IR 05000454/2022002

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000454/2022002 and 05000455/2022002
ML22217A063
Person / Time
Site: Byron  
Issue date: 08/08/2022
From: Hironori Peterson
Region 3 Branch 3
To: Rhoades D
Constellation Energy Generation, Constellation Nuclear
References
IR 2022002
Download: ML22217A063 (33)


Text

SUBJECT:

BYRON STATION - INTEGRATED INSPECTION REPORT 05000454/2022002 AND 05000455/2022002

Dear Mr. Rhoades:

On June 30, 2022, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Byron Station. On July 14, 2022, the NRC inspectors discussed the results of this inspection with Mr. H. Welt, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.

One finding of very low safety significance (Green) is documented in this report. This finding involved a violation of NRC requirements. We are treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violation or the significance or severity of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; the Director, Office of Enforcement; and the NRC Resident Inspector at Byron Station.

August 8, 2022 This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Hironori Peterson, Chief Branch 3 Division of Reactor Projects Docket Nos. 05000454 and 05000455 License Nos. NPF-37 and NPF-66

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000454 and 05000455

License Numbers:

NPF-37 and NPF-66

Report Numbers:

05000454/2022002 and 05000455/2022002

Enterprise Identifier:

I-2022-002-0045

Licensee:

Constellation Energy Generation, LLC

Facility:

Byron Station

Location:

Byron, IL

Inspection Dates:

April 1, 2022 to June 30, 2022

Inspectors:

D. Betancourt-Roldan, Senior Resident Inspector

J. Bozga, Senior Reactor Inspector

J. Cassidy, Senior Health Physicist

M. Gangewere, Reactor Inspector

D. Kimble, Senior Resident Inspector, Braidwood Station

E. Sanchez Santiago, Project Engineer

A. Shaikh, Senior Reactor Inspector

M. Siddiqui, Reactor Inspector

P. Smagacz, Resident Inspector, Braidwood Station

C. Thompson, Illinois Emergency Management Agency

J. Weigandt, Acting Senior Resident Inspector

Approved By:

Hironori Peterson, Chief

Branch 3

Division of Reactor Projects

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Byron Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Failure to Have Appropriate Work Instructions Leads to Inoperability of the Unit 1 Diesel Driven Auxiliary Feedwater Pump Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000454/2022002-01 Open/Closed None (NPP)71111.15 A finding of very low safety significance (Green) and associated non-cited violation (NCV) of Title 10 CFR Part 50, Appendix B, Criterion V, "Instructions, Procedures, Drawings," was self-revealed for the licensee's failure to have work instructions appropriate for the circumstances when replacing the 1B auxiliary feedwater (AF) pump jacket water braided hoses, an activity affecting quality. Specifically, Work Order (WO) 1888896, "Diesel Driven Auxiliary Feedwater Pump Inspection per BMP 3203-1," and WO 4633348. Replace Hoses that were not Replaced During B1R21 During B1R22, did not provide appropriate instructions on the number of flex hoses that needed to be fabricated and replaced. This ultimately led to a hose in the 1B AF pump not being replaced as specified in the WOs and subsequently failing due to age related degradation, which caused the 1B AF pump to be declared inoperable until the hose was replaced.

Additional Tracking Items

None.

PLANT STATUS

Unit 1 began the inspection period operating at full power. Apart from minor reductions in power to support scheduled testing activities or small load changes requested by the transmission dispatcher, the unit remained at or near full power for the entire inspection period.

Unit 2 began the inspection period operating at approximately 90 percent power, in coast down for the planned refueling outage. On April 18, 2022, the unit began a refueling outage. The unit went critical again on May 11, 2022, and returned to full power on May 15, 2022. The unit has remained at or near full power.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Seasonal Extreme Weather Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated summer readiness of offsite and alternate alternating current (AC) power systems on June 10, 2022.

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1)2B Residual Heat Removal (RH) Train aligned for shutdown cooling on April 22, 2022.

(2) Spent Fuel Pool cooling while the core was offloaded on April 27, 2022
(3) Component Cooling Water (CC) System following several alignment changes on June 6, 2022

Complete Walkdown Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated system configurations during a complete walkdown of the Unit 2 Containment Spray (CS) System on April 26, 2022.

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (6 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Fire Zone (FZ) 12.1-0; Fuel Handling Building, 401' -0" Elevation and 426' -0" Elevation on April 27, 2022
(2) FZ 1.3-2; Unit 2 Containment 426' -0" containment upper area on April 28, 2022
(3) Inner Missile Barrier Containment on April 28, 2022
(4) Turbine Deck on May 2, 2022
(5) FZs 11/5A-1, 11.5B-1, and 11.6-1; Unit 1 Auxiliary Building on June 10, 2022
(6) Auxiliary Building 426' Elevation, Division 11 and 12 ESF Switchgear rooms on June 28, 2022

71111.07T - Heat Exchanger/Sink Performance Heat Exchanger (Service Water Cooled) (IP Section 03.02)

The inspectors evaluated heat exchanger performance on the following:

(1) Motor Driven Auxiliary Feedwater Pump Oil Cooler (2AF01AA)
(2) CC Water Heat Exchanger (1CC01A)

Ultimate Heat Sink (IP Section 03.04) (1 Sample)

The inspectors evaluated the ultimate heat sink performance on the following:

(1) The ultimate heat sink, specifically Sections 03.04.b and 03.04.d were completed.

71111.08P - Inservice Inspection Activities (PWR) PWR Inservice Inspection Activities Sample (IP Section 03.01)

(1) The inspectors reviewed the licensee degradation monitoring and repair/replacement activities of the reactor coolant system boundary, steam generator tubes, reactor vessel internals, risk significant piping system boundaries, and containment boundary. Specifically, the inspectors reviewed the following activities from April 18 to May 3, 2022:

03.01.a - Nondestructive Examination and Welding Activities.

Remote inservice ultrasonic examination of reactor vessel nozzle to safe end, nozzle to pipe, and safe end to pipe welds

Liquid penetrant examination of residual heat removal system component 2RH-02-AA/RHES-01 (support skirt weld)

Ultrasonic examination (UT-1) of feedwater (FW) system, component ID 2FW03DA-16/C23, pipe-elbow weld Ultrasonic examination (UT-1) of FW system, component ID 2FW03DA-16/C24, elbow-pipe weld

Ultrasonic examination (UT-1) of FW system, component ID 2FW03DA-16/C25, pipe-elbow weld

Ultrasonic examination (UT-1) of FW system, component ID 2FW03DD-16/C17, elbow-pipe weld

Ultrasonic examination (UT-1) of FW system, component ID 2FW03DD-16/C18, pipe-elbow weld

AR 04376383; Rejectable NDE Indication on 2FW009C Final Plug Weld

AR 04376507; Rejectable NDE Indication on 2FW009C FW-5

Pressure boundary excavation and field weld (four locations) of 2VA03SA (WO 1950332)03.01.b - Pressurized-Water Reactor Vessel Upper Head Penetration Examination Activities.

ASME Code Case N-729 ultrasonic examination of all head penetrations including leak path assessment

ASME Code Case N-729 bare metal visual examination of upper head surface

Reactor vessel upper head penetration # 75 flaw acceptance and operability review

Bare metal visual (BMV) examination of the RPV upper head penetrations 03.01.c - Pressurized-Water Reactor Boric Acid Corrosion Control Activities.

Boric Acid Leakage Evaluation on Component ID 2CV8401B (Issue Report 4377597)

Boric Acid Leakage Evaluation on Component ID 2FE-0136 (Issue Report 4463896)

Boric Acid Leakage Evaluation on Component ID 2FC04F (Issue Report 4328082)

Boric Acid Leakage Evaluation on Component ID 2FC02F (Issue Report 4391135)03.01.d - Pressurized-Water Reactor Steam Generator Tube Examination Activities.

Steam generators A, B, C, and D, eddy current (ET) examination

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (2 Samples)

(1) The inspectors observed and evaluated licensed operator performance in the Control Room during Unit 2 downpower in preparation for refueling outage on April 17, 2022, and Unit 2 reactor vessel drain down for head set and loop fill on May 3, 2022.
(2) The inspectors observed and evaluated licensed operator performance in the Control Room during Unit 2 reactor startup and power ascension on May 11, 2022.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated the performance of licensed plant operators in the simulator on June 14, 2022.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (1 Sample)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) Unit 1 'A' CS system on April 8, 2022

Quality Control (IP Section 03.02) (1 Sample)

The inspectors evaluated the effectiveness of maintenance and quality control activities to ensure the following SSC remains capable of performing its intended function:

(1) Unit 1 'B' CS system, as documented in WOs 138757, 5110561, 5110562, and 1807588 on January 20, 2022

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Technical Specification (TS) 3.0.4.b Evaluation; mode change with TS equipment out of service.
(2) Evaluation of the emergent work associated with 1CV131 Letdown Control Valve malfunction, as documented in Issue Report (IR) 4494392 on April 20, 2022.
(3) Evaluation of the risk management associated with shutdown cooling and Reactor Coolant System (RCS) drain down per 2BGP 100-6, Refueling Outage, Revision 56, on April 20, 2022.
(4) Risk management during the week of May 2, 2022.
(5) D6 Control Cabinet Power Supply trouble for 1PA34J power supply Train B failure, as documented in IR 4501672 on May 25, 2022.

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (6 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) Evaluation of the operability of the 1A Emergency Diesel Generator (EDG) following identification of a low governor oil, as documented in IR 4490346 on April 5, 2022.
(2) Evaluation of the operability of the 1B AF pump following identification of a hose leak, as documented in IR 4492979 on April 14, 2022.
(3) Evaluation of the operability of the Unit 2 N-32 Source Range Nuclear Instrument, following observation of anomalous indications, as documented in IRs 4495778 and

===4494520, during the week ending May 7, 2022.

(4) Evaluation of the operability of the 2B EDG following identification of degraded equipment, as documented in IRs 4500831, 4500836, and 4500843, on May 20, 2022.
(5) Foreign Material Exclusion evaluation of material lost in SG, as documented in IR 4496744.
(6) Evaluation of the operability for Penetration 75 indication, as documented in IR 4495098.

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02)

=

The inspectors evaluated the following temporary or permanent modifications:

(1) Engineering Change (EC): 629149; 480V Substation Breaker Setting Change
(2) EC 627889: 25A-3" Pipe Replacement

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (7 Samples)

The inspectors evaluated the following post-maintenance testing activities to verify system operability and/or functionality:

(1) Functional and operational testing of the 2A Chemical and Volume Control pump following rotating element replacement, as documented in WO 4749380, on May 2, 2022.
(2) Functional and operational testing of the 2PS9356B following repairs, as documented in WO 5089242 on May 10, 2022.
(3) Functional and operational testing of the 2B AF pump following maintenance, as documented in multiple WOs on May 13, 2022.
(4) Functional and operational testing of the 1D Reactor Coolant Pump Seal following replacement, as documented in WO 5256214 on May 10, 2022.
(5) Functional and operational testing of post-refueling physics testing, as documented in WO 5091520 on May 16, 2022.
(6) Functional and operational testing of the Pressure Relief Tank Rupture Discs following replacement, as documented in WOs 5091495 and 5091498, on June 3, 2022.
(7) Functional and operational testing of the 2AF178 2B AF Suction Motor Operated Valve following troubleshooting and maintenance, as documented in WO 5089590 on June 3, 2022.

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated refueling outage B2R23 activities from April 18 to May 10, 2022.

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance testing activities to verify system operability and/or functionality:

Surveillance Tests (other) (IP Section 03.01) (4 Samples)

(1) Main Steam Safety Valve Trevi-Testing, as documented in WOs 5085883, 4723440,

===4724302, 4724303, 4724304, 4724305, 4724306, and 5206756 on April 12 and April 21, 2022.

(2)2B AF testing, as documented in WO 5085881 on April 13, 2021.

(3)1A EDG monthly testing, as documented in W 5248909 on May 6, 2022.

(4)2BOSR 5.5.8CV6-3; Missed Surveillance and Post-Maintenance Deferral, as documented in IR 4497553 on May 5, 2022.

Inservice Testing (IP Section 03.01)===

(1)2B EDG Endurance Run and Hot Restart Test, as documented in WO 4848734 on May 19, 2022.

Containment Isolation Valve Testing (IP Section 03.01) (1 Sample)

(1)2BOSR 6.1.1-21; Leak Rate Test of 2WO006A, as documented in WO 5091371-01 on April 28,

RADIATION SAFETY

71124.01 - Radiological Hazard Assessment and Exposure Controls

Radiological Hazard Assessment (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated how the licensee identifies the magnitude and extent of radiation levels and the concentrations and quantities of radioactive materials and how the licensee assesses radiological hazards.

Instructions to Workers (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated how the licensee instructs workers on plant-related radiological hazards and the radiation protection requirements intended to protect workers from those hazards.

Contamination and Radioactive Material Control (IP Section 03.03) (2 Samples)

The inspectors observed/evaluated the following licensee processes for monitoring and controlling contamination and radioactive material:

(1) Licensee surveys of potentially contaminated material leaving the Radiologically Controlled Area and workers exiting the Radiologically Controlled Area at 401' Main Control Point during a refueling outage.
(2) Licensee surveys of potentially contaminated material leaving the Radiologically Controlled Area and workers exiting the Radiologically Controlled Area at Unit 2 Contractor Access Facility during a refueling outage.

Radiological Hazards Control and Work Coverage (IP Section 03.04) (4 Samples)

The inspectors evaluated the licensee's control of radiological hazards for the following radiological work:

(1) Manual Movement of Reactor Thimble from the Unit 2 Seal Table
(2) Steam Generator Eddy Current
(3) Reactor Vessel Head Penetration 75 (Preparation and Mock-up)
(4) Unit 2 Steam Generator Manway/Diaphragm Removal High Radiation Area and Very High Radiation Area Controls (IP Section 03.05) (3 Samples)

The inspectors evaluated licensee controls of the following High Radiation Areas and Very High Radiation Areas:

(1) Unit 2 Incore Sump
(2) Unit 2 Steam Generator Manway Access
(3) Unit 2 377' Containment Inside Missile Barrier Radiation Worker Performance and Radiation Protection Technician Proficiency (IP Section 03.06) (1 Sample)
(1) The inspectors evaluated radiation worker and radiation protection technician performance as it pertains to radiation protection requirements.

71124.03 - In-Plant Airborne Radioactivity Control and Mitigation

Temporary Ventilation Systems (IP Section 03.02) (2 Samples)

The inspectors evaluated the configuration of the following temporary ventilation systems:

(1) Temporary High Efficiency Particulate Air (HEPA) Ventilation under the Unit 2 Reactor Head
(2) Temporary High Efficiency Particulate Air (HEPA) Ventilation used for Steam Generator work

Use of Respiratory Protection Devices (IP Section 03.03) (1 Sample)

(1) The inspectors evaluated the licensees use of respiratory protection devices.

71124.07 - Radiological Environmental Monitoring Program

Environmental Monitoring Equipment and Sampling (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated environmental monitoring equipment and observed collection of environmental samples.

Radiological Environmental Monitoring Program (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the implementation of the licensees radiological environmental monitoring program.

GPI Implementation (IP Section 03.03) (1 Sample)

(1) The inspectors evaluated the licensees implementation of the Groundwater Protection Initiative program to identify incomplete or discontinued program elements.

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

MS05: Safety System Functional Failures (SSFFs) Sample (IP Section 02.04)===

(1) Unit 1 (April 1, 2021 - March 31, 2022)
(2) Unit 2 (April 1, 2021 - March 31, 2022)

MS06: Emergency AC Power Systems (IP Section 02.05) (2 Samples)

(1) Unit 1 (April 1, 2021 - March 31, 2022)
(2) Unit 2 (April 1, 2021 - March 31, 2022)

MS07: High Pressure Injection Systems (IP Section 02.06) (2 Samples)

(1) Unit 1 (April 1, 2021 - March 31, 2022)
(2) Unit 2 (April 1, 2021 - March 31, 2022)

BI01: Reactor Coolant System (RCS) Specific Activity Sample (IP Section 02.10) (2 Samples)

(1) Unit 1 October 1, 2021 through May 31, 2022
(2) Unit 2 October 1, 2021 through May 31, 2022 OR01: Occupational Exposure Control Effectiveness Sample (IP Section 02.15) (1 Sample)
(1) October 1, 2021 through May 31, 2022 PR01: Radiological Effluent Technical Specifications/Offsite Dose Calculation Manual Radiological Effluent Occurrences (RETS/ODCM) Radiological Effluent Occurrences Sample (IP Section 02.16) (1 Sample)
(1) October 1, 2021 through May 31, 2022

71152A - Annual Follow-up Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) The inspectors performed a detailed review of IR 4496332; B2R23 CRDM Thermal Sleeve Metrology Results.
(2) The inspectors reviewed post-maintenance testing (PMT) IR 4474490, Incomplete PMT for MCB Hand Switch Replacement. As a result, the inspectors reviewed additional PMT work orders and IRs.
(3) Inconsistent Use of Test Instrument Selection Criteria when Testing CS Additive Tank Vacuum Relief.

71152S - Semiannual Trend Problem Identification and Resolution Semiannual Trend Review (Section 03.02)

(1) The inspectors reviewed the licensees corrective action program for potential adverse trends fuses and fuse holders that might be indicative of a more significant safety issue.

INSPECTION RESULTS

Failure to Have Appropriate Work Instructions Leads to Inoperability of the Unit 1 Diesel Driven Auxiliary Feedwater Pump Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000454/2022002-01 Open/Closed None (NPP)71111.15 A finding of very low safety significance (Green) and associated non-cited violation (NCV) of Title 10 CFR Part 50, Appendix B, Criterion V, "Instructions, Procedures, Drawings," was self-revealed for the licensee's failure to have work instructions appropriate for the circumstances when replacing the 1B auxiliary feedwater (AF) pump jacket water braided hoses, an activity affecting quality. Specifically, Work Order (WO) 1888896, "Diesel Driven Auxiliary Feedwater Pump Inspection per BMP 3203-1," and WO 4633348. Replace Hoses that were not Replaced During B1R21 During B1R22, did not provide appropriate instructions on the number of flex hoses that needed to be fabricated and replaced. This ultimately led to a hose in the 1B AF pump not being replaced as specified in the WOs and subsequently failing due to age related degradation, which caused the 1B AF pump to be declared inoperable until the hose was replaced.

Description:

On April 14, 2022, the 1B AF diesel driven pump was started to perform its scheduled monthly surveillance. Approximately 21 minutes into the run, local operators reported a jacket water leak and proceeded to secure the pump. Following evaluation of the leak by the operators and maintenance, the station determined that the leak was not able to be temporarily repaired and that it affected the operability of the pump. The licensee proceeded to enter Condition A of Technical Specifications (TS) 3.7.5, Auxiliary Feedwater System, which is a 72-hr action statement. The leaking hose was replaced, and the pump was returned to service after a successful post-maintenance run during night shift on April 14, 2022.

The affected hose was sent to Power Labs for failure analysis, where it was determined that the cause of the failure was age related degradation. The hose manufacturing stamp indicated it was manufactured in 2005, which meant the hose was 17 years old at the point when the failure occurred. In accordance with the stations preventive maintenance documents (PMID 103868-36 and 112168-36), the flexible hoses need to be replaced at a 12-year frequency. To meet the preventive maintenance the hoses for the 1B AF pump were scheduled to be replaced in 2017 and 2018 under WOs 1888896 and 4633348 (2018). The 2B AF pump hoses were replaced in 2018 under WO 1894388, Replace Flexible Hoses.

However, the WOs associated with the 1B AF pump did not provide appropriate instructions on the number of flex hoses that needed to be fabricated and replaced. This ultimately led to a hose in the 1B AF pump not being replaced, as was the purpose of the WOs, and subsequently failing due to age related degradation on April 14, 2022.

Corrective Actions: The affected jacket water braided hose was replaced and the 1B AF pump was returned to operable status on April 14, 2022. The licensee also plans to replace all flexible hoses on the 1B and 2B AF pumps as well as 0A and 0B essential service water diesel driven pumps with appropriate documentation to verify each flexible hose has been replaced with a new part.

Corrective Action References: AR 4492979

Performance Assessment:

Performance Deficiency: The inspectors determined that the licensee's failure to have work instructions appropriate for the circumstances to replace the 1B AF jacket water braided hoses, an activity affecting quality, was contrary to Title 10 CFR Part 50, Appendix B, Criterion V, "Instructions, Procedures, Drawings," and was a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor because if left uncorrected, it would have the potential to lead to a more significant safety concern. Specifically, not having appropriate work instructions led to a flexible hose not being replaced in accordance with the purpose of the WOs. That hose developed a leak due to age related degradation that affected the reliability and availability of the equipment.

Significance: The inspectors assessed the significance of the finding using IMC 0609 Appendix A, The Significance Determination Process (SDP) for Findings At-Power. The inspectors screened this finding against the Mitigating Systems screening questions in Exhibit 2 and answered "NO" to all six screening questions. Therefore, the finding screened to very low safety significance (Green).

Cross-Cutting Aspect: Not Present Performance. No cross-cutting aspect was assigned to this finding because the inspectors determined the finding did not reflect present licensee performance.

Enforcement:

Violation: Title 10 CFR 50 Appendix B, Part V, "Instructions, Procedures, Drawings," states, in part, that activities affecting quality shall be prescribed by documented instructions, procedures, or drawings, of a type appropriate to the circumstances and shall be accomplished in accordance with these instructions, procedures, or drawings.

Contrary to the above, on March 23, 2017, and September 25, 2018, technicians replaced flexible hoses on the 1B AF pump using WOs 1888896 and 4633348, an activity affecting quality, without appropriate work instructions for the work. Specifically, the WOs did not specify how many hoses needed to be replaced or how to install them. This ultimately led to one of the flexible hoses developing a leak due to age related degradation and affected the availability of the 1B AF pump, a safety related component.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Observation: Post-Maintenance Testing Inconsistencies with 1SX01PB and 2AF017B 71152A Based on post-maintenance testing (PMT) issue report (IR) 4474490, from January 28th, 2022, inspectors reviewed PMT WOs and IRs to assess the corrective action program (CAP) performance attributes of completeness, accuracy, evaluation, and corrective actions.

On March 22nd, 2022, following a work window, PMT, and comprehensive testing of 1SX01PB, Unit 1 B Essential Service Water pump, NRC inspectors performed a PMT inspection of 1SX01PB. The inspectors identified that the pump was running with a lower-than-normal oil level. The oil sump level was at the bottom of the sight glass.

Inspectors reviewed the associated WOs and noted that the associated PMT checks of oil level were already recorded as having been completed satisfactory. Operations staff was informed of the low oil condition and that the PMT oil level checks had been recorded as finished. Two gallons of oil were subsequently added to the running pump, and the issue was documented in the CAP as IR 4486869, NRC ID: 1B SX Pp oil low in sight glass after work window.

During another PMT review, inspectors noted inconsistencies with WO 5089590 2AF017B, Unit 2 B Auxiliary Feed Essential Service Water isolation motor operated valve. Inspectors found that task 4 (sway strut support removal and reinstallation) was completed, but its required engineering PMT, task 17, had not been completed. Inspectors also found that task 15, operations PMT, was closed to WO 04974921-01, which was completed in the previous year, May 11, 2021. Task 15 was the required PMT for completed work tasks 14, 19, and 20 (diagnostic testing, contactor replacement, and control relay and breaker handle replacement). The inspectors brought their concern to operations and maintenance management. The site documented the inspectors concerns in the CAP as IR 4501960, NRC Identified-Incorrect 2AF017B PMT closure and 4508013, NRC ID - PMT process not followed. Following discussions with different levels of management at the site, the inspectors were provided information that demonstrated that although a formal PMT was not performed, different tasks in the WO included portions that met the intent of the PMT.

Breakdowns in following PMT process procedures can result in incomplete or inaccurate PMT. Without proper PMT, a latent problem could prevent systems, structures, or components from operating as expected when needed to perform their safety function.

Consequently, PMT is especially important for the Auxiliary Feedwater system, which is not normally operated outside of testing. Inspectors reviewed the licensees procedure MA-AA-716-012, Post-Maintenance Testing (Rev. 27), in part, and saw the following steps:

4.2.4. stated, in part Post-Maintenance Testing shall be performed following any corrective and some preventive maintenance activities on plant equipment that may have impacted the equipments ability to perform its intended function. These activities may include:

-

1. Maintenance that affects the integrity or operation of a fluid or gas system or

components within those systems...

-

3. Maintenance that affects / disturbs electrical connections, control circuitry or

electronic components."

4.2.7. stated If it becomes necessary to deliberately deviate from established PMT, then the group responsible for performing the PMT shall OBTAIN and DOCUMENT justification for the deviation., and

4.3.3. stated If the scope of the work expands beyond the original maintenance task, then that task / Work Package shall be revised and reviewed for possible changes to Post-Maintenance Testing.

The inspector considered that the failure to follow MA-AA-716-012 was a performance deficiency and violation of 10 CFR 50, Appendix B, Criterion V, Instructions, Procedures, Drawings. The performance deficiency was determined to be of minor significance.

Although a formal PMT was not performed, other actions in the same work order accomplished the intent of the PMT prior to returning the equipment to service.

The review of the January PMT-related IR and subsequent related issues suggest there are opportunities to better use the CAP for evaluation of IRs and for more timely corrective actions to optimize development, execution, and oversight of subsequent PMT. There were no findings as a result of this review, and the observation was shared with the site, who is addressing this item as part of their planned corrective actions.

No findings or violations of NRC requirements of more than minor safety significance were identified in the course of this review.

Observation: Test Instrument Selection Criteria Not Being Used for Testing Containment Spray Additive Tank Vacuum Relief Valves 71152A Inspectors evaluated the CAP to assess completeness, timeliness, and evaluation of an identified problem.

Based on some past challenges related to measurement and test equipment (M&TE), a maintenance effectiveness inspection was performed for Unit 1 Containment Spray (CS)vacuum breaker relief valve tests (WO 5110561 & 5110562). The testing is required by ASME OM code. In the event of a CS actuation, the safety related vacuum breaker relief valves open as vents for the spray additive tank to allow sodium hydroxide (NaOH) to be adducted from the tank into the discharge of the CS pumps. The safety function provides for a design flow of 55 gallons per minute of NaOH into containment to obtain pH = 7 in the containment sump. Accordingly, if the vacuum breaker relief valves dont properly open, design flow may not be obtained.

In April, inspectors noted issues of concern related to the documentation of the test instrument used, force gauge serial no. 2906994. The work orders were performed in 2022, but the recorded calibration due date was February 22, 2021. Additionally, the force gauge that was used to check ounces of force to move the valve stem open was calibrated for a range above the test setpoint. Specifically, the recorded setpoints measured were between 1.32 oz to 3.32 oz (.0825 lbf to

.277 lbf), while the calibrations recorded test range of 16 oz to

144 oz (1 lbf to 9 lbf). According to the work package instructions, Engineering Change Request (ECR) 163345, and ECR 167093, the acceptance criteria for unseating force is less than or equal to 7 oz (.4375 lbf).

On April 11th, 2022, inspectors discussed their concerns with Byron staff and questioned whether the calibration due date and instrument used were correct. The concern would be that an out of calibration instrument or incorrect instrument may provide invalid test results.

Staff clarified that the listed calibration due date was mistakenly entered as the calibration date and noted that calibration was not overdue. To address the concern of the test force setpoint being below the calibration range, the licensee entered the condition into the CAP as IR 4500840, NRC identified issue with vacuum breaker testing, on May 19th, 2022, and conducted a post-test calibration check of the force gauge at 7 oz. The satisfactory post-test calibration check, certification no. 11394822, was provided to the NRC and demonstrated that test acceptance criteria was met.

Inspectors further checked if the work package included adequate instruction for proper test equipment selection. The instructions used by technicians appeared as a single step that stated, in part:

7.2.1. Using a calibrated force gauge, selected for oz., APPLY force linearly and directly up the stem of the valve However, the work order also included BMP 3100-9 IST Bench Testing Safety/Relief Valves, Rev. 23, a Reference Use procedure, which did not appear to be used. The BMP listed more specific test instrument selection instructions as follows:

F.2.c.3) Pressure gauges (all tests), with range appropriate to valve being tested and to type of test using following criteria:

1. Gauge must be calibrated.

2. Gauge must be specific to test medium.

3. Range of gauge should be approximately two times max. test pressure, BUT NOT

less than 1 1/2 times OR greater than four times test pressure.

4. Gauge used to determine set pressure MUST have, as a minimum, tolerance of

plus 1% AND minus 1% of the relief/safety valve set pressure.

Inspectors noted that evaluation of the above criteria of BMP 3100-9, provided adequate instructions for test equipment selection. A historical review indicated that the issue of concern has been recurring for both units for beyond ten years. The station appeared to be using a similar gauge during this time, so the satisfactory calibration check at 7 oz demonstrated assurance of historical operability.

The inspectors determined that the failure to assure that adequate test instrumentation was available and used to test safety related equipment was a performance deficiency and contrary to 10 CFR 50, Appendix B, Criterion XI. Per Inspection Manual Chapter 0612, Appendix B and example 5.d in Appendix E, the team determined that this performance deficiency was minor, because the licensee was able to show reasonable assurance that acceptance criteria was met.

Corrective actions planned by the licensee include measures to obtain the correct tools for future vacuum breaker tests. Inspectors briefed management on the use of CAP for performing comprehensive and timely documentation of longstanding test deficiencies.

No findings or violations of NRC requirements of more than minor safety significance were identified in the course of this review.

Observation: Thermal Sleeves 71152A The inspectors performed a detailed review of IR 4496332; B2R23 CRDM Thermal Sleeve Metrology Results.

The sample selected was associated with a 10 CFR Part 21 notification to the NRC (Westinghouse LTR-NRC-19-79, dated December 12, 2019; ADAMS Accession No. ML19346H873) and additional information on the 10 CFR Part 21 in Nuclear Safety Advisory Letter (NSAL) NSAL-20-1, Reactor Vessel Head Control Rod Drive Mechanism Penetration Thermal Sleeve Cross-Sectional Failure, dated February 14, 2020 (ADAMS Accession No. ML20063J583). The specific issue was associated with mechanical fatigue and fracture that leads to flange separation of thermal sleeves in the control rod drive mechanism penetration tubes which could have a safety consequence that was not previously considered. In addition, the sample was associated with NSAL-18-1, Thermal Sleeve Flange Wear Leads to Stuck Control Rod, July 9, 2018 (ADAMS Accession No. ML18198A275). The specific issue was associated with thermal sleeve flange wear that leads to complete flange separation of the thermal sleeves which may prevent control rod insertion. PWROG-16003-P, Evaluation of Potential Thermal Sleeve Flange Wear, Revision 2 provides acceptance criteria for evaluation of thermal sleeve flange wear associated with NSAL 18-1.

The licensee performed an evaluation of the actual thermal sleeve wear measurements taken at thermal sleeve penetrations during the spring Unit 2 2022 outage, and the NSAL-20-1 acceptance criteria was met. In addition, the PWROG-16003-P, Revision 2 acceptance criteria was met.

No findings or violations were identified Observation: Trend in Fuse Deficiencies 71152S The inspectors performed a semiannual review of the licensee's CAP for adverse trends. An abnormally high number of fuse problems had been identified in the second quarter of 2022.

The 18 issue reports (IRs) with month and day are as follows:

  • 4493936, Fuse holder broken during fuse removal, 4/18
  • 4493879, Fuse holder broken during fuse removal, 4/18
  • 4493880, Control power fuse holder broken during fuse removal, 4/18
  • 4494336, Fuse holder broken during fuse removal, 4/20 4494301, Bus 257 AB Phase fuse open, 4/20 4494275, Fuse holder installed upside down, 4/20
  • 4494589, Broken fuse holder, 4/21
  • 4494659, MCC Fuse holder broken, 4/21
  • 4495221, Control Power Fuse Detached from panel 2AP60E-F1-FU, 4/24 4496383, 2AF017B Blown Fuse in MCC Bucket 232X3-CUB A5, 4/28 4496204, Fuses not installed and no EPN label present, 4/28 4498267, Bad fuse for 2AP60E-E3-FU (control power), 5/07 4498895, 2B FW Pump Fuse 12 N/P Blown, 5/10
  • The licensee also identified a related trend, documenting 12 of the 18 deficiencies in their CAP as 4502316, Potential Trend identified in broken fuse holders, 5/27.

After reviewing the reports, the inspectors did not identify a performance deficiency. The inspectors determined the licensee appropriately followed the corrective action process and did not identify existence of a more safety significant concern.

No findings or violations of NRC requirements of more than minor safety significance were identified in the course of this review.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On July 14, 2022, the inspectors presented the integrated inspection results to Mr. H. Welt, Site Vice President, and other members of the licensee staff.

On April 29, 2022, the inspectors presented the radiation protection inspection results to Mr. S. Leach, Radiation Protection Manager, and other members of the licensee staff.

On May 4, 2022, the inspectors presented the inservice inspection results to Mr. J. Kowalski, Site Vice President, and other members of the licensee staff.

On June 23, 2022, the inspectors presented the triennial heat sink inspection results to Mr. H. Welt, Site Vice President, and other members of the licensee staff.

On June 24, 2022, the inspectors presented the radiation protection inspection results to Mr. H. Welt, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

4504518

NRC ID: Piping Support Missing from 2A DG Fuel Supply Line

06/08/2022

Corrective Action

Documents

Resulting from

Inspection

4504519

NRC ID: 231X Broken Cover Glass for Relay

06/08/2022

Drawings

KSV-31-3

Fuel Transfer Pump

C

0BOSR XHT-A1

High Temperature Equipment Protection

71111.01

Procedures

BOP 199-XHT-1

Hot/Extreme Weather Operations

Corrective Action

Documents

Resulting from

Inspection

4499160

NRC Identified: Breaker Open Light not Lit

05/11/2022

M-129 Sheet 1A

Diagram of Containment Spray Unit 2

AL

M-129 Sheet 1B

Diagram of Containment Spray Unit 2

AM

M-129 Sheet 1C

Diagram of Containment Spray Unit 2

AH

M-136 Sheet 4

Diagram of Safety Injection Unit 2

AZ

M-63-1A

Diagram of Fuel Pool Cooling and Clean-Up

BI

M-63-1B

Diagram of Fuel Pool Cooling and Clean-Up

BC

M-63-1C

Diagram of Fuel Pool Cooling and Clean-Up

AY

Drawings

M-66, Sheet 3B

Diagram of Component Cooling Critical Control Room Drawing

AP

Miscellaneous

BOP FC-T2

Fuel Pool Cooling One Line Diagram

BOP CC-1

Component Cooling Water System Startup

BOP CC-10

Alignment of the U-0 CC Pump and U-0 CC Hx to a Unit

BOP CC-M2

Component Cooling System Valve Lineup

BOP CS-E2

Containment Spray System Electrical Lineup (Unit 2)

BOP CS-M2

Containment Spray System Valve Lineup

BOP FC-E1

Fuel Pool Cooling System Electrical Lineup

BOP FC-M1

Fuel Pool Cooling and Cleanup System Valve Lineup

71111.04

Procedures

BOP RH-M2B

Train "B" Residual Heat Removal System Valve Lineup

Drawings

FP-7,

Fire Barrier Location Plan Elev 426-0

F

71111.05

Fire Plans

FZ 1.3-2

Containment 426' 0" Elevation Unit 2, Containment Upper

Area

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

FZ 12.1-0

Fuel Handling Building 426'-0" Elevation

FZ 12.1-0

Fuel Handling Building 401'-0" Elevation

PFP AB1 414 FZ

11.5A-1 11.5B-1

Pre-Fire Plan Auxiliary Building Unit 1 414-0 Elevation

Electrical Penetration Area FZ 11.5A-1, 11.5B-1 PLAN #152

PFP AB1 426-0

FZ 11.6-1

Pre-Fire Plan Auxiliary Building Unit 1 426-0 Elevation

Division 12 Electrical Penetration Area FZ 11.6-1

PFP AB1 426-0

FZ 5.1-1

Pre-Fire Plan Auxiliary Building Unit 1 426-0 Elevation

Division 12 ESF Switchgear Room FZ 5.1-1 Plan #41

PFP AB1 426-0

FZ 5.2-1

Pre-Fire Plan Auxiliary Building Unit 1 426-0 Elevation

Division 11 ESF Switchgear Room FZ 5.2-1 Plan #43

BYR97-034

Byron Essential Service Water Cooling Tower Basin Minimum

Volume Versus Level and Minimum Usable Volume

Calculation

Calculations

CC-MP-01

Verification of CC System Overpressure Protection

2/01/1988

4162710

SX Piping Leaks Trend IR

01/08/2019

26273

1A SX Pump Oil Leak Outboard Pump

04/12/2020

26982

1A SX Pump Vent Valve Broken

04/15/2020

4449689

Oil Leak on 1AF01PB Filter Housing

09/30/2021

Corrective Action

Documents

4505718

NRC ID: Inactive Oil Leak on 1A AF Pump

06/15/2022

4505244

NRC ID: Ops Surveillance missing "N/A" on open bullet steps.

06/13/2022

4505468

NRC ID - Incorrect Date & Test ID on 2AF017B Report

06/14/2022

4505468

NRC ID: Incorrect Date and Test ID on 2AF017B

06/14/2022

4505517

NRC ID: Insulation Not Fully Secured

06/14/2022

4505533

NRC ID: Small Pools of Oil Underneath 1AF01PB

06/14/2022

4505717

NRC ID: Inactive Oil Leak on 2A AF Pump

06/15/2022

4505756

NRC ID: Procedure Usage on WO 4785428 (HX Inspection

Report)

06/15/2022

4505757

NRC ID: Review 1/2BOSR 6.6.2-1 for Procedure Change

06/15/2022

4505978

NRC ID: Gaps in Work Package Documentation

06/16/2022

4506114

NRC ID: Gaps in Inspection Form Documentation

06/17/2022

4506137

A Potential Trend in WO and Surveillance Paperwork

Closeouts

06/17/2022

71111.07T

Corrective Action

Documents

Resulting from

Inspection

4506178

NRC ID: Incorrect Data on WO 4785428 (HX Inspection

06/17/2022

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Report)

Drawings

M-126

Diagram of Essential Service Water Sections D-F 6-8

04/04/2000

339308

Acceptance Criteria for As-found Heat Exchanger Tube

Blockage

401538

Anode Removal of Stainless-Steel Coolers

09/02/2015

Engineering

Changes

634142

Through Wall Leak on Line 1SX68AB-1 1/2"

2-14-233.410

0B Intake Bay - South Side of RSH River Screen House

Inspection

08/20/2019

AH-CC-654

Exchanger Specification Sheet Component Cooling HX

2/19/1974

N-1661

Heat Transfer Division American-Standard Power & Controls

Group: Heat Exchanger Specification Sheet

09/08/1977

Miscellaneous

Sargent & Lundy

Heat Exchanger

Data Sheets,

attached to

1/17/90 S&L letter

S.C. Mehta to F.

Lentine

1/2AF01AA Heat Exchanger Data Sheet

01/17/1990

NDE Reports20-064

Ultrasonic Thickness Calibration Sheet

06/01/2020

Operability

Evaluations

1BOA PRI-7

Essential Service Water Malfunction Unit 1

110

0BOSR

5.5.8SX.5-1c

Unit Zero Comprehensive Inservice Testing (IST)

Requirements for Essential Service Water Makeup Pump 0A

1BOSR

5.5.8.SX.5-1c

Unit One Comprehensive Inservice Testing (OST)

Requirements for the Essential Service Water (SX) Pump

1SX01PA and Unit 1 SX Pumps Discharge Check Valves

2BOA PRI-7

Essential Service Water Malfunction Unit 2

111

2BOSR

5.5.8.SX.5-1c

Unit Two Comprehensive Inservice Testing (IST)

Requirements for the Essential Service Water (SX) Pump

2SX01PA and Unit 2 SX Pumps Discharge Check Valves

BVP 800-30

Essential Service Water Fouling Monitoring Program

(GL 89-13 Program Basis Document)

Procedures

CC-AA-404

Maintenance Specification: Application Selection, Evaluation

and Control of Temporary Leak Repairs

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

CY-AA-120-400

Closed Cooling Water Chemistry

CY-AA-120-4110-

F-02

Byron Raw Water Treatment and Control

CY-AP-120-1000-

F-02

Byron Primary Strategic Water Chemistry Plan

CY-AP-2000-F-02

Byron Secondary Strategic Water Chemistry

ER-AA-335-1006

Heat Exchanger Electromagnetic Testing Methodology

ER-AA-340

GL 89-13 Program Implementing Procedure

ER-AA-340-1001

GL 89-13 Program Implementation Instructional Guide

ER-AA-340-1002

Service Water Heat Exchanger Inspection Guide

7, 9, 11

ER-AA-340-1003

GL 89-13 Program Performance Indicators

ER-BY-450

Byron Structures Monitoring Program

MA-AA-736-600

Torquing and Tightening of Bolted Connections

Shipping Records

4949137

LR-Support Diver Inspection/Cleaning of RSH North 0A Intake

Sed PM

10/02/2019

1480642-01

Perform 2A Mtr Drv AF PP Oil Clr Eddy Current Testing

09/16/2013

1653824-01

Perform Guided Wave Inspection of 2SX67AA-1.5 During

B2R18

06/17/2014

1838239

LR-OTI Auxiliary Feedwater System Inspection

04/10/2019

1897106-02

Dive Inspection of 0B RSH Intake Bay per ER-AA-450

09/16/2020

1908363-01, 04,

LR U2 Ultrasonic Thickness Examination of Selected Service

Water

05/10/2016

4767804

EWP IM Perform Calibration of Loop 0SX-065

09/20/2019

4785428-03

LR-U2 Motor Driven AF Pump - Clean and Inspect Lube Oil

Cooler

11/08/2018

4856571

LR-Support Diver Inspection/Cleaning SXCT South 0B Basin

06/24/2020

4864027

LR-Support Diver Inspection/Cleaning SXCT North 0A Basin

05/29/2020

4876057

LR-Support Eddy Current Testing Concurrent with GL 89-13

08/26/2020

487741

EWP IM Perform Calibration of 0SX-064

06/04/2020

4889682

0SX02PA Comprehensive IST Req for SX Makeup Pump

05/30/2019

24503

LR-Support Diver Inspection/Cleaning RSH South IB Intake

Sed PM ID

08/20/2019

Work Orders

24816

LR-RSH Center Bay Diver Inspection

05/21/2020

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

4932711

0SX02PA Comprehensive IST Req for SX Makeup Pump

08/01/2019

4950925

0SX02PA Comprehensive IST Req for SX Makeup Pump

10/03/2019

4964642

EWP IM Perform Calibration of Loop 0SX-065

05/11/2021

29921

Reactor Containment Fan Cooler Surveillance

06/24/2020

5041533-03

LR-U2 Motor Driven AF Pump - Clean and Inspect Lube Oil

Cooler

11/02/2021

505039

EWP IM Perform Calibration of 0SX-064

10/28/2021

256027-01

LR-2A AF Pump SX Suction Line Flushing Surveillance

06/01/2022

Calculations

51-9131378-006

Technical Justification for Detection of Leak Path Indications in

RPV Upper Head Penetrations

006

04376383

Rejectable NDE Indication on 2FW009C Final Plug Weld

10/13/2020

04376507

Rejectable NDE Indication on 2FW009C FW-5

10/14/2020

04495098

U2 Reactor Head Indication at Pen-75

04/23/2022

04496413

FME - Foreign Object Found in 2C SG Secondary Side

04/29/2022

04496417

FME - Foreign Object Found in 2A SG Secondary Side

04/29/2022

04496418

FME - Foreign Object Found in 2D SG Secondary Side

04/29/2022

044964210

FME - Foreign Object Found in 2B SG Secondary Side

04/29/2022

04496744

FME - Floating Tie Wrap lost in SG B (2RC01BB)

4/30/2022

28082

Active Leak Identified in 2FC04F Vault

03/20/2020

4377597

WO 5084887 Failed PMT - 2CV8401B External Leakage

10/19/2020

4391135

Standing Water in 2FC02F

2/18/2020

Corrective Action

Documents

4463896

2FE-0136 Inactive, Non-Minor Boric Acid Leakage from

Bolting

11/30/2021

Corrective Action

Documents

Resulting from

Inspection

4494383

NRC ID: WO#1950332-01 Missing Work Package Instructions

04/20/2022

Engineering

Evaluations

EC 636638

Operability Evaluation Reactor Head Penetration 75

Rev 0

B2R23-VEN-006

2RC01R Reactor Top Head BMV

04/28/2022

BR23-PT-001

Liquid Penetrant Examination of Component

2RH-02-AA/RHES-01 (Support Skirt)

04/24/2022

71111.08P

NDE Reports

BR23-UT-012

Ultrasonic Examination of Component 2AF02DA-4/C04

04/20/2022

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

BR23-UT-013

Ultrasonic Examination of Component 2AF02DA-4/C03

04/20/2022

BR23-UT-014

Ultrasonic Examination of Component 2AF02EA-4/C01

04/20/2022

BR23-UT-015

Ultrasonic Examination of Component 2AF02DE-4/C06

04/20/2022

BR23-UT-016

Ultrasonic Examination of Component 2AF02EA-4/C03

04/20/2022

BR23-UT-017

Ultrasonic Examination of Component 2AF02EA-4/C02

04/20/2022

BR23-UT-018

Ultrasonic Examination of Component 2AF02EA-4/C04

04/20/2022

BR23-UT-019

Ultrasonic Examination of Component 2AF02EA-4/C05

04/20/2022

54-ISI-604

Automated Ultrasonic Examination of Open Tube RPV Closure

Head Penetrations

ER-AA-335-002

Liquid Penetrant (PT) Examination

ER-AA-335-018

Visual Examination of ASME IWE Class MC and Metallic

Liners of Class CC Components,

ER-AA-335-030

Ultrasonic (UT) Examination of Ferritic Piping Welds

ER-AP-335-001

Bare Metal Visual Examination for Nickel Alloy Materials

ER-AP-420-002

Byron/Braidwood Unit 2: Steam Generator Eddy Current

Activities

MRS-2.4.2 GEN-

Eddy Current Inspection of Pre-Service and In-Service

Heat Exchanger Tubing

Procedures

WDI-STD-1165

Remote Inservice Inspection of Reactor Vessel Nozzle to Safe

End, Nozzle to Pipe and Safe End to Pipe Welds Using the

Athena Phased Array System

Work Orders

1950332

Repair Channel Head Based on Inspection Results

05/21/2021

2BGP 100-2A1

Reactor Startup

71111.11Q

Procedures

BOP RC-4

Reactor Coolant System Drain

293785

Certificate of Calibration

2/22/2021

Calibration

Records

11363988

Certificate of Calibration

2/08/2022

Corrective Action

Documents

04484018

1CS01PA - Elevated Vibration

05/13/2022

Corrective Action

Documents

Resulting from

Inspection

4500840

NRC Identified Issue with Vacuum Breaker Testing

05/19/2022

71111.12

Procedures

ER-AA-320

Maintenance Rule Implementation per NEI 18-10

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

4418373

1AF-012 TRP Update

04/22/2021

4494392

1CV131 Failed to Respond

04/20/2022

Corrective Action

Documents

4501672

1PA34J Power Supply Trouble Card C12-335

05/24/2022

Corrective Action

Documents

Resulting from

Inspection

4502395

Response to NRC Question on 1AF-012 Test Report Status

05/27/2022

Drawings

6E-1-4031AF02

Loop Schematic Diagram Aux. Feedwater Steam

Gen. 1A Flow Control System ESF-12 Pnl. 1PA34J

O

Miscellaneous

OU-AP-104

Shutdown Safety Equipment Status Checklist - MODE 6 399',

Vented

1BOA PRI-15

CVCS Abnormalities Unit 1

2BGP 100-6

Refueling Outage

BAR 1-4-D6

Cont Cab Pwr Sup Trouble

BAR 1-8-A5

Ltdwn HX Outlt Flow High

BHC 1-LD

Letdown Malfunction

000

BOP CV-15

Excess Letdown Operations

Procedures

TRP 1AF-012

Auxiliary Feedwater to Steam Generator 1A Flow Control

Loop (AF) (Train B)

5145422

1FI-AF012A/B Reading 7.5 GPM in MCR & RSP, should

be 0 GPM

10/28/2021

71111.13

Work Orders

262089

1PA34J Power Supply Trouble Card C12-335

05/24/2022

04492979

Jacket Water Leak on 1B Auxiliary Water Pump

04/14/2022

04496008

Extent of Condition for 2B Auxiliary Feedwater Pump

04/27/2022

4490436

1A EDG Mechanical Governor Oil Level Adjustment

04/05/2022

4494520

Unexpected Rise in Source Range Counts - N32

04/21/2022

4495098

U2 Reactor Head Indication at Pen-75

04/23/2022

4495778

2NY-NR8039 Showing Abnormal Reading

04/26/2022

4496744

FME - Floating Tie Wrap lost in SG B (2RC01BB)

04/30/2022

4500836

2B DG Brg Temp Hi Trip Press Sw 2PS-DG105B OOT

05/19/2022

4500836

2B DG Brg Temp Hi Trip Press Sw 2PS-DG105B OOT

05/19/2022

Corrective Action

Documents

4500843

2B DG Crankcase Oil Level Low in Band

05/19/2022

71111.15

NDE Reports

INR-B2R23-UT-

Penetration 75, Reportable Indication Notification Report

04/22/2022

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

1BOSR 8.1.2-1

Unit One 1A Diesel Generator Operability Surveillance

BAP 370-1

Station Lubrication Program

ER-AA-321-1007

Inservice Testing (IST) Program Corporate Technical Positions

MA-AA-716-006

Control of Lubricants Program

Procedures

OP-BY-101-0002

Byron Operations Expectations Philosophy Handbook

1888896

Diesel Driven Auxiliary Feedwater Pump Inspection per

BMP 3203-1

03/23/2017

1894388

Replace Flexible Hoses

10/12/2017

Work Orders

4633348

Replace Hoses that were not Replaced During B1R21

During B1R22

09/25/2018

EC 627884

2SXE5A-3" SX Pipe Replacement with Stainless-Steel

71111.18

Engineering

Changes

EC 629149

480 Volt Substation Breaker Setting Change

4495080

2PS9356B Failed LLRT at 56.4 SCFH @ 40 PSIG Test

Pressure

04/23/2022

4495217

2RY16AB - PRT Rupture Disc as Found

04/24/2022

4495218

2RY16AA - PRT Rupture Disc as Found

04/24/2022

4495500

Failed PMT-2PS9356B Failed PMT STT

04/25/2022

4495518

B2R23 2PS9356B Failed as Left LLRT

04/25/2022

4497789

Dual Indication on 2PS9356B with Valve in Closed Position

05/05/2022

Corrective Action

Documents

4497834

Entered 2BOA RCP-1, Reactor Coolant Pump Seal Failure

Unit 2

05/05/2022

4497746

NRC Concern with Troubleshooting Activity

05/04/2022

4498278

Discretionary Near Miss/Working at Height/2B AF Pump Room

05/07/2022

Corrective Action

Documents

Resulting from

Inspection

4501960

NRC Identified - Incorrect 2AF017B PMT Closure.

05/25/2022

Engineering

Evaluations

ECR 454558

Request Engineering to Evaluate Proper Torque Valve for

Rupture Discs.

05/03/2022

Miscellaneous

UFSAR 5.4.11

Pressurizer Relief Discharge System

Procedures

ER-AA-200

Preventive Maintenance Program

4498740

2AF024 Not Indicating Open During 2BOSR 0.5-3.AF.3-2

05/10/2022

4698389

Rebuild Actuator, Regulators/Replace Elastomers

05/10/2022

71111.19

Work Orders

4699260

PM Inspection, In-Service Diag. Test, PIT

05/03/2022

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

4749380

OPS Perform 2BOSR 5.C.2-1 CV System Flow Balance

05/02/2022

4910712

Replace Time Delay Relay 2AF01J-K4

05/11/2022

4955752

Replace AF PP/Gearbox Lube Oil System Relief Valve

05/11/2022

4955906

Replace AF PP/Gearbox Lube Oil System Relief Valve

05/11/2022

4965733

EOC Inspection on 2AF01PB

05/11/2022

5008479

Replacement of the Synchro Start Speed Pickup

05/11/2022

5089242

2PS9356B Doesn't Stroke Fully Open Following Maintenance

05/06/2022

5089590

2AF017B - Minor Degradation Identified During Diagnostic

Testing

05/11/2022

5091168

2AP05EQ Relay #AF1AX for 2AF01PA

05/01/2022

5091392

2AF01J Relay #K2 for Bus 2AF01PB

05/09/2022

5091394

2AF01J Relay #K4 for Bus 2AF01PB

05/11/2022

5091452

Calibrate K11 TDR

05/11/2022

5091479

2AF053A IST Relief Valve Test

05/10/2022

5091489

Inspect Coupling 2AF01PA-L

05/01/2022

5091495

EWP MM 2RY16AB Replace and Test Rupture

05/01/2022

5091498

EWP MM 2RY16AA Replace and Test Rupture Disk

05/01/2022

5091520-01

OP RE - NF-BY-510, Low Power Physics Testing Program

05/11/2022

5091560

2SX174 IST Maintenance DIS/INSP

05/11/2022

5091593

2AF001A IST Disassembly and Inspection

05/07/2022

5092341

2AF014B IST Disassembly and Inspection

05/07/2022

5093954

LR-2AF02A - HX Inspection per Generic Letter 89-13

05/11/2022

5168425

Diesel Driven AF PP Insp to Support 2BVSR Z.7.A.1

05/11/2022

237933

Request Inspect/Replace L2X Relay - 2B AF Pump

05/11/2022

256214-02

OPS PMT - 2D RCP Seal Flow

256214-17

MS - PMT Check/Monitor Vibration Levels

257808

2AF015B Leaking by When Valve Shut

05/11/2022

04498444

Unexpected 2A Auxiliary Feedwater Pump Start

05/08/2022

04498497

2B Auxiliary Feedwater Pump Oil Leak

05/09/2022

4497253

Fatigue Assessment/Waiver

05/02/2022

4498320

2D RCP No. 1 Seal Degradation

05/07/2022

4498888

U2 Rod Drive Group 1AC Rods Not Moving

05/10/2022

71111.20

Corrective Action

Documents

4498901

U2 Rod Drive Power Cabinet SCDE Rods Not Moving

05/10/2022

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

4499196

Unplanned entry into 2BOA ROD-2

05/11/2022

4499220

U2 Turbine Trip After Syncing

05/12/2022

4494234

Oil leak - 2SI8808B

04/19/2022

Corrective Action

Documents

Resulting from

Inspection

4494283

Unit-2 Cnmt Oil Leakage on Charcoal Filtration Housing.

04/20/2022

Miscellaneous

B2R23 Shutdown Safety Process Overview

2BOSR Z,5.b.1-1

Unit Two Containment Loose Debris Inspection

ER-AA-200-1001

Equipment Classification

OP-AA-111-1001

Operations Standards and Expectations

OU-AP-104

Shutdown Safety Management Program Byron/Braidwood

Annex

OU-AP-200

Administrative Controls During Fuel Handling Activities for

Byron and Braidwood

OU-AP-204

Fuel Movement in the Spent Fuel Pool for Byron and

Braidwood

OU-AP-205

Fuel Movement in Containment for Byron and Braidwood

Procedures

OU-AP-4001

PWR Fuel and Core Component Handling Practices

04492638

2MS016D Lifted in Unacceptable Range During Testing

04/12/2022

Corrective Action

Documents

04497533

2BOSR 5.5.8.CV.6-3 Cannot be Performed as Scheduled

05/04/2022

B2R23 MSSV Trevi-Testing Plan

04/12/2022

Miscellaneous

PMC-22-135071

Change Frequency of 1/2CV8368 Check Valves

05/12/2022

23440

2MS013A IST Set Point Verification

04/13/2022

24302

2MS014A IST Set Point Verification

04/13/2022

24303

2MS014D IST Set Point Verification

04/13/2022

24304

2MS016A IST Set Point Verification

04/13/2022

24305

2MS016D IST SET Point Verification

04/13/2022

24306

2MS017B IST Set Point Verification

04/13/2022

4848734

2B Diesel Generator 24 Hr Endurance Run and Hot Restart

05/19/2022

5085881-01

OPS - 2BOSR 5.5.8.AF.5-2C Comprehensive IST

Requirements 2AF01PB

04/14/2022

5085883

Main Steam Safety Valves Operability Test (<94% RX PWR)

04/13/2022

71111.22

Work Orders

5091371

LLRT for P-6 and P-10 - 2WO006A/B, 2WO007A/B

05/05/2022

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

5091371-01

As Found LLRT for P-6 and P-10 - 2WO006A/B, 2WO007A/B

04/28/2022

206756

2MS017D IST Trevi-Test

04/13/2022

5848909

(NEIL)-LR-1A Diesel Generator Operability Surveillance

05/06/2022

Corrective Action

Documents

AR 04494811

B2R23 Lessons Learned - Loop Drain

04/22/2022

Corrective Action

Documents

Resulting from

Inspection

AR 04496343

NRC ID: EC Stickers not added to S/G HEPA Units

04/28/2022

RP-AA-302

Alpha Area Level Assessment

04/15/2021

Miscellaneous

RP-AA-302

Alpha Area Level Assessment

04/13/2022

NISP-RP-004

Radiological Posting and Labeling

RP-AA-300-1002

Electron Capture Isotope Control

Procedures

RP-AA-302

Determination of Alpha Levels and Monitoring

Radiation Surveys RP-AA-460

Controls for High and Locked High Radiation Areas

BY-0-22-00705

S/G Eddy Current Testing and Tube Repairs

BY-2-22-00654

Seal Table Activities

BY-2-22-00683

Thimble Tube Removal / Replacement

BY-2-22-00710

Task

S/G Diaphragms

71124.01

Radiation Work

Permits (RWPs)

BY-2-22-00710

Task 1

S/G Manways

Annual Radiological Environmental Operating Report

Byron Generating Station Units 1 and 2

04/30/2022

Monthly Report on the Meteorological Monitoring Program at

the Byron Nuclear Generating Station

2/04/2020

Monthly Report on the Meteorological Monitoring Program at

the Byron Nuclear Generating Station

05/04/2020

Annual Report on the Meteorological Monitoring Program at

the Byron Nuclear Generating Station 2019

03/23/2020

Annual Site Survey - Exelon Meteorological Monitoring Sites

08/28/2020

71124.07

Miscellaneous

Teledyne Brown Engineering Environmental Services Quality

2/04/2022

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Assurance Report

Radiologic Groundwater Protection Program Results for 2019

01/21/2020

21 Annual RGPP Monitoring Report Summary of Results

and Conclusions

Byron Generating Station

2/11/2021

20 Annual RGPP Monitoring Report Summary of Results

and Conclusions

Byron Generating Station

2/17/2021

Teledyne Brown Engineering Environmental Services Quality

Assurance Report

2/22/2021

11102547 Report

Hydrogeologic Investigation Report

01/31/2020

CY-AA-170-1001

Environmental Dosimetry - Performance Specifications,

Testing, and Analysis

Procedures

CY-BY-170-301

Offsite Dose Calculation Manual for Byron Station Units 1

and 2

Self-Assessments

NUPIC Audit

Number 24879

Supplier Audit Report for ATI Environmental, Inc.

Northbrook, IL

2/18/2020

1Q22 BYR U1

ROP PI Summary

Mitigating Systems Performance Indicators

06/18/2022

LS-AA-2090

Monthly Data Elements for NRC ROP Indicator - Reactor

Coolant System (RCS) Specific Activity

10/01/2021 -

05/31/2022

LS-AA-2140

Monthly Data Elements for NRC ROP Indicator - Occupational

Exposure Control Effectiveness

10/01/2021 -

05/31/2022

Miscellaneous

LS-AA-2150

Monthly Data Elements for NRC ROP Indicator - RETS/ODCM

Radiological Effluent Occurrences

10/01/2021 -

05/31/2022

ER-AA-2008

Mitigating Systems Performance Index (MSPI) Monitoring and

Margin Evaluation

LS-AA-2200

Mitigating System Performance Index Data Acquisition and

Reporting

71151

Procedures

LS-AA-2200

Mitigating System Performance Index Data Acquisition &

Reporting

4474490

Incomplete PMT for MCB Hand Switch Replacement

01/28/2022

71152A

Corrective Action

Documents

4496332

B2R23 CRDM Thermal Sleeve Metrology Results

04/28/2022

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

4486869

NRC ID: 1B SX Pp Oil Low in Sight Glass After Work Window

03/23/2022

4490884

Security Equipment Security Door Anti Pick Plate Loose.

04/06/2022

4508013

NRC ID - PMT Process Not Followed

06/29/2022

Corrective Action

Documents

Resulting from

Inspection

4508013

NRC ID - PMT Process Not Followed

06/28/2022

Document No.

2-9348016-000

Byron 2 CRDM Thermal Sleeve As-Found Dimensional

Report 2022

04/25/2022

Miscellaneous

UFSAR 06.5z

A

Iodine Removal Effectiveness Evaluation of Containment

Spray System

71152S

Corrective Action

Documents

4502316

Potential Trend Identified in Broken Fuse Holders

05/27/2022