IR 05000346/2011011

From kanterella
Jump to navigation Jump to search
IR 05000346-11-011, on 03/23/2011 - 04/29/2011, Davis-Besse Nuclear Power Station Temporary Instruction 2515/183 - Followup to the Fukushima Daiichi Nuclear Station Fuel Damage Event
ML111320341
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 05/13/2011
From: Jamnes Cameron
NRC/RGN-III/DRP/B6
To: Allen B
FirstEnergy Nuclear Operating Co
References
IR-11-011
Download: ML111320341 (22)


Text

May 13, 2011

SUBJECT:

DAVIS-BESSE NUCLEAR POWER STATION - NRC TEMPORARY INSTRUCTION 2515/183 INSPECTION REPORT 05000346/2011011

Dear Mr. Allen:

On April 29, 2011, the U .S. Nuclear Regulatory Commission (NRC) completed an inspection at your Davis-Besse Nuclear Power Station, using Temporary Instruction 2515/183, Followup to the Fukushima Daiichi Nuclear Station Fuel Damage Event. The enclosed inspection report documents the inspection results which were discussed on April 29, 2011, with Mr. Vito Kaminskas, Director, Site Engineering, and other members of your staff.

The objective of this inspection was to promptly assess the capabilities of the Davis-Besse Nuclear Power Station to respond to extraordinary consequences similar to those that have recently occurred at the Japanese Fukushima Daiichi Nuclear Station. The results from this inspection, along with the results from this inspection performed at other operating commercial nuclear plants in the United States will be used to evaluate the U. S. nuclear industrys readiness to safely respond to similar events. These results will also help the NRC to determine if additional regulatory actions are warranted.

All of the potential issues and observations identified by this inspection are contained in this report. The NRCs Reactor Oversight Process will further evaluate any issues to determine if they are regulatory findings or violations. Any resulting findings or violations will be documented by the NRC in a separate report. You are not required to respond to this letter. In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and your response (if any) will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS)

component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Jamnes L. Cameron, Chief Branch 6 Division of Reactor Projects Docket No. 50-346 License No. NPF-3

Enclosure:

Inspection Report 05000346/2011011 w/Attachment: Supplemental Information

REGION III==

Docket No: 50-346 License No: NPF-3 Report No: 05000346/2011011 Licensee: FirstEnergy Nuclear Operating Company (FENOC)

Facility: Davis-Besse Nuclear Power Station Location: Oak Harbor, OH Dates: March 23, 2011, through April 29, 2011 Inspectors: D. Kimble, Senior Resident Inspector A. Wilson, Resident Inspector Approved by: Jamnes L. Cameron, Chief Branch 6 Division of Reactor Projects Enclosure

INSPECTION SCOPE IR 05000346/2011011, 03/23/2011 - 04/29/2011; Davis-Besse Nuclear Power Station Temporary Instruction 2515/183 - Followup to the Fukushima Daiichi Nuclear Station Fuel Damage Event This report covers an announced Temporary Instruction inspection. The inspection was conducted by Resident inspectors. The NRCs program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649, Reactor Oversight Process, Revision 4, dated December 2006.

INSPECTION SCOPE The intent of the TI is to provide a broad overview of the industrys preparedness for events that may exceed the current design basis for a plant. The focus of the TI was on (1) assessing the licensees capability to mitigate consequences from large fires or explosions on site, (2) assessing the licensees capability to mitigate station blackout (SBO) conditions, (3) assessing the licensees capability to mitigate internal and external flooding events accounted for by the stations design, and (4) assessing the thoroughness of the licensees walk downs and inspections of important equipment needed to mitigate fire and flood events to identify the potential that the equipments function could be lost during seismic events possible for the site. If necessary, a more specific follow-up inspection will be performed at a later date.

INSPECTION RESULTS All of the potential issues and observations identified by this inspection are contained in this report. The NRCs Reactor Oversight Process will further evaluate any issues to determine if they are regulatory findings or violations. Any resulting findings or violations will be documented by the NRC in a separate report.

1 Enclosure

03.01 Assess the licensees capability to mitigate conditions that result from beyond design basis events, typically bounded by security threats, committed to as part of NRC Security Order Section B.5.b issued February 25, 2002, and severe accident management guidelines and as required by Title 10 of the Code of Federal Regulations (10 CFR) 50.54(hh). Use Inspection Procedure (IP) 71111.05T, Fire Protection (Triennial), Section 02.03 and 03.03 as a guideline. If IP 71111.05T was recently performed at the facility, the inspector should review the inspection results and findings to identify any other potential areas of inspection. Particular emphasis should be placed on strategies related to the spent fuel pool. The inspection should include, but not be limited to, an assessment of any licensee actions to:

Licensee Action Describe what the licensee did to test or inspect equipment.

a. Verify through test or inspection Licensee actions included the identification of equipment (active and passive) utilized for that equipment is available and implementation of B.5.b actions and any additional equipment used in Severe Accident functional. Active equipment Management Guidelines (SAMGs). The scope of the equipment was defined as that shall be tested and passive equipment specifically designated for B.5.b or SAMG mitigation (i.e., special hoses, fittings, equipment shall be walked down diesel battery charger, etc.). Permanent plant equipment (i.e., in situ equipment) was not and inspected. It is not considered in the scope, since it is normally in service, subjected to planned maintenance, expected that permanently and/or checked on operator rounds. The licensee then identified surveillances/tests and installed equipment that is performance frequencies for the identified equipment, and reviewed the results of recent tested under an existing tests. Active equipment within the scope defined above that did not have recent test results regulatory testing program be was tested. Passive equipment within the scope was walked down and inspected.

retested. Describe inspector actions taken to confirm equipment readiness (e.g., observed a test, reviewed test results, discussed actions, reviewed records, etc.).

This review should be done for a The licensees actions as discussed above were completed prior to the issuance of NRC reasonable sample of mitigating TI 2515/183. The inspectors assessed the licensees capabilities by conducting a review of strategies/equipment. the licensees walkdown activities. In addition, the inspectors independently walked down and inspected all major B.5.b contingency response equipment staged throughout the site.

With one exception, the results of the inspectors independent walkdowns confirmed the results obtained by the licensee.

In one instance, however, the inspectors identified a discrepancy with the necessary equipment staged to perform the actions to start an Emergency Diesel Generator (EDG)

without normal station direct current (dc) power available. Specifically, Attachment 8 of DB-OP-02600, Operational Contingency Response Action Plan, requires a total of 11 prepared 8 gauge insulated wires. Nine wires are used to connect 10 emergency batteries in series, and 2 longer lead wires are provided to connect positive and negative sides of the series batteries to the EDG panel. When the batteries are connected they are able to produce an approximate 60 volts direct current (Vdc) supply used to provide excitation needed for field flash of the EDG. During a walkdown of the required inventory, the 2 Enclosure

inspectors only found a total of 10 wires staged and available. One longer lead wire was missing from the bundle.

The inspectors determined that this NRC-identified issue constituted a minor violation of Technical Specification (TS) 5.4.1 for the licensees failure to establish, implement, and maintain procedures recommended by Regulatory Guide 1.33, Revision 2, Appendix A, which requires, in part, procedures for abnormal occurrences. This failure to comply with TS 5.4.1 was determined to have been a violation of minor significance that was not subject to enforcement action in accordance with Section 2.3 of the NRC Enforcement Policy. The review by the inspectors concluded that the licensees electric shop would have had the ability to create a wire in a reasonable amount of time, and that there was no significant impact to the licensees ability to have been able to execute the procedure as a result of the missing electrical connector.

The licensee entered the issue into their corrective action program (CAP) as condition report (CR) 11-92756 and had a replacement electrical connector fabricated and staged immediately. Additionally, a corrective action was initiated to revise abnormal procedure DB-OP-02600 to ensure that the procedure clearly and consistently listed the correct amount of wires (11) needed to perform Attachment 8.

Discuss general results including corrective actions by licensee.

The licensee has no equipment designated for use in the SAMGs that is not considered in situ plant equipment. All equipment (active and passive) designated for B.5.b was verified by the licensee to be in applicable procedures. All passive equipment was walked down and verified to be in place and ready for use. Passive equipment which had surveillance and/or preventative maintenance tasks had those activities performed to verify readiness for use.

All active equipment located at the site was verified in place by the licensee. The licensee retested almost all active equipment; flow testing was not performed on the designated B.5.b fire pump, a diesel fire pump mounted on a trailer. Testing is normally done by a vendor at their facilities, because after use the pump is sent to the vendor for special cleaning and lay-up to prevent corrosion of the internal parts. The licensee has entered the issue into their CAP as CR 11-91560 to track completion of the pumps flow testing.

3 Enclosure

Describe the licensees actions to verify that procedures are in place and can be Licensee Action executed (e.g. walkdowns, demonstrations, tests, etc.)

b. Verify through walkdowns or Licensee actions included the identification of those procedures utilized to mitigate the demonstration that procedures consequences of a B.5.b related event and severe accidents. The licensee then compiled to implement the strategies verification documentation for procedure validations and identified any procedures not associated with B.5.b and issued or validated and any with open change requests. Open change requests were 10 CFR 50.54(hh) are in place reviewed for potential impacts on procedure functionality. Licensee personnel were then and are executable. Licensees dispatched to walk down all applicable procedures to verify the ability of the procedures to may choose not to connect or be executed.

operate permanently installed equipment during this Describe inspector actions and the sample strategies reviewed. Assess whether verification. procedures were in place and could be used as intended.

The licensees actions as discussed above were completed prior to the issuance of NRC This review should be done for a TI 2515/183. The inspectors assessed the licensees capabilities by conducting a review of reasonable sample of mitigating the licensees walkdown activities. In addition, the inspectors selected several sections of a strategies/equipment. sample of the procedures walked down by the licensee and walked those down to independently verify the licensees conclusions. As discussed in section 03.01(a) above, the inspectors did identify one instance where a licensee procedure could not be executed as written due to a missing piece of equipment.

Discuss general results including corrective actions by licensee.

The licensee reviewed SAMG strategies and did not identify any issues. Procedures used for B.5.b were reviewed by the licensee, and walkdowns were performed by operators to ensure actions taken in the field in response to a B.5.b event could be performed. Open procedure change requests were reviewed by the licensee to verify that no immediate procedure changes were required. Some minor enhancements were identified by the licensee and entered into the CAP. Specific CRs are listed in the Attachment.

4 Enclosure

Describe the licensees actions and conclusions regarding training and qualifications Licensee Action of operators and support staff.

c. Verify the training and Licensee actions included the identification of training/qualification requirements for qualifications of operators and operators for the implementation of actions needed to mitigate a B.5.b related event and for the support staff needed to the implementation of actions needed for the SAMGs. The licensee documented that implement the procedures and operator training requirements were current and identified those operators with qualification work instructions are current for requirements that were not current. In addition, the licensee identified the activities related to Security training/qualification requirements for applicable emergency response organization (ERO)

Order Section B.5.b and severe command and support staff for the implementation of actions needed to mitigate a B.5.b accident management related event, and for the implementation of actions needed for the SAMGs, and guidelines as required by documented that ERO command and support staff training requirements were current.

10 CFR 50.54 (hh). Where applicable, those ERO command and support staff with qualification requirements that were not current were identified.

Describe inspector actions and the sample strategies reviewed to assess training and qualifications of operators and support staff.

The licensees actions as discussed above were completed prior to the issuance of NRC TI 2515/183. The inspectors assessed the licensees training and qualification activities by conducting a review of training and qualification materials and records related to B.5.b and SAMG event response.

Discuss general results including corrective actions by licensee.

The training requirements, qualifications, and associated records needed for operators for the implementation of SAMGs and B.5.b event response were reviewed by the licensee.

Training was identified for shift managers, shift engineers, and unit supervisors, and verified that the training requirements were embedded within the position qualifications for the operators. The licensee confirmed that all shift operators verify their qualifications prior to assuming a shift position. The training requirements, qualifications, and associated records needed for ERO command and support staff for the implementation of actions needed to mitigate a B.5.b event or implement the SAMGs were also reviewed. All ERO command and support staff training requirements were verified as current by the licensee.

Describe the licensees actions and conclusions regarding applicable agreements Licensee Action and contracts are in place.

d. Verify that any applicable Licensee actions included the identification of all applicable contracts and agreements agreements and contracts are in committed to be in place for the mitigation of a B.5.b related event. The licensee verified place and are capable of that the contracts and agreements were current, and documented whether or not the meeting the conditions needed contracts/agreements were capable of meeting the mitigation strategy.

5 Enclosure

to mitigate the consequences of For a sample of mitigating strategies involving contracts or agreements with offsite these events. entities, describe inspector actions to confirm agreements and contracts are in place and current (e.g., confirm that offsite fire assistance agreement is in place and This review should be done for a current).

reasonable sample of mitigating The licensees actions as discussed above were completed prior to the issuance of NRC strategies/equipment. TI 2515/183. The inspectors assessed the licensees capabilities by conducting an independent review of the licensees emergency response agreement with the Carroll Township Emergency Medical & Fire Service, Inc. This is the only emergency response agreement the licensee has in place. The inspectors review of the agreement verified that it was current and assessed whether or not it was adequate for meeting the licensees mitigation strategy.

Discuss general results including corrective actions by licensee.

The licensee reviewed their letter of agreement with the Carroll Township Fire Department (CTFD). The letter of agreement with CTFD was last revised in November 2008. The CTFD Chief was contacted by the licensee as part of their review efforts to ensure that the letter of agreement was still in effect and that no changes were necessary. The CTFD Chief confirmed the status of the letter of agreement. In addition, the licensee also verified the status of a contingent purchase order developed for the delivery of electrical generation and distribution equipment. During the course of their review, the licensee identified that the original purchase order developed as part of their response for a B.5.b event had expired.

The licensee entered this issue into their CAP as CR 11-91468, and reviewed the purchase order with the vendor to ensure that the desired equipment was still available within the time frames specified.

Document the corrective action report number and briefly summarize problems noted Licensee Action by the licensee that have significant potential to prevent the success of any existing mitigating strategy.

e. Review any open corrective The inspectors reviewed each CR for potential impact to the licensees mitigation strategies.

action documents to assess No significant impacts were identified. Three minor issues, one which constituted a minor problems with mitigating violation of NRC requirements, were identified during the inspectors reviews; these issues strategy implementation were discussed in sections 03.01(a) [CRs 11-91560 and 11-92756] and 03.01(d)

identified by the licensee. [CR 11-91468] above. A complete list of the specific CRs reviewed is provided in the Assess the impact of the Attachment.

problem on the mitigating capability and the remaining capability that is not impacted.

6 Enclosure

03.02 Assess the licensees capability to mitigate station blackout (SBO) conditions, as required by 10 CFR 50.63, Loss of All Alternating Current Power, and station design, is functional and valid. Refer to TI 2515/120, Inspection of Implementation of Station Blackout Rule Multi-Plant Action Item A-22 as a guideline. It is not intended that TI 2515/120 be completely reinspected. The inspection should include, but not be limited to, an assessment of any licensee actions to:

Describe the licensees actions to verify the adequacy of equipment needed to Licensee Action mitigate a SBO event.

a. Verify through walkdowns and Licensee actions included the identification of equipment utilized/required for mitigation of a inspection that all required SBO. The licensee then conducted walkdowns of this equipment to ensure they were materials are adequate and adequate and properly staged. Additionally, the licensee also conducted a review of open properly staged, tested, and CAP items for potential SBO equipment impact.

maintained. Describe inspector actions to verify equipment is available and useable.

The inspectors assessed the licensees capability to mitigate SBO conditions by conducting a review of the licensees walkdown activities. In addition, the inspectors selected a sample of equipment utilized/required for mitigation of a SBO and conducted independent walkdowns of that equipment to verify that the equipment was properly aligned and staged.

The sample of equipment selected by the inspectors included, but was not limited to, the SBO diesel generator and its auxiliaries.

Discuss general results including corrective actions by licensee.

In general, the licensees reviews verified that SBO equipment was ready to respond to a SBO condition. During their CAP review, however, the licensee noted that a previously identified condition documented in CR 10-79719 had not yet been fully corrected. That condition, a reduction in the SBO diesel generators cooling capacity, presently limits SBO diesel generator availability such that the SBO diesel generator must be declared unavailable whenever outside ambient air temperature exceeds 95 degrees F. Corrective actions planned by the licensee include cleaning and inspection of the SBO diesel generator radiator tubes. The licensee initiated CR 11-91648 to capture this issue in their CAP.

Licensee Action Describe the licensees actions to verify the capability to mitigate a SBO event.

b. Demonstrate through Licensee actions included the identification of procedures required for response to a SBO, walkdowns that procedures for along with verification that the identified procedures were current and that no critical revision response to a SBO are requests were in place. The licensee then verified that the mitigating procedures had been executable. properly validated. Additionally, the licensee also conducted a review of open CAP items for potential impact to SBO procedures.

7 Enclosure

Describe inspector actions to assess whether procedures were in place and could be used as intended.

The inspectors assessed the licensees capabilities by conducting a review of the licensees walkdown activities. In addition, the inspectors selected several sections of a sample of the procedures walked down by the licensee and walked those down to independently verify the licensees conclusions.

Discuss general results including corrective actions by licensee.

The licensee procedure utilized to respond to a SBO is within the sites emergency operating procedures (EOPs). Actions to start the SBO diesel generator and supply power to site essential buses are performed from the control room with permanently installed plant equipment. For the purposes of this requirement, the licensee credited their original validation of the specific EOP by a crew of licensed operators on the simulator prior to the implementation of the current revision. No current issues were identified by the licensee.

03.03 Assess the licensees capability to mitigate internal and external flooding events required by station design. Refer to IP 71111.01, Adverse Weather Protection, Section 02.04, Evaluate Readiness to Cope with External Flooding as a guideline. The inspection should include, but not be limited to, an assessment of any licensee actions to verify through walkdowns and inspections that all required materials and equipment are adequate and properly staged. These walkdowns and inspections shall include verification that accessible doors, barriers, and penetration seals are functional.

Describe the licensees actions to verify the capability to mitigate existing design Licensee Action basis flooding events.

a. Verify through walkdowns and Licensee actions included the identification of equipment and penetration seals inspection that all required utilized/required for mitigation of internal and external flooding. The licensee then materials are adequate and conducted walkdowns of this equipment to ensure it was adequate and properly staged.

properly staged, tested, and Doors, barriers, and penetration seals that were utilized for mitigation of flooding were maintained. identified, and checked to see if they were routinely inspected to ensure functionality.

Where routine inspections were not performed or could not be relied upon to ensure functionality, the licensee performed walkdowns and inspections to ensure that the components were functional.

8 Enclosure

Describe inspector actions to verify equipment is available and useable. Assess whether procedures were in place and could be used as intended.

The inspectors assessed the licensees capabilities to mitigate flooding by conducting a review of the licensees walkdown activities. In several instances, these reviews involved the inspectors accompanying licensee engineering personnel during their in-field walkdowns. In addition, the inspectors conducted independent walkdowns of selected flood mitigation equipment to contribute to the overall assessment of the licensees flood mitigating capabilities. Licensee flood mitigation procedures were reviewed to verify usability. The inspectors conclusions were consistent with the results obtained by the licensee.

Discuss general results including corrective actions by licensee.

The licensees verification of flood mitigation capability consisted of walkdowns and verification that the systems, structures, and components (SSCs) were present, periodically tested, and in acceptable condition. All design features, such as curbs, were present and in good condition with one exception. The licensee initiated CR 11-91555 to document a missing curb seal in a mechanical penetration room (No. 4, Room 314). The licensees assessment of operability, which was reviewed by the inspectors, determined that the missing seal did not have any significant adverse impact on flood mitigation capability. Of the more than 40 pieces of equipment evaluated, the licensee found six items that did not have periodic testing requirements. In two cases, the need to establish full verification testing was documented in CRs 11-92101 and 11-92105. The licensee noted four cases in CR 11-92402 where sump pump preventive maintenance activities were not in place.

Doors, barriers, and seal penetrations credited with flood propagation control were determined from the sites flooding analyses, barrier function list, and door function list.

Those lists identify the doors and barriers assumed to maintain integrity to limit the spread of flooding throughout the sites buildings. The licensees reviews confirmed that all flood doors were inspected as part of a routine maintenance program. Flood barriers and penetrations that also serve as fire barriers were determined by the licensee to have been inspected on a routine basis as part of the sites fire protection program. However, the barriers and penetrations that were not part of the fire protection program were identified as not being routinely inspected. The licensee entered this issue into their CAP as noted above. Where accessible, the licensee walked down these flood barriers and penetrations as part of their review for this item. Four of the 117 barriers inspected were found to have minor deficiencies that did not affect the operability of any of the protected equipment. All of 9 Enclosure

the flood doors were inspected and found to have no noted deficiencies. A complete list of the specific CRs reviewed is provided in the Attachment.

03.04 Assess the thoroughness of the licensees walkdowns and inspections of important equipment needed to mitigate fire and flood events to identify the potential that the equipments function could be lost during seismic events possible for the site. Assess the licensees development of any new mitigating strategies for identified vulnerabilities (e.g., entered it into the CAP and any immediate actions taken). As a minimum, the licensee should have performed walkdowns and inspections of important equipment (permanent and temporary) such as storage tanks, plant water intake structures, and fire and flood response equipment; and developed mitigating strategies to cope with the loss of that important function. Use IP 71111.21, Component Design Basis Inspection, Appendix 3, Component Walkdown Considerations, as a guideline to assess the thoroughness of the licensees walkdowns and inspections.

Describe the licensees actions to assess the potential impact of seismic events on Licensee Action the availability of equipment used in fire and flooding mitigation strategies.

a. Verify through walkdowns that Licensee actions included the identification of equipment utilized/required for mitigation of all required materials are fire and flood events. An engineering inspection plan (No. IP-A-010) was established by the adequate and properly staged, licensee to govern the conduct of walkdowns and inspections of the equipment, both tested, and maintained. permanent and temporary. Licensee engineering personnel determined if the equipment was seismically qualified or assessed whether it would be possible to evaluate the equipment as being seismically rugged. Seismic vulnerabilities, including storage locations, were identified, along with mitigating strategies for equipment that was not seismically qualified.

Describe inspector actions to verify equipment is available and useable. Assess whether procedures were in place and could be used as intended.

The inspectors conducted multiple walkdowns, both independently and in conjunction with licensee personnel, of important equipment needed to mitigate fire and flood events to identify the potential that the equipments function could be lost during a seismic event.

This equipment included, but was not limited to:

  • all major B.5.b contingency response equipment staged throughout the site;
  • all installed fire protection and suppression equipment in the turbine building on the 565 ft, 623 ft, 643 ft, and 658 ft elevations;
  • the installed diesel and electric fire pumps and their controls; and
  • watertight doors, roof hatches and floor plugs at the plants intake structure.

Licensee flood and fire mitigation procedures were reviewed to verify usability. The results of the inspectors reviews were consistent with the licensees conclusions that there were a number of seismic vulnerabilities that potentially need to be addressed, as described below.

10 Enclosure

Discuss general results including corrective actions by licensee. Briefly summarize any new mitigating strategies identified by the licensee as a result of their reviews.

Seismically qualified is defined as the safety-related SSCs that have been formally qualified to function during and after a design basis earthquake, as applicable. The licensees reviews for this issue determined that non-safety related SSCs, in general, were not considered to be either seismically qualified or seismically rugged due to a wide variety of issues. The majority of room flood mitigation sump pumps and flooding detectors were not designed as seismically qualified and have not been evaluated as being seismically rugged. Similarly, the vast majority of the fire protection system, including both installed fire pumps, was not designed as seismically qualified and cannot be considered seismically rugged. Firefighting equipment staged to respond to B.5.b events was not stowed in seismically qualified buildings and locations, as a seismic event and B.5.b event have never been assumed to occur coincidentally.

The licensees reviews identified instances where response capability could be enhanced.

These included improving procedural guidance, reviewing the locations of portable equipment, and reviewing the need for supplemental portable equipment to compensate for the possible loss of the fire water storage tank, the fire pumps, and much of the fire suppression system piping.

Further, reviews by the licensee identified that in the event of a postulated earthquake, various equipment may not function properly due to loss of essential power or being subjected to physical displacement. The existing mitigation strategy, to conduct station surveys per emergency plan off normal occurrence procedure RA-EP-02820, Earthquake, was considered presently sufficient by the licensee. Further mitigation strategies, the licensee determined, will entail following industry recommendations from other plants that have identified similar beyond-design-bases vulnerabilities. The licensee entered the issues identified into their CAP as CR 11-92571. Specific documents reviewed during this inspection are listed in the Attachment.

11 Enclosure

Exit Meeting On April 29, 2011, the inspectors presented the inspection results to Mr. Vito Kaminskas, Director, Site Engineering, and other members of the licensee staff. The licensee acknowledged the issues presented. The inspectors confirmed that proprietary information reviewed during the course of the inspection had either been returned to the licensee or was being controlled in accordance with NRC policies regarding the handling of sensitive unclassified information.

ATTACHMENT: SUPPLEMENTAL INFORMATION 12 Enclosure

SUPPLEMENTAL INFORMATION KEY POINTS OF CONTACT Licensee