SUBJECT:

UPDATED INSPECTION PLAN AND ASSESSMENT FOLLOW-UP LETTER FOR BYRON STATION, UNITS 1 AND 2 (REPORT 05000455/2024005 AND 05000454/2024005)

Dear David Rhodes:

The enclosed inspection plan lists the inspections scheduled through June 30, 2026, for Byron Station, Units 1 and 2. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last 12 months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.

Between January 18 and February 14, 2025, the NRC will be performing a Functional Engineering Inspection in the area of Commercial Grade Dedication at your facility. The NRC will also be performing a Problem Identification and Resolution Inspection between September 15 and October 3, 2025, at your facility.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

August 28, 2024

D. Rhoades

Please contact me at 630-829-9833 with any questions you have regarding this letter.

Sincerely, Richard Skokowski, Chief Reactor Projects Branch 3 Division of Operating Reactor Safety Docket Nos. 05000454, 05000455, and 07200068 License Nos. NPF-37 and NPF-66 Enclosure:

Inspection Plan cc: Distribution via LISTSERV Signed by Skokowski, Richard on 08/28/24

ML24241A141

SUNSI Review

Non-Sensitive

Sensitive

Publicly Available

Non-Publicly Available OFFICE RIII RIII NAME RElliott:anm RSkokowski DATE 08/28/2024 08/28/2024

Site Inspection Activity Plan Byron 07/01/2024 - 06/30/2026 Unit Start End Activity CAC Title Staff Count Inservice Inspection Unit 1

1 9/9/2024 9/27/2024 IP 71111.08P 000702 Inservice Inspection Activities (PWR)

Radiation Protection Baseline Inspection

1,2 9/16/2024 9/20/2024 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1,2 9/16/2024 9/20/2024 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation Emergency Preparedness Baseline Inspection / Performance Indicator Verification

1,2 10/21/2024 10/25/2024 IP 71114.02 000717 Alert and Notification System Testing 1,2 10/21/2024 10/25/2024 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 1,2 10/21/2024 10/25/2024 IP 71114.05 000720 Maintenance of Emergency Preparedness 1,2 10/21/2024 10/25/2024 IP 71151 001397 Performance Indicator Verification Security Baseline Inspection

1,2 8/26/2024 8/30/2024 IP 71130.14 000743 Review of Power Reactor Target Sets 1,2 10/28/2024 11/1/2024 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance 1,2 10/28/2024 11/1/2024 IP 71130.09 001656 Security Plan Changes Eplan and EAL Changes Review

1,2 11/1/2024 12/31/2024 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes Byron Biennial Requalification Program Inspection

1,2 11/17/2024 11/23/2024 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance Functional Engineering Inspection - Commercial Grade Dedication

1,2 1/27/2025 2/14/2025 IP 71111.21N.03 001808 Commercial Grade Dedication Byron February 2025 Initial License Examination

1,2 1/12/2025 1/18/2025 OV 000956 FB-OR-Onsite Validation Of Initial License Examination (OV)

1,2 2/9/2025 2/15/2025 EXAD 000500 FB-OR-Initial License Exam Administration (EXAD)

Security Baseline Inspection

1,2 2/10/2025 2/14/2025 IP 71130.02 000734 Access Control 1,2 2/10/2025 2/14/2025 IP 71151 001338 Performance Indicator Verification 1,2 3/17/2025 3/21/2025 IP 71130.07 000739 Security Training 1,2 3/17/2025 3/21/2025 IP 71130.09 001656 Security Plan Changes Radiation Protection Baseline Inspection

1,2 3/24/2025 3/28/2025 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1,2 3/24/2025 3/28/2025 IP 71124.04 000728 Occupational Dose Assessment 1,2 3/24/2025 3/28/2025 IP 71124.05 000729 Radiation Monitoring Instrumentation Prepared on 8/21/2024 9:44:59 AM 1 of 3

Site Inspection Activity Plan License Renewal Unit 2 Phase 1

2 4/14/2025 5/2/2025 IP 71003 000687 Post-Approval Site Inspection for License Renewal Inservice Inspection Unit 2

2 4/14/2025 5/2/2025 IP 71111.08P 000702 Inservice Inspection Activities (PWR)

Radiation Protection Baseline Inspection

1,2 4/21/2025 4/25/2025 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1,2 4/21/2025 4/25/2025 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation Material Control and Accountability Triennial Inspection

1,2 7/28/2025 9/1/2025 IP 71130.11 000742 Material Control and Accounting (MC&A)

Force-on-Force Planning and Exercise Weeks - BYR

1,2 7/21/2025 7/25/2025 IP 71130.03 000735 Contingency Response - Force-On-Force Testing 1,2 8/11/2025 8/15/2025 IP 71130.03 000735 Contingency Response - Force-On-Force Testing Radiation Protection Baseline Inspection

1,2 9/8/2025 9/12/2025 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment 1,2 9/8/2025 9/12/2025 IP 71124.07 000731 Radiological Environmental Monitoring Program 1,2 9/8/2025 9/12/2025 IP 71151 000746 Performance Indicator Verification Biennial Problem Identification and Resolution Inspection

1,2 9/15/2025 10/3/2025 IP 71152B 000747 Problem Identification and Resolution Emergency Preparedness Exercise Inspection / Performance Indicator Review

1,2 10/20/2025 10/24/2025 IP 71114.01 000716 Exercise Evaluation 1,2 10/20/2025 10/24/2025 IP 71151 001397 Performance Indicator Verification Eplan and EAL Changes Review

1,2 11/1/2025 12/31/2025 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes Corporate Security Baseline Inspection

1,2 1/19/2026 1/23/2026 IP 71130.08 000740 Fitness-For-Duty Program Cyber Security

1,2 2/2/2026 2/6/2026 IP 71130.10 000741 Cybersecurity Security Baseline Inspection

1,2 2/9/2026 2/13/2026 IP 71130.08 000740 Fitness-For-Duty Program Inservice Inspection - Unit 1

1 3/2/2026 3/20/2026 IP 71111.08P 000702 Inservice Inspection Activities (PWR)

Radiation Protection Baseline Inspection

1,2 3/9/2026 3/13/2026 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls Emergency Preparedness Baseline Inspection / Performance Indicator Verification

1,2 3/16/2026 3/20/2026 IP 71114.02 000717 Alert and Notification System Testing Prepared on 8/21/2024 9:44:59 AM 2 of 3

Site Inspection Activity Plan 1,2 3/16/2026 3/20/2026 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 1,2 3/16/2026 3/20/2026 IP 71114.05 000720 Maintenance of Emergency Preparedness 1,2 3/16/2026 3/20/2026 IP 71151 001397 Performance Indicator Verification Radiation Protection Baseline Inspection

1,2 5/4/2026 5/8/2026 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, & Transportation License Renewal Post Approval Phase 2 - Unit 2

1,2 5/18/2026 6/5/2026 IP 71003 000687 Post-Approval Site Inspection for License Renewal Security Baseline Inspection

1,2 6/8/2026 6/12/2026 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance Prepared on 8/21/2024 9:44:59 AM 3 of 3