IR 05000454/2022003
| ML22307A163 | |
| Person / Time | |
|---|---|
| Site: | Byron (NPF-037, NPF-066) |
| Issue date: | 11/07/2022 |
| From: | Laura Kozak NRC/RGN-III/DORS/RPB3 |
| To: | Rhoades D Constellation Energy Generation |
| References | |
| IR 2022003 | |
| Download: ML22307A163 (18) | |
Text
SUBJECT:
BYRON STATION - INTEGRATED INSPECTION REPORT 05000454/2022003 AND 05000455/2022003
Dear Mr. Rhoades:
On September 30, 2022, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Byron Station. On October 13, 2022, the NRC inspectors discussed the results of this inspection with Mr. H. Welt, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, Laura L. Kozak, Acting Chief Reactor Projects Branch 3 Division of Operating Reactor Safety Docket Nos. 05000454 and 05000455 License Nos. NPF-37 and NPF-66
Enclosure:
As stated
Inspection Report
Docket Numbers:
05000454 and 05000455
License Numbers:
Report Numbers:
05000454/2022003 and 05000455/2022003
Enterprise Identifier:
I-2022-003-0045
Licensee:
Constellation Energy Generation, LLC
Facility:
Byron Station
Location:
Byron, IL
Inspection Dates:
July 01, 2022 to September 30, 2022
Inspectors:
R. Knutson, Illinois Emergency Management Agency
J. Masse, Acting Resident Inspector
V. Petrella, Resident Inspector, Point Beach Nuclear Plant
C. Thompson, Illinois Emergency Management Agency
J. Weigandt, Acting Senior Resident Inspector
Approved By:
Laura L. Kozak, Acting Chief
Reactor Projects Branch 3
Division of Operating Reactor Safety
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Byron Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
PLANT STATUS
Unit 1 began the inspection period operating at full power. With the exception of minor reductions in power to support scheduled testing activities or small load changes requested by the transmission dispatcher, the unit remained at or near full power for the entire inspection period.
Unit 2 began the inspection period operating at full power. With the exception of minor reductions in power to support scheduled testing activities or small load changes requested by the transmission dispatcher, the unit remained at or near full power for the entire inspection period.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
REACTOR SAFETY
71111.01 - Adverse Weather Protection
External Flooding Sample (IP Section 03.03) (1 Sample)
- (1) The inspectors evaluated that flood protection barriers, mitigation plans, procedures, and equipment are consistent with the licensees design requirements and risk analysis assumptions for coping with external flooding on August 16, 2022
71111.04 - Equipment Alignment
Partial Walkdown Sample (IP Section 03.01) (5 Samples)
The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:
- (1) Unit 1 auxiliary feedwater (AF) following essential service water (SX) flushing on July 8, 2022
- (2) Steam generator power operated relief valve power due to batter deficiencies, as documented in Issue Report (IR) 4512057 on July 22, 2022
- (3) Spent fuel cooling due to impending motor replacement on July 27, 2022
- (4) Unit 1 diesel oil following sampling activities associated with Work Orders (WOs) 5264835 and 5281179 on August 23, 2022
- (5) Unit 1 B Train containment spray during A Train work window on September 8, 2022 Complete Walkdown Sample (IP Section 03.02) (1 Partial)
(1)
(Partial)
The inspectors evaluated system configurations during a complete walkdown of the control room ventilation system on September 22, 2022
71111.05 - Fire Protection
Fire Area Walkdown and Inspection Sample (IP Section 03.01) (5 Samples)
The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:
(1)0B Control Room HVAC equipment room on July 22, 2022
- (2) Unit 2 emergency diesel generator (EDG) fire detection system on July 15, 2022
- (3) Fuel handling building dry cask laydown area on August 10, 2022
- (4) Unit 2 containment spray (CS) and residual heat removal (RHR) pump rooms on September 27, 2022
Fire Brigade Drill Performance Sample (IP Section 03.02) (1 Sample)
- (1) The inspectors observed and evaluated on-site fire brigade training and performance during Fire Drill Scenario 22-03 on July 26, 2022
71111.06 - Flood Protection Measures
Inspection Activities - Internal Flooding (IP Section 03.01) (1 Sample)
The inspectors evaluated internal flooding mitigation protections in the:
- (1) Flooding strategy for the auxiliary electric equipment rooms on August 15 and September 28, 2022
71111.07A - Heat Exchanger/Sink Performance
Annual Review (IP Section 03.01) (1 Sample)
The inspectors evaluated readiness and performance of:
- (1) The SX cooling towers and pumps on August 2 and 3, 2022
71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance
Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)
- (1) The inspectors observed and evaluated licensed operator performance in the Control Room during various activities involving on-watch operations crews including the restoration of the U1 station auxiliary transformer on September 17, 2022
Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)
- (1) The inspectors observed and evaluated performance of a complex casualty graded scenario by a crew of licensed plant operators in the facility's simulator on July 19, 2022
71111.12 - Maintenance Effectiveness
Maintenance Effectiveness (IP Section 03.01) (3 Samples)
The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:
(1)2A service air compressor overhaul, as documented in WO 5122221 on July 28, and September 12 and 28, 2022
- (2) Evaluation of the work and management of failing reactor protection system/emergency core cooling system instrumentation cards, as documented in WOs 5127822 and 5288015 on August 4 and September 12, 2022
- (3) The conditions and maintenance of 1FC02F, as documented in IRs 4517343 and
===4513808 on August 16 and 22, and September 19 through 21, 2022
71111.13 - Maintenance Risk Assessments and Emergent Work Control
Risk Assessment and Management Sample (IP Section 03.01) (3 Samples 1 Partial)
The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:
- (1) Evaluation of the emergent work associated with the 2B EDG control power, as documented in WO 5278894 on July 25, 2022
- (2) Evaluation of the planned work associated with dry cask storage fuel moves, as documented in WO 5181453 on July 18 and August 22 through 25, 2022
- (3) Evaluation of the planned Unit 1 station auxiliary transformer work, as documented in WOs 5136977 and 5135929 on September 12, 2022 (4)
(Partial)
Evaluation of the planned work associated with U1 spent fuel cooling pump motor replacement, as documented in WO 5136095 on July 27, 2022
71111.15 - Operability Determinations and Functionality Assessments
Operability Determination or Functionality Assessment (IP Section 03.01) (5 Samples 1 Partial)
The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:
- (1) Evaluation of the operability of the 1A RHR recirculation suction (1SI06BA-24" piping)following identification of a void, as documented in IR 4511789 and WO 5270802 on July 20, 2022
- (2) Evaluation of the operability of the 2FP010 containment isolation valve following identification of degrading trend of stroke time, as documented in IR 4512817 on July 27, 2022
- (3) Evaluation of the operability of the 0A SX makeup pump following identification of a degraded limit switch signal, as documented in IR 4515366 on August 9, 2022
- (4) Evaluation of the operability of the 2SI121A following an out of tolerance as-found test, as documented in IR 4521501 and WO 5237431 on September 9, 2022
- (5) Evaluation of the operability of the 1A EDG following identification of a degraded airbox inlet cover bolt, as documented in IR 4522015 on September 13, 2022 (6)
(Partial)
Evaluation of the operability of the 2B EDG following identification of a degraded Kilovac relay, as documented in IR 4512731 on July 29 and August 1, 2022
71111.18 - Plant Modifications
Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02)
=
The inspectors evaluated the following temporary or permanent modifications:
- (1) Engineering Change (EC) 634165: Lifting AT-VD52X Trip Contact for 1VD01CA, 1A EDG Supply Fan on August 22, 25, and 26, 2022
71111.19 - Post-Maintenance Testing
Post-Maintenance Test Sample (IP Section 03.01) (6 Samples)
The inspectors evaluated the following post-maintenance testing activities to verify system operability and/or functionality:
- (1) Functional and operational testing of the 0B VC makeup charcoal filter following replacement, as documented in WOs 5083557-06 and 5101493 on July 15, 2022
- (2) Functional and operational testing of the 2A station air compressor following maintenance as documented in WOs 5168382 and 4512903 on July 28, 2022
- (3) Functional and operational testing of the 0A SX makeup pump actuation following limit switch repair and calibration, as documented in WO 5282389 on August 9, 2022
- (4) Functional and operational testing of the 1A steam generator steam flow channel following circuit card replacement, as documented in WO 5288015-1 on September 1, 2022
- (5) Functional and operational testing of the 2A safety injection pump following maintenance, as documented in WO 5135571 on September 19, 2022
- (6) Functional and operational testing the of Unit 1 station auxiliary transformer following inspections and testing, as documented in multiple WOs on September 17, 2022
71111.22 - Surveillance Testing
The inspectors evaluated the following surveillance testing activities to verify system operability and/or functionality:
Surveillance Tests (other) (IP Section 03.01) (3 Samples)
- (1) Calibration of AF feed flow loop electronics (BISR 3.4.2-200), as documented in WO 5110628 on July 15, 2022 (2)2B AF monthly and quarterly tests, as documented in WOs 5272240 and 5258941 on July 14 and 15, 2022 (3)1BOSR 5.5.8.CC.5-1C, 1A CC Comprehensive test, as documented in WO 5267098 on August 4, 2022
Inservice Testing (IP Section 03.01) (2 Samples)
(1)1BOSR 5.5.8.AF.5-1B, 1A AF group B test, as documented in WO 5267096 on September 6, 2022
- (2) 1BOSR 5.5.8.SI.5-2A, 1B SI group A test, as documented in WO 5266248 on August 11, 2022
FLEX Testing (IP Section 03.02) (1 Sample)
- (1) Review of FLEX Surveillance, as documented in WO 5235105 and FLEX Building general equipment inspection on August 11 and 16, 2022
71114.06 - Drill Evaluation
Select Emergency Preparedness Drills and/or Training for Observation (IP Section 03.01) (1 Sample)
- (1) Byron 2022 Off-Year Exercise on September 13, 2022
Drill/Training Evolution Observation (IP Section 03.02) (1 Sample)
The inspectors evaluated:
- (1) An emergency action level declaration, notification, and post-exercise critique on August 2,
OTHER ACTIVITIES - BASELINE
71152S - Semiannual Trend Problem Identification and Resolution Semiannual Trend Review (Section 03.02)
- (1) The inspectors reviewed the licensees corrective action program for potential adverse trends in spent fuel cooling filter leakage that might be indicative of a more significant safety issue on the week ending 24 September,
INSPECTION RESULTS
Observation: Repeated Leakage in Pipe Tunnel 71152S Inspectors performed a semiannual review to identify trends that might indicate the existence of a more significant safety issue. For their review, the inspectors focused on corrective action program entries for active boric acid leaks associated with auxiliary building filter vaults above the pipe tunnel. From 2020 through 2022, inspectors noted several instances of spent fuel cooling system filter leaks into their vaults, which then wetted SSCs in the pipe tunnel below. Notable examples were documented in the following condition reports:
4323495, Inactive Boric Acid Leak in Short Door Valve Aisle Blockwall, 03/03/2020
4445731, Active Leak Identified in 1FC02F Vault, 09/10/2021
4492901, Active Leak Identified in 1FC02F Vault, 04/13/2022
4513808, 1FC02F - Water Found After Removing the Filter Floor Plug, 07/29/2022 The inspectors found that some of the closure notes of the listed reports and earlier reports did not document how the issue was addressed. As part of their review, the inspectors performed a walkdown of the adjacent rooms and found white deposits at the base of the Unit 1 valve aisle wall (IR 45117343, NRC ID: U1 Valve Aisle Dried Boric Acid). After discussions with multiple departments and a review of subsequent borescope results, the inspectors identified that safety related auxiliary building ventilation (VA) ducting was being wetted with boric acid as evidenced by visible deposits. Boric acid was observed on the inside of several VA dampers, (0VA346Y, 347Y, 354Y, & 355Y) as well as external to the carbon steel ducting from the inspection images. The station tracked filter leakage targets in their boric acid corrosion control program. The station conducted cleaning and corrective repairs for a portion of the noted conditions. However, the impact to the safety related ducting was not part of the documented conditions or evaluations. Follow-up conversations with station personnel revealed that the adverse condition would not have reasonably prevented performance of the safety function. The inspectors determined that the failure to promptly identify and correct boric acid on safety related ducting was a performance deficiency and violation of Title 10 of the Code of Federal Regulations, Appendix B, Criterion XVI. The performance deficiency was determined to be of minor significance since the boric acid on this part of the VA exhaust flow path would not reasonably prevent performance of the safety function.
As a result of this observation and the station's investigations, the licensee has determined that the long-term trend of repeated leakage demonstrates further corrective actions are required to prevent future recurrence of these types of leaks. Byron has generated condition reports (IRs 4523779, 4523782, 4523784, & 4523787) for dried boric acid in each of the dampers listed. Additionally, the station updated their open corrosion evaluation (4519861, Repeated 0FC01F Leakage Long Term Solution Required) and further documented the following corrective actions to address the primary cause:
4519864, Repeated 1FC02F Leakage Long Term Solution Required
4519868, Repeated 1FC04F Leakage Long Term Solution Required
4519870, Repeated 2FC02F Leakage Long Term Solution Required
4519874, Repeated 2FC04F Leakage Long Term Solution Required,
4519876, Repeated FC Filter Leakage -A-Frame Hoist Enhancement
4519877, Repeated FC Filter Leakage - Replacement Filter Enhancement The inspectors did not identify any findings or violations of more than minor significance during their review.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
On October 13, 2022, the inspectors presented the integrated inspection results to Mr. H. Welt, Site Vice President, and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Corrective Action
Documents
Resulting from
Inspection
4517215
NRC ID: NRC North Roof Walkdown
08/16/2022
Procedures
OP-AA-108-111-
1001
Severe Weather and Natural Disaster Guidelines
Corrective Action
Documents
4512057
1D S/G PORV UPS Battery Bank Cell Leakage
07/20/2022
4516269
NRC ID: 1SX243 and 1SX242 Valve Stem Length
Dissimilarities
08/11/2022
Corrective Action
Documents
Resulting from
Inspection
23921
NRC ID: 0VC01JC-1-C3 Alarm Locked in and will Not Reset
09/21/2022
1BOSR SX-M1
1A AF Pump SX Suction Line Monthly Flushing Surveillance
BOP CS-M1B
Containment Spray System Train B Valve Lineup
BOP DO-300-2
Sampling the 50,000 Gallon Fuel Oil Storage Tank 0DO12T
BOP DO-M1
Diesel Fuel Oil System Valve Lineup
BOP VC-E1
Control Room Ventilation Electrical Lineup Unit 0
BOP VC-M1
Control Room Heating and Ventilation (HVAC) System
Valve Lineup
Procedures
RP-BY-907
Process Radiation Monitoring System Alert/High Alarm
Setpoints
264835
LR-(Sample) U-1 A D/G Fuel Day Tank
08/23/2022
Work Orders
281179
LR-(SAMPLE) 50,000 Gal Fuel Oil Storage Tank
08/23/2022
4516203
NRC ID: Extension Cord Usage in Fuel Handling Building
08/10/2022
24985
NRC ID: 2A RH Pp Cub Cooler Fan Stop Lights Not Lit
09/27/2022
Corrective Action
Documents
Resulting from
Inspection
25015
NRC Identified Loose Material in the 2A RH Pp Room
09/27/2022
18.4-2
Pre-Fire Plan Auxiliary Building 451-0 Elevation Control
Room HVAC Equipment Room Train B FZ 18.4-2 Plan #200
PFP AB1 346-0
FZ 11.2A-1
Pre-Fire Plan Auxiliary Building Unit 1 346-0 Elevation 1A
RHR Pump Room FZ 11.2A-1 Plan #103
Fire Plans
PFP AB1 346-0
Pre-Fire Plan Auxiliary Building Unit 1 346-0 Elevation 1A
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
FZ 11.2B-1
Containment Spray Pump Room FZ 11.2B-1 Plan #105
PFP AB1 346-0
FZ 11.2C-1
Pre-Fire Plan Auxiliary Building Unit 1 346-0 Elevation 1B
Containment Spray Pump Room FZ 11.2C-1 Plan #107
PFP AB1 346-0
FZ 11.2D-1
Pre-Fire Plan Auxiliary Building Unit 1 346-0 Elevation 1B
RHR Heat Removal Pump Room FZ 11.2D-1 Plan #109
PFP AB2 346-0
FZ 11.2A-2
Pre-Fire Plan Auxiliary Building Unit 2 346-0 Elevation 2A
RHR Pump Room FZ 11.2A-2 Plan #104
PFP AB2 346-0
FZ 11.2B-2
Pre-Fire Plan Auxiliary Building Unit 2 346-0 Elevation 2A
Containment Spray Pump Room FZ 11.2B-2 Plan #106
PFP AB2 346-0
FZ 11.2C-2
Pre-Fire Plan Auxiliary Building Unit 2 346-0 Elevation 2B
Containment Spray Pump Room FZ 11.2.C-2 PLAN #108
PFP AB2 346-0
FZ 11.2D-2
Pre-Fire Plan Auxiliary Building Unit 2 346-0 Elevation 2B
RHR Pump Room FZ 11.2D-2
PFP FHB 401-0
FZ 12.1-0
Pre-Fire Plan Fuel Handling Building 401-0 Elevation FZ
2.1-0 PLAN #176
PFP FHB 426-0
FZ 12.1-0, Rev
003
Pre-Fire Plan Fuel Handling Building 426-0 Elevation FZ
2.1-0
PFP TB1 426-0
FZ 8.5-1 SE
Pre-Fire Plan Turbine Building Unit 1 426-0 Elevation
General Area FZ 8.5-1 Southeast Plan #71
PFP TB1 426-0
FZ 8.5-1 SW
Pre-Fire Plan Turbine Building Unit 1 426-0 Elevation
General Area - SW FZ 8.5-1 Southwest Plan #72
Miscellaneous
FPR Chapter 2.3
Fire Area Analysis
2e
Procedures
0VC02FB 2S-4
Calculations
Aux Building Flood Level
Corrective Action
Documents
Resulting from
Inspection
4516367
NRC ID: Paint Peeling on Outside Acid Tank Building
08/11/2022
Miscellaneous
2-4-1
Cycle 22-4 OBE
03/24/2022
4513808
1FC02F - Water Found After Removing the Filter Floor Plug
07/29/2022
Corrective Action
Documents
4514880
Unexpected Alarm Pressurizer Pressure Low
08/04/2022
Station One-Line Diagram
U
Drawings
6E-2-4031RY02
Loop Schematic Diagram Pressurizer Pressure
G
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
BHP 4200-172
System Auxiliary Transformer Preventive Maintenance
Inspection
Procedures
BOP AP-51
Isolating Unit 1 System Aux Transformer 142-1 And 142-2
While Unit is at Power
22221
Minor Overhaul
07/28/2022
Work Orders
27822
Calibration of the Pressurizer Pressure Protection Channel
08/04/2022
19.13.0-BYR15-
109
Evaluation of Fuel Handling Building at Elevation 411'-0" for
Loads Associated with the Temporary Placement of
Shipping Casks
8.1.3-BYR16-018
Evaluation of Fuel Handling Building EL 411 In-Place
Structure for Additional Loading from Panels 0EW10EA and
0AP132EA BYR16-018
Calculations
ECR 418511
Laydown Area for MPC Lid on EL. 411 OF FHB
04/03/2015
Corrective Action
Documents
Resulting from
Inspection
4518829
NRC Identified MPC Lid Staging on 411'
08/25/2022
M-27, Sheet 7
Equipment Removal Fuel Handling Building Units 1 & 2
D
S-1706
Auxiliary Building Floor Loading Diagram Misc. Plans
C
Drawings
S-812
Fuel Handling Building Ground Floor Framing Plan ELEV
401-0 AREA 2
AI
374705
Evaluation of FHB Structure for ISFSI Equipment Laydown
Areas
Engineering
Changes
637035
Evaluation of Rigging for Unit 1 Spent Fuel Pool Cooling
Pump (1FC01P) Motor
BFP FH-69
HI-TRAC Movement within the Fuel Building - ISFSI
BFP FH-70
HI-TRAC Loading Operations - (ISFSI)
Procedures
BMP 3000-1
Control of the Movement of Heavy Loads
5135929
SS Inspection and Testing PM - SAT 142-1
09/17/2022
5136095
LT Pump/Motor - Onetime 1FC01P Motor Replacement
07/11/2022
5136977
SS Inspection and Testing PM - SAT 142-2
09/17/2022
5181453
Dry Cask Storage Campaign (2022)
09/20/2022
Work Orders
278894-03
WM Kilovac Relay Replacement 2 PL08J-4X3A
08/19/2022
Corrective Action
4371195
EDG Kilovac Control Relay failure susceptibility
09/22/2020
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
4511789
Gas Void Detected in 1SI06BA-24" Near 1SI8811A
07/19/2022
4512817
2FP010 Increasing Stroke Time
07/25/2022
4515366
Unexpected 0A SX Makeup Pump (0SX02PA) Auto Start
08/06/2022
21501
Relief Valve Failed As-Found Test
09/09/2022
Documents
22015
Sheared Bolt Head On 1A DG
09/13/2022
Engineering
Evaluations
379408
Past Operability Evaluation of Gas Void at 1SI8811A
237431
Create a WO to test 2SI121A (Scope Expansion for
1SI121B)
09/12/2022
253389-01
2BOSR 6.3.5-4 (EWP), STT for 2FP010 (WK J)
07/25/2022
Work Orders
270802
U1 Monthly Gas Void UT Exams
07/20/2022
Engineering
Changes
634165
Lifting AR-VD52X Trip Contact for DG Room 1A Supply Fan
1VD01CA
04519060
1FI-0513 Steam Flow Channel Failed High
08/27/2022
Corrective Action
Documents
2A SAC High Bearing Oil Temperature
07/26/2022
455613
Request For Engineering to Provide Methodology for
Testing New Style (6D30740G01) NMD Card for Steam
Flow Function in SF/FF Mismatch Loops
08/30/2022
Engineering
Changes
637389
DETERMINATION
OF NEW
CHANNEL GAINS
FOR UPDATED
7300 NMD CARD
Determination of New Channel Gains for Updated 7300
NMD Card (6D30740G01)
Miscellaneous
TRP 1FW-0515
Calibration of Steam Generator 1A Steam Flow/Feed Flow
Mismatch (FW) Protection Set II
2BOSR 5.5.8.SI.5-
1a
Unit Two Group A Inservice Testing (IST) Requirements for
Safety Injection Pump 2SI01PA
Procedures
BISR 3.2.10-200
Surveillance Calibration of Steam Generator Steam
Flow/Feed Flow Mismatch Protection Set I And II (FW)
288015-01
EWP IM Troubleshoot 1A SG Steam Flow Channel
08/27/2022
Work Orders
5083557-06
EWP IM PMT: Perform 0BISR 7.10.2-4 Halide Test
07/13/2022
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
5101493
0B Control Room Makeup System Charcoal Adsorber Bank
Operability
07/13/2022
5135571-02
OP 2BOSR 5.5.8.SI.5-1a SI ASME Pump Run
09/06/2022
5168382
External/Internal Inspection/Thermography
07/28/2022
282389
Calibration of Ess SW Clg Twr Basin 0A Lvl Sw 0LS-SX096
08/09/2022
4511047
NRC ID: Junction Box Door Found Open - 2JB2093A
07/14/2022
4517210
NRC ID: 0FX02PB Low Oil Level
08/16/2022
Corrective Action
Documents
Resulting from
Inspection
4517213
NRC ID: NRC Flex Building Walkdown
08/16/2022
1BOSR
5.5.8.AF.5-1b
Unit One Group B Inservice Testing (IST) Requirements for
Motor Driven Auxiliary Feedwater Pump 1AF01PA
BOP AF-5
Motor Driven Auxiliary Feedwater Pump _A Startup on
Recirc
Procedures
BOP AF-6
Motor Driven Auxiliary Feedwater Pump _A Shutdown
267096-01
LR-(NEIL)-1AF01PA GRP B IST Requirements for Motor
Driven AF
09/02/2022
5110628
Calibrate Electronic Portion of AF Loop
07/11/2022
235105
Unit 0 FLEX Equipment Inventory Surveillance
08/29/2022
258941
LR-OPS 2BOSR 5.5.8.AF.5-2B - 2B AF Group B Test
07/15/2022
266248-1
OPS 1BOSR 5.5.8.SI.5-2A 1B SI IST Group A Pump Test
08/11/2022
267098
(NEIL) - 1CC01PA Comprehensive IST Reqmts for CC
Pump
08/04/2022
Work Orders
272240
2BOSR 7.5.4-2, 2B AF PP Run
07/14/2022
4373330
Water Accumulation in the 1FC02F Vault
09/30/2020
4391130
Active Leak Identified in 1FC02F Vault
2/18/2020
4445731
Active Leak Identified in 1FC02F Vault
09/10/2021
Corrective Action
Documents
4492901
Active Leak Identified in 1FC02F Vault
04/13/2022
4515003
NRC ID - Keys in Vehicle Inside PA
08/04/2022
4517343
NRC ID: U1 Valve Aisle Dried Boric Acid
08/17/2022
23779
NRC ID: Dried Boric Acid in Ductwork Downstream of
0VA346Y
09/21/2022
Corrective Action
Documents
Resulting from
Inspection
23782
NRC ID: Dried Boric Acid in Ductwork Downstream of
0VA347Y
09/21/2022
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
23784
NRC ID: Dried Boric Acid in Ductwork Downstream of
0VA354Y
09/21/2022
23787
NRC ID: Dried Boric Acid in Ductwork Downstream of
0VA355Y
09/21/2022