IR 05000454/2022010

From kanterella
Jump to navigation Jump to search
Design Basis Assurance Inspection (Programs) Inspection Report Report 05000454/2022010 and 05000455/2022010
ML23017A094
Person / Time
Site: Byron  Constellation icon.png
Issue date: 01/17/2023
From: Karla Stoedter
NRC/RGN-III/DORS/EB1
To: Rhoades D
Constellation Energy Generation, Constellation Nuclear
References
IR 2022010
Download: ML23017A094 (1)


Text

SUBJECT:

BYRON STATION - DESIGN BASIS ASSURANCE INSPECTION (PROGRAMS) INSPECTION REPORT 05000454/2022010 AND 05000455/2022010

Dear David Rhoades:

On December 20, 2022, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Byron Station and discussed the results of this inspection with Adam Schuerman, Plant Manager, and other members of your staff. The results of this inspection are documented in the enclosed report.

Two findings of very low safety significance (Green) are documented in this report. Two of these findings involved violations of NRC requirements. We are treating these violations as non-cited violations (NCVs) consistent with section 2.3.2 of the Enforcement Policy.

If you contest the violations or the significance or severity of the violations documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; the Director, Office of Enforcement; and the NRC Resident Inspector at Byron Station.

January 17, 2023 This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Karla K. Stoedter, Chief Engineering Branch 1 Division of Operating Reactor Safety Docket Nos. 05000454 and 05000455 License Nos. NPF-37 and NPF-66

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000454 and 05000455

License Numbers:

NPF-37 and NPF-66

Report Numbers:

05000454/2022010 and 05000455/2022010

Enterprise Identifier:

I-2022-010-0057

Licensee:

Constellation Energy Generation, LLC

Facility:

Byron Station

Location:

Byron, IL

Inspection Dates:

November 28, 2022 to December 20, 2022

Inspectors:

K. Barclay, Senior Reactor Inspector

L. Rodriguez, Senior Reactor Inspector

M. Siddiqui, Reactor Inspector

Approved By:

Karla K. Stoedter, Chief

Engineering Branch 1

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a design basis assurance inspection (programs) inspection at Byron Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors.

Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Failure to Establish a Preventive Maintenance Schedule to Replace Solenoid Valve 1CV8116 Prior to the End of its Specific Lifetime Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000454,05000455/2022010-01 Open/Closed None (NPP)71111.21N.

The inspectors identified a finding of very low safety significance (Green) and an associated non-cited violation (NCV) of technical specification (TS) 5.4.1 for the licensees failure to establish a preventive maintenance schedule to replace solenoid valve 1CV8116 prior to the end of its specific lifetime of 38.5 years as documented in EQ-BB-HE-10A, Revision 6.

Although the licensee established preventive maintenance schedule PMID 00105874-01 for replacing internal components of the 1CV8116 valve, this preventive maintenance activity did not replace all components of the valve which had a specific lifetime such as the position indication reed switch assembly and the terminal block.

Failure to Use Correct Valve Factors to Ensure Motor Operated Valves Continued to be Capable of Performing Their Design Basis Functions Cornerstone Significance Cross-Cutting Aspect Report Section Barrier Integrity Green NCV 05000454,05000455/2022010-02 Open/Closed None (NPP)71111.21N.

The inspectors identified a finding of very low safety significance (Green) and an associated non-cited violation (NCV) of Title 10 of the Code of Federal Regulations (CFR) 50.55a(b)(3)(ii)for the licensee's failure to establish a program that ensured motor operated valves (MOVs)continued to be capable of performing their design basis safety functions. Specifically, the licensee did not use the highest applicable Generic Letter (GL) 89-10, Joint Owners Group (JOG), or valve specific, empirically determined, stable valve factors to properly size and set-up MOVs 2RY8000B,1CC685, and other MOVs at the site. The licensee incorrectly used lower non-conservative valve factors to size and set-up the MOVs, which did not ensure the MOVs continued to be capable of performing their design basis safety functions.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.21N.02 - Design-Basis Capability of Power-Operated Valves Under 10 CFR 50.55a Requirements POV Review (IP Section 03)

The inspectors:

a.

Determined whether the sampled power operated valves (POVs) were being tested and maintained in accordance with NRC regulations along with the licensees commitments and/or licensing bases.

b.

Determined whether the sampled POVs were capable of performing their design-basis functions.

c.

Determined whether testing of the sampled POVs was adequate to demonstrate the capability of the POVs to perform their safety functions under design-basis conditions.

d.

Evaluated maintenance activities including a walkdown of the sampled POVs (if accessible).

(1)1CV8116, 1B Charging Pump Minimum Flow Recirculation Solenoid Valve (2)1SX005, 1B Essential Service Water (ESW) Supply Valve to the Common Component Cooling (CC) Heat Exchanger (3)2SI8811B, 2B Containment Recirculation Sump Outlet Isolation Valve (4)1SX168, Auxiliary Feedwater Pump 1B Cubicle Cooler ESW Temperature Control Valve (5)1CC685, Reactor Coolant Pumps Thermal Barrier CC Return Isolation Valve (6)1RY456, 1B Pressurizer Power Operated Relief Valve (PORV)

(7)2RY8000B, 2B Pressurizer PORV Block Valve (8)1FW009C, 1C Steam Generator Feedwater Isolation Valve

INSPECTION RESULTS

Failure to Establish a Preventive Maintenance Schedule to Replace Solenoid Valve 1CV8116 Prior to the End of its Specific Lifetime Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000454,05000455/2022010-01 Open/Closed None (NPP)71111.21N.0

The inspectors identified a finding of very low safety significance (Green) and an associated non-cited violation (NCV) of technical specification (TS) 5.4.1 for the licensees failure to establish a preventive maintenance schedule to replace solenoid valve 1CV8116 prior to the end of its specific lifetime of 38.5 years as documented in EQ-BB-HE-10A, Revision 6.

Although the licensee established preventive maintenance schedule PMID 00105874-01 for replacing internal components of the 1CV8116 valve, this preventive maintenance activity did not replace all components of the valve which had a specific lifetime such as the position indication reed switch assembly and the terminal block.

Description:

Byron station had centrifugal charging pumps which would realign on receipt of a safety injection (SI) signal during an event to form the high head portion of the emergency core cooling system (ECCS) for injection. A minimum flow bypass line with a normally open solenoid operated valve was provided on each pump discharge to recirculate flow to the pump suction after cooling the water via the seal water heat exchanger during normal plant operation. These valves had a safety function to close automatically upon receipt of an SI signal concurrent with a low-low reactor coolant system (RCS) pressure to isolate the minimum flow recirculation lines in order to ensure adequate SI flow to the RCS. These valves also had a safety function to open to protect the pumps should the RCS pressure increase above their open setpoint with an SI signal present. The minimum flow solenoid valves were designed to fail open on a loss of power.

The inspectors reviewed the 1B charging pump minimum flow recirculation solenoid valve (1CV8116) during the inspection. The inspectors noted environmental qualification (EQ)binder EQ-BB-HE-10A, "Environmental Qualification of Target Rock Solenoid Valve 79AB-010," Revision 6, applied to the valve. The inspectors also noted tab E, "Maintenance &

Surveillance Schedule," section 2, "Maintenance/Surveillance Requirements to Maintain Qualification," step 2.B stated, "The solenoid valve is qualified for 38.5 years. Replace the solenoid valve prior to expiration of qualified life." Therefore, the inspectors determined the valve had a specific lifetime of 38.5 years. The inspectors then reviewed the preventive maintenance (PM) scheduled for valve 1CV8116 and noted there was no replacement of the valve scheduled before the end of its specific lifetime (qualified life) of 38.5 years.

The inspectors discussed this discrepancy with the licensee. The licensee stated valve 1CV8116 was not replaced in its entirety and was not scheduled to be replaced. The licensee had established EQ PM schedule PMID 00105874-01, "Replace the Elastomers and Coil," to replace the elastomers and solenoid assembly of the valve on an 18-year frequency.

However, the scheduled PM did not require replacement of all susceptible components inside the valve which had an EQ qualified life. Specifically, the PM did not require replacement of the position indication reed switch assembly nor the terminal block inside the valve. The inspectors determined the failure of those internal components could render the valve incapable of performing its safety functions during an event.

Corrective Actions: The licensee entered this issue into their corrective action program and determined solenoid valve 1CV8116 had been in service less than its specific lifetime and remained qualified. The licensee planned to perform an extent of condition review on all PM activities scheduled for valves covered by EQ-BB-HE-10A to ensure EQ requirements had been correctly incorporated.

Corrective Action References: AR 04543031

Performance Assessment:

Performance Deficiency: The licensee's failure to establish a PM schedule to replace solenoid valve 1CV8116 prior to the end of its specific lifetime of 38.5 years as documented in EQ-BB-HE-10A was a performance deficiency and a violation of TS 5.4.1. Although the licensee established PM schedule PMID 00105874-01 for replacing internal components of the 1CV8116 valve, that PM activity did not replace all components of the valve which had a specific lifetime such as the position indication reed switch assembly and the terminal block.

Screening: The inspectors determined the performance deficiency was more than minor because if left uncorrected, it would have the potential to lead to a more significant safety concern. Specifically, absent NRC's intervention, the licensee's failure to establish a PM schedule to replace solenoid valve 1CV8116 before the end of its specific lifetime could lead to failure of the valve's internal components, rendering the valve incapable of performing its safety functions, similar to example 13.a of IMC 0612 appendix E, "Examples of Minor Issues."

Significance: The inspectors assessed the significance of the finding using IMC 0609 appendix A, The Significance Determination Process (SDP) for Findings At-Power. The inspectors determined this finding was of very low safety significance (Green) because although it was a deficiency affecting qualification of a mitigating structure, system, or component (SSC), the SSC maintained its operability. Specifically, solenoid valve 1CV8116 had been in service less than its specific lifetime and remained qualified at the conclusion of the inspection.

Cross-Cutting Aspect: Not Present Performance. No cross-cutting aspect was assigned to this finding because the inspectors determined the finding did not reflect present licensee performance. Specifically, the PM strategy developed for valve 1CV8116 was created prior to the 3-year period used to assess present licensee performance.

Enforcement:

Violation: Technical specification section 5.4.1 requires, in part, that written procedures shall be established, implemented, and maintained covering the applicable procedures recommended in Regulatory Guide 1.33, Revision 2, appendix A, February 1978.

NRC Regulatory Guide 1.33, Revision 2, appendix A, section 9 addresses Procedures for Performing Maintenance" and section 9.b states, "Preventive maintenance schedules should be developed to specify lubrication schedules, inspections of equipment, replacement of such items as filters and strainers, and inspection or replacement of parts that have a specific lifetime such as wear rings."

EQ-BB-HE-10A, "Environmental Qualification of Target Rock Solenoid Valve 79AB-010,"

Revision 6, which applies to valve 1CV8116 states in tab E, "Maintenance & Surveillance Schedule," section 2, "Maintenance/Surveillance Requirements to Maintain Qualification,"

step 2.B, "The solenoid valve is qualified for 38.5 years. Replace the solenoid valve prior to expiration of qualified life."

Contrary to the above, as of December 15, 2022, the licensee failed to establish a procedure to address the requirements of Regulatory Guide 1.33, appendix A, section 9.b. Specifically, the licensee failed to establish a preventive maintenance schedule to replace solenoid valve 1CV8116 prior to the end of its specific lifetime of 38.5 years as documented in EQ-BB-HE-10A. Although the licensee established preventive maintenance schedule PMID 00105874-01, "Replace the Elastomers and Coil," for replacing internal components of the 1CV8116 valve, that preventive maintenance activity did not replace all components of the valve which had a specific lifetime such as the position indication reed switch assembly and the terminal block.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with section 2.3.2 of the Enforcement Policy.

Failure to Use Correct Valve Factors to Ensure Motor Operated Valves Continued to be Capable of Performing Their Design Basis Functions Cornerstone Significance Cross-Cutting Aspect Report Section Barrier Integrity Green NCV 05000454,05000455/2022010-02 Open/Closed None (NPP)71111.21N.0 The inspectors identified a finding of very low safety significance (Green) and an associated non-cited violation (NCV) of Title 10 of the Code of Federal Regulations (CFR)50.55a(b)(3)(ii) for the licensee's failure to establish a program that ensured motor operated valves (MOVs) continued to be capable of performing their design basis safety functions.

Specifically, the licensee did not use the highest applicable Generic Letter (GL) 89-10, Joint Owners Group (JOG), or valve specific, empirically determined, stable valve factors to properly size and set-up MOVs 2RY8000B. 1CC685, and other MOVs at the site. The licensee incorrectly used lower non-conservative valve factors to size and set-up the MOVs, which did not ensure the MOVs continued to be capable of performing their design basis safety functions.

Description:

The inspectors reviewed the 2B pressurizer power operated relief valve (PORV) block valve (2RY8000B) during the inspection. The valve was in a pipe between the reactor coolant system (RCS) pressurizer and the pressurizer relief tank (PRT), directly upstream of a pressurizer PORV. The valve had a safety function to open to provide a flow path from the pressurizer to the PRT. The valve also had a safety function to close to isolate the pressurizer PORV.

The inspectors also reviewed the reactor coolant pumps (RCPs) thermal barrier component cooling (CC) return isolation valve (1CC685) during the inspection. This normally open MOV was required to close to isolate containment from the CC system upon receipt of a containment isolation signal during a design basis event. This valve was also required to close on receipt of a high flow signal (indicating an RCP thermal barrier rupture) to isolate the CC system from the RCS.

The inspectors then reviewed calculations BYR-2RY8000B, "Midacalc Results BYR-2RY8000B (BYR-2)," Revision 5, and BYR-1CC685, "Midacalc Results BYR-1CC685 (BYR-1)," Revision 4, for the 2RY8000B and 1CC685 MOVs, respectively. These calculations were used by the license to demonstrate the MOVs were capable of performing their design basis safety functions. The inspectors noted the valve factors used for both valves came from reference document MPR-2524-A, "Joint Owner's Group (JOG) Motor Operated Valve Periodic Verification Program Summary," Revision 1. Chapter 7 step 5 of the reference document stated, "each plant is responsible for the design bases for its gate valves. Although a plant can decide to conservatively increase its gate valve disk-to-seat coefficients of friction (COFs) to meet these thresholds, it is not acceptable to decrease a plant specific COF to the threshold value." Therefore, the inspectors requested the basis for the valve factors (the disk to seat COFs) in use for the 2RY8000B and 1CC685 MOVs since these had been obtained directly from the JOG document.

While reviewing the basis for the valve factors in use for the 2RY8000B and 1CC685 valves, the licensee determined they were incorrectly using valve factors from the JOG document in their calculations. Procedure ER-AA-302-1001, "MOV Rising Stem Motor Operated Valve Thrust and Torque Sizing and Set-Up Window Determination Methodology," Revision 13, was a licensee procedure established to properly size and set-up MOVs to ensure their design basis functionality. Step 4.1.5.2.B stated, in part, "Where possible, it is expected MOV program valve calculations will use the highest applicable GL 89-10, JOG, or valve specific, empirically determined, stable valve factor. At no time is it acceptable to utilize a valve factor determined via grouping or industry data if valid, valve-specific test data demonstrates a higher valve factor exists." The licensee incorrectly used lower non-conservative valve factors to size and set-up the 2RY8000B and 1CC685 MOVs. Therefore, their calculations and MOV program did not ensure the MOVs continued to be capable of performing their design basis safety functions.

Corrective Actions: The licensee entered this issue into their corrective action program and re-analyzed the design basis capability of valves 2RY8000B and 1CC685 using bounding valve factors. The licensee was able to demonstrate both valves were still capable of performing their design basis functions after removing available margins in the calculations.

The licensee also performed an extent of condition review during the inspection and determined an additional 33 valves also had non-conservative valve factors. The licensee re-analyzed those valves and determined they were all still capable of performing their design basis functions. The licensee planned to formally update their calculations to incorporate bounding valves factors for the affected valves, perform a fleetwide extent of condition, and perform additional diagnostic testing as required by their MOV program procedures for valves which had a loss of margin.

Corrective Action References: ARs 04540308, 04540309, 04541139, 04541231, and 04541543

Performance Assessment:

Performance Deficiency: The licensee's failure to ensure MOVs 2RY8000B, 1CC685 and 33 additional MOVs at the site continued to be capable of performing their design basis safety functions was contrary to 10 CFR 50.55a(b)(3)(ii) and was a performance deficiency.

Specifically, the licensee incorrectly used lower, non-conservative valves factors to size and set-up the MOVs instead of using the highest applicable GL 89-10, JOG, or valve specific, empirically determined, stable valve factors.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the SSC and Barrier Performance attribute of the Barrier Integrity cornerstone and adversely affected the cornerstone objective to provide reasonable assurance that physical design barriers protect the public from radionuclide releases caused by accidents or events. Specifically, the failure to ensure the 2RY8000B and 1CC685 MOVs were capable of closing during a design basis event adversely affected the objective of the RCS and containment barriers to protect the public from radionuclide releases. Similar to example 3.l of IMC 0612 appendix E, the licensee had to re-perform a number of valve design calculations to demonstrate they could meet their design basis functions and several valves required additional testing and maintenance per the site MOV program procedures because of a loss of margin.

Significance: The inspectors assessed the significance of the finding using IMC 0609 appendix A, The Significance Determination Process (SDP) for Findings At-Power. The inspectors determined the finding was of very low safety significance (Green) because they answered "No" to all of the questions in exhibit 3, "Barrier Integrity Screening Questions,"

section B, "Reactor Coolant System (RCS) Boundary," and section C, "Reactor Containment."

Cross-Cutting Aspect: Not Present Performance. No cross-cutting aspect was assigned to this finding because the inspectors determined the finding did not reflect present licensee performance. Specifically, the valve factors selected to demonstrate that MOVs were capable of performing their design basis safety functions were chosen prior to the 3-year period used to assess present licensee performance.

Enforcement:

Violation: Title 10 CFR 50.55a(b)(3)(ii) states, in part, the licensee must establish a program to ensure that MOVs continue to be capable of performing their design basis safety functions.

Procedure ER-AA-302-1001, "MOV Rising Stem Motor Operated Valve Thrust and Torque Sizing and Set-Up Window Determination Methodology," Revision 13, is a licensee procedure established to properly size and set-up MOVs to ensure the valves are capable of performing their design basis safety function. Step 4.1.5.2.B states, in part, "Where possible, it is expected MOV program valve calculations will use the highest applicable GL 89-10, JOG, or valve specific, empirically determined, stable valve factor." The procedure also states, "At no time is it acceptable to utilize a valve factor determined via grouping or industry data if valid, valve-specific test data demonstrates a higher valve factor exists."

Contrary to the above, as of December 1, 2022, the licensee failed to establish a program that ensured MOVs continued to be capable of performing their design basis safety functions.

Specifically, the licensee did not use the highest applicable GL 89-10, JOG, or valve specific, empirically determined, stable valve factors to properly size and set-up MOVs 2RY8000B, 1CC685, and 33 other MOVs at the site. The licensee incorrectly used lower non-conservative valve factors to size and set-up the MOVs, which did not ensure the MOVs continued to be capable of performing their design basis safety functions.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with section 2.3.2 of the Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On December 20, 2022, the inspectors presented the design basis assurance inspection (programs) inspection results to Adam Schuerman, Plant Manager, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

06-0615-C-002

Byron and Braidwood Reactor Pressurizer System MOV

Design Basis Document and dP Calculation

AOV-MARG-

BYR-1SX168

ACE Calculation for 1(2)SX168 Byron Unit 0

BYR-1CC685

Midacalc Results BYR-1CC685 (BYR-1)

BYR-1SX005

Midacalc Results BYR-1SX005 (BYR-1)

BYR-2RY8000B

Midacalc Results BYR-2RY8000B (BYR-2)

and 6

BYR-2SI8811B

Midacalc Results BYR-2SI8811B (BYR-2)

BYR01-084

Generic Thermal Overload Heater Sizing Calculation for

Motor Operated Valves

BYR01-087

MOV Actuator Motor Terminal Voltage and Thermal

Overload Sizing Calculation Component Cooling System

1B and 2

BYR01-094

Motor Operated Valves (MOV) Actuator Motor Terminal

Voltage and Thermal Overload Sizing Calculation - Safety

Injection (SI) System

BYR08-001

Owner Review of Seismic/Weak Link Report for 30 Inch

SX Butterfly Valves

3B

BYR08-011

Owner Review: Determination of Butterfly Valve Operating

Torque

1A and 1E

BYR97-386

Safety Injection (SI) MOV Differential Pressure Calculation

1A

Calculations

BYR97-386

MOV Differential Pressure Calculation Sheets

01072841

Work Request Needed for Grease in 2SI8811B

05/25/2010

2563274

B1R20 M3 AOV 1SX168 Failed to Meet Stroke Length AC

09/15/2015

04107333

Partial Stem Lube During the RH Work Window

2/23/2018

04169589

Inactive Packing Leak

09/03/2018

04174658

1CV8116 Shows Dual During STT and PIT

09/19/2018

241119

2RY456 Will Not Open

04/18/2019

04328947

1FW009D Low Pressure

03/24/2020

04403064

MOV 2SI8811B Actuator Grease at Grade 3

2/17/2021

04446314

1SX168 Fail Open Test Failed

09/14/2021

71111.21N.02

Corrective Action

Documents

04447170

B1R24 Expanded Scope on 1SX168

09/17/2021

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

04448697

B1R24 - Recommendations from Internal 1SX168

Inspect / Repair

09/26/2021

04503607

Evaluation Request for SST Frequency of 1/2SX005

06/03/2022

04539975

NRC ID - 2SX005 Valve Operator Bolt Issues

11/30/2022

04539976

NRC ID - 1SX005 Valve Operator Bolt Issue

11/30/2022

04540295

NRC ID - 1CC685 Limit Control Scheme

2/01/2022

04540308

NRC ID - 2RY8000B Valve Factor Discrepancy

2/01/2022

04540309

NRC ID - 1CC685 Valve Factor Discrepancy

2/01/2022

04540550

NRC ID - PZR PORV IST Test Requirements

2/02/2022

04541139

NRC ID - POV Inspection Valve Factor Application

2/06/2022

04541231

NRC ID - Byron MOV Program Valve Factor

Discrepancies

2/06/2022

04541543

NRC ID - 2CV8105 Follow up to IR 4541231

2/08/2022

04541949

NRC ID - 2SI8811B Test Documentation Discrepancy

2/10/2022

04542182

NRC ID - 2SI8811B - WO Documentation Discrepancy

2/12/2022

04542414

NRC ID - Housekeeping of 1C MSIV Room

2/13/2022

04542707

NRC ID - Inadequate Past Operability Review for 1SX168

Failure

2/14/2022

04542770

EOC for IR 04539975 - SX Valve Operator (HBC)

Mounting Bolts

2/14/2022

04542773

EOC for IR 04539975 - SX Valve Operator (HBC)

Mounting Bolts

2/14/2022

04542780

EOC for IR 04539975 - SX Valve Operator (HBC)

Mounting Bolts

2/14/2022

04542912

NRC ID - 2SI8811 Installed Packing Doesn't Match

Drawing

2/15/2022

04543031

NRC POV Insp. - EQ PM Missing Required Components

Replacement

2/15/2022

04543204

NRC ID - Follow-up on RY PORV Testing per IST

2/16/2022

Corrective Action

Documents

Resulting from

Inspection

04543255

NRC ID - Maintenance Rule Evaluation Dispositioning

2/16/2022

6434E05

Motor Operated Gate Valve Model 03000GMBBFNH000

3-1525 ASME Class I

Drawings

6E-1-4030CC04

Schematic Diagram CCW from Reactor Coolant Pumps

O

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Thermal Barrier Isolation Valves - 1CC9438 & 1CC685

6E-1-4030SX06

Schematic Diagram Component Cooling Heat Exchangers

& 0 Inlet Valves 1SX004 & 1SX005

K

77920

Valve Assembly, Gate - 24 Inch, 300 lb., Cres., Motor

Operated

79AB-010

2" Solenoid Opr. Valve High Temp. and High Press.

Energize to Close

F

CD04101

General Assembly Plain Wafer Per MSS-SP-68 & MSS-

SP-44

D

M-135

Diagram of Reactor Coolant

AM

M-136

Diagram of Safety Injection

AZ

M-36

Diagram of Feedwater (Main) Loop 3

BC

M-42 Sheet 3

Diagram of Essential Service Water

BG

M-60

Diagram of Reactor Coolant

AO

M-64

Diagram of Chemical & Volume Control & Boron Thermal

Regeneration

AZ

MS-18

Large Bore Isometric Main Steam (MS) System

P4-6775-N-1

Sheet 1

3" & 6" 150# Bolted Bonnet Manual Globe Valve (Cast)

Q

P4-6775-N-1

Sheet 2

3" & 6" 150# Bolted Bonnet Manual Globe Valve (Cast)

C

96-064

Technical Evaluation Checklist Pressurizer Relief Isolation

Valve

BYR-2RY8000B

JOG MOV Evaluation Report

BYR-2SI8811B

JOG MOV Evaluation Report

EQ-BB-047

Environmental Qualification of Borg Warner Valves

7A

Engineering

Evaluations

EQ-BB-HE-10A

Environmental Qualification of Target Rock Solenoid Valve

79AB-010

MPR-2524-A

Joint Owner's Group (JOG) Motor Operated Valve

Periodic Verification Program Summary

2RY8000B

Gate and Globe Valve Data Sheet Byron Unit 2

2/25/1991

BB-PRA-005.04

Byron and Braidwood Probabilistic Risk Analysis Auxiliary

Feedwater System Notebook (AF)

Miscellaneous

BVP 200-2T5

IST Valve Reference Value/Acceptance Criteria

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

CECO-0267

Vendor Manual: Invar Industries: Operating and

Maintenance Manual for Pneumatic Valve Actuators

03/01/2002

DM-0162

Velan Valve and Pneumatic Actuator Design

Information - 1SX168

INL/CON-11-

21863

OM Code Requirements for MOVs - OMN-1 and Appendix

III - Eleventh NRC/ASME Symposium on Valves, Pumps,

& Inservice Testing for Operating & New Reactors

08/01/2011

IST-BYR-BDOC-

V-CC

Inservice Testing Basis Document - 1CC685

10/08/2022

IST-BYR-BDOC-

V-CV

Inservice Testing Basis Document - 1CV8116

10/09/2022

IST-BYR-BDOC-

V-FW

Inservice Testing Basis Document - 1FW009C

10/09/2022

IST-BYR-BDOC-

V-RC

Inservice Testing Basis Document - 1RY456

10/10/2022

IST-BYR-BDOC-

V-RC

Inservice Testing Basis Document - 2RY8000B

03/01/2019

IST-BYR-BDOC-

V-SI

Inservice Testing Basis Document - 2SI8811B

03/01/2019

IST-BYR-BDOC-

V-SX

Inservice Testing Basis Document - 1SX168

03/01/2019

IST-BYR-BDOC-

V-SX

Inservice Testing Basis Document - 1SX005

03/01/2019

IST-BYR-PLAN

Byron Nuclear Power Station Units 1 & 2 - Inservice

Testing Program Fourth Ten Year Interval

03/25/2021

MR System

Basis Document

- AF

Maintenance Rule System Basis Document - Auxiliary

Feedwater

11/08/2022

MR System

Basis Document

- CC

Maintenance Rule System Basis Document - Component

Cooling

11/03/2022

MR System

Basis Document

- SX

Maintenance Rule System Basis Document - Essential

Service Water

11/09/2022

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

MR System

Basis Document

- VA

Maintenance Rule System Basis Document - Auxiliary

Building HVAC

11/09/2022

NES-MS-06.6

MOV Valve Factors

OSR 86-242

Valve Stroke Time of Pressurizer Power Operated Relief

Valve

2/19/1986

TR-113561

EPRI MOV Performance Prediction Program - Friction

Coefficients for Non-Metallic Butterfly Valve Bearing

Materials

2/01/1999

White Paper 176

Borg-Warner Valve Factors

04/06/1995

1BOSR

0.5-2.FW.4

Main Feedwater System Valves 1FW009A/B/C/D

Indication Test 18 Month Surveillance

1BOSR 4.11.3-1

Unit 1 Pressurizer PORV Accumulator Pressure Decay

Test

1SX-154

Calibration of Auxiliary Feedwater Pump 1B Diesel Room

Temperature Control Loop

ER-AA-302-1001

MOV Rising Stem Motor Operated Valve Thrust and

Torque Sizing and Set-Up Window Determination

Methodology

ER-AA-302-1003

MOV Margin Analysis and Periodic Verification Test

Intervals

ER-AA-302-1006

Motor-Operated Valve Maintenance and Testing

Guidelines

ER-AA-321-1007

Inservice Testing (IST) Program Corporate Technical

Positions

ER-AA-410-1002

Air Operated Valve Testing Requirements

Procedures

MA-AA-736-600

Torquing and Tightening of Bolted Connections

00688020

Perform Inspection of Solenoid Operated CV Recirc.

Valves

04/02/2008

01178660

MOV PM, Actuator Inspection, Diagnostic Testing

05/25/2010

01646720

MOV PM, Actuator Inspection, Diagnostic

Testing - 2SI8811B

11/25/2014

Work Orders

01674690

PM - MOV Actuator Inspection, Diagnostic Testing

1SX005

07/28/2015

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

01789861

(Check) 2B Cnmt. Recirc. Sump Isol. Vlv.

05/26/2016

01860589

Perform Inspection of Solenoid Operated CV Recirc.

Valves

09/17/2018

01882186

"B" Train CVCS Isolation Valve Indication Test

05/22/2017

01910301

1CV8116 SOV Stroke Closed IST Test (Adverse Trend)

11/29/2017

01932426

(Check) 2B Cnmt. Recirc. Sump Isol. Vlv.

2/23/2018

01932872

STT/PIT for 2SI8802B, 2SI8809B, 2SI8811B, 2SI8923B

10/07/2017

04618029

EWP EVR Perform Thermal O.L. Surveillance (MCC

2X4) - 1AP28E-D4

09/18/2018

04646661

"B" Train CVCS Isolation Valve Indication Test

09/19/2018

04718799

PM Inspection, In-Service Diag. Test, PIT

2/16/2021

04752319

PM - MOV Stem Clean/Lube & Act. Grease Inspect.

2/16/2021

04788240

STT for 1CV8116 (Week L)

09/19/2018

04831101

Inservice Diagnostic Testing - 1CC685

03/16/2020

04834737

"B" Train CVCS Isolation Valve Indication Test

03/17/2020

04910760

MOV Stem Clean/Lube & Act. Grease Inspection

05/07/2020

04927935

MOV Thermal Overload Surveillance (MCC 232X4-H1

2SI8811B CNM)

2/17/2021

04950919

EXTST for 2SI8802B, 2SI8809B, 2SI8811B, 2SI8923B

10/09/2020

05020408

Internal Valve Inspection - 1SX-168

09/21/2021

05022355

EWP EM Perform Actuator Wiring

09/21/2021

05024052

"B" Train CVCS Isolation Valve Indication Test

09/21/2021

05025484

STT/PIT for 1RY455A and 1RY456

08/30/2021

05026595

1FW009A-D Full Stroke Test

09/28/2021

05047204

EWP IM Flowscan Valve 1RY456

08/31/2021

05088698

STT for 2RY800A and 2RY8000B

04/05/2021

05172217

1BOSR 7.5.4-2, 1B AF PP RUN

08/18/2021

209224

STT for 1CV8116 (Week L)

03/11/2022

242413

STT for 1CV8116 (Week L)

05/17/2022

269739

STT for 1CV8116 (Week L)

09/06/2022

86008721

Repack Valves with Graphite Packing

2/18/1986