 years. From basic principles, if an axial crack grew at a constant rate over

those 4 years, the leak rate would have increased exponentially because leak rate has been shown

to be an exponential function of crack length. If the crack tip had reached a region of low residual

stress in the nozzle material, it is possible that the crack growth rate would have substantially

decreased. However, complete arrest of the crack growth appears unlikely given the stress levels

created at the tip of the crack by internal pressure forces and the high crack growth rate exhibited

by this nozzle material. Also, the rate at which air filters inside containment needed to be changed

over the 4-year period indicates that a substantial increase in the amount of airborne boric acid

occurred during the period. Although the rate of increase appears to be more exponential than

linear, it is not feasible to quantify the erosion rate based on the available air filter data.

The physical shapes of the cavities at Nozzles 2 and 3 also suggest that the cavity at Nozzle 3 grew

in multiple phases. The cavity at Nozzle 2 followed the nozzle contour over a small fraction of its

circumference and spanned the annulus length from near the J-groove weld to the top of the RPV

head. This suggests that the leakage was directed upward onto the upper surface of the head,

probably in the form of steam for low rates of leakage. The upper portion of the cavity around

Nozzle 3 is dish-shaped, suggesting that the leak rate eventually increased to the point that a liquid

puddle formed on the head surface and was corroding the head in a downward direction. Below the

dish-shaped portion of the cavity is another shaped like a football with its nose pointing away from

the nozzle in the direction that the axial crack was focusing the leakage. This section is not smooth,

as would be expected if the cavity were excavated by erosion from an escaping jet of steam or

water. Its surface is pocked, suggesting corrosion by a liquid pool or slurry. The licensees root

cause report proposes that the pool was either an aqueous solution of boric acid, or a pool of molten

orthoboric acid crystals continuously hydrated with water from the nozzle leak.

Corrosion rates for aqueous boric acid solutions in a variety of physical situations are provided in the

Electric Power Research Institute Boric Acid Corrosion Guidebook (reference 8). Typically, the rates

are below 2-inches/year for most physical situations. However, there are no physical test results

available for a situation like the postulated pool of molten orthoboric acid hydrated by a low rate of

water leakage into the pool. The closest situation covered by the Guidebook appears to be the tests

where an aqueous solution of boric acid flowed across a low-alloy steel surface that was heated to

600 oF. In the central portions of the surfaces wetted by the aqueous solutions, the corrosion rates

were similar to that observed for steel immersed in a boric acid solution. However, at the edges of

8

the wetted surfaces where the boric acid solution became saturated and solid crystals were formed

with continuing hydration from the wetted areas, local corrosion rates as high as 7-inches/year were

reported. Therefore, it seems prudent to consider the possibility that the last stages of cavity growth

on the Davis-Besse RPV head may have experienced corrosion rates on the order of 7-inches/year.

At that rate, the football-shaped portion of the cavity could have begun developing in the latter half of

the last operating cycle and reached its observed size by February 2002, when the cavity was

discovered. An interesting coincidence is that there was an abrupt decrease in the necessary rate

for CAC cleaning in May of 2001, suggesting that something about the leakage path had changed at

that time. The change may have been only in the path past the insulation that the airborne particles

followed to reach the containment atmosphere, or it may signify that the leakage had been directed

into the pool in the cavity at that time, starting the formation of the footbal-shaped portion. The

containment radiation monitors showed continuing increases in the RCS leak rate until about

December 2001.

Because the observed size of the cavity is over 6 inches in depth and about 6 inches radially from

the leaking crack, average corrosion rates less than 1.5 to 2 inches/year would be inconsistent with

the licensees proposed time-line for cavity formation. Maximum rates as high as

7-inches/year would be consistent with the experimental results in aqueous boric acid solutions

where solid boric acid crystals are on a heated, wetted steel surface.

For purposes of this analysis, two plausible cases are considered. One uses 2 inches/year as a

lower bound for the maximum growth rate. The other addresses the implications of the rapid

corrosion rates up to 7 inches/year associated with the hydrated boric acid crystals. It is not known

at this time which case or what intermediate value is more likely.

Time for cavity growth:

In order to evaluate the range of sizes that the cavity might have reached before discovery, it is

necessary to consider the potential variability of the corrosion rate in the context of the potential for

variation in the amount of time available for the corrosion to occur before discovery. For corrosion to

occur, first an axial crack had to initiate and grow large enough to penetrate the nozzle and leak

coolant onto the low-alloy steel that is exposed on the outside surfaces of the reactor head. Both

the cracking process and the corrosion process appear to occur when the reactor is operating, but

not when it is shut down. So, the amount of reactor operation that occurred prior to discovery of the

cavity appears to be the relevant time parameter for determining the final size of the cavity.

That is not a typical circumstance for risk assessments and significance determinations. Usually, it

is the duration of the performance deficiency that is the relevant factor limiting the risk. In this case,

there are a large number of historical factors that, acting together, limited the risk by resulting in the

development and discovery of two large circumferential cracks at Oconee unit 3, causing the

subsequent inspections and repairs that ultimately revealed the occurrence of the wastage

phenomenon at Davis-Besse. The complexity of this case introduces factors that are not addressed

by available PRA tools. We were unable to reach a consensus with our NRC colleagues on a

relevant and appropriate approach, supported by data, for quantifying this part of the risk

assessment. Therefore, this part of the analysis does not produce a numerical result that can be

combined with the results of the other parts, which makes the total incomplete by an amount that

may or may not be substantial.

9

Available insights on the potential for wastage to the point of cavity rupture:

Combining the two corrosion rate cases and the amounts of growth needed to reach the point of

rupture for different shaped cavities produces a range of estimates for the amount of additional

operating time that the cavity would need to grow large enough to rupture at normal operating

pressure. For corrosion rates on the order of 2 inches per year, it would require the cavity to grow

for 7 years in a shape similar to what was found or another 4 years into a more rounded shape

before rupture is predicted. For the higher corrosion rate case of about 7 inches/year, only another

1 to 2 years of operation could be sufficient to produce a rupture, depending on the shape the cavity

took.

However, it must be recognized that the failure pressure analyses used to make these estimates do

not include some factors that may change both the size that the cavity would attain before failure

and the manner in which failure would occur. The potential importance of flaws in the clad layer was

discussed in the section of this assessment that addresses the as-found cavity. In addition, all the

enlarged cavity shapes would completely engulf Nozzle 11. Nozzle 11 and its attached J-groove

weld would create a circular area in the exposed clad material that would not stretch and is

constrained against tilting after small amounts of deflection. It is apparently free to rise and fall in

the vertical direction. Adding these constraints to the clad material stress-strain calculations may

have some reinforcing effects on the clad. However, the long, free-standing CRDM nozzle and

housing assembly may also experience significant vibrations during operation, once wastage of the

head material frees the nozzle from constraint within the head. It is conceivable that vibrations might

fatigue the clad metal at the edge of the J-groove weld and cause a failure that would eject the

nozzle and weld, together, resulting in a medium instead of a large LOCA from an enlarged cavity.

Alternatively, the vibrations conceivably might result in anomalous instrument readings in the control

room, leading to investigation that results in the discovery of the loose nozzle and cavity before a

rupture occurs. Similarly, unusual displacement or looseness of the CRDM on Nozzle 11 might be

noticed during an outage for cases where corrosion rates are slow enough to incur an outage at an

opportune time. Similarly, a small amount of additional wastage in the uphill direction could have

created the same conditions for Nozzle 3. Any or none of these considerations could substantially

change the risk calculations if their effects could be quantified.

Probability that a circumferential crack could grow large enough to eject a CRDM nozzle:

Four nozzles in the center of the RPV head do not have demonstrable annular gaps at operating

conditions. For this reason, there was a concern that leakage from a nozzle crack deep in the

annulus would not reach the top of the reactor head to leave visible deposits. Therefore, visual

inspection was not a qualified technique for detecting leakage through axial cracks in these nozzles.

The licensees Risk Assessment of CRDM Nozzle Cracks (reference 10), submitted on November 1,

2001, excluded these four nozzles from the analysis on the basis that they were not prone to

circumferential cracking due to the residual stress fields associated with their location in the center

of the RPV head, and they therefore were not risk significant. Within two weeks of that submittal,

the fall inspection at Oconee Unit 3 revealed circumferential cracking in a central nozzle (No. 2).

Also, the fall inspection at Oconee Unit 3, reinforced the finding from the spring 2001 inspection at

the same unit, which revealed that the heat of material used to fabricate the nozzles for that unit was

exhibiting an unusually high incidence of cracking and leakage. The five central nozzles at Davis-

Besse are fabricated from the same material. Subsequent inspection of the central nozzles at

10

Davis-Besse in the spring of 2002, revealed that four of those five nozzles had developed axial

cracks, three were leaking and one of the leaking nozzles (No. 2) had developed a circumferential

crack. The size of the circumferential crack, as determined by ultrasonic testing (UT), was

approximately 30°. However, this size characterization is considered to be highly uncertain on the

basis of comparisons between UT sizing and physical examination of the two circumferential cracks

that were first found at Oconee Unit 3 in the spring of 2001. For those 2 cracks, both of which were

physically measured to extend about 165°, UT did not detect one and sized the other as 60°.

Therefore, the best evidence is that the central nozzles are subject to circumferential cracking with a

probability similar to other nozzle locations. The available physical evidence is not adequate to

demonstrate that circumferential cracking is less rapid in the central nozzles than it is elsewhere on

the head.

The licensees root cause report provides estimates that Nozzle 3 had been leaking since 1996 or

1994. Thus, the Nozzle 3 annulus was potentially subject to circumferential crack development and

growth for a period of 6 to 8 years. The fact that Nozzle 3 began leaking so early in plant life is

another indication of the highly susceptible nature of the material used to fabricate the nozzle.

Monte Carlo analyses provided by Argonne National Laboratory (ANL) were used to estimate the

risk of nozzle failure for the 5 central nozzles (references 11 and 12). These analyses assumed that

the material used for the nozzles at Davis-Besse is similar to the worst heat of material for which

laboratory cracking test results are available. This assumption is likely but not guaranteed to be

conservative. It will be checked by planned analyses of the Nozzle #3 material from Davis-Besse.

The stress assumptions are based on the high-stress solution for center nozzles provided by

Engineering Mechanics Corporation of Columbus (reference 13). The high stress solution was

picked in recognition of the higher prevalence of cracking in this material at Davis-Besse (60

percent) than was observed at Oconee Unit 3 (20 percent). A probability of 0.22 was used for

initiation of a circumferential crack in an annulus wetted by reactor coolant leakage when an axial

crack grows through a nozzle. This value was derived from the available inspection results.

Circumferential crack sizes of 20° and 60° were considered at crack initiation, to account for

potential initiation at multiple sites along the highest stress region.

The ANL results indicate a probability range of 1.1 x 10!2 to 2.2 x 10!2 (for 20° and 60° initiation,

respectively) that one of the five nozzles would fail within Davis-Besses 16 years of operation

without effective inspection for crack development or leakage. For a single nozzle, the probability is

2.3 x 10!3 to 4.5 x 10!3. An alternative perspective is that, given that one nozzle is considered to

have started leaking early in plant life, the probability that a circumferential crack will form and grow

to the point of nozzle failure is about 2.6 to 5.6 x 10!2 within 6 years of leak initiation and about 4.9 to

8.7 x 10!2 within 8 years.

The perspective that uses knowledge of an early onset of leakage indicates higher risk than the

calculation that statistically predicts both beginning of leakage and the time of nozzle ejection. This

occurs because that calculation uses a probability of 1.0 for the onset of leakage by the date

assumed in the licensees root cause analysis. In contrast, the ANL calculations that probabilistically

predict the date of first leakage from one of five nozzles produce a probability of only about 0.25 that

the date will be as early as the licensee has speculated actually occurred. The results based on

knowledge of early leakage are used in this assessment as being most representative of the

situation at the Davis-Besse plant.

11

For SDP analyses, the increase in the core damage frequency or large early release frequency

during the last year of operation is the metric that is used to quantify risk significance. The

probability of nozzle failure during the last year is the difference between the cumulative probability

for failure by the end of the last year and the probability for failure by the end of the year before,

adjusted for the probability that no failure had occurred by the end of the next-to-last year. For the

6th year of operation with a wetted annulus, the estimated probability of failure is 1.15 to 1.99 x 10!2,

for the 7th year it is 1.28 to 1.80 x 10-2, and for the 8th year, it is 1.37 to 2.14 x 10-2. For the purposes

of this analysis, the average value of 1.6 x 10-2 will be used for Nozzle 3 to fail in the last year of

operation. The range of results for the various wetted times and circumferential flaw initiation sizes

is only about 30 percent, which is not significant compared to other sources of modeling uncertainty

such as the susceptibility of the material to cracking.

Estimates of the additional contributions from Nozzles 2 and 5 depend upon the time the outer

surfaces of these nozzles were wetted by leaking axial cracks. Those times were not estimated in

the root cause report. Based on the lesser degrees of cavity formation in Nozzles 2 and 5, it is

reasonable to assume those nozzles were wet for shorter periods than was Nozzle 3, but that is not

certain. For purposes of illustrating plausible levels of effect on the results of this analysis, a value

of 4 wetted years is assumed for Nozzle 2 and 2 years for Nozzle 5. This results in values of 0.57 to

1.52 x 10!2 for nozzle 2 and essentially zero to 1.45 x 10!3 for nozzle 5. So, Nozzle 2 would increase

the failure probability by about 64 percent and Nozzle 5 by about 4 percent, giving a total nozzle

failure probability of 2.7 x 10!2 using these assumptions. If all 3 nozzles were assumed to be wetted

for the same period, the total failure probability estimate would increase to 4.9 x 10!2, which is a

factor of 1.8 times the value that will be used in this analysis.

Conditional Core Damage Frequency for Loss-of-Coolant Accidents:

The probability that a LOCA will cause core damage is calculated for large, medium and small

LOCAs in all PRAs for pressurized water type power reactors. In the Davis-Besse individual plant

examination (IPE), the CCDPs are 6.87 x 10-3 for medium LOCAs and 1.08 x 10-2 for large LOCAs.

Because the medium LOCA size range is large and the worst case parameters from both ends of

the range were combined in a conservative manner for the IPE analysis, the licensee recalculated

the CCDP for a rupture the size of the exposed clad area under the as-found cavity. That value is

2.91 x 10-3 with a 95 percent confidence bound of 6.07 x 10-3 and a 5 percent confidence bound of

1.29 x 10-3. These values are consistent with the values obtained in other IPEs and in PRAs

sponsored by the NRC. Therefore, they will be used in this SDP analysis without further review.

Potential for Failure of Control Rods Due to Damage from Ruptured Cavity or Ejected Nozzle:

Both the licensee and the NRC have evaluated the potential for consequential damage to multiple

control rod drives to prevent shutting down the chain reaction in the reactor core after failure of a

nozzle or exposed clad (references 3 and 14). The NRC analysis concluded that the chain reaction

would be successfully terminated without producing a pressure pulse in the RCS.

The reason for this result is that the design requirements for the reactor core have been established

to make the nuclear fission chain reaction stop when bubbles form in coolant and the fuel rods

overheat. In the event of a LOCA, the depressurization of the RCS allows some boiling to occur in

the reactor core, and this is sufficient to stop the chain reaction without insertion of any of the control

12

rods. When cold ECCS water fills the reactor and stops the boiling, the high concentration of boron

in that water is sufficient to maintain the shutdown condition, even without the control rods.

Therefore, no modifications are required to the reactivity control top events in typical PRA LOCA

analyses to make them applicable to LOCAs on top of the RPV head.

Implications of GSI-191, Containment Sump Blockage:

Recently, the NRCs Office of Regulatory Research identified a potential vulnerability associated with

the assumptions used in the licensing of pressurized-water reactors (PWRs). Specifically, the

concern is that debris from the containment could wash to the screen that surrounds the sump in the

containment building and block the water flow through it sufficiently to fail the ECCS when it

switches to recirculation mode and draws water from that sump. This issue is not unique to

Davis-Besse. This issue has been designated as a generic safety issue, GSI-191, and is applicable

to all PWRs, including Davis-Besse.

A Los Alamos National Laboratory (LANL) report documents the results of a research effort that was

focused on determining whether sump blockage due to debris posed a credible concern. This LANL

study used a number of assumptions in debris generation, transport, and accident sequence

modeling, data from one volunteer plant, and limited data from other plants. The study concluded

that debris poses a credible concern. However, with respect to the plant-specific results in the

report, the LANL report concluded that the tabulated results and the supporting parametric study are

inadequate to draw conclusions about the susceptibility of specific plants to sump clogging. This is

due to lack of plant-specific data and the degree to which a number of assumptions were employed

in the development of the tabulated results.

On that basis, it would be inappropriate to incorporate the results for Davis-Besse from the LANL

study in the base estimate for the CDF in this risk analysis. However, it is appropriate to include a

sensitivity study case for the effect of the LANL results, so that a measure can be obtained for the

level of uncertainty that the outstanding issue represents.

The LANL results for the parameter evaluation study case that used available Davis-Besse

parameters assigned unlikely ratings for sump blockage during small and medium LOCAs and a

likely rating for large LOCAs. An unlikely rating is qualitatively defined as indicating that sump

blockage is not a concern. A likely rating was given a nominal quantification with a probability of

0.6. Therefore, the sensitivity case has no effect on the CCDPs for the nozzle ejection event or the

rupture of the clad under the as-found cavity, which are medium LOCAs. However, rupture of the

clad under a cavity that had grown large enough to be susceptible to normal RCS operating

pressure would constitute a large LOCA, and, although no quantification was achieved for that

contribution to the CDF, that contribution would be increased by a factor of about 56 for the

sensitivity case.

The LANL study definition of a large LOCA spans a wide range of rupture sizes, from one hole 6-

inches in diameter to two holes 36-inches in diameter, and it did not consider ruptures located on the

reactor pressure vessel. For this reason, the assumptions for a hole approximately 20 inches in

diameter located on the reactor vessel head should be reconsidered with the LANL parameter study

methodology before drawing any conclusions with respect to the affect of sump blockage on the risk

due to head wastage. Additional plant-specific information that indicates the risk effect may be less

13

than indicated are (1) there is no fibrous insulation material inside the reactor cavity at Davis-Besse

and (2) the bottom of the reactor cavity does not have a direct path to the containment sump.

Implications of Fuel Assembly Spacer Collapse:

In a letter dated May 24, 1996, Framatome Technologies informed the NRC of a Potential Safety

Concern related to the performance of its fuel assemblies under physical loads resulting from a

design-basis large LOCA (reference 15). Specifically, the loads associated with the double-ended

break of the largest cooling water pipe, combined with the design-basis seismic loads, were

calculated to deform the zirconium alloy spacer grids and compact the fuel pins into a less easily

cooled configuration in the interior of the core as well as at the core periphery. The calculations

used to demonstrate compliance of the ECCS with 10 CFR 50.46 had addressed deformation of

peripheral assemblies, but not interior assemblies. The solution requested was to allow credit for

leak-before-break behavior of the largest RCS pipes so that the consequential damage to the fuel

assembly grids could be excluded from the design-basis analysis. An NRC staff member raised this

issue as having potential relevance to this SDP analysis, because leak-before-break credit cannot

be applied to the exposed clad material under a large cavity in the low-alloy steel pressure

boundary. For a cavity large enough to fail at normal operating pressure, the resulting LOCA would

be larger than the 10.5-inch diameter core flood tank pipe that is the most limiting break when leak-

before-break credit is applied.

Review of the material supplied by Framatome indicates that this issue should not affect the

conclusions of this analysis for several reasons. Foremost is the location of the break. Fuel

assembly grid deformation is caused by horizontal depressurization loads that are greatest for break

locations to one side of the core, such as in one of the large coolant loop pipes. For failure of a

nozzle in the center of the head, horizontal loads are expected to be substantially less.

Also, the Framatome analyses indicate that loads up to one-third those calculated for the largest

break would not produce plastic deformation in the core interior assemblies. For the sequence

involving failure of the clad under an enlarged cavity, the equivalent diameter of the failed area

would be about 18-to-20 inches. This is about one-quarter to one-third of the cross sectional area of

the largest pipe. For design-basis accidents, the pipe break is assumed to discharge reactor coolant

from both ends. So, the LOCA postulated for rupture of an enlarged cavity should be within the

LOCA size range that Framatome indicates would not produce an unanalyzed degree of plastic

deformation in the fuel spacers.

Finally, the Framatome analyses indicate that the fuel geometry would remain coolable following

the plastic deformation from a larger LOCA, although the heat transfer capability would be reduced

enough to cause the fuel temperature to exceed the ECCS acceptance criterion of 2200 °F. With

respect to the risk analysis, the significant question for a larger LOCA is whether the change in

coolability would change the number of trains of ECCS equipment needed to prevent the core from

melting, which would change the CCDP for the LOCA. Based on the information submitted by

Framatome, the size LOCA contemplated for cavity failure in the RPV head would not be expected

to deform the fuel enough to change the amount of ECCS equipment needed to prevent core

damage.

On that basis, this issue does not affect the analyses for mitigation of the potential LOCAs

associated with the Davis-Besse head degradation mechanisms.

14

Increase in Core Damage Frequency ( CDF):

Normally, the total risk increase would be computed by simple multiplication of the frequency for

each type of pressure boundary failure by the CCDP appropriate for the LOCA size and summation

of the products. However, in this case, the frequency estimates for two of the three types of

pressure boundary failures are not complete enough to be treated in the normal manner. Each is

discussed separately, below.

Rupture of the as-found cavity

Engineering evaluations of the as-found cavity predict a very high failure pressure, but do not

include the potential effects of flaws in the clad material that could be exposed by the cavity.

Without consideration of clad flaws, rupture of the as-found cavity during a transient RCS pressure

increase does not appear to make a significant contribution to the core damage frequency.

Frequency estimates for the as-found cavity to burst due to pressure transients are on the order of

10-4 to 10-7/RY.

Consideration of the size distribution of flaws and the probability of one occurring in an area of

exposed clad could change this result, but without doing that analysis in a quantitative manner, it is

not possible to conclude whether a predominance of large flaws would increase the risk by lowering

burst pressures of small cavities or a predominance of small flaws would decrease the overall risk by

introducing a substantial probability that the cavity floor failure would be a leak before the exposed

area became large enough to rupture. In the limited consideration of cavities no larger than the one

found at Davis-Besse, the occurrence of flaws is most likely to increase the contribution to the

overall risk. Therefore, the risk contribution from this part of the analysis is considered to be

potentially greater than indicated by the product of the calculated LOCA frequencies and the CCDP

for the Medium LOCA.

Rupture LOCA

Type Size Frequency CCDP CDF

as-found medium $ 10-4/RY * 2.91 x 10-3 $ 3 x 10-7/RY *

cavity or or

$ 10-7/RY * $ 3 x 10-10/RY *

  • Does not account for effects of flaws in clad

Both alternative estimates produce numerical results that are in the lowest SDP significance range

for CDF values. However, without an analysis for the effects of flaws in the clad material, it is not

possible to use this result to assign a color to the as-found condition, because the true value may be

substantially higher. Engineering evaluations of the effects of flaws on clad strength are in-progress,

but are not available in time for this preliminary risk assessment.

Rupture of an enlarged cavity

Additional enlargement of the cavity to the point of rupture appears to have the potential to dominate

the risk associated with this performance deficiency. This is due to the relatively short times, 1 to 2

years, that would be required for the cavity to grow from the as-found size to a size that would

15

rupture, if the rate of corrosion during the additional period is as high as some laboratory

experiments have found to be possible. However, it is not known whether the conditions on the

Davis-Besse head were capable of producing such high rates of corrosion or sustaining those rates

when the cavity size became much larger. So, there is also a potential that the cavity would not be

able to grow large enough to rupture.

Because we were unable to reach a consensus within the NRC staff on a relevant and appropriate

approach, with supporting data for treating the cavity size in a probabilistic manner, it is not feasible

to quantify the risk contribution from the cavity growth potential. It is important to recognize that this

unquantified contribution exists, and may or may not increase the total CDF substantially above the

total produced from the quantifiable parts of this analysis.

Nozzle ejection due to circumferential cracking

The estimate for the frequency of nozzle ejection is based on 1) knowledge that three of the center

nozzles appear to have been leaking for extended periods, 2) that they are made of a heat of Alloy

600 material that has been found to be relatively susceptible to cracking in two plants and 3) that this

material has behaved worse at Davis-Besse than at the other plants. The evaluation of

circumferential cracking is based on models that draw on substantial laboratory data. This provides

a greater degree of confidence that the appropriate phenomena have been identified and some

confidence that the quantification process has produced results in an appropriate range. Still, this

assessment required the selection of some plausible values from the range of laboratory data,

based on inferences from the circumstances of this inspection finding. Until laboratory analyses are

completed on the nozzle material that was taken from the Davis-Besse reactor, there will be

significant uncertainty in the appropriateness of the values chosen. But, for this portion of the

assessment, the analysis is adequately complete and the level of uncertainty not outside customary

levels for significance determination.

Rupture LOCA

Type Size Frequency CCDP CDF

nozzle medium 2.7 x 10-2/RY 2.91 x 10-3/RY 8.0 x 10-5/RY

ejection

The CDF increase is in the high end of the 10-5/RY range and plausibly in the low end of the

10-4/RY range if leakage from all nozzles is considered.

Conclusions about total CDF increase

Due to the substantially different nature of the results from the three parts of this risk assessment, it

is difficult to draw conclusions about the overall risk significance. The estimate of the risk due to the

potential for circumferential cracking is sufficient to put the total in the high

10-5/RY range. The unquantified risk due to additional cavity growth modifies the overall conclusion

to be at least in the 10-5/RY range.

Contrast with Conditional Core Damage Probability:

16

From the standpoint of the level of risk that actually existed at the Davis-Besse site in February

2002, neither the size of the as-found cavity around Nozzle 3, nor the indicated size of the

circumferential flaw that was detected in Nozzle 2 suggest that the plant was in imminent danger of

experiencing a LOCA. However, until the effects of flaws in the clad material are analyzed for their

effects on the probabilities of rupture and leak before rupture, it is not possible to conclude what

level of risk was created by the as-found cavity.

It is important to recognize that the CDF estimate for the performance deficiency at

Davis-Besse differs from a risk assessment of the as-found condition. In addition to the as-found

condition, it considers what other outcomes could have occurred, given the lack of preventive

capabilities inherent in the performance deficiency. This provides an instructive insight for focusing

NRC inspection efforts on the deficiencies that have high risk significance, even when the specific

manifestation that first reveals a deficiency does not constitute an immediate hazard to the public

safety.

Sensitivity to Sump Blockage:

The GSI-191 parameter study report assigns a significant sump blockage probability to Davis-Besse

for large LOCAs only. Thus, for this risk assessment, only the unquantified risk contribution from

rupture of a substantially enlarged cavity would be affected by this issue. The GSI-191 report

assigns a nominal value of 0.6 to the cases it terms likely to experience sump blockage. If the

CCDP for a large LOCA is increased to 0.6, the unquantified contribution due to cavity growth would

be increased by a factor of 56. That would make it more likely to make a substantial increase in the

total CDF, but that is not certain until the contribution due to cavity growth can be quantified.

Therefore, consideration of the sump blockage issue cannot substantially alter the risk perspective

achieved with this assessment.

Increase in Large Early Release Frequency ( LERF):

Davis-Besse has a large dry type containment. This containment type typically has a relatively small

probability for early failure following a core damage accident caused by a LOCA. The Davis-Besse

IPE estimates the conditional containment failure probability as 0.006. Values less than 0.1 will not

affect the color assignment in an SDP analysis, because the color thresholds for increases in LERF

are a factor of 0.1 times the thresholds for the increases in CDF.

Sensitivity to Davis-Besse Containment Corrosion Concern:

To date, no information has been reported that indicates the Davis-Besse containment is degraded

to the point that its probability for early failure following a medium or large LOCA is significantly

increased. If the significance determination for the nozzle leaks is based only on the risk associated

with nozzle ejection due to circumferential cracking, then an increase in containment failure

probability to a value of at least 0.13 would be needed to increase the significance from greater than

8x10-5/RY based on CDF to greater than 1x10-5/RY based on LERF. The value of 0.13

represents an increase by about a factor of 20 over the value derived in the Davis-Besse IPE.

Any containment degradation finding would receive a separate risk assessment and a separate color

assignment, and the ROP action matrix would be applied to determine the appropriate regulatory

response for the combination of the two findings.

17

References:

1. Stochastic Failure Model for the Davis-Besse RPV Head, ORNL/NRC/LTR, P.T. Williams and B.

R. Bass, Oak Ridge National Laboratory, August 23, 2002.

2. Elasto-Plastic Analysis of Constrained Disk Burst Tests, ASME 72-PVP-12, P. C. Riccardella,

American Society of Mechanical Engineers, 1972.

3. Letter serial number 1-1268 from FirstEnergy Nuclear Operating Company to U. S. Nuclear

Regulatory Commission dated April 8, 2002, transmitting Safety Significance Assessment of the

Davis-Besse Nuclear Power Station (DBNPS) Reactor Pressure Vessel head.

4. Letter serial number 1-1277 from FirstEnergy Nuclear Operating Company to U. S. Nuclear

Regulatory Commission dated June 12, 2002, subject Confirmatory Action Letter: Response to

Request for Additional Information Related to the Davis-Besse Nuclear Power Station Safety

Significance Assessment.

5. E-mail from Dale Wuokko, FirstEnergy Nuclear Operating Company to Jon Hopkins, U. S.

Nuclear Regulatory Commission dated August 27, 2002, 9:11 am, subject Instability for Failure

Pressure.

6. Pressure-Dependent Fragilities for Piping Components, NUREG/CR-5603, October 1990.

7. Assessment of ISLOCA Risk-Methodology and Application to a Babcock and Wilcox Nuclear

Power Plant, NUREG/CR-5604, April 1992.

8. Boric Acid Corrosion Guidebook, Revision 1, Electric power Research Institute, November

2001. [Licensed Proprietary Material]

9. Analysis of the Davis-Besse RPV Head wastage Area and Cavity, ORNL/NRC/LTR, P.T.

Williams and B. R. Bass, Oak Ridge National Laboratory, September 2002.

10. Letter serial number 2745 from FirstEnergy Nuclear Operating Company to U. S. Nuclear

Regulatory Commission dated November 1, 2001, subject Transmittal of Davis-Besse Nuclear

Power Station Risk Assessment of Control Rod Drive Mechanism Nozzle Cracks.

11. Memorandum from W. J. Shack, Argonne National Laboratory to W. H. Cullen, Jr., U. S.

Nuclear Regulatory Commission, subject Updated Calculations for Probability of Failure of CRDM

Nozzles, July 31, 2002.

12. E-mail from W. J. Shack, Argonne National Laboratory to W. H. Cullen, Jr., U. S. Nuclear

Regulatory Commission, subject Update on Probability of Cracking, July 31, 2002, 5:42 pm.

13. Summary of On-Going NRC Efforts to Define Circumferential-Crack-Driving-Force Solutions for

CRDM Nozzles, G. Wilkowski, Z. Feng, D. Rudland, Y.-Y. Wang, R. Wolterman, and W. Norris,

Transactions of the 2002 Nuclear Safety Research Conference, NUREG/CP-0178, October 2002.

14. Memorandum from Walton Jensen, U. S. Nuclear Regulatory Commission to Gary Holahan,

U.S. Nuclear Regulatory Commission, subject Sensitivity Study of PWR Reactor Vessel Breaks,

May 10, 2002. ADAMS Accession Number ML021340306.

15. Letter from Framatome ANP to U. S. Nuclear Regulatory Commission, subject Interim Report

of Potential Safety Concern on Mark-B Grid Deformation, Framatome Technologies PSC 21-96-5,

May 24, 1996.

-2-

Application of the Principles of Risk-Informed Decision-Making

to the Phase 3 Significance Determination

for Cavity in Davis Besse Reactor Pressure Vessel Head

The phenomena that produced the cavity were not expected and are still not adequately

understood. In addition, it is not clear how to construct the appropriate logic for estimating the

probability that a similar cavity would be discovered before it ruptures during operation. The cavity

at Davis-Besse was discovered because of actions taken by the NRC in response to discoveries of

a different degradation phenomenon (circumferential cracking of CRDM nozzles) at a different

plant a year before the discovery at Davis-Besse. Therefore, properly understanding the

probability of discovery before rupture involves understanding the probabilities for two different,

(though perhaps linked) degradation phenomena at multiple plants.

In addition to the problems with obtaining a realistic risk estimate for the Davis-Besse cavity

creation process and circumstances, it is arguable that the risk value alone does not fully

represent the significance of this licensees performance deficiency. For example, even if the clad

is found to be uniformly strong and the cavity is found to be growing slowly enough to allow many

more years of operation before rupture would occur, it was still only a matter of good fortune,

rather than good design or good planning, that the clad successfully served as the pressure

boundary. The structural element that was designed to provide the pressure boundary had been

completely corroded away.

Because the staff recognizes substantial vulnerabilities in purely risk-based decision processes,

Regulatory Guide (RG) 1.174 was developed to provide a risk-informed decision-making process

that integrates numerical risk estimates with other deterministic information. Consideration of the

other key principles enumerated in RG 1.174 provides additional insights that may be useful for

reaching a risk-informed decision regarding appropriate agency actions in response to the

performance deficiency.

Principle 1 - Regulations are met: In this case, regulations were not met in more than one

respect. Clearly, pressure boundary leakage** occurred, although none is permitted by technical

specifications, but, pressure boundary leakage occurs occasionally in plants without unacceptably

poor licensee performance. The highly significant aspect of this leakage at Davis-Besse was the

extended period over which it was allowed to persist, and the extent of the damage that it created

to a safety-significant structure. That damage is contrary to the general design criteria (GDC)

requirements in the regulations, in particular, the requirement that the RCS be inspected and

maintained in a condition that has an extremely low probability of abnormal leakage or gross

failure.

Pressure boundary leakage is defined in Technical Specifications to be leakage

through a nonisolatable flaw in a reactor coolant system component body, pipe wall or vessel

wall (except flaws in steam generator tubes, where leakage is limited by separate

specifications). It does not include leakage through bolted connections or valves.

Attachment B

-2-

Principle 2 - Defense-in-depth is maintained: In this case, no physical barrier was breached,

although one physical barrier was nearly eliminated. The physical effect on the part of that barrier

that is credited in the plants design-basis appears to be more appropriately addressed in the next

principle with respect to safety margins. However, the defense-in-depth principle applies to

processes as well as barriers. The processes of design, fabrication, pre-service testing, operation

within limits, maintenance and in-service inspection are intended to provide assurance through

redundancy of the adequacy of the RCS pressure boundary for the life of the plant. In that

context, failures of the maintenance and inspection aspects of the licensees performance were

sufficient to defeat the design feature. Based on the licensees analysis of the root cause, if the

head had been maintained in a clean state or the inspections had been performed for leaking

nozzles in a complete manner, the cavity would have been discovered before it reached a

threatening size. This is a performance deficiency that degraded the level of defense in depth.

Principle 3 - Sufficient safety margins are maintained: In this case, the design margin for the

strength of reactor pressure vessel head is provided solely by the carbon steel forging; the

strength of the clad material was not credited in the design process. Therefore, safety margins

were not maintained during this degradation event.

Principle 4 - The risk is low: This principle is addressed in Attachment A (Risk Assessment and

Insights report).

Principle 5 - The impact of the situation was monitored with strategies sufficient to assure

adequate performance: In this case, the licensee was unaware of the leaks in the CRDM

nozzles and of the possibility for corrosion of the low alloy steel during operation. In addition,

dispositions of several noted abnormal conditions were inappropriately based on false

assumptions about the locations of leaks and the possibilities of nozzle cracking and head

wastage. The licensees performance provided no basis for assuring that the degradation would

be adequately managed or even discovered prior to pressure boundary rupture.

In summary, the licensees performance was inconsistent in some manner with all four of the

principles that are used in conjunction with low risk to find that an action or design change is

acceptable. These additional insights could be used to support a deviation from the agency

response specified by the Action Matrix if portions of the numerical risk assessment are

considered too speculative to be the basis for a significance determination, and the remaining

quantifiable aspects do not appear to adequately capture the risk significance.