LR-N04-0013, December 2003 Monthly Operating Report Salem Generating Station Unit 2

From kanterella
Jump to navigation Jump to search
December 2003 Monthly Operating Report Salem Generating Station Unit 2
ML040280411
Person / Time
Site: Salem PSEG icon.png
Issue date: 01/15/2004
From: Fricker C
Public Service Enterprise Group
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
LR-N04-0013
Download: ML040280411 (3)


Text

Nuclear Training Center I.

PSEG Nuclear LLC 244 Chestnut Street, Salem, NJ 08079 JAN 1 5 2004 LR-N04-001 3 o PSEG A Tnlem-LLC U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 MONTHLY OPERATING REPORT SALEM GENERATING STATION UNIT 2 DOCKET NO. 50-311 In compliance with Section 6.9, Reporting Requirements for the Salem Unit 2 Technical Specifications, the operating statistics for December 2003 are being forwarded.

Sincerely, C rl ricker Sale Plant Manager Attachments C Distribution NATIONAL III ACADEMY III FOR NUCLEAR I TRAINING I>a'L

DOCKET NO.:

50-311 UNIT:

DATE:

COMPLETED BY:

TELEPHONE:

Salem 2 1/9/04 F. Todd (856) 339-1316 Reporting Period December 2003 OPERATING DATA REPORT Design Electrical Rating (MWe-Net)

Maximum Dependable Capacity (MWe-Net)

No. of hours reactor was critical No. of hours generator was on line (service hours)

Unit reserve shutdown hours Net Electrical Energy (MWH) 1131 6_-_4____

1116 Month Year-to-date Cumulative 744 7418 127834 744 7355 124313 0

o 0

851243 8095612 127284587 UNIT SHUTDOWNS NO.

DATE TYPE DURATION REASON METHOD OF CORRECTIVE ACTION/

F=FORCED (HOURS)

(1)

SHUTTING COMMENT S=SCHEDULED DOWN THE

_ _ I _

_ I R EA C TO R (2)

(1) Reason (2) Method A - Equipment Failure (Explain)

B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training/License Examination F - Administrative G - Operational Error (Explain)

H - Other 1 - Manual 2 - Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain)

DOCKET NO.: 50-311 UNIT: Salem 2 DATE: 1/9/04 COMPLETED BY: R. Ritzman TELEPHONE: (856) 339-1445 Summary Of Monthly Operating Experience Salem 2 entered the month at a reduced power level and reached 99% power on December 1. Salem 2 operated at 99% power for the remainder of the month.

At the end of the month, Salem 2 completed 34 days of continuous on-line operation.