LR-N04-0013, December 2003 Monthly Operating Report Salem Generating Station Unit 2

From kanterella
(Redirected from LR-N04-0013)
Jump to navigation Jump to search
December 2003 Monthly Operating Report Salem Generating Station Unit 2
ML040280411
Person / Time
Site: Salem PSEG icon.png
Issue date: 01/15/2004
From: Fricker C
Public Service Enterprise Group
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
LR-N04-0013
Download: ML040280411 (3)


Text

Nuclear Training Center PSEG Nuclear LLC I. 244 Chestnut Street, Salem, NJ 08079 JAN 1 5 2004 LR-N04-001 3 o PSEG T

A nlem- LLC U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 MONTHLY OPERATING REPORT SALEM GENERATING STATION UNIT 2 DOCKET NO. 50-311 In compliance with Section 6.9, Reporting Requirements for the Salem Unit 2 Technical Specifications, the operating statistics for December 2003 are being forwarded.

Sincerely, C rl ricker Sale Plant Manager Attachments C Distribution NATIONAL III ACADEMY III FOR NUCLEAR I TRAINING I>a'L

DOCKET NO.: 50-311 UNIT: Salem 2 DATE: 1/9/04 COMPLETED BY: F. Todd TELEPHONE: (856) 339-1316 Reporting Period December 2003 OPERATING DATA REPORT Design Electrical Rating (MWe-Net) 1131 6_-_4____

Maximum Dependable Capacity (MWe-Net) 1116 ___ ___ __ _ .__

Month Year-to-date Cumulative No. of hours reactor was critical 744 7418 127834 No. of hours generator was on line (service 744 7355 124313 hours)

Unit reserve shutdown hours 0 o 0 Net Electrical Energy (MWH) 851243 8095612 127284587 UNIT SHUTDOWNS NO. DATE TYPE DURATION REASON METHOD OF CORRECTIVE ACTION/

F=FORCED (HOURS) (1) SHUTTING COMMENT S=SCHEDULED

_ _ _ _ _ _ __ _ I __ _ _ I _ _ _ _ _ _ _ _ _ _ _

DOWN THE REA CTOR (2) _ _ _ _ _ _ _ _

(1) Reason (2) Method A - Equipment Failure (Explain) 1 - Manual B - Maintenance or Test 2 - Manual Trip/Scram C - Refueling 3 - Automatic Trip/Scram D - Regulatory Restriction 4 - Continuation E - Operator Training/License Examination 5 - Other (Explain)

F - Administrative G - Operational Error (Explain)

H - Other

DOCKET NO.: 50-311 UNIT: Salem 2 DATE: 1/9/04 COMPLETED BY: R. Ritzman TELEPHONE: (856) 339-1445 Summary Of Monthly Operating Experience

  • Salem 2 entered the month at a reduced power level and reached 99% power on December 1. Salem 2 operated at 99% power for the remainder of the month.

At the end of the month, Salem 2 completed 34 days of continuous on-line operation.