Constellation.*

May 2, 2024 L TR:

BYRON 2024-0022 File:

1D.101 5A.106 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001 Byron Station, Units 1 and 2 Renewed Facility Operating License Nos. NPF-37 and NPF-66 NRC Docket Nos. STN 50-454 and STN 50-455 Constellation Energy Generation. LLC (CEG)

Byron Station 4450 N German Church Road Byron IL 61010-9794 wwA constellat1onene1gy com

Subject:

2023 Regulatory Commitment Change Summary Report The purpose of this report is to provide the Constellation Energy Generation, LLC (CEG)

"Regulatory Commitment Change Summary Report" for Byron Station for commitment changes processed during the period from January 1, 2023 through December 31, 2023. Commitment changes are processed in accordance with Nuclear Energy lnstitute's (NEI) 99-04, Revision 0, "Guidance for Managing NRC Commitment Changes," dated July 1999 and associated implementing procedures. For the period from January 1, 2023 through December 31, 2023, there were no commitment changes processed in accordance with NEI 99-04, Revision O and associated implementing procedures requiring NRC notification.

If you have any questions concerning this report, please contact Ms. Zoe Cox, Regulatory Assurance Manager at (815) 406-2800.

Respectfully, jl./lJ

Harris Welt Site Vice President Byron Station HW/ZC/hh