SUBJECT:
BYRON STATION - INTEGRATED INSPECTION REPORT 05000454/2022004 AND 05000455/2022004
Dear David Rhoades:
On December 31, 2022, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Byron Station. On January 17, 2023, the NRC inspectors discussed the results of this inspection with Harris Welt, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, Hironori Peterson, Chief Reactor Projects Branch 3 Division of Operating Reactor Safety Docket Nos. 05000454 and 05000455 License Nos. NPF-37 and NPF-66
Enclosure:
As stated
Inspection Report
Docket Numbers:
05000454 and 05000455
License Numbers:
Report Numbers:
05000454/2022004 and 05000455/2022004
Enterprise Identifier:
I-2022-004-0045
Licensee:
Constellation Energy Generation, LLC
Facility:
Byron Station
Location:
Byron, IL
Inspection Dates:
October 01, 2022 to December 31, 2022
Inspectors:
B. Bartlett, Senior Operations Engineer
J. Cassidy, Senior Health Physicist
G. Hansen, Senior Emergency Preparedness Inspector
R. Knutson, Illinois Emergency Management Agency
J. Masse, Acting Resident Inspector
G. Roach, Senior Operations Engineer
J. Robbins, Senior Resident Inspector
J. Weigandt, Acting Senior Resident Inspector
Approved By:
Hironori Peterson, Chief
Reactor Projects Branch 3
Division of Operating Reactor Safety
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Byron Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
PLANT STATUS
Unit 1 began the inspection period operating at full power. With the exception of minor reductions in power to support scheduled testing activities, the unit remained at or near full power for the remainder of the inspection period.
Unit 2 began the inspection period operating at full power. Due to an issue with automatic voltage control equipment associated with the main generator, the generator was taken offline in order to implement corrective actions. The unit began reducing power on the evening of December 16, 2022, and the output breaker was opened in the early morning hours on December 17, 2022. Reactor power was reduced from full power to approximately 15 percent during this evolution. Corrective actions were completed on the evening of December 17, 2022, and the generator was brought online and power was raised. Full power was achieved on the morning of December 18, 2022. The unit remained at or near full power for the remainder of the inspection period.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, appendix D, Plant Status, observed risk significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
REACTOR SAFETY
71111.01 - Adverse Weather Protection
Seasonal Extreme Weather Sample (IP Section 03.01) (1 Sample)
- (1) The inspectors evaluated readiness for seasonal extreme weather conditions prior to the onset of seasonal cold temperatures on December 1, 2022.
Impending Severe Weather Sample (IP Section 03.02) (1 Sample)
- (1) The inspectors evaluated the adequacy of the overall preparations to protect risk-significant systems from impending high winds on November 5, 2022.
71111.04 - Equipment Alignment
Partial Walkdown Sample (IP Section 03.01) (1 Sample)
The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:
(1)2B emergency diesel generator (EDG) starting air with a dryer out of service on October 17 and 18, 2022
Complete Walkdown Sample (IP Section 03.02) (1 Sample)
- (1) The inspectors evaluated system configurations during a complete walkdown of the control room ventilation system on September 22, 2022.
71111.05 - Fire Protection
Fire Area Walkdown and Inspection Sample (IP Section 03.01) (2 Samples)
The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:
- (1) Unit 1 & 2, A and B Train auxiliary feedwater (AF) pumps on October 21, 2022
- (2) Unit 1 & 2, A and B Train essential service water (SX) pump rooms on November 15, 2022
71111.11A - Licensed Operator Requalification Program and Licensed Operator Performance
Requalification Examination Results (IP Section 03.03) (1 Sample)
- (1) The inspectors reviewed and evaluated the licensed operator examination failure rates for the requalification annual operating tests administered from October 18, 2021 through December 10, 2021.
71111.11B - Licensed Operator Requalification Program and Licensed Operator Performance
Licensed Operator Requalification Program (IP Section 03.04) (1 Sample)
- (1) Biennial Requalification Written Examinations The inspectors evaluated the quality of the licensed operator biennial requalification written examination administered on October 21, 2022.
Annual Requalification Operating Tests The inspectors evaluated the adequacy of the facility licensees annual requalification operating test.
Administration of an Annual Requalification Operating Test The inspectors evaluated the effectiveness of the facility licensee in administering requalification operating tests required by 10 CFR 55.59(a)(2) and that the facility licensee is effectively evaluating their licensed operators for mastery of training objectives.
Requalification Examination Security The inspectors evaluated the ability of the facility licensee to safeguard examination material, such that the examination is not compromised.
Remedial Training and Re-examinations The inspectors evaluated the effectiveness of remedial training conducted by the licensee, and reviewed the adequacy of re-examinations for licensed operators who did not pass a required requalification examination.
Operator License Conditions The inspectors evaluated the licensees program for ensuring that licensed operators meet the conditions of their licenses.
Control Room Simulator The inspectors evaluated the adequacy of the facility licensees control room simulator in modeling the actual plant, and for meeting the requirements contained in 10 CFR 55.46.
Problem Identification and Resolution The inspectors evaluated the licensees ability to identify and resolve problems associated with licensed operator performance.
71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance
Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)
- (1) The inspectors observed and evaluated the performance of an On-Watch Operations Shift Crew in the Control Room during generator Automatic Voltage Regulator replacement on December 16 and 17, 2022.
Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)
- (1) The inspectors observed and evaluated a complex casualty graded scenario by a crew of licensed plant operators in the facility's simulator on October 18, 2022.
71111.12 - Maintenance Effectiveness
Maintenance Effectiveness (IP Section 03.01) (1 Sample)
The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:
(1)2A EDG work window, as documented in Work Orders (WOs) 5096009, 5067415,
===5067416, 5070711, and 5070714 on October 3 through 8, and October 12, 2022
71111.13 - Maintenance Risk Assessments and Emergent Work Control
Risk Assessment and Management Sample (IP Section 03.01)===
The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:
- (1) Evaluation of the emergent work associate with 1FW-530B, as documented in WO 5301980 and Issue Report (IR) 4529642 on October 17, 2022
- (2) Evaluation of the planned work associated with 1B AF battery replacement, as documented in WO 5173533 on October 21, 2022
- (3) Direct current charger 111, as documented in WO 5000925-1 on October 27, 2022
- (4) Evaluation of the planned work associated with 2C steam generator power operated relief valve, as documented in WO 5302060 and IR 4523122 on October 26, 2022
71111.15 - Operability Determinations and Functionality Assessments
Operability Determination or Functionality Assessment (IP Section 03.01) (5 Samples)
The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:
- (1) Evaluation of the operability of the 2B EDG following identification of a degraded starting air and a cooler leak, as documented in IRs 4525597, 4520402, and 4529716 on October 17, 2022
- (2) Evaluation of the operability of the 1C Reactor Containment Fan Coolers (RCFC)following identification of a degraded control circuit as documented in IR 4530816 on October 20 and 21, 2022
- (3) Evaluation of the operability of the direct current (DC) bus 112 following identification of a degraded cross-tie breaker, 1DC06E-DF1, as documented in IR 4528942 on October 27, 2022
- (4) Evaluation of the operability of the 2B EDG following identification of a degraded fitting, as documented in IR 4536285 on November 18, 2022
- (5) Evaluation of the operability of the 1D RCFC and leak detection following identification of a leak in containment, as documented in IRs 4538679 and 4538981 on November 23, 2022
71111.18 - Plant Modifications
Severe Accident Management Guidelines (SAMG) Update (IP Section 03.03) (1 Sample)
The inspectors verified the site SAMGs were updated in accordance with the Pressurized Water Reactor Generic Severe Accident Technical Guidelines and validated in accordance with Nuclear Energy Institute (NEI) 14-01, Emergency Response Procedures and Guidelines for Beyond Design Basis Events and Severe Accidents, Revision 1, as follows:
- (1) Changes to the Byron Unit 1 and Unit 2 SAMGs were reviewed on November 9, 2022.
71111.19 - Post-Maintenance Testing
Post-Maintenance Test Sample (IP Section 03.01) (3 Samples)
The inspectors evaluated the following post-maintenance testing activities to verify system operability and/or functionality:
- (1) Functional and operational testing of the 2SI8811B residual heat removal suction valve following relay work, as documented in WOs 5077907, 5126886-2, 5280816, and 5155721 on October 18, 2022
- (2) Functional and operational testing of the 1B AF pump following battery replacement, as documented in WO 5173533 on October 20, 2022
- (3) Functional and operational testing of various residual heat removal valves, following motor operated valve (MOV) motor replacement and MOV operator inspections, as documented in various work orders on November 1, 2022
71111.22 - Surveillance Testing
The inspectors evaluated the following surveillance testing activities to verify system operability and/or functionality:
Surveillance Tests (other) (IP Section 03.01) (1 Sample)
(1)1N44 power range nuclear instrument channel operational test, as documented in WO 5142373 on October 18, 2022
71114.02 - Alert and Notification System Testing
Inspection Review (IP Section 02.01-02.04) (1 Sample)
- (1) The inspectors evaluated the following maintenance and testing of the alert and notification system:
Annual siren inspection and maintenance records for the period from November 2020 to October 2022
Monthly alert notification system (siren) tests for the period from November 2020 to October 2022
71114.03 - Emergency Response Organization Staffing and Augmentation System
Inspection Review (IP Section 02.01-02.02) (1 Sample)
- (1) The inspectors evaluated the readiness of the Emergency Preparedness Organization.
71114.04 - Emergency Action Level and Emergency Plan Changes
Inspection Review (IP Section 02.01-02.03) (1 Sample)
- (1) The inspectors evaluated the following submitted Emergency Action Level and Emergency Plan changes:
Evaluation No. 22-05, Emergency Action Levels for Byron Station, March 7, 2022 This evaluation does not constitute NRC approval.
71114.05 - Maintenance of Emergency Preparedness
Inspection Review (IP Section 02.01 - 02.11) (1 Sample)
- (1) The inspectors evaluated the maintenance of the emergency preparedness program.
71114.06 - Drill Evaluation
Drill/Training Evolution Observation (IP Section 03.02) (1 Sample)
The inspectors evaluated:
- (1) The inspectors observed and evaluated the emergency action level declaration, notification, and post exercise critique on November 9,
RADIATION SAFETY
71124.05 - Radiation Monitoring Instrumentation
Walkdowns and Observations (IP Section 03.01) (8 Samples)
The inspectors evaluated the following radiation detection instrumentation during plant walkdowns:
(1)area radiation monitors in the auxiliary building (2)friskers used at the main exit from the radiologically controlled area (3)portable radiation protection equipment stored ready for use in the calibration facility (4)personal contamination monitors 'ready for use' at the exit from the radiologically controlled area (5)personal contamination monitors 'ready for use' at the primary access facility exit (6)continuous air monitors in the auxiliary building (7)tool and equipment monitors 'ready for use' at the exit from the radiologically controlled area (8)friskers used in the personnel decontamination room
Calibration and Testing Program (IP Section 03.02) (14 Samples)
The inspectors evaluated the calibration and testing of the following radiation detection instruments:
- (1) FASTSCAN1 Whole Body Counter
- (2) Ludlum 9-7, Serial Number 264357
- (3) Rad Pro 5, Serial Number 0012890
- (4) AMP-100, Serial Number 077023
- (5) Ludlum 177, Serial Number 0025402
- (6) Ludlum 3, Serial Number 0011968
- (7) Ludlum 3030P, Serial Number 0012321
- (8) Telepole, Serial Number 334965
- (9) RADeCO HD-28, Serial Number 3090
- (10) RADeCO H-809V, Serial Number 11948
- (11) RADeCO AVS-28, Serial Number 6389
- (12) ThermoScientific SAM-12, Serial Number 259
- (13) Mirion ARGOS-5, Serial Number 161
- (14) ThermoScientific PM-12, Serial Number 38 Effluent Monitoring Calibration and Testing Program Sample (IP Sample 03.03) (2 Samples)
The inspectors evaluated the calibration and maintenance of the following radioactive effluent monitoring and measurement instrumentation:
- (1) Auxiliary Building Vent Effluent Monitor - 1RE-PR028
- (2) Liquid Radwaste Effluent Monitor - 0RE-PR001
OTHER ACTIVITIES - BASELINE
===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:
MS08: Heat Removal Systems (IP Section 02.07)===
- (1) Unit 1 (July 1, 2021 through September 30, 2022)
- (2) Unit 2 (July 1, 2021 through September 30, 2022)
MS09: Residual Heat Removal Systems (IP Section 02.08) (2 Samples)
- (1) Unit 1 (July 1, 2021 through September 30, 2022)
- (2) Unit 2 (July 1, 2021 through September 30, 2022)
MS10: Cooling Water Support Systems (IP Section 02.09) (2 Samples)
- (1) Unit 1 (October 1, 2021 through September 30, 2022)
- (2) Unit 2 (October 1, 2021 through September 30, 2022)
BI02: RCS Leak Rate Sample (IP Section 02.11) (2 Samples)
- (1) Unit 1 (July 1, 2021 through September 30, 2022)
- (2) Unit 2 (July 1, 2021 through September 30, 2022)
EP01: Drill/Exercise Performance (DEP) Sample (IP Section 02.12) (1 Sample)
- (1) January 1, 2021 through June 30, 2022 EP02: Emergency Response Organization (ERO) Drill Participation (IP Section 02.13) (1 Sample)
- (1) January 1, 2021 through June 30, 2022 EP03: Alert and Notification System (ANS) Reliability Sample (IP Section 02.14) (1 Sample)
- (1) January 1, 2021 through June 30,
INSPECTION RESULTS
No findings were identified.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
On January 17, 2023, the inspectors presented the integrated inspection results to M. Welt, Site Vice President, and other members of the licensee staff.
On October 21, 2022, the inspectors presented the biennial licensed operator requalification program inspection results to A. Schuerman, Plant Manager, and other members of the licensee staff.
On October 31, 2022, the inspectors presented the emergency preparedness inspection results to A. Schuerman, Plant Manager, and other members of the licensee staff.
On November 2, 2022, the inspectors presented the radiation protection inspection results to S. Leach, Senior Manager Site Radiation Protection, and other members of the licensee staff.
On November 28, 2022, the inspectors presented the emergency action level and emergency plan changes inspection results to G. Armstrong, Principal Regulatory Engineer, and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Corrective Action
Documents
4535012
0B Essential Cooling Tower Switchgear Room Heaters
11/05/2022
Miscellaneous
Certification of 2023 Winter Readiness
10/12/2022
0BOSR XFT-A4
Freezing Temperature Equipment Protection Protected Area
Buildings Ventilation Systems and Tanks
1BOA ENV-1
Adverse Weather Conditions Unit 1
101
2BOA ENV-1
Adverse Weather Conditions Unit 2
101
Procedures
OP-AA-108-111-
1001
Severe Weather and Natural Disaster Guidelines
4460406
0VC33 Indicated Intermediate When Fully Closed
11/12/2021
4490148
0VC24Y Damper Failed to Reposition
04/04/2022
4510429
0VC01CB Failed to Start
07/12/2022
23857
Hydramotor Damper Actuator 0FZ-VC024A Excessive
Cycling
09/21/2022
Corrective Action
Documents
4535389
Control Room Ventilation - Operational Margin
11/07/2022
6E-2-4030DG14
Schematic Diagram Diesel Generator 2A and 2b Starting Air
Compressors Air Dryers 2DG01SA-C, 2DG01SA-D,
2DG01SB-C and 2DG01SB-D Unit 2
N
M-96, Sheet 1
Diagram of Control Room HVAC System
AG
M-96, Sheet 2
Diagram of Control Room HVAC System
AK
M-96, Sheet 3
Diagram of Control Room HVAC System
U
M-96, Sheet 4
Diagram of Control Room HVAC System
S
Drawings
M-96, Sheet 5
Diagram of Control Room HVAC System
G
BOP DG-E2B
Diesel Generator Train B Electrical Lineup (Unit 2)
BOP VC-1
Startup of Control Room HVAC System
Procedures
BOP VC-6
Removing the Control Room HVAC System Makeup Air
Filter Unit and Recirculation Charcoal Absorber from Service
11.3-0 N
Pre-Fire Plan Auxiliary Building 364-0 Elevation General
Area South FZ 11.3-0 North Plan #113
11.3-0 S
Pre-Fire Plan Auxiliary Building 364-0 Elevation General
Area South FZ 11.3-0 South Plan #111
Fire Plans
Pre-Fire Plan Auxiliary Building 383-0 Elevation General
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
11.4-0 N
Area North FZ 11.4-0 North Plan #132
PFP AB1 330-0
FZ 11.1A-0
Pre-Fire Plan Auxiliary Building Unit 1 330-0 Elevation
Essential Service Water Pump Room 11.1A-0 Plan #96
PFP AB1 383-0
FZ 11.4A-1
Pre-Fire Plan Auxiliary Building Unit 1 383-0 Elevation 1B
Auxiliary Diesel Feedwater Pump and Day Tank Room FZ
11.4A-1 Plan #137
PFP AB2 330-0
FZ 11.1B-0
Pre-Fire Plan Auxiliary Building Unit 2 330-0 Elevation
Essential Service Water Pump Room 11.1B-0 Plan #97
PFP AB2 383-0
FZ 11.4A-2
Pre-Fire Plan Auxiliary Building Unit 2 383-0 Elevation 2B
Auxiliary Diesel Feedwater Pump and Day Tank Room FZ
11.4A-2 Plan #138
Miscellaneous
FPR Chapter 2.3
Fire Area Analysis
Procedures
TQ-AA-150-F25
LORT Annual Exam Status Report
2/16/2022
4.0 Critique - Unit 2 Coming Offline for B2R22
10/05/2020
Exam Security Violation
11/12/2020
4.0 Critique - Fire Protection Pipe Rupture
2/27/2020
Exam Security Violation
03/10/2021
4.0 Critique of Ramp to Full Power Following Unit 1 Turbine
Valve Testing
03/28/2021
Exam Security Violation
10/20/2021
4.0 Critique for 2BOA INST-2 Entry
06/05/2022
Exam Security Violation
07/22/2022
4.0 Critique - 1BOA ROD-3 Entry Due to DRPI "B" Failure
M08
08/04/2022
4.0 Critique of Pressurizer Low Pressure Alarm
08/04/2022
Corrective Action
Documents
TR 220804-002
Simulator Training on DRPI Failure and Rod Control Failures
08/04/2022
ANSI Simulator
Accuracy
45% Steady State Simulator Test
05/18/2022
ANSI Simulator
Accuracy
70% Steady State Simulator Test
05/18/2022
ANSI Simulator
Accuracy
100% Steady State Simulator Test
05/18/2022
Miscellaneous
Cycle 25
Transient Testing
Transient 1: Manual Reactor Trip
2/08/2022
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Cycle 25
Transient Testing
Transient 3: Simultaneous Closure of all MSIVs
2/08/2022
Cycle 25
Transient Testing
Transient 4: Simultaneous Trip of all RCPs
2/08/2022
Cycle 25
Transient Testing
Transient 9: Maximum Steam Break
2/08/2022
Dynamic
Scenario BY-49
REQUALIFICATION SIMULATOR SCENARIO GUIDE
Dynamic
Scenario BY-54
REQUALIFICATION SIMULATOR SCENARIO GUIDE
Dynamic
Scenario BY-79
REQUALIFICATION SIMULATOR SCENARIO GUIDE
Dynamic
Scenario BY-85
REQUALIFICATION SIMULATOR SCENARIO GUIDE
JPM N001b
Raise Accumulator Level With 1B SI Pump (1SI8821A Fails
to Close)
JPM N004
Lower SI Accumulator Pressure
JPM N027a
Perform an Emergency Boration
JPM N029
Rod Drive MG Set Startup
JPM N033
Shutdown the _B Auxiliary Feed Pump Locally
JPM N054a
Respond to a WS System Malfunction (0A WS Pump
Rotating Backwards)
JPM N056b
Local Start of _B AFW Pump
JPM N084
Synchronize a SAT to a Bus being Fed by a DG Following
Surveillance
JPM N114
Cross-Tie DC Bus _11/_11
JPM N123
Respond to High Radiation in Aux Building (Align VA)
JPM S017t
Classify Event and Fill Out a NARS Form (Loss of Heat
Sink)
JPM S026t
Classify Event and Fill Out a NARS Form (Low SFP Level)
Reactivation of License Log
04/14/2020
Active License Tracking Log - 1st, 2nd, and 3rd Qtr 2022 a
Total of 36 Samples
03/18/2022
Examination Security and Administration
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
TQ-AA-306-F-02
Simulator Review Board Minutes
06/24/2021
TQ-AA-306-F-02
Simulator Review Board Minutes
2/13/2021
TQ-AA-306-F-02
Simulator Review Board Minutes
04/12/2022
TQ-AA-306-F-03
Advanced Nuclear Dispatch Ramp Comparison to Plant
Event
04/27/2020
TQ-AA-306-F-03
Advanced Nuclear Dispatch Ramp Comparison to Plant
Event
07/24/2020
TQ-AA-306-F-20
19-3-1 Out of the Box Evaluation Scenario Based Testing
05/13/2019
TQ-AA-306-F-20
22 NRC Annual Operating Test Dynamic Scenario BY-85
Scenario Based Testing
06/20/2022
1B RCP Fails to Trip on Loss of DC Bus 112
06/17/2019
Incorrect Simulator Response to Loss of Offsite Power
01/09/2020
MPT Heat Up Model May Be Incorrect
03/26/2022
EC 636727 EH Reservoir Level Transmitter and PPC Alarm
03/31/2022
EC 634802 Unit 1 MPT Monitoring and Logic Changes
04/23/2022
Work Orders
EC 634801 Auto Runback FW Ovation
08/25/2022
2BGP 100-3
Power Ascension
103
2BGP 100-4
Power Descension
2BGP 100-8
Generic Reactor Control Guidance
Procedures
BOP CV-6T2
Transient RCMS Operation in Borate Checklist
5067415
LR-2A DG Upper and Lower JW HX GL 89-13 Inspection
10/08/2022
5067416
LR-2A DG Jacket Water Upper Cooler Eddy Current Testing
10/06/2022
5070711
LR Perform DG Lube Oil Cooler Eddy Current Inspection
10/08/2022
5070714
LR Perform DG Lube Oil Cooler Eddy Current Inspection
10/08/2022
5071031
Replace and/or Calibrate AMOT Engine Trip Device
10/06/2022
5096009
(NEIL)-Mechanical Inspection
10/08/2022
Work Orders
21101
2PS-DG077A Tubing Leak
10/06/2022
Corrective Action
Documents
23122
2MS018JC Tach Loss light blinking
09/17/2022
Corrective Action
Documents
Resulting from
Inspection
4533710
NRC Question about DC112 Cross-Tie Breaker
10/31/2022
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
5000925-1
EWP EM Replace Sensing/Current Limit, Amplifier/ Firing
Board
10/27/2022
5173533
AF Battery Surveillance Results Below Admin Limit
10/20/2022
5301980
Failed FW Flow Channel
10/16/2022
Work Orders
5302060
EWP IM T-Shoot 2MS018JC 2C MS PORV TACH Loss
Light Blinking
10/26/2022
4446687
2 Bus DF1 Crosstie Breaker Stuck Off (1DC06E-DF1)
09/16/2021
28942
DC 112 Cross-Tie to 212 Breaker Latch Misaligned
10/13/2022
4530816
1C RCFC Hi Speed Breaker / Control Switch Issue
10/20/2022
4536285
2B DG Tripped Shortly After Post-Maintenance Start
11/10/2022
4538679
Abnormal Level Rise of Containment Floor Drn Sump
11/22/2022
Corrective Action
Documents
4538981
1VP01AD 1D RCFC SX Coil Assy Leak-Top Left When
Looking @ Rx
11/25/2022
Miscellaneous
PWROG-15015-P
PWROG Severe Accident Management Guidelines
Corrective Action
Documents
4530249
Request New Predefine and Procedure
10/18/2022
04769515-02
OPs PMT - Stroke 2SI8812A
10/31/2022
04990298-03
OPs PMT - Stroke and PIT 2CC9412A
10/31/2022
05136304-02
OP PMT: Verify Proper RH Pump Motor Oil Level
10/31/2022
05136975-03
OPs PMT - Stroke Valve 2AP21E-F2 (2RH610)
10/31/2022
05187012-04
OPs PMT - PIT & Stroke Test 2SI8812A
10/31/2022
4844150
1SX01PA Replace All (4) Breathers
10/25/2022
4844348-2
OP PMT - 1SX01PA Function / Leak Check
10/25/2022
5070007-2
OP PMT - Vibe Check 1BOSR 5.5.8.SX.5-1C
10/26/2022
5070007-3
OP PMT - Bearing Temperatures
10/26/2022
5077907-3
10/18/2022
5100624-2
OPS PMT - Functional Test to Run Fan After Relay
Replacement
10/25/2022
26886-2
2BOSR 5.2.5-1, TRN B ECCS Valve Auto Actuation Test
10/18/2022
5155721
2BOSR 0.5-2.RH.4-2, STT for 2RH611 (Week H)
10/18/2022
280816
(NEIL)- 2RH01PB Group A IST Requirements for RH Pump
10/18/2022
Work Orders
295767
(NEIL)- LR-1SX01PA COMPREHENSIVE IST REQ FOR SX
PUMP
10/26/2022
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Work Orders
5142373
1BOSR 3.1.7-44, N-44 COT (WK H)
10/18/2022
Relocation of Byron Back Up Siren Repeater
2/23/2020
EP-SIREN FAILURE (BY02,BY06)
01/05/2021
EP-SIREN FAILURE (BY44)
07/14/2021
Sirens BY01 & BY43 Indicated an Issue During Growl Test
2/06/2021
Corrective Action
Documents
EP-SIREN FAILURE (BY41)
08/15/2022
Byron Station 2020 Warning System Maintenance &
Operational Reports
11/01/2020 -
2/31/2020
Byron Station 2021 Warning System Maintenance &
Operational Reports
01/01/2021 -
2/31/2021
Byron Station Monthly Siren Availability Reports
10/01/2020-
08/30/2022
Byron Station Siren Corrective Maintenance Reports
10/01/2020-
09/30/2022
- U.S. Department of Homeland Security, FEMA Letter;
Backup Alert and Notification System
2/10/2012
Exelon Nuclear Manager, Midwest Emergency
Preparedness Letter to Program Enhancement Manager,
Illinois Emergency Management Agency; Submission of
Byron Generating Station Public Alert and Notification
System (ANS) Design Report' Revision 3
10/01/2018
Miscellaneous
KLD-TR-986
Byron Generating Station Alert and Notification System
(ANS) Design Report
09/19/2018
Offsite Emergency Plan Alert and Notification System
Addendum for Byron Nuclear Power Station
Radiological Emergency Plan Annex for Byron Station
Procedures
Byron Station Radiological Emergency Plan
ERO Vacancies Identified - New Members Needed
2/14/2020
SM DEP Failure During Simulator Evaluation
05/03/2021
Corrective Action
Documents
ERO Qualifications
05/02/2022
Quarterly Unannounced Off-Hours Call-In Augmentation Drill
Results
11/01/2020 -
09/30/2022
Emergency Response Organization Duty Team Roster
09/21/22
Miscellaneous
ERO Staff Training Records Review (Sample - 15)
10/19/2022
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
PIO Organization Activation and Operation
Addendum 1
On-Shift Staffing Technical Basis
Emergency Response Organization (ERO) / Emergency
Response Facility (ERF) Activation and Operation
EP-AA-112-100-
F-06
ERO Notification or Augmentation
Z
TSC Activation and Operation
OSC Activation and Operation
EOF Activation and Operation
EP-BY-1000 Part
II, Section B
Byron Station Emergency Response Organization
EP-BY-1000, Part
III, Appendix 5
Emergency Response Organization (ERO) Staffing and
Augmentation Plan
Procedures
ERO Training and Qualification
Miscellaneous
Q 22-05
Emergency Action Levels for Byron Station
03/07/2022
ADDENDUM 3
Emergency Action Levels for Byron Station
Procedures
ADDENDUM 3
Emergency Action Levels for Byron Station
NRC Red Phone in the MCR
10/09/2020
TSC Phone Issues
01/11/2021
Evaluation of EAL HU6 Due to Rockton Chemical Plant Fire
06/14/2021
Potential Gap in Addressing Public Address Speaker Issues
2/25/2022
Byron Station NRC Phone Lines Inoperable
09/09/2022
Corrective Action
Documents
Byron Station NRC Phone Lines Inoperable
04/14/2022
Byron 8 Year EP Drill / Exercise Cycle Objectives Table
10/19/2022
Byron 2021 Medical / Health Physics Drill Report
2/15/2021
Byron 2022 Off-Year Exercise Evaluation Report
09/20/2022
Byron Station 2021 Accountability Drill Report
01/04/2022
Emergency Preparedness Tabletop Drill Report
08/05/2022
Byron 2021 Health Physics Drill Report
06/16/2021
Miscellaneous
Off-site Response Letters of Agreement for Emergency Plan
11/01/2020 -
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Implementation
10/31/2022
21/2022 Emergency Planning for the Byron Area
(Community Information Booklet)
01/01/2021
22/2023 Emergency Planning for the Byron Area
(Community Information Booklet)
01/01/2022
EP-BY-124-F-01
Byron Control Room/Simulator Inventory Records
10/01/2020-
09/30/2022
EP-BY-124-F-02
Byron Technical Support Center Inventory Records
10/01/2020-
09/30/2022
EP-BY-124-F-03
Byron Operations Support Center Inventory Records
10/01/2020-
09/30/2022
EP-BY-124-F-05
Field Team Inventory Records
10/01/2020-
09/30/2022
EP-BY-124-F-06
Medical Response Kit (Ambulance) Inventory Records
10/01/2020-
09/30/2022
EP-BY-124-F-08
Monthly NARS Communications Test Records
10/01/2020-
09/30/2022
EP-BY-124-F-09
Monthly ENS Communications Test Records
10/01/2020-
09/30/2022
EP-BY-124-F-10
Quarterly Directors Hotline Test Records
10/01/2020-
09/30/2022
EP-BY-124-F-11
Quarterly Operations Status Line Test Records
10/01/2020-
09/30/2022
EP-BY-124-F-12
Quarterly Field Team Satellite Phone Test Records
10/01/2020-
09/30/2022
EP-BY-124-F-16
Byron Hospital Cabinet Inventory Records
10/01/2020-
09/30/2022
NOSA-BYR-22-
Byron Station Emergency Preparedness Audit Report
04/13/2022
Radiological Emergency Plan Annex for Byron Station
Addendum 3
Emergency Action Levels for Byron Station
Procedures
Byron Station Radiological Emergency Plan
Miscellaneous
EP-MW-114-100-
Nuclear Accident Reporting System (NARS) Form
K
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
F-01
Event Notification Worksheet
Procedures
EP-AA-112-100-
F-01
Emergency Director Checklist
FASTSCAN1
FASTSCAN Calibration Acceptance Criteria
03/18/2021
FASTSCAN1
FASTSCAN Calibration Acceptance Criteria
06/30/2022
Serial Number
26240
AVS-28A Calibration Data Sheet
08/17/2022
Serial Number
11948
H-809V Calibration Data Sheet
08/17/2022
Serial Number
161
ARGOS-5 Calibration Data Sheet
03/21/2022
Serial Number
259
SAM-2 Calibration Data Sheet
04/15/2022
Serial Number
264357
Model 9-7 Calibration Data Sheet
07/22/2022
Serial Number
3090
HD-28 Calibration Data Sheet
04/12/2022
Serial Number 38
PM-12 Calibration Data Sheet
08/10/2022
Calibration
Records
Serial Number
8142
Shepherd Calibration Package
07/12/2022
Corrective Action
Documents
Resulting from
Inspection
Two Observations - NRC Exit 71124.05 Radiation Monitoring
Instrumentation
11/03/2022
Controls for Radiation Protection Instrumentation
Calibration of Shepherd Box Irradiators
Calibration of Low-Vol Air Samplers
Calibration of Hi-Vol Air Samplers
Operation and Calibration of the PM-12 Gamma Portal
Monitor
Operation and Calibration of the Model SAM-12 Small
Articles Monitor
Procedures
Operation and Calibration of the Canberra ARGOS-5
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Personnel Contamination Monitor
RP-BY-754
Calibration, Source Check, and Operation of the Ludlum 9-7
Ion Chamber
04933501 01
Calibration of Radiation Monitor 1PR28J
03/05/2021
Work Orders
05065548 01
Calibration of Radiation Monitor 0PR10J
04/12/2022
Corrective Action
Documents
ERO Participation PI Indicator Revision February/March
21
05/12/2021
NRC Performance Indicator Data; Emergency Preparedness
- Alert and Notification System Reliability
01/01/2021 -
06/30/2022
NRC Performance Indicator Data; Emergency Preparedness
- ERO Readiness
01/01/2021 -
06/30/2022
71151
Miscellaneous
NRC Performance Indicator Data; Emergency Preparedness
- Drill/Exercise Performance
01/01/2021 -
06/30/2022
4447391
1RY8010B Failed As-Found Testing at Vendor
09/19/2021
4450104
1RY8010A Failed As-Found Testing at Vendor
10/01/2021
Corrective Action
Documents
4450108
1RY8010C Failed As-Found Testing at Vendor
10/01/2021
Engineering
Evaluations
Byron Evaluation of Pressurizer Safety Out of Tolerance
Impact on Accident Analyses
0