Integrated Inspection Report 05000454/2024001; 05000455/2024001 and 07200068/2024001
ML24130A198
Person / Time
Site: Byron  Constellation icon.png
Issue date: 05/10/2024
From: Richard Skokowski
NRC/RGN-III/DORS/RPB3
To: Rhoades D
Constellation Energy Generation, Constellation Nuclear
References
IR 2024001
Download: ML24130A198 (1)


Text

SUBJECT:

BYRON STATION - INTEGRATED INSPECTION REPORT 05000454/2024001; 05000455/2024001 AND 07200068/2024001

Dear David Rhoades:

On March 31, 2024, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Byron Station. On April 12, 2024, the NRC inspectors discussed the results of this inspection with H. Welt, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Richard A. Skokowski, Chief Reactor Projects Branch 3 Division of Operating Reactor Safety Docket Nos. 05000454; 05000455 and 07200068 License Nos. NPF-37 and NPF-66

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000454; 05000455 and 07200068

License Numbers:

NPF-37 and NPF-66

Report Numbers:

05000454/2024001; 05000455/2024001 and 07200068/2024001

Enterprise Identifier:

I-2024-001-0068 and 1-2024-001-0101

Licensee:

Constellation Energy Generation, LLC

Facility:

Byron Station

Location:

Byron, IL

Inspection Dates:

January 01, 2024 to March 31, 2024

Inspectors:

A. Demeter, Resident Inspector

R. Elliott, Senior Project Engineer

R. Knutson, Illinois Emergency Management Agency

M. Learn, Team Leader

J. Robbins, Senior Resident Inspector

D. Sargis, Health Physicist

Approved By:

Richard A. Skokowski, Chief

Reactor Projects Branch 3

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Byron Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

PLANT STATUS

Unit 1 operated at or near rated thermal power for the entire inspection period.

Unit 2 operated at or near rated thermal power for the entire inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk-significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Impending Severe Weather Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the adequacy of the overall preparations to protect risk-significant systems from impending severe weather during a winter storm watch and extreme cold weather during the week ending January 13, 2024.

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Partial Walkdown of the Unit 1 "A" Train Safety Injection (SI) and Residual Heat Removal Systems prior to a scheduled "B" Train SI work window on February 12, 2024.
(2) Partial Walkdown of the 1A, 1B, and 2B Diesel Generators (DG) following vent fan failure of the 2A DG on February 1, 2024.
(3) Partial Walkdown of Unit 0 and Unit 2 Component Cooling (CC) Systems during a Unit 1 CC Heat Exchanger Work window, as documented in Work Order (WO)

===5284272 on March 8, 2024.

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01)===

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Fire Zone 5.2-2, Unit 2, Auxiliary Building 426' Elevation, Division 21 ESF Switchgear Room on January 24, 2024.
(2) Fire Zone 8.3-1, Unit 1 Turbine Building 401'-0" Elevation, following spurious actuation of suppression zone 1S-23, as documented in Issue Report (IR) 4725659 on January 2, 2024.
(3) Fire Zone 12.1-0, Fuel Handling Building 426' and 401' Elevations, following concerns over improperly breached fire seals, as documented in IR 4722396 on January 10, 2024.
(4) Fire Zone 9.1-1 and 9.4-1, Auxiliary Building 401'-0" Elevation, 1B Diesel Generator &

Day Tank Room, following smoke coming from the starting air compressor, as documented in IR 4730725 on January 16, 2024.

(5) Assessment of Diesel Generator Cable Tunnel Hatch 1DSH120 following identification of inadequate hatch sealing, as documented in IR 4704957 on January 25, 2024.

Fire Brigade Drill Performance Sample (IP Section 03.02) (1 Sample)

(1) Observation and evaluation of the station's on shift fire brigade during an unannounced fire drill on March 19, 2024.

71111.06 - Flood Protection Measures

Flooding Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated internal flooding mitigation protections in the:
  • Unit 1, Turbine Building, 401' Elevation, the four quadrants of Fire Zone 8.3-1.
  • Unit 1, Essential Service Water Pump Room, 330' Elevation, Fire Zone 11.1A-0.
  • Unit 2, Essential Service Water Pump Room, 330' Elevation, Fire Zone 11.1B-0.

71111.07A - Heat Exchanger/Sink Performance

Annual Review (IP Section 03.01) (1 Sample)

The inspectors evaluated readiness and performance of:

(1) Evaluation of the condition and performance of Unit 1, Train B, Safety Injection Pump Bearing Oil Cooler as documented in WO 5391301.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control room during routine activities March 4 through March 7, 2024.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated the performance of a complex casualty graded scenario by a crew of licensed plant operators in the facility's simulator on February 8, 2024.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (3 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) Review of the station's periodic evaluation of effectiveness of maintenance activities per 10 CFR 50.65(a)(3).
(2) Review of the station's treatment of Maintenance and Test Equipment (M&TE)calibration failures over the previous 24-months.
(3) Review of the station's maintenance strategy for replacing Main Steam Power Operated Relief Valve controllers.

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Review and evaluation of the risk associated with the replacement of 2PS-DG098A on the 2A Diesel Generator following a failure to start, as documented in IR 4727211 on January 4, 2024.
(2) Review of the station's B2R24 TS 3.0.4.b Evaluation - Mode Change with Technical Specification Equipment Out of Service on January 11, 2024.
(3) Verification of select risk mitigating actions implemented in the plant during emergent work on the 2A Diesel Generator on January 31, 2024.
(4) Review and evaluation of the risk associated with removing and replacing the 1B Diesel Generator Starting Air Compressor, as documented in WO 5443933 on March 12, 2024.
(5) Review and evaluation of the risk associated with the loading of spent fuel into the Dry Cask Storage (DCS) system throughout several weeks of the campaign, as documented in WO 5332871.

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (8 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) Evaluation of the operability of 2PS9356B and its impact on containment based on failing the local leak rate test, as documented in IR 4710010 on January 26, 2024.
(2) Evaluation of the operability of the 1B Containment Spray Pump following identification of observable indications during NDE (Nondestructive Examination)exams, as documented in IR 4703543 on January 10, 2024.
(3) Evaluation of the operability of the 2A Diesel Generator following vent fan trip on high differential pressure, as documented in IR 4739551 on February 22, 2024.
(4) Evaluation of the operability of 1AF049D as documented in IR 4706401 on March 6, 2024.
(5) Evaluation of the operability of motor operated valve (MOV) 1SI8812B following discovery of issues with a mounting bolt, as documented in IR 4689931 on March 6, 2024.
(6) Evaluation of the operability of the 2A Auxiliary Feedwater Pump following discovery of high oil viscosity, as documented in IR 4752721 on March 14, 2024.
(7) Evaluation of the operability of 0A Essential Service Water Makeup Pump following discovery of severe coating degradation on the gear oil cooler, as documented in IR 4761004 on March 29, 2024.
(8) Evaluation of the operability of the limit switch control scheme of various essential service water valves, as documented in IR 4540295 on March 29, 2024.

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (2 Samples)

The inspectors evaluated the following temporary or permanent modifications:

(1) Review of temporary plant modification per Engineering Changes (EC) 634666, Lift Lead on SAT 242-2 PD-Guard to Eliminate Nuisance Alarm.
(2) Review of temporary/permanent plant modification per EC 640554: TCCP (Temporary Configuration Change Package) for U2 Train A Sensor #8 RVLIS Leads Lifted.

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (7 Samples)

(1) Functional and operational testing of 2A Essential Service Water Pump Cubicle Cooler following a scheduled work window, as documented in WO 4945433 on February 1, 2024.
(2) Functional and operational testing of 0VV23C and Technical Support Center ventilation following identification of an acrid odor, as documented in IR 4748769 on February 15, 2024.
(3) Functional and operational testing of the 1D Steam Generator Power Operated Relief Valve (PORV) following a work window, as documented in WO 5443249 on March 4, 2024.
(4) Functional and operational testing of the 2B and 2C Pressurizer Heater Transformers following inspection and maintenance, as documented in multiple WOs on March 14, 2024.
(5) Functional and operational testing of the 1B Essential Service Water Pump following a work window, as documented in WO 5359119 on March 20, 2024.
(6) Functional and operational testing of 2B Component Cooling Pump following a work window, as documented in WO 5476077 on March 22, 2024.
(7) Functional and operational testing of the 2A Residual Heat Removal pump following a work window, as documented in WO 5379461 on March 26, 2024.

Surveillance Testing (IP Section 03.01) (5 Samples)

(1)2BOSR 5.5.8.SI.5-1a, Inservice Testing of the 2A Safety Injection Pump, as documented in WO 5456687 on February 28, 2024.

(2)1&2 BOSR 0.5-2.AF.1-1, Surveillance Testing of Unit 1, and Unit 2 Auxiliary Feedwater Valves _AF005A-D, as documented in WOs 5426049 AND 5426050, on March 4, 2024.

(3)1BOSR 8.1.2-1, surveillance testing of the 1B Diesel Generator, as documented in WO 5475997 on February 29, 2024.

(4)0BOSR 7.10.1-1, Control Room Ventilation Train 0A Quarterly Surveillance, as documented in WO 5425042 on March 4, 2024.

(5)1BOSR 8.1.2-1 and 1BOSR DG-8A, surveillance testing of 1A Emergency Diesel Generator and Turbocharger Spin Down, as documented in WO 5380211 on March 28, 2024.

Inservice Testing (IST) (IP Section 03.01) (1 Sample)

(1)1BOSR 5.5.8.CS.5-2c, Inservice Testing of the 1B Containment Spray Pump, as documented in WO 5417950 on February 7, 2024.

Diverse and Flexible Coping Strategies (FLEX) Testing (IP Section 03.02) (1 Sample)

(1) Review of Compensatory Actions related to the failure of the 0C High Head Flex Pump, as documented in IR 4717747 on February 21,

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

IE01: Unplanned Scrams per 7000 Critical Hours Sample (IP Section 02.01)===

(1) Unit 1 (January 1, 2023 through December 31, 2023)
(2) Unit 2 (January 1, 2023 through December 31, 2023)

IE03: Unplanned Power Changes per 7000 Critical Hours Sample (IP Section 02.02) (2 Samples)

(1) Unit 1 (January 1, 2023 through December 31, 2023)
(2) Unit 2 (January 1, 2023 through December 31, 2023)

IE04: Unplanned Scrams with Complications (USwC) Sample (IP Section 02.03) (2 Samples)

(1) Unit 1 (January 1, 2023 through December 31, 2023)
(2) Unit 2 (January 1, 2023 through December 31, 2023)

71152A - Annual Follow-up Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) The inspectors reviewed the issues identified in open IRs and WOs for Unit 1, Unit 2, and Unit 0 [common to both units], as documented the Control Room Deficiencies report generated January 29, 2024.
(2) The inspectors reviewed the corrective actions associated with non-cited violation (NCV) 05000454(05000455)/2023012-01, Relief Valve Scope Testing, as documented in IR

OTHER ACTIVITIES

- TEMPORARY INSTRUCTIONS, INFREQUENT AND ABNORMAL

60855 - Operation Of An ISFSI Operation Of An ISFSI

(1) The inspectors evaluated the licensees independent spent fuel storage installation (ISFSI) cask loading activities from March 11 through March 14, 2024. Specifically, the inspectors observed the following activities during the loading of multi-purpose canister (MPC) No. 952:
  • heavy load movement of loaded MPC out of the spent fuel pool
  • closure welding and nondestructive evaluations
  • radiological field surveys
  • heavy load lift into stack-up configuration
  • downloading loaded MPC into overpack The inspectors performed walkdowns of the ISFSI pad and walkdowns of the ISFSI haul path.

The inspectors evaluated the following:

  • spent fuel selected for loading into dry cask storage during this loading campaign
  • selected corrective action program documents
  • changes to the site's 10 CFR 72.212 report since the previous inspection

INSPECTION RESULTS

Observation: Review of Corrective Actions for Non-Cited Violation 05000454(05000455)/2023012-01, Relief Valve Scope Testing 71152A The inspectors performed a detailed review of Issue Report (IR) 4712019, NCV 05000454(05000455)/2023012-01, Relief Valve Scope Testing. The IR was written in response to a green finding and associated non-cited violation (NCV) for the failure to comply with a procedure as written. The station determined the failure to complete a step in BMP 3100-23, IST Crosby Safety/Relief Valve Bench Testing, was contrary to the stations requirements of HU-AA-104-101, Procedure Use and Adherence (PUA), and contributed to the untimely scope expansion testing.

The inspectors concluded that the licensees actions taken in accordance with their correction action program were reasonable given the overall safety significance of the issue. Corrective Action Program (CAP) actions were focused on reinforcing the standards of PUA and work package close out within the Mechanical Maintenance Department (MMD) and revising procedures to remove the self-imposed expansion scope timeframe.

During the review of the IR, the inspectors identified additional minor issues with PUA or CAP closure documentation. These work products collaborated on by individuals from MMD, maintenance planning, programs engineering, regulatory assurance, and others, contained several issues pertaining to PUA and PI-AA-125, Corrective Action Program (CAP)

Procedure. The failure to complete documentation as required for one corrective action (CA)resulted in the CA being rejected during a subsequent monthly scheduled CA review, weeks after the CA was marked complete (Action Tracking Item (ATI)-11). Multiple gaps were identified in the Organizational Effectiveness Evaluation required per one CA (ATI-05),despite requiring review and approval by a senior leadership team member or designee.

Closure documentation for one CA was not retrievable by the inspectors nor Regulatory Assurance when requested (ATI-04).

Many CAs focus on PUA weaknesses, particularly within MMD. The extent of condition performed under the IR investigation reviewed similar procedures and valve performance analyses, but did not include aspects related to PUA, despite this being listed as a cause of the finding and NCV. While not necessarily prescriptive of a broader issue, the inspectors find it prudent to elucidate the gaps in PUA that occurred during the implementation of the CAs, as noted in our observations.

No findings or violations of NRC requirements of more than minor safety significance were identified by the inspectors in the course of this review.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On April 12, 2024, the inspectors presented the integrated inspection results to H. Welt, Site Vice President, and other members of the licensee staff.
  • On March 15, 2024, the inspectors presented the 1Q2024 ISFSI Cask Loading Inspection results to S. Harvey, Plant Manager, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

AR 4513323

Trend of Grid Strap Damage during DCS Inspections

07/27/2022

AR 4716128

MPC Lift Stud Has A Defect on the Threads

11/08/2023

AR 4724719

Debris Discovered on Fuel Assembly

2/20/2023

AR 4755324

FM in MPC 0951

03/04/2024

Corrective Action

Documents

AR 4757851

DCS HI-STORM Made Contact with Outer Train Shed Roll Up

Door

03/13/2024

AR 4757750

NRC-MPC Lid Punch Mark Observation

03/13/2024

AR 4757790

NRC-Cask Spacing on ISFSI Pad Observation

03/13/2024

Corrective Action

Documents

Resulting from

Inspection

AR 4757795

NRC-Lift Yoke Paint Observation

03/13/2024

Drawings

Drawing 5490

Sheet 2

Dry Fuel Storage Project Cask Storage Pad Details

EC 639565

Byron Fuel Selection Packages and Alternate List for 2024

ISFSI Campaign

Engineering

Changes

ECO-5014-312

Foreign Material to Be Stored in MPC

HI-2125116

Thermal Evaluation of Cask Spacing on ISFSI at Exelon Sites

2/07/2012

Engineering

Evaluations

HI-2230448

Thermal Inertia Calculation for Braidwood and Byron

2.48-221

Review of CoC Holder ECOs, SMDRs, and the Associated

2.48 Reviews Related to the Casks to be Loaded in BYNPS

22 Spent Fuel Loading Campaign

2.48-222

Casks for the 2022 Spent Fuel Loading Campaign (Byron)

2.48-224

Holtec SMDR No. 1024-3004 for HI-STORM 100S Version B

Serial Nos. 100-1406 and 100-1407

2.48-226

EC 635094

2.48-235

HI-2230448 - Thermal Inertia Calculation for Braidwood and

Byron

2.48-236

Spent Fuel Casks and Fuel Selection Packages for the 2024

Spent Fuel Loading Campaign (Byron) - ISFSI

60855

Miscellaneous

NOSA-BYR-22-

Independent Spent Fuel Storage Installation Audit

06/10/2022

4003-R95-24-

007-03132024-

Helium Leak Test Report

03/13/2024

NDE Reports

20443-952-01

Root Layer Liquid Penetrant Examination Report

03/11/2024

BFP FH-69

HI-TRAC Movement within the Fuel Building

BFP FH-70

HI-TRAC Loading Operations

MA-AA-716-022

Control of Heavy Loads Program

OU-MW-671-300

MPC Processing

Procedures

RP-AA-306

HOLTEC HI-STORM Radiation Survey

Radiation

Surveys

23-199992

ISFSI Pad Annual Survey

08/29/2023

05332871-12

Obtain and Analyze Wet Cask Pit Boron Concentration

03/12/2024

MREQ 4725997-

Concrete Pad and HI-STORM Casks Integrity Inspection

2/21/2023

WO 5319749-01

Overhead Crane Annual Mechanical Inspection

11/21/2023

60855

Work Orders

WO 5332871-05

Lifting Device Inspection Per BHP FH-85

11/30/2023

4714678

2SH15AB Fan Would Not Run. WINTER READINESS

11/02/2023

4714679

2SH15AF Fan Would Not Run. WINTER READINESS

11/02/2023

4714683

2SH15AH Fan Would Not Run. WINTER READINESS

11/02/2023

4714684

2SH15AJ Fan Would Not Start. WINTER READINESS

11/02/2023

4714686

2SH15AL Fan Would Not Start. WINTER READINESS

11/02/2023

4714687

2SH15AS Fan Would Not Start. WINTER READINESS

11/02/2023

4714688

2SH15AT Fan Would Not Start. WINTER READINESS

11/02/2023

4716405

Aquaguard Conveyor Belt At River Not Always Working

11/09/2023

21130

2SH15AJ Fan Would Not Start. WINTER READINESS

2/02/2023

21133

2SH15AT Fan Would Not Start. WINTER READINESS

2/02/2023

21135

1SH15AS Fan Would Not Start. WINTER READINESS

2/02/2023

21136

1SH02AG Fan Does Not Run WINTER READINESS

2/02/2023

21143

WINTER READINESS: 0BOSR XFT-A1 Roll Up

2/02/2023

Corrective Action

Documents

21594

PM Hold Codes Applied due to Winter Readiness (RISK)

2/04/2023

BOP HT-T1

Heat Tracing Locations

BOP XFT-1

Cold Weather Operations

OP-AA-108-111-

1001

Severe Weather and Natural Disaster Guidelines

71111.01

Procedures

WC-AA-107

Seasonal Readiness

4560616

1B SI Pump Branch Flow Difference

03/09/2023

4562249

1TS-SI059 Needs Setpoint Reset

03/15/2023

21527

RWST Heater (1SI01TA) Not Energized as Expected

2/05/2023

Corrective Action

Documents

4734884

WR Needed for 1B SI Oil Cooler Pipe Replacements in

B1R26

01/23/2024

M-42 Sheet 4

Diagram of Essential Service Water

AQ

Drawings

M-62 Sheet 1A

Diagram of Safety Injection Unit 1

AW

BOP CC-10

Alignment of the U-0 CC Pump and U-0 CC HX to A Unit

BOP CC-E2

Unit 2 Component Cooling System Electrical Lineup

BOP CC-M2

Unit 2 Component Cooling System Valve Lineup

BOP DG-E1

Unit 1 Diesel Generator Electrical Lineup

BOP DG-E2B

Unit 2 Diesel Generator B Train Electrical Lineup

BOP DG-M1A

Unit 1 Diesel Generator A Train Valve Lineup

BOP DG-M1B

Unit 1 Diesel Generator B Train Valve Lineup

BOP DG-M2B

Unit 2 Diesel Generator B Train Valve Lineup

BOP RH-E1A

Residual Heat Removal System Train A Electrical Lineup

BOP RH-M1

Residual Heat Removal System Valve Lineup

BOP RH-M1

Residual Heat Removal System Valve Lineup

BOP SI-E1A

Safety Injection System Train A Electrical Lineup

BOP SI-E1A

Safety Injection System Train A Electrical Lineup

BOP SI-M1A

Safety Injection System Train A Valve Lineup

Procedures

BOP SI-M1C

Safety Injection System Train A Valve Lineup

4930085

Degraded QSS Switch On 1SX007

03/06/2024

284270

Replace Cubicle Fuse Block (1 Pole FU)

03/06/2024

284272

1SX004 Replace Disc Oper Mech LG & SM (131X1-A2)U1

Component Cooling Heat Exchanger

03/06/2024

5369433

PM Inspection, In-Service Diagnostic Test, PIT

03/06/2024

5391301

LR-1SI01SB - Heat Exchanger Inspection Per Generic Letter 89-13

2/07/2024

71111.04

Work Orders

5417950

(NEIL)-1CS01PB Comprehensive IST Requirements for

Containment Spray

2/07/2024

1098450

Four of Eight Studs Are Broken for 1DSH120

08/05/2010

238814

APS As-Found IW Found 3 Broken Studs on Cable Tunnel

Hatch

04/12/2019

71111.05

Corrective Action

Documents

4518198

Broken Studs on 1DSH120

08/22/2022

4563319

Small Air Leak on 1B Starting Air Compressor

03/19/2023

4670991

Four of Eight Studs Are Broken for 1DSH120

04/18/2023

4690260

1B DG Air Dyer Fan Did Not Start

07/13/2023

4696282

Fuel Handling Building Communication Support

08/14/2023

4702285

1SA142D Extremely Hard to Turn

09/13/2023

4704957

U1 Cable Tunnel Hatch 1DSH120 Broken Studs

09/26/2023

4719720

Submission Requested for Storage Area Approval MA-AA-

716-026

11/27/2023

22396

Unit 1 - Unapproved Modification Requires Removal

2/08/2023

22398

Unit 2 - Unapproved Modification Requires Removal

2/08/2023

22508

Quarterly Review of Fire Brigade Drill Performance

2/09/2023

22845

Staging Wood Pallets near CP Room in light of NFPA 1,

34.10

2/11/2023

22855

0B Fire Pump Right Angle Gear Anti Rotation Device

Damaged

2/11/2023

24102

Unexpected FP Alarm Received in the MCR (1S-23)

2/17/2023

24890

0DSD585 PBI Change

2/21/2023

24992

FP Relay Did Not Actuate as Expected

2/21/2023

25014

UAT 141-1 (1S-15) FP Tamper Switch Not Alarming

2/21/2023

25014

UAT 141-1 (1S-15) FP Tamper Switch Not Alarming

2/21/2023

25659

Spurious Actuation of Fire Suppression Zone 1S-23

2/27/2023

27098

1FP5121 Needs Replaced

01/08/2024

27098

1FP5121 Needs Replaced

01/08/2024

27152

0FP03PB - OB Fire Pump

01/08/2024

27152

0FP03PB - OB Fire Pump

01/04/2024

27203

0FP5351 Handwheel broken

01/08/2024

27455

Fire Barrier Penetrations Found Degraded (Worse Than

Expected)

01/08/2024

4730725

B DG Starting Air Compressor 1DG01SB-B Smoking

01/12/2024

4735591

FP Program Health cornerstone YELLOW for 2P2023

01/24/2024

4736310

Need Removed Valves Inspected

01/25/2024

4749190

Procedure Rev and Replace 0FP578 Vlv

2/10/2024

4759567

Quarterly Review of Fire Brigade Drill Performance

03/20/2024

660861

Broken Stud on Cover of U-1 DG Cable Vault

08/15/2007

Drawings

Auxiliary Building Mezzanine Floor Plan Area 1

AI

PRE-FIRE PLAN

  1. 176

FZ 12.1-0 Fuel Handling Building 401-0 Elevation Fuel

Handling Building

PRE-FIRE PLAN

  1. 177

FZ 12.1-0 Fuel Handling Building 426-0 Elevation Fuel

Handling Building

PRE-FIRE PLAN

  1. 185

FZ 18.1-1 Auxiliary Building 401-0 Elevation 1B DG &

Switchgear Room Air Shaft

Pre-Fire Plan

  1. 44

Fire Zone 5.2-2, Unit 2, Auxiliary Building 426' Elevation,

Division 21 ESF Switchgear Room

PRE-FIRE PLAN

  1. 60

FZ 8.3-1 Northwest Turbine Building 401-0 Elevation Unit 1

Turbine Building - NW

PRE-FIRE PLAN

  1. 61

FZ 8.3-1 Southeast Turbine Building 401-0 Elevation Unit 1

Turbine Building - SE

PRE-FIRE PLAN

  1. 62

FZ 8.3-1 Southwest Turbine Building 401-0 Elevation Unit 1

Turbine Building - SW

PRE-FIRE PLAN

  1. 63

FZ 8.3-1 Northeast Turbine Building 401-0 Elevation Unit 1

Turbine Building - NE

Pre-Fire Plan

  1. 75

FZ 11.6C-0 Auxiliary Building 426'-0" Elevation EMD MOV

Room

Fire Plans

PRE-FIRE PLAN

  1. 88

FZ 9.1-1, FZ 9.4-1 Auxiliary Building 401-0 Elevation 1B

Diesel Generator & Day Tank Room

0BOL 10.d

LCOAR CO2 Systems

0BOL 10.g

LCOAR Fire Assemblies

BAP 1100-10

Response Procedure for Fire/Fire Alarm

BAP 1100-3

Plant Barrier Impairment Program

BOP DG-21

Diesel Generator Air Receiver Pressure Control

CC-AA-211

Fire Protection Program

Procedures

OP-AA-201-008

Pre-Fire Plan Manual

Work Orders

5356800

FNM Replace Broken Studs On 1DSH120 Hatch

11/29/2023

Corrective Action

Documents

27692

Flooding of WF Pump Room

2/16/2012

Miscellaneous

Report

Individual Plant Examination Submittal Report

04/28/1994

Pre-Fire Plan

  1. 60

Turbine Building 401' Elevation Unit 1 Turbine Building North-

West

71111.06

Procedures

Pre-Fire Plan

  1. 61

Turbine Building 401' Elevation Unit 1 Turbine Building South-

East

Pre-Fire Plan

  1. 62

Turbine Building 401' Elevation Unit 1 Turbine Building South-

West

Pre-Fire Plan

  1. 63

Turbine Building 401' Elevation Unit 1 Turbine Building North-

East

Pre-Fire Plan

  1. 96

Auxiliary Building 330' Elevation Unit 1 Essential Service

Water Pump Room

71111.06

Procedures

Pre-Fire Plan

  1. 97

Auxiliary Building 330' Elevation Unit 2 Essential Service

Water Pump Room

Calculations

BYR95-074

SI Pump Oil Cooler Evaluation

10/19/1995

Corrective Action

Documents

4734884

WR Needed for 1B SI Oil Cooler Pipe Replacements in

B1R16

01/23/2024

Miscellaneous

Photographs

36-Photographs of the Heat Exchanger Internal Surfaces and

Pipe Connections

2/08/2024

71111.07A

Work Orders

5391301

LR-1SI01SB - Hx Inspection per Generic Letter 89-13

2/12/2024

71111.11Q

Miscellaneous

SEG 24-1-1

LORT Cycle Training

0478846

M&TE Calibration and Control Process

04/14/2006

4348031

N2 Leak on 1B SI Accumulator

06/04/2020

4446314

1SX168 Fail Open Test Failed

09/14/2021

4447840

Sparks Observed after Energizing 133z Transformer

09/22/2021

4449848

Maintenance Rule - 17th (a)(3) Assessment

09/30/2021

4452847

1B VP Chiller Failed to Trip Locally and Remotely

10/14/2023

4453027

NOS ID: Monitor Timeliness of IR Screenings for MRule

10/14/2021

4469617

M&TE OOT Evaluation Tracking - 2022

01/03/2022

4490482

0A SX Makeup Pump Trip

04/05/2022

4492979

JW Leak on 1B AF Pp

04/14/2022

4497537

2CW001C Breaker Needs EMD Troubleshooting

05/04/2022

4498888

U2 Rod Drive Group 1AC Rods Not Moving

05/10/2022

4499432

Received unexpected Unit 2 Rod Control Urgent Failure

Alarm

05/12/2022

4512324

2A SX cooler 2A and 2B Fans Not Running

07/22/2022

4512731

2B DG Trouble Alarm, Inop 2B DG

07/25/2022

29961

2FP010 Failed STT

10/17/2022

4531661

1FP010 Failed Stroke Time Test

10/24/2022

71111.12

Corrective Action

Documents

4532569

M&TE OOT Evaluation Tracking - 2022

10/27/2022

4538981

1VP01AD 1D RCFC SX Coil Assy Leak-Top Left When

Looking @ Rx

11/25/2022

4540536

MRULE A1 Determinations Performed Incorrectly

2/02/2022

4543255

NRC ID: Maintenance Rule Evaluation Dispositioning

2/16/2022

4543811

M&TE OOT Evaluation Tracking - 2023

2/20/2023

4545582

Gaps Identified During Corp MR Self-Assessment

2/30/2022

4666560

Maintenance Rule - 18th (a)(3) Assessment

03/31/2023

4711156

Intentionally Abbreviated Maintenance on 2FP010

10/20/2023

4713250

Maintenance Rule - Issue Screening Timeliness

10/28/2023

21264

M&TE OOT Evaluation Tracking - 2023

2/03/2023

27420

M&TE OOT Evaluation Tracking - 2024

01/08/2024

Corrective Action

Documents

4751090

MS PORV Controller Major Electronics PM Coming Due

2/18/2024

Miscellaneous

Maintenance Rule (A)(3) Assessment for July 2021 through

December 2022

03/31/2023

ER-AA-320-1004

Maintenance Rule 18-10 Performance Monitoring and

Dispositioning Between (a)(1) and (a)(2)

ER-AA-320-1007

Maintenance Rule 18-10 - Periodic (a)(3) Assessment

71111.12

Procedures

MA-AA-716-040

Control of Portable Measurement and Test Equipment

Program

4690260

1B DG Air Dyer Fan Did Not Start

07/13/2023

4698132

Install Thermal Covers on Empty HI Storms

08/23/2023

4700488

ISFSI/DCS Helium Tube Trailer Quantity Needs Verification

09/05/2023

4714534

DCS - Heaters Not Working in Dry Cask Storage Building

11/01/2023

27211

2A DG Failed to Start

01/08/2024

4730048

New DCS/ISFSI Building Heater Transformer Failure

01/11/2024

4730498

Spare RCP Motor Required to Be Rotated to Support

DCS/ISFSI Activities

01/12/2024

4730725

B DG Starting Air Compressor 1DG01SB-B Smoking

01/12/2024

4732126

Framatome Replica Assembly Not Accepted

01/17/2024

4739702

Damaged Grid Strap on Fuel Assembly X27J

01/31/2024

4739765

PMID 00185680-01 ISFSI Installation Inspection Results

01/31/2024

4739796

NRC Identified Discrepancy in Protected Equipment Posting

01/31/2024

4751415

Water in Instrument Lines

2/16/2024

4752030

Change to MPC0951 FSP 2024 DCS

2/20/2024

71111.13

Corrective Action

Documents

4753384

DCS Trackmobile Parking Break Can Not Be Released

2/26/2024

4753389

DCS - Damaged Cable Port on SLS Jack

2/26/2024

4753579

24 DCS - Weld Vendor Mobilization LL

2/27/2024

4755324

FM in MPC0951

03/04/2024

4755372

DCS - Determination of Supplemental Cooling Required

03/04/2024

4755532

24 DCS - PCI Weld Head Power Supply Error Encountered

03/04/2024

4756524

Alternates Needed for 2024 DCS Assemblies D66H and

D67H

03/07/2023

4757779

NRC-Closure Rings Observation

03/12/2024

4757790

NRC-Cask Spacing on ISFSI Pad Observation

03/13/2024

4757793

Mating Device Air Bags Did Not Hold Pressure

03/13/2024

4757795

NRC-Lift Yoke Paint Observation

03/12/2024

4757824

1B DG Air Compressor Constantly Blowing Down

03/13/2024

4757851

DCS HI-STORM Made Contact With Outer Train Shed Roll

Up Door

03/13/2024

6E-2-4030DG33

Schematic Diagram-Diesel Generator 2A Starting Sequence

Control 2DG01KA Part 3

T

6E-2-4030DG34

Schematic Diagram-Diesel Generator 2A Starting Sequence

Control (Description of Operation) 2DG01KA Part-4

D

Drawings

6E-2-4030DG40

Schematic Diagram-Diesel Generator 2A Shutdown and

Alarm System 2DG01KA

Q

Engineering

Changes

2055

Engineering Review of Rigging Scaffold for 1B DG

Compressor

03/01/2024

Holtec ECO-

5014-312

Engineering Change Order (ECO) for HI-STORM 100 FSAR

NF230405

Cask Loading Requirements Memorandum

OP-AA-102-104

Standing Order 2024 Dry Cask Campaign Spent Fuel Pool

Boron Concentration

Plant Barrier

Impairment

Permit 24-014

1B DG roll up door

Miscellaneous

PRA Application

Notebook BY-

MODE-036

TS 3.0.4.b Evaluation - Mode Change with Technical

Specification Equipment out of Service

0BDCSR 3.2.2.1

MPC Surface Contamination Verification

0BDCSR 3.3.1.1

DCS Boron Concentration

Procedures

2BOSR 8.1.2-1

Unit Two 2A Diesel Generator Operability Surveillance

2BOSR DG-3

Unit Two 2B Diesel Generator Relay Operation Verification

BFP FH-34

Water Transfers of The Spent Fuel Pool, Wet Cask Pit or

Transfer Canal

BFP FH-65

Spent Fuel Cask Site Transportation

BFP FH-73

Unrestrained Stack-Up Support

BFP FH-83

Spent Fuel Cask Contingency Actions

BOP DG-12T1

Inadvertent Diesel Generator Trip Log

CC-AA-402

Maintenance Specification: Installation of Temporary Rigging

ER-AA-600

Risk Management

ER-AA-600-1012

Risk Management Documentation

ER-AA-600-1042

On-Line Risk Management

NF-AA-309

Special Nuclear Material and Core Component Move Sheet

Development;

NF-AA-622

Fuel Selection and Documentation for Dry Cask Loading

OP-AA-108-117

Protected Equipment Program

OP-BY-108-117-

1000

1: Protected Equipment Matrix

OP-BY-108-117-

1000

2: Protected Equipment Worksheet

OU-AA-630-1000

Spent Fuel Loading Campaign Management

OU-AA-630-101

Dry Cask Storage / ISFSI Inspection Surveillance Program

OU-AP-104

Shutdown Safety Management Program Byron/Braidwood

OU-AP-204

Fuel Movement in the Spent Fuel Pool for Byron and

Braidwood

OU-MW-671-300

MPC Processing Forced Helium Dehydration (FHD) for

PWRS (ISFSI)

OU-MW-679-300

MPC Alternate Cooling for PWRs

RP-AA-306

Holtec HI-Storm Radiation Survey

WC-AA-101

On-Line Work Control Process

5332871

Dry Cask Storage Campaign (2024)

03/18/2024

22895

Passport to Asset Suite Contingency (Replace 2PS-DG098A)

01/03/2023

Work Orders

5443933

B DG Starting Air Compressor 1DG01SB-B Smoking

03/12/2024

71111.15

Calculations

NED-M-MSD-33

Seismic Thrust Limits of the Byron Motor Operated Valves

1(2)SI8812A(B) (Westinghouse, 12, Gate with SB-2-80

Operator)

1617138

0A SX Makeup Pump Jacket Water Failed Coating

2/04/2014

1617139

0A SX Makeup Pump Gear Oil Heat Exchanger Cover Plate

Failed Coating

2/04/2014

4131136

Inactive Boric Acid Leak on Inlet Flange of 1B CS Eductor

04/26/2018

4189826

0A SX Makeup Pump Gear Oil Cooler Heat Exchanger Cover

Plate Coating

10/30/2018

4673210

Intentional abbreviated maintenance

04/25/2023

4680035

Inactive BA Leak - 1B CS Eductor Inlet Flange

05/22/2023

4680371

Unit 1 BACC Focused Walkdown Results

05/22/2023

4682823

NOS ID: LLRT Summary Procedure Not Updated with Current

License Requirements

06/05/2023

4682825

NOS ID: LLRT Summaries Did Not Incorporate New

Administrative Limit, Etc.

06/05/2023

4682827

NOS ID: LLRT Procedure References Not Updated to Current

Regs.

06/05/2023

4689931

1SI8812B Stripped MOV Actuator Motor Mount Bolt

07/11/2023

4690368

1SI8812B Motor Mounting Bolts Not Long Enough

07/12/2023

4702543

Recordable Indications Observed

09/18/2023

4706401

Leakage past 1AF049D

10/01/2023

4710010

2PS9356B Failed As-Found LLRT at 36.6 SCFH

10/16/2023

4717262

P-32 Adverse LLRT Trend (2FC011 & 2FC012)

11/13/2023

4717360

1SX027A EOC Review from IR 4540295

11/13/2023

4717365

1SX027B EOC Review from IR 4540295

11/13/2023

4717379

1SX016A EOC Review from IR 4540295

11/13/2023

4717382

1SX027A EOC Review from IR 4540295

11/13/2023

4717384

1SX027B EOC Review from IR 4540295

11/13/2023

23644

WR/WO for Inspection of SX04AA

2/14/2023

4739551

2A DG Vent Fan Trip on High DP

01/31/2024

4752721

2AF01PA Pump Oil High Viscosity

2/23/2024

4753381

2AF01PA Pump Oil Confirmatory Sample High Viscosity

2/26/2024

4761004

Severe Coating Degradation on 0SX04AA

03/25/2024

Corrective Action

Documents

4761452

WSA/DSA WO# 5429686-02 Support LR Oil Cooler

inspection

03/26/2024

Engineering

Changes

406504

Installation of Vent Valve n Flex Line 1FX001BC-4"

1FX001AD-4" At 401 Elevation In MSIV Rooms

EM-4981

Stress Report for Westinghouse Electro-Mechanical Division

Class I Nuclear Valves

Miscellaneous

F-2891/MRR

7650

Manufacturers' Code Data Report for 0A SX Makeup Pump

10/01/1979

NDE Reports23-089

VT-3 Visual Examination for WO 5368348

09/18/2023

1BOSR FX-S1

Unit 1 Auxiliary Feedwater FLEX Connection Low Point Drain

Semiannual Inspection

2BOSR

5.5.8.AF.5-1c

Unit Two Comprehensive Inservice Testing (IST)

Requirements For The Motor Driven Auxiliary Feedwater

Pump 2AF01PA

BMP 3000-16

Application of Metal-Clad Ceramalloy Thin-Film Coating

System

BMP 3222-2

Preventative Maintenance of Essential Service Water

Makeup Pump Drive Unit

BOP AF-300-1

Sampling The Motor Driven Auxiliary Feedwater Pumps

Lubricating Oil Reservoirs

BOP AF-5

Motor Driven Auxiliary Feedwater Pump A Start-up on Recirc

BOP AF-5T1

Motor Driven Auxiliary Feedwater Pump Operating Log

BVP 800-30

Essential Service Water Fouling Monitoring Program

(GL 89-13 Program Basis Document)

ER-AA-340-1002

Service Water Heat Exchanger Inspection Guide

ER-AP-331-1002

Boric Acid Corrosion Control (BACC) Program Identification,

Screening, and Evaluation

ER-AP-331-1002

Evaluation of Leakage From Bolted Connection (Including

ASME Section XI Bolted Connection) for 1B Containment

Spray Pump Eductor Flange

05/31/2023

MA-AA-716-001

Quality Material/Components Control and

Identification/Segregation of Non-Conforming Items

MA-AA-716-011

Work Execution and Close out

MA-AA-716-230-

1001

Oil Analysis Interpretation Guideline

OP-AA-108-115

Operability Determinations (CM-1)

OP-AA-108-115-

1000

Byron Operability Determination Guide

Procedures

OP-AA-108-115-

1002

Supplemental Consideration for On-Shift Immediate

Operability Determinations (CM-1)

1811207

0SX04AA - HX Inspection per Generic Letter 89-13

10/23/2018

4850777

0A SX MU PP Gear Oil Cooler HX Cover Plate Peeled

Coating

04/20/2023

4883641

1RH01PB-M Perform Dynamic Baker Testing

03/01/2020

25070

Replace AF PP/Gearbox Lube Oil System Relief Valve

10/26/2021

4945179

(Change) RHR Pump 1B

2/10/2021

5013683

Perform Inspection of Motor (1RH01PB-M)

01/07/2022

26228

(Change) RHR Pump 1B

10/10/2022

244739

0A SX Makeup Pump Heat Exchanger Coating Inspection

Results

09/30/2023

275473

Essential Service Water Makeup Pump Support 0BVSR

Z.7.A.6-1

03/29/2024

275688

0A SX Diesel Driven Pump Flexible Hoses Replacement

03/29/2024

275688

0A SX Diesel Driven Pump Flexible Hoses Replacement

2/06/2023

279058

PM Inspection, In-Service Diag Test, PIT for 1B RH PP

RWST Suction Isolation Valve (EOP Valve)

07/05/2023

5302761

(Change) RHR Pump 1B

07/10/2023

20059

Perform UT Thickness Exams

03/29/2024

20060

Perform 6Y PM Tasks

01/19/2024

26484

LR-Byron Unit 1 BACC Programmatic Walkdown

09/17/2023

5342199

0019386501, PMSR, 1AF049A-D Seat Leakage Test (Drain

Test), W: 1BOSR FX-S1

10/03/2023

5359325

Intentional Abbreviated Maintenance

04/27/2023

5368348

Inactive BA Leak - 1B CS Eductor Inlet Flange

09/18/2023

5419716

EOC 0A SX Makeup Engine Cylinder Inspection

03/29/2024

29686

WR/WO Needed for Inspection on 0SX02PA-K

03/29/2024

29732

WR/WO for Inspection on 0SX04AA

2/23/2024

5460427

Rebuild/Replace Hydramotor

01/31/2024

5502957

EWP FNM Contingency Change Oil in 2AF01PA Pump

2/27/2024

Work Orders

5510474

LR-0A SX Makeup Pump Operability Surveillance

03/29/2024

4711654

RVLIS Changes Following Disconnect/Reconnect

10/22/2023

4734985

U2 RVLIS Leads Lifting Contrary to Configuration Processes

01/23/2024

Corrective Action

Documents

4758129

NRC Identified - TCC EC 640554 Processing Gaps

03/14/2024

6E-2-4030AP119

Schematic Diagram SAT 242-2 TMS Monitoring, Sheet 8

A

71111.18

Drawings

6E-2-4421G

Internal Wiring Diagram SAT 242-2 Back Panel #2, Sheet 3

A

633137

Temporary Configuration Change to Remove from Service

Unit 2 RVLIS Train A Sensor #5 and Sensor #8

634666

TCCP - Lift Lead on SAT 242-2 PD-Guard to Eliminate

Nuisance Alarm

Engineering

Changes

640554

TCCP for U2 Train A Sensor #8 RVLIS Leads Lifted

CC-AA-112

Temporary Configuration Changes

CC-AA-112

Temporary Configuration Changes

LS-AA-104

Exelon 50.59 Review Process

LS-AA-104

Exelon 50.59 Review Process

Procedures

MA-AA-716-004

Conduct of Troubleshooting

Work Orders

5414330

RVLIS Changes Following Disconnect/Reconnect

03/14/2024

4518614

OIO BRW/Byron High Head Flex Pump PM Frequency

Difference

08/24/2022

4679767

High Head Flex Pump Design Deficiency

05/22/2023

4690109

FLEX EMNet Satellite Communication Project Timeline >90

Days

07/12/2023

4697929

0FX02PC High Head Flex Pump Has Stuck Open or Bad

Piston

08/22/2023

4702883

2CC9473B - Apparent High Stem to Stem-Nut COF Update

09/14/2023

4715845

NOS ID: FLEX BLDG shelves did not have weight limits

posted

11/02/2023

4717747

0BOL FX1 Comp Actions

11/15/2023

4717962

0A VC Supply Fan Outside Damper (0VC33Y) Dual Indication

11/15/2023

4719261

0A VC Recirculation Charcoal Absorber Inlet Damper

0VC21Y Dual Indication

11/22/2023

4719579

0FX01KD Warning Light Lit

11/25/2023

4719582

0FX01KB Battery Charger Amps and Voltage cycling

11/25/2023

23460

OP-AA-105-102, Att 1 Not Complete for 1st Qtr. 2019

08/20/2019

23737

FLEX Equipment Moving Machines Degraded

2/13/2023

24879

Flex Pump Operating Strategy

2/21/2023

4736374

NRC ID: CETI - 2VA01SA Cooler Outlet Piping

01/25/2024

4736401

NRC CETI - 2A SX Pump Coupling outside of Tolerances

01/24/2024

4748769

Supply Fan 0VV23C Acrid Odor

2/08/2024

4753481

2MS018JDE-BAT Cells 21 and 27 Electrolyte Leaks

2/27/2024

71111.24

Corrective Action

Documents

4753706

Conditional Release of Switch CID 1718662-1

2/27/2024

4753923

Precharge Pushbutton Not Functional

2/28/2024

4754643

1D PORV Possible Oil Leak

03/01/2024

4755304

0A VC Recirculation Charcoal Absorber Inlet Damper

0VC21Y Dual Indication

03/04/2024

4757447

U2 Pressurizer Backup Group B Htrs 3, 4, & 25 Brkr

03/12/2024

4757527

Pressurizer Heater Breaker Found in the Trip Position

03/12/2024

4757544

Pressurizer Htr Group B & C Lockout Relay Failed to Trip

03/12/2024

4757636

Unit 2 Pressurizer Heater Work Beyond the Scheduled Time

03/13/2024

4757684

Degrading Trip Air Header Pressure on 1B EDG

03/13/2024

4760918

Oil leak on 2RH8716B

03/25/2024

4761540

Active JW Leak on 1A EDG at 9R Inlet Connection

03/27/2024

Drawings

M-42 Sheet 3

Diagram Of Essential Service Water Unit 1 Critical Control

Room Drawing

BG

Engineering

Changes

640749

Modify valve stem of 2CC9473B to Allow Quick Stem Sensor

(QSS) Installation

Plant Barrier

Impairment

Permit 23-089

1DSFSO03 Flood Seal S-672

Miscellaneous

Standing Order

23-027

C High Head Flex Pump Comp Actions

11/10/2023

0BOL FX1

LOCAR Flex Support Equipment

0BOSR FX-14M

Flex Equipment Monthly Surveillance

0BOSR FX-A1

Flex Pump Annual Flow Surveillance

1BOSR 0.5-

2.SX.3-3

Unit One Position Indication Test of 1SX004, 1SX010,

1SX011, 1SX033, 1SX034, and 1SX136

1BOSR 6.3.5-19

Unit One Main Steam System Containment Isolation Valve

Stroke Test

1BOSR 8.1.2-1

Unit One 1A Diesel Generator Operability Surveillance

1BOSR 8.1.2-1

Unit One 1A Diesel Generator Operability Surveillance

1BOSR DG-8A

Unit One 1A DG Turbocharger Spin Down Measurement

1BOSR MS-R1

Unit One Manual Stroke of the S/G PORVS 18 Month

Surveillance

Procedures

2BOSR 0.5-

2.SI.1-1

Unit Two 2SI8821A, 2SI8812A, 2SI8924, 2SI8807B, and

2SI8814 Exercise Test

2BOSR 0.5-

2.SI.2-2.1

Unit Two 2SI8802A, 2SI8806, 2SI8809A, 2SI8835, 2SI8840,

2CV8804A, 2SI8811A, and 2SI8923A Stroke Test and

Position Indication Test

2BOSR 0.5-

2.SI.3-1

Unit Two 2SI8821A, 2SI8812A, 2SI8924, 2SI8807B, and

2SI8814 Position Indication Test

2BOSR 5.2.5-1

ECCS Subsystem Automatic Valve Actuation Test

2BOSR

5.5.8.CC.5-2c

Unit Two Comprehensive Inservice Testing (IST) Surveillance

Requirements for Component Cooling Pump 2CC01PB

2RH-003

Residual Heat Removal Pump 2A Suction Pressure Loop

(RH) Test Package

2RH-0601

Calibration of Residual Heat Removal Pump 2A Suction

Pressure Indicator (RH) Test Report Package

BAP 370-1

Station Lubrication Program

BHP 4200-170

4160 to 480 Volt Unit Substation Transformer Inspection and

Testing

BMP 3100-5

Limitorque Operator SMB/SMC Removal and Installation

BMP 3114-1

Charging and Draining Of Main Steam Power Operated Relief

Valve Actuator-Hydraulic and Nitrogen Components

BOP AP-5

Racking out a 4160V or 6900V Air Circuit Breaker to the

Disconnect Position

BOP AP-6

Racking In a 4160V or 6900V Air Circuit Breaker

BOP AP-7

4160V or 6900V Air Circuit Breaker Test Positioning

BOP DG-11T2

Diesel Generator Operating Log

BOP RH-3

Fill and Vent of the Residual Heat Removal System

BOP RH-4

Draining the RH System

BOP SX-1

Essential Service Water Pump Start-Up

BOP VV-23

Operations Of Technical Support Center Hvac System

(VV-TSC)

BOP VV-28

Start-Up And Shutdown Of The Technical Support Center

Hvac Makeup Filter Unit 0VV19S

ER-AA-302-1006

Motor Operated Valve Maintenance and Testing Guidelines

MA-AA-1000

Conduct of Maintenance Manual

MA-AA-716-003

Tool Pouch / Minor Maintenance

MA-AA-716-004

Conduct of Troubleshooting

71111.24

Procedures

MA-AA-716-011-

1003

Maintenance Walk Downs / Feedback

MA-AA-716-234

FIN Team Process

MA-AA-723-300

Diagnostic Testing of Motor Operated Valves

MA-AA-723-301

Periodic Inspection of Limitourque Model SMB/SB/SBD-000

through 5 Motor Operated Valves

MA-AA-723-401

Receipt Inspection of New or Refurbished Westinghouse

Type DHP 4kV, 6.9kV, and 13.8kV Circuit Breakers

MA-AA-725-102

Preventative Maintenance on Westinghouse Type DHP 4kV,

6.9kV, and 13.8kV Circuit Breakers

MA-AA-725-103

Preventative Maintenance on Westinghouse T4kV, 6.9kV, and

13.8kV Switchgear Cubicles

MA-BY-721-001

Three Phase Thermal Overload Relay Testing for Motor

Operated Valves and Various Other Plant Equipment

MA-BY-724-054

Limitorque MOV Motor Removal and Replacement

MA-BY-773-512

Unit 2 - 480V Unit Substation Feed Breaker Relay Routine

OP-BY-FX-1001

Flex Diesel Generator Operation Guideline

WC-AA-2000

Emergent Issue Response

1BHSR PM-2

Calibration of Time Delay Relays

26549

MOV PM, Actuator Inspection, Diagnostic Testing

03/20/2024

4945433

LR-2VA01SA - HX Inspection Per Generic Letter 89-13

01/25/2024

4947965

Bus 241 Outage MCC 231X1-H4 Breaker Tripped out of

Tolerance

2/27/2024

5002175

Ops - 3 Year Performance Full Flow Test of Flex Pump

11/29/2023

217787

4KV Switchgear Cubicle Inspection (Bus 244 CUB 10) -

2AP08E-K

03/13/2024

217788

4KV Breaker Swap (Bus 244 CUB 10) - 2AP08E-K

03/13/2024

25499

Clean, Inspect, and Tighten All Connections on Transformer

2RY01EB

03/13/2024

25864

Clean, Inspect, and Tighten All Connections on Transformer

2RY01EC

03/13/2024

252454

4KV Relay Routine Calibration (244 FD to PZR Heater B & C)

03/13/2024

271130

PM Inspection, In-Service Diag Test, PIT

03/26/2024

281470

Replace Motor on 0VV23C

2/09/2024

283878

U1 (SX-3-2) VT XI (1B Pump Train Work)

03/20/2024

Work Orders

284271

1SX033 Replace Cub Fu Blk(1)(131X1-A4) U1 Pump

Discharge Crosstie

03/20/2024

290075

(Change/Sample) [Oil] Safety Injection Pump 2A

2/28/2024

290745

Retorque 2SI8814 in 1 Year

2/27/2024

296469

EXTST for

2SI8802A,8806,8809A,8835,8840,8804A,8811A,8923A

03/26/2024

299138

4kV Switchgear Cubicle Inspection (But 242 Cub 13) -

2AP06E-N

03/22/2024

299424

2CC9473 Discharge Crosstie Thermal Overload Surveillance

(MCC 232X1-D5)

03/21/2024

5302762

EXTST for 2SI8811A

03/26/2024

5303074

ECCS Sub System Automatic Valve Actuation Test

03/26/2024

5304096

4kV Breaker Swap (But 242 Cub 13) - 2AP06E-N

03/22/2024

5304097

CC Surge Tank Low Level Switch;

03/22/2024

5311498

2B CC Pump Motor, Outboard Bearing Oil Drain Plug

Rounded Off

03/22/2024

5312094

1AP06EB Relay #SX1BX for 1SX01PB

03/20/2024

5312096

Perform Static Baker Test MA-AA-723-330

03/20/2024

21154

U-1 Manual Stroke of the S/G PORVS-1D

2/29/2024

5330915

(Sample/Change) Component Cooling Pump 2B

03/22/2024

5351732

1SX01PB-M Perform Dynamic Baker Testing

03/20/2024

5359119

Position Indication Test of 1SX033

03/20/2024

5364407

(Check) Essential Service Water Strainer 1B

03/20/2024

5364412

(Sample) Essential Service Water Pump 1B

03/20/2024

5379461

Need WR/WO to Clean 2A RH Pump Bowl during Next Work

Window

03/26/2024

5380211

Measure Turbocharger Spin Down Time 1BOSR DG-8A

03/28/2024

5384649

2SI8807B Thermal OL Surveillance (MCC 232X1-G3)

2/27/2024

5394121

0FX02PC High Head Flex Pump Has Stuck Open or Bad

Piston

2/28/2023

5401563

2CC9473B - Apparent High Stem to Stem-Nut COF Update

03/22/2024

5401563-02

Machine Threads off Valve Stem per EC 640749 to Allow

Sensor Installation

5401563-16

Cut Stem in Field to Munt QSS Sensor

5402721

LR-(Sample) Essential Service Water Pump 1B

03/20/2024

5416167

EOC Work Required for DG Vent Fan failure

03/28/2024

25042

LR-Control Room Ventilation Train 0A Surveillance

03/04/2024

26049

Stroke Time Test 1AF005A-D

03/04/2024

26050

Stroke Time Test 2AF005A-D

03/04/2024

5443249

Samp/Repl/Flush Hyd Fluid In Actuator & Hand Pump

2/29/2024

5456687

2SI01PA Group A IST Requirements for Safety Injection

Pump

2/28/2024

5475997

(NEIL)-LR-1A Diesel Generator Operability Surveillance

2/28/2024

5476077

(NEIL)- 2CC01PB Comp IST RQMTS for Residual CC Pump

03/22/2024

5512994

LR-(Sample) 1A Diesel Generator

03/28/2024

BHP 4200-52

Polarization Index and Delta Resistance Tests

BHP-EQ-93B

Replacement of Single and Double Pole Fuse Block

Assemblies

BOP SX-300-1

Sampling the Essential Service Water Pumps Lubricating Oil

Reservoirs (1SX01PB)

MA-AA-723-301

Periodic Inspection of Limitorque Model SMB/SB/SBD-000

Through 5 Motor Operated Valves

MA-AA-723-330

Electrical Testing of AC Motors Using Baker Instrument

Advanced Winding Analyzer

MA-BY-722-003

Annual Inspection and Testing of 4kV and 6.9kV Motors

200578

2PM10J SEVERAL LED BUTTONS ON 2RM23 PANEL

FAILING

2/05/18

242491

2ES013C NOT INDICATING FULL CLOSED ON 2PM03J

04/22/2019

245106

2MS031D Low Point Drain Valve Not Cycling Correctly

05/01/2019

4357146

Containment Pressure Channel Deviation

07/16/2020

4374425

2CB118A Failed to Auto Open

10/05/2020

4386121

Electrically Determine Why 2CB118A Fails to Stroke Open

11/23/2020

4386606

PMT Failed WO 4946434 2HD059A indicates Dual When

Open

11/26/2020

4396737

2A FW Pump Flow Is Showing 0.5 MBH When There Is no

Flow

01/19/2021

20709

Unexpected Alarm Bus 214 Inverter Trouble

05/01/2021

4431096

SAT 242-2 Trouble Alarm in MCR

06/23/2021

4446965

LPMS TROUBLE

09/16/2021

4454399

2PS230A Position Indication Not Working

10/20/2021

4456900

Button and Backlamp Bulb on 2RIU-PR030

10/28/2021

71152A

Corrective Action

Documents

4461721

Unit-2 FSIC Trouble

11/18/2021

4470046

2S-34 Trouble Light Not Lit

01/05/2022

4482056

2C RCP Stator Winding Temp Failed

03/02/2022

4491651

MS Line Low Pt. Drain, 2MS031D, Not Cycling Properly

04/08/2022

4493780

2CB118A Failed to Open

04/18/2022

4497311

Sat 242-2 Unexpected Alarms

05/03/2022

4498553

2ES013C Not Indicating Closed

05/09/2022

4498812

2FW034C Not Showing Closed on FWI Monitor Lights

05/10/2022

4498972

U-2 LPMS Channel 11 Dead

05/11/2022

4499303

2FW046A Won't Swap Back to Manual on 2PM04J

05/12/2022

4499388

2BOSR FW-Q1 Failed Acceptance Criteria

05/12/2022

4499469

2ES017B Open Light Not Working

05/12/2022

4500072

2ES017C Shows Dual on MCB

05/16/2022

4500221

2D RCP #1 Seal Inj Line LPMS Alarm

05/17/2022

4503765

2ES079 Open Light Did Not Light

06/04/2022

4506033

Zone 2D-75 Spurious Fire Alarm

06/17/2022

4509598

Low HP GS Pressure

07/06/2022

4510089

Pressurizer Liquid Temp Indicating Lower Than Expected

07/09/2022

4511307

Unit 2 RVLIS Train B, Sensor #3 Error Codes

07/06/2022

4514245

Unit 2: B Train RVLIS Sensor #3 Alarm

08/01/2022

4515989

U-2 Loose Parts Monitoring System Alarm, 2-13-E9

08/09/2022

4516609

Unexpected Annun. 2-18-D13, H2 Stator Clg Panel Trouble

08/12/2022

4517694

2HD059A Indicates Dual When Open

08/19/2022

4519559

2C Feedwater Pump Low Oil Alarm

08/30/2022

20244

ES Level Controller output Is Suspect

09/01/2022

22678

2FW046A Controller (2FK-FW245) Degraded and Needs

Replaced

09/15/2022

26264

Unexpected H2/Stator Cooling Panel Trouble Alarm

(2-18-D13)

10/02/2022

27378

2D MSR First Stage Drain Tank Level Oscillation

10/06/2022

4535311

LPMS TRM Elimination Project

11/07/2022

4538144

2D 1st Stage RDT Level High/Low Alarm (2-18-B5)

11/19/2022

4543602

2D First Stage Reheat Drain Tank High/Low

2/19/2022

4551270

2A MSIV Accumulator Pressure Low

01/30/2023

4561565

Unexpected 'MAIN XFMR 2E TROUBLE' Alarm in the MCR

03/13/2023

4699955

Procedure Enhancements for Causal Evaluation

09/01/2023

4700973

NRC ID: Procedure Enhancement for BMP 3100-23

09/06/2023

4713783

2ES008 Limit Switch

10/30/2023

4713788

2ES015B Showing Dual in MCR

10/30/2023

4713789

2ES032B open

10/30/2023

20070

Containment Sum Isolation Relief Valves Trend IR

11/28/2023

4731466

Misc. Byron IST and App J Actions

01/16/2024

4754631

Rejection of CA 4712019-11

03/01/2024

4754631

Rejection of CA 4712019-11

03/01/2024

Miscellaneous

None

Control Room Deficiencies Report

01/29/2024

BMP 3100-23

IST Crosby Safety/Relief Valve Bench Testing

HU-AA-104-101

Procedure Use and Adherence

OP-AA-108-105

Equipment Deficiency Identification and Documentation

OP-AA-108-105-

1001

MCR and RWCR Equipment Deficiency Management and

Performance Indicator Screening

PI-AA-125

Corrective Action Program (CAP) Procedure

Procedures

PI-AA-125-1006

Investigation Techniques Manual

7