IR 05000346/2020001

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000346/2020001
ML20139A017
Person / Time
Site: Davis Besse 
Issue date: 05/15/2020
From: Billy Dickson
NRC/RGN-III
To: Bezilla M
Energy Harbor Nuclear Corp
References
IR 2020001
Download: ML20139A017 (23)


Text

May 15, 2020

SUBJECT:

DAVIS-BESSE NUCLEAR POWER STATION - INTEGRATED INSPECTION REPORT 05000346/2020001

Dear Mr. Bezilla:

On March 31, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Davis-Besse Nuclear Power Station. On April 20, 2020, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Billy C. Dickson, Jr., Chief Branch 2 Division of Reactor Projects

Docket No. 05000346 License No. NPF-3

Enclosure:

As stated

Inspection Report

Docket Number:

05000346

License Number:

NPF-3

Report Number:

05000346/2020001

Enterprise Identifier: I-2020-001-0044

Licensee:

Energy Harbor Nuclear Corp.

Facility:

Davis-Besse Nuclear Power Station

Location:

Oak Harbor, OH

Inspection Dates:

January 01, 2020 to March 31, 2020

Inspectors:

S. Bell, Health Physicist

E. Fernandez, Reactor Inspector

J. Harvey, Resident Inspector

D. Mills, Senior Resident Inspector

C. Norton, Senior Resident Inspector

J. Park, Reactor Inspector

J. Rutkowski, Project Engineer

Approved By:

Billy C. Dickson, Jr., Chief

Branch 2

Division of Reactor Projects

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Davis-Besse Nuclear Power Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

PLANT STATUS

The plant began the inspection period at rated thermal power. On January 16, 2020, the plant started coasting down with periodic power reductions. The licensee shut down the plant for the refueling outage on February 29, 2020. The plant remained shut down for 25 days. On March 24, 2020, the licensee started up the plant, but operators tripped the plant at very low power on March 25, 2020, due to a failed transformer fuse. The licensee restarted the plant on March 26, 2020, and the plant reached rated thermal power on March 30, 2020. The plant remained at or near full power for the rest of the inspection period.

On February 27, 2020, the licensees parent company successfully completed its Chapter 11 restructuring process and emerged from bankruptcy as Energy Harbor Nuclear Corp. The NRC Region III inspectors used flexibility in the baseline inspection program to assess the potential impact of the financial conditions on licensee performance. Through February 27, 2020, the inspectors applied additional focus to the following areas:

(1) impact on regulatory required plant staffing,
(2) corrective maintenance backlog,
(3) changes to the planned maintenance schedule,
(4) corrective action program implementation, and
(5) reduction in outage scope, including risk-significant modifications. No concerns were identified.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/readingrm/doc-collections/insp-manual/inspection-procedure/index.html.

Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. From January 1 - March 19, 2020, the inspectors performed plant status activities described in IMC 2515, Appendix D, Plant Status, and conducted routine reviews using IP 71152, Problem Identification and Resolution. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), resident inspectors were directed to begin telework and to remotely access licensee information using available technology. During this time the resident inspectors performed periodic site visits each week and during that time conducted plant status activities as described in IMC 2515, Appendix D; and observed risk significant activities when warranted. In addition, resident and regional baseline inspections were evaluated to determine if all or portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In the cases where it was determined the objectives and requirements could not be performed remotely, management elected to postpone and reschedule the inspection to a later date.

REACTOR SAFETY

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Decay heat/low pressure injection (DH/LPI) train 2 while DH/LPI train 1 was out of service for planned emergency core cooling system room cooler maintenance during the week ending January 11, 2020
(2) Emergency diesel generator (EDG) train 2 while component cooling water train 1 was out of service for planned testing during the week ending February 1, 2020
(3) High pressure injection train 1 while DH/LPI train 2 was out of service for planned maintenance and EDG 2 was out of service for planned testing during the week ending February 22, 2020
(4) Decay heat/low pressure injection train 1 while DH/LPI train 2 was in operation during the planned reactor drain down during the week ending March 7, 2020
(5) Decay heat/low pressure injection train 2 while defueled and credited as an alternate means of spent fuel pool cooling during the week ending March 14, 2020

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Electrical penetration room 2, fire area DF, during the week ending February 8, 2020
(2) East and southwest penetration areas of the annulus, fire areas A and AB, during the week ending March 21, 2020
(3) High voltage switchgear room A, fire area S, during the week ending April 4, 2020

71111.08P - Inservice Inspection Activities (PWR) PWR Inservice Inspection Activities Sample (IP Section 03.01)

(1) The inspectors verified the reactor coolant system boundary, steam generator tubes, reactor vessel internals, risk-significant piping system boundaries, and containment boundary were appropriately monitored for degradation and repairs and replacements were appropriately fabricated, examined and accepted by reviewing the following activities from March 2nd, 2020 to March 13th, 2020:

03.01.a - Nondestructive Examination and Welding Activities.

  • Ultrasonic Examination (UT) of 2.5 Elbow to Pipe Weld for High Pressure Injection Emergency Core Cooling, Component ID HP-33C-CCB-2-35-SWE
  • Liquid Penetrant Examination (PT) of the 8.25 SG 1 Upper Primary Head Nozzle Head Vent Safe-End Weld Component ID RC-SG-1-2-W253
  • Inservice Inspection (ISI) Report 21-PT-030 Non-Relevant Indication (<1/16")

on Upper Primary Head Nozzle Head Vent Safe-End Weld Component ID RC-SG-1-2-W253

  • Work Order (WO) 200744645-01 2 1/2" HP2A Valve Replacement

03.01.b - Pressurized-Water Reactor Vessel Upper Head Penetration Examination Activities.

03.01.c - Pressurized-Water Reactor Boric Acid Corrosion Control Activities.

  • CR-2019-02550 Decay Heat and Low-Pressure Injection DH Pumps Test Line Relief DH2761
  • CR-2020-00129 Emergency Sump, Borated Water Storage Tank Isolation Valve DH7A

03.01.d - Pressurized-Water Reactor Steam Generator Tube Examination Activities.

  • Secondary side visual examinations of SG 1B and SG 2A to Inspect Tie Rod Bowing and Tube Bowing

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control room during the shutdown for the planned refueling outage during the week ending February 29, 2020, and the plant trip recovery during the week ending March 28, 2020

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) Licensed operator requalification simulator scenario on February 11, 2020

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (1 Sample)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) Structures monitoring and aging management associated with pipe supports

Quality Control (IP Section 03.02) (1 Sample)

The inspectors evaluated the effectiveness of maintenance and quality control activities to ensure the following SSC remains capable of performing its intended function:

(1) Component cooling water pump 1 pump bearing replacement, constant level oiler installation, and new pump bearing oil seal installation

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (10 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Planned replacement of integrated control system modules and delta Tcold adjustment during the week ending January 11, 2020
(2) Emergent issue during nuclear instrument calibration resulting in unplanned power change during the week ending January 18, 2020
(3) Planned maintenance on component cooling water train 1 during the week ending January 25, 2020
(4) Emergent work on the seal oil vacuum pump and planned orange risk to personal safety (confined space activity) during the week ending February 8, 2020
(5) Planned maintenance on decay heat/low pressure injection 2 pump resulting in an orange risk to nuclear generation window during the week ending February 22, 2020
(6) Emergent conflict between high pressure injection system maintenance work and the reactor coolant system drain down contingency plan during the week ending March 7, 2020
(7) Yellow shutdown defense-in-depth risk window for reactor coolant system reduced inventory and steam generator nozzle dam installation during the week ending March 7, 2020
(8) Heavy lift associated with the reactor head removal and movement to head stand during the week ending March 7, 2020
(9) Planned fuel movement and defueled activities during the week ending March 14, 2020
(10) Yellow shutdown defense-in-depth risk window for planned reactor coolant drain following core reload during the week ending March 21, 2020

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (5 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) Condition Report (CR) 2019-10096: Bolt found missing in diesel fuel oil pressure relief valve DO3672
(2) CR 2020-01984: 1R21 Framatome - Potentially incorrect CRDM [control rod drive mechanism] o-ring lubricant supplied as equivalent
(3) CR 2020-01840: Transverse crack in peripheral weld AFPT [auxiliary feedwater pump turbine] #2 governor
(4) CR 2020-02064: CF [core flood] 1544 LLRT [local leak rate test] exceeded its MALR

[maximum allowable leakage rate]

(5) CR 2020-01702: Rust and staining on reactor vessel closure head flange

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (2 Samples)

The inspectors evaluated the following temporary or permanent modifications:

(1) ECP 16-0332-001, Emergency feedwater (EFW) NFPA 805 manual isolation circuit
(2) ECP 19-0011-004, Replacement of RCP [reactor coolant pump] seal return flow instrumentation

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (7 Samples)

The inspectors evaluated the following post maintenance test activities to verify system operability and functionality:

(1) Auxiliary feedwater pump 1 after planned maintenance during the week ending January 4, 2020
(2) Component cooling water pump 1 following planned maintenance during the week ending February 1, 2020
(3) Decay heat/low pressure injection train 2 following planned maintenance during the week ending February 22, 2020
(4) Startup transformer X02 following tap changes during the week ending March 7, 2020
(5) High pressure injection 2A following planned maintenance during the week ending March 7, 2020
(6) Emergency diesel generator 1 governor testing and tuning following planned governor replacement during the week ending March 14, 2020
(7) Zero power physics testing during the week ending March 28, 2020

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01) (1 Partial)

(1)

(Partial)

The inspectors evaluated licensee activities during refueling outage 21 from February 28, 2020 to March 30, 2020

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance tests:

Surveillance Tests (other) (IP Section 03.01)

(1) Auxiliary feedwater pump 2 quarterly surveillance during the week ending February 15, 2020
(2) Spent fuel pool ventilation system refueling interval test during the week ending March 7, 2020
(3) Safety features actuation system train 2 integrated test during the week ending March 7, 2020
(4) Off-Site AC sources train B bus transfer test during the week ending March 14, 2020
(5) Emergency diesel generator 2 monthly surveillance run during the week ending March 14,

RADIATION SAFETY

71124.01 - Radiological Hazard Assessment and Exposure Controls

Radiological Hazard Assessment (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated how the licensee identifies the magnitude and extent of radiation levels and the concentrations and quantities of radioactive materials and how the licensee assesses radiological hazards

Instructions to Workers (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated radiological protection-related instructions to plant workers

Contamination and Radioactive Material Control (IP Section 03.03) (2 Samples)

The inspectors evaluated licensee processes for monitoring and controlling contamination and radioactive material:

(1) Observed licensee surveys of potentially contaminated material leaving the radiologically controlled area (RCA)
(2) Observed licensee contamination surveys during steam generator work activities

Radiological Hazards Control and Work Coverage (IP Section 03.04) (3 Samples)

The inspectors evaluated in-plant radiological conditions during facility walkdowns and observation of radiological work activities:

(1) Steam Generation Nozzle Dam Installation under RWP 120-5301
(2) Auxiliary Building Radiological Controls for Radiography under RWP 120-6052
(3) HP2A (high pressure injection line 2-1 isolation) Valve Replacement under RWP 120-6053

High Radiation Area and Very High Radiation Area Controls (IP Section 03.05) (2 Samples)

The inspectors evaluated licensee controls of the following High Radiation Areas and Very High Radiation Areas:

(1) Auxiliary Building for Radiography
(2) Containment 603' Elevation Refueling Floor Radiation Worker Performance and Radiation Protection Technician Proficiency (IP Section 03.06) (1 Sample)
(1) The inspectors evaluated radiation worker and radiation protection technician performance as it pertains to radiation protection requirements

71124.02 - Occupational ALARA Planning and Controls

Implementation of ALARA and Radiological Work Controls (IP Section 03.03) (2 Samples)

The inspectors evaluated the licensees communication of as low as is reasonably achievable ALARA and radiological work controls for the following work activities:

(1) Steam Generation Nozzle Dam Installation under RWP120-5301
(2) HP2A (high pressure injection line 2-1 isolation). Valve Replacement under RWP 120-6053

Radiation Worker Performance (IP Section 03.04) (1 Sample)

The inspectors evaluated radiation worker and radiation protection technician performance during:

(1) The inspectors evaluated the implementation of as low as is reasonably achievable techniques for work activities during the 1R21 refueling outage

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification

The inspectors verified licensee performance indicators submittals listed below:

IE01: Unplanned Scrams per 7000 Critical Hours Sample (IP Section 02.01)===

(1) Unit 1 (January 2019 - December 2019)

IE03: Unplanned Power Changes per 7000 Critical Hours Sample (IP Section 02.02) (1 Sample)

(1) Unit 1 ( January 2019 - December 2019)

IE04: Unplanned Scrams with Complications (USwC) Sample (IP Section 02.03) (1 Sample)

(1) Unit 1 (January 2019 - December 2019)

71152 - Problem Identification and Resolution

Semiannual Trend Review (IP Section 02.02) (1 Sample)

Trend of Work Planning and Work Management issues

(1) The inspectors reviewed the licensees corrective action program for potential adverse trends in work management that might be indicative of a more significant safety issue

71153 - Follow-up of Events and Notices of Enforcement Discretion Personnel Performance (IP Section 03.03)

(1) The inspectors evaluated the plant trip during start-up due to a failed Potential Transformer (PT) fuse and licensees performance on March 25,

INSPECTION RESULTS

Observation: Trend of Work Planning and Work Management issues 71152 The inspectors reviewed the licensees corrective action program for potential adverse trends in work planning and work management that might be indicative of a more significant safety issue. During the review period for this inspection sample, the inspectors noted that a significant number of low-level performance issues and errors had challenged the licensee.

The inspectors determined that though some of these issues were directly attributable to human performance and/or procedural compliance, there were several that could be attributed to work planning and work management deficiencies. Specific examples associated with this trend included, but were not limited to:

  • During the third quarter of 2019, the licensee commenced work to replace the control room emergency air temperature control system train 2 compressor. The plant risk due to the work was modeled as green but when maintenance personnel went out into the field, they identified the lift path for the train 2 compressor required lifting it over the train 1 equipment.

The personnel correctly identified that this situation significantly increased the nuclear safety and generation risk (to yellow) and stopped work. The inspectors noted that the work planning process could have identified this issue prior to work starting. (CR 2019-06415)

  • While performing a field walkdown for motor driven feedwater pump target rock cable replacement, the licensee recognized that the conduit intended for use had other safety-related cables running through it that had not been identified during preparation of the engineering change package and work order. The licensee halted the work and developed an alternate approach. The inspectors determined that if this condition had not been recognized and work had proceeded as originally planned, the risk could have been higher than expected. Additionally, the inspectors noted this issue could have been identified during the engineering change process or the work planning process. (CR 2019-06418)
  • During a post maintenance run of the emergency feedwater pump, the work order mistakenly directed operators to run the emergency feedwater pump with valves aligned for steam generator injection and not recirculation as intended. The error resulted in an unintended emergency feedwater pump injection into Steam Generator 1 (SG1) for one minute and seventeen seconds. The inspectors noted this event could have been avoided at multiple points during the work planning process and execution of the work order. The inspectors documented this issue in inspection report 2019004 (section 71152).

(CR 2019-07705)

  • During a scheduled functional test of the train 2 containment normal range radiation monitor (RE4597BA), the operator performing the test was provided the procedure written for the train 1 containment normal range radiation monitor (RE4597AA). The operator followed the procedure he was given and initiated work on the wrong train component rendering both trains inoperable. The inspectors documented this issue in inspection report 2019002 (section 71152). (CR 2019-03346)

Individually, none of these examples may suggest an ongoing problem but when viewed in the aggregate, the inspectors determined they may indicate a programmatic weakness.

Specifically, for these and other work planning deficiencies the station may be missing the opportunity to identify and resolve deficiencies prior to the work being started, potentially resulting in an adverse impact to the plant. The inspectors provided these observations to the licensee and the licensee agreed that additional focus may be necessary to evaluate the trend. The NRC inspectors plan to continue monitoring the licensees actions to address work planning and work management issues.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On April 20, 2020, the inspectors presented the integrated inspection results to Mr. M. Bezilla, Site Vice President, and other members of the licensee staff.
  • On March 6, 2020, the inspectors presented the radiation protection baseline inspection results to Mr. G. Norlund, Radiation Protection Manager, and other members of the licensee staff.
  • On March 25, 2020, the inspectors presented the Davis-Besse ISI Inspection results to Mr. P. McCloskey, Performance Improvement Director, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.04

Corrective Action

Documents

CR-2019-02774

DHP#2 Suction Pressure Gauge Out of Cal

03/25/2019

CR-2019-07307

Oil Drop Found on LPI Pump 2 Inboard Bearing

09/03/2019

Drawings

M-033A

High Pressure Injection

M-033B

Decay Heat Train 1

M-033C

Decay Heat Train 2

M-035

Spent Fuel Pool Cooling System

Procedures

DB-OP-06011

High Pressure Injection System

DB-OP-06012

Decay Heat and Low-Pressure Injection Operating

Procedure

DB-OP-06316

Diesel Generator Operating Procedure

Work Orders

200728759

DB-SP3447-001 - Decay Heat Train 2 Pump and Valve Test

09/24/2019

71111.05

Fire Plans

PFP-AB-325

High Voltage Switchgear Room A

PFP-CB-A236H

Annulus Space Except East and Southwest Penetration

Areas at Elevations 585 and 603

PFP-CB-A236L

East Penetration Area of Annulus Space Elevations 585 and

603

Miscellaneous

Fire Hazards Analysis Report

Procedures

DB-FP-04014

Fire Hose Station Inspections

71111.08P

Corrective Action

Documents

Resulting from

Inspection

CR-2020-01702

Rust Deposits and Staining Noted on RVCH Fange

03/20/2020

CR-2020-01798

New Indication Type Identified During SG Tube Examination

03/04/2020

CR-2020-02164

Non-Relevant Indications Observed on Nine Nozzles During

RVCH UT Exams

03/12/2020

Procedures

280-TECR-

104262

EPRI Appendix H/N Eddy Current Technique Validation

54-ISI-240-048

Visible Solvent Removable Liquid Penetrant Examination

Procedure

05/24/2019

54-ISI-603-011

Automated Ultrasonic Examination of RPV Closure Head

Penetrations Containing Thermal Sleeves

2/24/2020

54-ISI-829-014

PDI Generic Procedure for the Ultrasonic Examination of

Dissimilar Metal Welds PDI-UT-10

01/22/2020

54-ISI-836-018

PDI Generic Procedure for Ultrasonic Examination of

Austenitic Piping Welds PDI-UT-2

01/22/2020

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Work Orders

200744645-01

Davis-Besse 2 1/2 HPA Valve Replacement

2/17/2019

71111.11Q Miscellaneous

Simulator Guide CYC 2020-01

Procedures

DB-OP-02528

Instrument Air System Malfunctions

NOP-OP-1002

Conduct of Operations

71111.12

Corrective Action

Documents

CR-2019-10259

CCW Pump Outboard Bearing Design

2/09/2019

CR-2020-00174

Component Cooling Water Pump #1 Mechanical Seal Leak

01/10/2020

CR-2020-00362

Design Engineering Review/Evaluation of Data for any

Impact on Design Basis of CCW Pump 1

01/17/2020

CR-2020-00365

Abnormal Color in Oil Sample from CCW Pump 1 Outboard

Bearing

01/18/2020

CR-2020-00642

Design Engineering Evaluation of CCW Pump 1

Performance per DB-PF-03572, Step 4.41

01/27/2020

CR-2020-00651

CC1 (CCW Pump 1 Suction Valve) Stem Lock Handle is

Missing

01/27/2020

CR-2020-01257

CCW Pump #1 Lessons Learned

2/18/2020

CR-2020-02239

Change oil in P43-1 as Soon as Practical Due to High Iron

and Silicon

03/15/2020

CR-2020-10256

CCW Pump Inboard and Outboard Bearing Reservoir

Coatings are Deteriorating

2/09/2019

Corrective Action

Documents

Resulting from

Inspection

CR-2020-02858

Rust Identified on Spring Can Pipe Support 33-GCB-1-H3

04/01/2020

Miscellaneous

Structures Monitoring Inspection ECCS Pump Rm 1

03/31/2017

Structures Monitoring Inspection ECCS Pump Rm 1

08/16/2019

Structures Monitoring Inspection ECCS Pump Rm 2

03/13/2017

LRPD-05

3.7

Aging Management Program Evaluation Results - Structures

Monitoring Program

MRPM

Maintenance Rule Program Manual

NDE Reports

20-VT-101

Section XI Variable Spring Hanger Support Aux/Rm 500

03/10/2018

20-VT-108

Section XI Variable Spring Support AFP #1 Rm

03/13/2018

Procedures

DB-PF-03572

Component Cooling Water Pump 1 Baseline Test

DBBP-OPS-0011

Protected Equipment Posting

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

EN-DP-01511

Structures Monitoring

NA-QC-05560

Visual Examination Procedure for VT-1, VT-3, and General

Visual Examinations

Work Orders

200708089

Repair Inboard Bearing Oil Leak

03/19/2020

200736805

CCW Pump 1 Clean/Lubricate/Inspect

03/18/2020

200739481

CCW Pump1 Oil Level Validation

03/23/2020

200763444

CCW Pump 1 Constant Level Oilers

01/29/2020

71111.13

Corrective Action

Documents

CR 2017-10941

Pipe Spring Identified on the Separator Tank for the Seal Oil

Vacuum Pump (P76_H)

10/31/2017

CR 2020-00607

Main Gen Seal Oil Vacuum Pump Degraded

01/25/2020

CR-2020-00230

Power Excursion While Placing ICS Back in Auto

01/13/2020

CR-2020-01255

As Found Condition Identified with the New Seal Cartridge

for the Decay Heat Pump

2/17/2020

CR-2020-01257

CCW Pump #1 Lessons Learned

2/18/2020

CR-2020-01363

Decay Heat Pump 2 Inboard Seal Package Leakage ~2 dpm

2/21/2020

CR-2020-01622

ICS11A Failed to Operate from Control Room During Plant

Shutdown

03/01/2020

CR-2020-01848

1R21 Framatome - Nuclear Instrument (NI) Well Covers

Leaking

03/05/2020

Drawings

M-035

Spent Fuel Pool Cooling System

OS-025

Main Generator Seal Oil System

Miscellaneous

Response to Generic Letter Number 88-17, Loss of Decay

Heat Removal

01/03/1989

Acuren Radiography Shot Plan for HP2A at DBNPS

1R21 Shutdown

Defense In Depth

Report

Contingency Plan for RCS Drain Below Flange Level and

Operation Below 80 Inches Above the RCS Hot Leg

Centerline

Lesson Plan G-

OPS-FHT

G-OPS-FHT Operations and Operation Contract Support

Personnel Fuel Handling Equipment

NOBP-OP-0007-

IPTE

Worksheet

1R21 Reactor Head Lifts From and to the Reactor Vessel

2/10/2020

NOP-CC-5703-05 Repair/Replacement Certification Record

NOP-OP-1007-01 Risk Management Plan

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Procedures

DB-MM-09088

Reactor Vessel Head Removal

DB-MM-09089

Reactor Vessel Closure Head Stud Removal

DB-MM-09388

Reactor Vessel Head CRDM Service Structure Disconnects

DB-MN-00006

Control of Lifting and Handling of Heavy Loads

DB-OP-02016

Generator Alarm Panel 16 Annunciators

DB-OP-02527

Loss of Decay Heat Removal

DB-OP-06002

RCS Draining and Nitrogen Blanketing

DB-OP-06902

Power Operations

DBBP-OPS-0011

Protected Equipment Posting

NOBP-OP-0007

Conduct of Infrequently Performed Tests or Evolutions

NOP-OP-2018-02 Report of Repair/Replacement Activities for Nuclear

Facilities

Work Orders

200755711

Decay Heat and Low Pressure Injection Install Cartridge

Seals

03/12/2020

71111.15

Corrective Action

Documents

2019-00351

Info Only Test on Relief Valve DO3671. Valve did not Lift

01/14/2019

2019-10096

Bolt Found Missing in Diesel Relief Valve DO3672

2/03/2019

20-01840

Transverse Crack in Peripheral Weld AFPT #2 Governor

03/05/2020

20-02064

CF1544 LLRT Exceeded Its MALR

03/10/2020

CR 2020-01984

1R21 Framatome - Potentially Incorrect CRDM [Control Rod

Drive Mechanism] O-Ring Lubricant Supplied as Equivalent

03/09/2020

CR-2020-01257

CCW Pump #1 Lessons Learned

2/18/2020

CR-2020-01702

Rust and Staining on Reactor Vessel Closure Head Flange

03/02/2020

CR-2020-01798

New Indication Type Identified during SG Tube Examination

03/04/2020

CR-2020-01840

Transverse Crack in Peripheral Weld AFPT #2 Governor

03/05/2020

CR-2020-01925

Nuclear Fuel - DB1R21: Fuel Inspection - Fuel to Baffle

Interaction Fuel Rod Wear Observed on Fuel Assembly

03/07/2020

CR-2020-01936

DB-ZS-ICS-11B-B1 Position Switch for PV-ICS11B Not

Charging

03/08/2020

CR-2020-01992

White Fibrous Material Identified on the Top Side of RVCH

CRDM Nozzle 23

03/09/2020

Drawings

DB-MM-09190

Control Rod Drive Mechanism Quick Vent and Hydraulic

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Closure Maintenance

OS-041C

Emergency Diesel Generator Diesel Oil System

Engineering

Evaluations

601154925

Evaluate ICS38A Seat Seal Weld Crack

03/11/2018

Miscellaneous

ISTB4

Pump and Valve Basis Document, Volume IV - Maximum

Allowable Leakage Rate (MALR) Basis

Procedures

DB-MM-09344

Emergency and Station Blackout Diesel Engine 4-Year

Maintenance

DB-OP-06012

Decay Heat and Low Pressure Injection System Operating

Procedure

DB-OP-06234

Emergency Feedwater System

NOP-LP-2018-02

Report of Repair/Replacement Activities for Nuclear

Facilities

NOP-OP-1009

Operability Determinations and Functionality Assessments

Shipping Records Purchase Order

45382204/0

Quality Control Receiving Inspection Report for DC Fuel Oil

Pump

05/08/2012

Purchase Order

45463301/1

Quality Control Receiving Inspection Report for Valve -

Relief from Supplier Engine Systems Incorporated

06/12/2015

71111.18

Engineering

Changes

16-0332

Emergency Feedwater (EFW) NFPA Manual Initiation Circuit

19-0011-004

Replacement of RCP Seal Return Flow Instrumentation -

FEMU60D/FTMU60D (and Installation of Relief Valve to

Address Potential Overpressurization of Penetration 56

Piping)

71111.19

Corrective Action

Documents

CR 2020-02613

ZPPT: Cycle 22 Control Rod Worth Greater than Predicted

03/25/2020

CR 2020-02682

Cycle 22 Hot Zero Power (HZP) Reactivity Anomaly Larger

than Expected

03/27/2020

CR-2020-01245

Voided Pipe Upstream of DH200

2/17/2020

CR-2020-01257

CCW Pump #1 Lessons Learned

2/18/2020

CR-2020-01363

Decay Heat Pump 2 Inboard Seal Package Leakage ~2 dpm

2/21/2020

CR-2020-01891

HP2A Stroke Times are Less Than Expected Stroke Times

03/06/2020

CR-2020-01895

HPI Pump 2-D Horizontal Vibe Reading in the Alert Range

03/07/2020

DB-SP-03151

AFP 1 Quarterly Test

Miscellaneous

NOP-CC-5703-05 Repair/Replacement Certification Record

Procedures

DB-ME-09700

Woodward 2301A Electronic Load Sharing and Speed

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Control Setup and Adjustment

DB-MM-09098

AFPT Governor Maintenance

DB-MM-09150

AFPT Maintenance

DB-OP-06314

13.8 KV Switching

DB-OP-06316

Diesel Generator Operating Procedure

DB-PF-03207

HPI Pump Comprehensive and Check Valve Forward Flow

Test Train 1

DB-PF-03208

HPI Pump Comprehensive and Check Valve Forward Flow

Test Train 2

DB-PF-03572

Component Cooling Water Pump 1 Baseline Test

DB-PF-09302

Testing Motor Operated Valves

NOP-LP-2018-02

Report of Repair/Replacement Activities for Nuclear

Facilities

Work Orders

200738187

AFP 1 Quarterly Test

01/02/2020

200746960

Auxiliary Feedwater Pump Turbine 1-1 Preventive

Maintenance

01/02/2020

200755827

NE3212-001 Zero Power Physics Test RFL

03/25/2020

200755962

HPI Pump Comprehensive Test

03/07/2020

71111.20

Corrective Action

Documents

20-02269

TYTRC7A [Reactor Coolant Loop 2 Temperature Difference

Indicator] Found Out of Tolerance

03/16/2020

CR-2020-00683

Procedure Non-compliance: NOP-LP-4011 - Work Hour

Controls

01/29/2020

CR-2020-00984

Cycle 22 Fuel Receipt - Marking Identified on Fuel Cladding

of Assembly UDDG65 During Receipt Inspection

2/08/2020

CR-2020-01190

Pipe Supports Removed During MFPT #2 Pre-Outage Work

2/14/2020

CR-2020-01617

DB-PF-03180 Leakage Observed from RC 51

2/29/2020

CR-2020-01758

1R21 Framatome Spring Scale Not Used for CRDM

Leadscrew Uncoupling Parking

03/04/2020

CR-2020-01863

Cooling Tower Column Degradation

03/06/2020

CR-2020-01880

HP2A Critical Path Re-Assembly Delays

03/06/2020

CR-2020-01886

Rust Buildup Found on Internals of New Aux Feed Trip

Throttle Valve

03/06/2020

CR-2020-01897

Ground on Bus E1

03/07/2020

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

CR-2020-01904

Corrosion Found on Shield Building Wall

03/07/2020

CR-2020-02009

1R21 - Incidental Duties Performed Off-site Result in Fatigue

Rule Violations

03/09/2020

CR-2020-02112

DB 1R21 Trend in Work Hour Rule Compliance

03/11/2020

CR-2020-02112

DB 1R21 Trend in Work Hour Control Compliance

03/11/2020

CR-2020-02164

Non-Relevant Indications Observed on Nine Nozzles During

RVCH UT Exams

03/12/2020

CR-2020-02203

Emergency Diesel Generator 1 Emergency Shutdown

03/13/2020

CR-2020-02217

SP7A 3-way Valve Vent Hole is Leaking

03/14/2020

CR-2020-02222

Diode for K2 Relay Shorted

03/14/2020

CR-2020-02238

Issue Noted During Performance of DB-MI-03743

03/15/2020

CR-2020-02248

ICS11A Did Not Operate Smoothly

03/15/2020

CR-2020-02448

1R21 CTMT Closeout Inspection Results

03/20/2020

CR-2020-02524

1R21 - Unapproved Material Found in CTMT During Mode 3

03/23/2020

CR-2020-02557

Foreign Material Identified During Mode 3 Inspection of

Integrated Head Assembly

03/24/2020

CR-2020-02562

1R21 BACC: A Packing and Pipe Cap Leak Was Found on

CF60

03/24/2020

CR-2020-02576

1R21 Final CTMT Closeout Inspection Results

03/24/2020

Corrective Action

Documents

Resulting from

Inspection

CR-2020-01376

Fuel Handling JFG Documentation Issue

2/21/2020

CR-2020-01650

Material Control Within a Posted Protected Equipment Area

03/01/2020

CR-2020-02063

1R21 Framatome - Spent Fuel Building FME Area Sign

03/10/2020

Miscellaneous

NOBP-OP-1004-

Evolution Specific Reactivity Plan

1/7/2020

Procedures

Cycle 22 COLR

Cycle 22 Core Operating Limits Report

DB-MM-09234

Equipment Hatch Removal and Reinstallation

DB-NE-06303

Fuel Handling in the Auxiliary Building

DB-NE-06307

Fuel Storage Handling Bridge Operating Procedure

DB-NE-06308

Main Fuel Handling Bridge Operating Procedure

DB-OP-02547

Spent Fuel Pool Cooling Malfunctions

DB-OP-06021

Spent Fuel Pool Operating Procedure

GEN-MNT- 0004

Foreign Material Exclusion

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

NG-DB-0017

Shutdown Defense in Depth Assessment

NOBP-OP-1004-

Cycle 21 End of Cycle Shutdown While Restoring Tave to

2F

2/24/2020

Radiation

Surveys

CR-2020-02258

CF-4A1A Found Leaking (CF-LT3A1)

03/15/2020

71111.22

Corrective Action

Documents

CR 2020-01837

DB-SS-03708 Spent Fuel Pool Ventilation System Refueling

Interval Test Acceptance Criteria 5.3 Not Met

03/05/2020

CR-2020-02423

Field Copy of DB-SC-03121 Lost Before Transferring Data to

Master

03/19/2020

Drawings

E-1043 Sh 1

Emergency Diesel Generator 1-2 Loading Table

E-1043 Sh 2

Emer. Diesel Generator 1-2 Loading Table

Miscellaneous

Recommended Enhanced Monitoring of the AFPT 2

Governor and Governor Valve Linkage Prior/During the

Performance of DB-SP-03160 AFP 2 Quarterly Testing

2/14/2020

Technical Requirements Manual

Procedures

DB-SC-03022

Off-Site AC Sources Bus Transfer Test

DB-SC-03071

Emergency Diesel Generator 2 Monthly Test

DB-SP-03160

AFP 2 Quarterly Test

Work Orders

200756129

SFAS Train 2 Integrated Response Time Test

03/19/2020

200756227

SS3708-001 SFP Ventilation Test

03/05/2020

200817786

SFAS Component Test CV5075

03/17/2020

71124.01

Calculations

DB-HP4344-01

Source Term Determination

08/02/2019

Calibration

Records

Containment Access Facility Exit Radiological Monitor

Calibration and Setpoint Data

Various

Corrective Action

Documents

CR-2019-05009

Elevated Contamination Levels Found in Clean Areas of

Auxiliary Building

06/07/2019

CR-2019-08502

Continuous Noble Gas Monitor, AMS-4, Failed Due to Water

Intrusion

10/16/2019

CR-2019-08763

Individual Received a Dose Rate Alarm

10/22/2019

CR-2019-10082

Individual Alarmed Passive Monitoring

2/02/2019

CR-2019-10166

Elevated Dose Rates Identified in Dry Shielded Container

Drain Port Hole

2/05/2019

Procedures

NOP-OP-4101

Access Controls for Radiologically Controlled Areas

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

NOP-OP-4102

Radiological Posting and Labeling

NOP-OP-4104

Job Coverage

NOP-OP-4701

Radiation and Contamination Surveys

Radiation

Surveys

Steam Generator Lower Bowl and Platform Radiological

Surveys and Air Sample Data

Various

Radiation Work

Permits (RWPs)

20-5302

Once-Through Steam Generator Activities

71124.02

ALARA Plans

1R21 Refuel Outage Dose Estimate Trend

03/06/2020

Miscellaneous

Shutdown Chemistry and Source Term Reduction Plan 1R21 0

RWP 120-5019

Alara Plan Waiver Form

11/16/2019

RWP 120-5405

Alara Work in Progress Review

03/04/2020

Procedures

NOP-OP-4107

Radiation Work Permit (RWP)

Radiation Work

Permits (RWPs)

20-5104

Reactor Head Disassembly and Reassembly Work Activities

20-5304

Rotate Orifice Plate Inside Steam Generator 1-1 and 1-2

71151

Corrective Action

Documents

CR 2019-00201

Steam Leak on MS100-1 Piping

01/08/2019

Miscellaneous

Licensee Logs

Various

NEI 99-02

Regulatory Assessment Performance Indicator Guideline

71152

Corrective Action

Documents

CR-2019-06415

CREATCS Train 2 Compressor Replacement Under Order

200582815 was Not Identified as Yellow Nuclear Safety and

Generation Risk

07/30/2019

CR-2019-06418

Critical Order ECP15-0138-004 Target Rock Work Order

Dropped at T+1

07/30/2019

CR-2019-06544

Chemistry Step in the WIS was Incorrectly Scheduled for the

Auxiliary Boiler Outage

08/04/2019

CR-2019-07192

On-line Preparation Milestones not Followed IAW NOP-WM-

0001 Work Management Process

08/28/2019

CR-2019-07763

System Leakage Test of CCW Pump #3 as #1 - Schedule

Change at T-0

09/20/2019

CR-2019-07864

Field Problem Resolution was not Processed Correctly

09/25/2019

CR-2019-09876

Unexpected Loss of Power on Security MUX6 Primary

Communication AdTran

11/22/2019

CR-2019-09925

AD110 HFA Relay Testing concerns

11/25/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

CR-2019-09949

Poor Planning for #2 Circ Pump Maintenance

11/26/2019

CR-2019-10670

AFW Train 1 Lube PM Removed from Schedule at T5 and

Placed Back into Schedule at NWW Without Crew

Acknowledgement

2/30/2019

CR-2019-10674

LPI 1 Post-Quarterly Run Oil Sample Requires a Clearance

and Determination to Defer the Sample not Completed at T2

2/30/2019

CR-2020-00037

Switchyard Breaker 34560 Project Schedule Impacts

01/02/2020

CR-2020-01036

1R21 Orders Changing from RDEX to APLN for Additional

Information

2/11/2020