IE Insp Repts 50-327/79-33 & 50-328/79-18 on 790614.No Noncompliance Noted.Major Areas Inspected:Emergency Tests & Drills
ML19249B167
Person / Time
Site: Sequoyah  Tennessee Valley Authority icon.png
Issue date: 07/03/1979
From: Hufham J, Trojanowski R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML19249B160 List:
References
50-327-79-33, 50-328-79-18, NUDOCS 7909040032
Download: ML19249B167 (3)


Text

.

nnarco

/

o UNITED STATES 8'

>.,, 7, ',j NUCLEAR REGULATORY COMMISSION

'

" f.

c REGION 11 I-g ' %/ [j

o g;.

101 M ARIETTA sT., N.W., sulTE 3100

ATL ANTA, GEORGIA 30303

.....

Report No. 50-327/79-33 and 50-328/79-18 Licensee: Tennessee Valley Authority 500A Chestnut Street Chattanooga, Tennessee 37401 Facility Name: Sequoyah Units 1 and 2 License Nos.

CPPR-72 and CPPR-73 Inspection near Chattanooga, Tennessee

,

Inspected by:

b

'/

//

/

- - -

R. E. Troja oC D te Signed

) 3!7f Approved by: h A M.

i 'nm J.

Hufham,'Se ion Chief, FFMS Branch pateSigned

\\

'

'

SUMMARY Inspection on June 14, 1979 Areas Inspected This routine, announced inspection involved 5 inspector hours onsite in the areas of emergency tests and drills Results Of the one area inspected, no apparent items of noncompliance or deviations were identified.

l)C'Wi?>

79090400$c,

,

.

DETAILS 1.

Persons Contacted Licensee Employees

  • J. M. Ballentine, Plant Superintendent
  • R. J. Kitts, Health Physics Supervisor W. E. Andrews, QA Supervisor Other licensee employees contacted included one operator.

2.

Exit Interview The inspection scope and findings were summarized on June 14, 1979, with those persons indicated in Paragraph I above.

3.

Licensee Action on Previous Inspection Findings Not inspected.

4.

Unresolved Items Unresolved items were not identified during this inspection.

5.

Emergency Tests and Drills a.

Appendix E to 10 CFR 50, paragraph IV.I. specifies that the emergency plan shall contain provisions for testing, by periodic drills, of radiation emergency plans to assure that employees of the licensee are familiar with their specific duties, and provisions for participation in the drills by other persons whose assistance may be needed in the event of a radiation emergency.

Section XI.B of the SNP Site REP specifies that Site REP will be activated at least annually to confirm the operability and function of the applicable emergency alarm systems; the adequacy of personnel emergency responses, and, the interfacing with outside agencies.

b.

A simulated radiation emergency was conducted on June 14, 1979, as a result of a postulated fuel handling accident.

Consequences of the postulated accident resulted in simulated off-site radioactive releases to the environment and simulated contaminated and injured personnel.

Organizations participating in the simulated radiation emergency consisted of but were not limited to the following:

(1) Tennessee Valley Authority (2) Tennessee Office of Civil Defense and Emergency Preparedness -

Nashville, Tennessee coma 9 u v gesD >

.

-2-

,

(3) Hamilton County Civil Defense - Chattanooga, Tennessee (4) The Department of Public Health - Nashville, Tennessee (5) Erlanger Hospital - Chattanooga, Tennessee

~

(6) REAC/TS - Oak Ridge, Tennessee (7) Other local support agencies listed in Appendix A. V.

of the Site REP The objective of the simulated radiation emergency was to test the following aspects of the Site REP:

(1) Actuation of the Site REP (2) Sounding the emergency evacuation alarms in order to ensure the adequacy of assembling and accountability of personnel.

(3) Actuation of the Nashville and Chattanooga Emergency Operations Centers.

(4) Adequacy of the conununications systems among the State Radiological Health, Civil Defense Operations Centers, and the TVA Operations Centers.

(5) Adequacy of the emergency medical treatment facilities at the Sequoyah Site and at Erlanger Hospital.

An NRC inspector was situated in the control room of the Sequoyah Nuclear Plant and observed the emergency response actions of the Emergency Director and his staff during the simulated radiation emer-gency. These observations confirmed that the exercise objectives as noted above were adequately fulfilled.

c.

There were no items of noncompliance or deviations.