05000348/LER-1980-058, Submits Description of Actions Taken Subsequent to Initial 3-yr Containment post-tensioning Sys Testing & Insp,Per LER 80-058/03L-1.Sys Is Performing Design Function W/Margin of Safety,Therefore No Addl Action Necessary

From kanterella
Jump to navigation Jump to search
Submits Description of Actions Taken Subsequent to Initial 3-yr Containment post-tensioning Sys Testing & Insp,Per LER 80-058/03L-1.Sys Is Performing Design Function W/Margin of Safety,Therefore No Addl Action Necessary
ML20071K331
Person / Time
Site: Farley Southern Nuclear icon.png
Issue date: 07/20/1982
From: Clayton F
ALABAMA POWER CO.
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
NT-82-2364, NUDOCS 8208020074
Download: ML20071K331 (2)


LER-2080-058, Submits Description of Actions Taken Subsequent to Initial 3-yr Containment post-tensioning Sys Testing & Insp,Per LER 80-058/03L-1.Sys Is Performing Design Function W/Margin of Safety,Therefore No Addl Action Necessary
Event date:
Report date:
3482080058R00 - NRC Website

text

E ' * *' MJiling Address Alabama Power Company 600 North 18th Street Post Office Ocx 2641 Birmingham. Alabama 35291 Telephone 205 783-6081 F. L. Clayton, Jr.

COCZdl"' Alabama Power NT-82-2364 ttv scort"" ekt"c astem Docket No. 50-348 July 20,1982 M .

c_

Mr. J. P. O'Reilly p , ,,

U. S. Nuclear Regulatory Commission x ,f Office of Inspection and Enforcement w ..

Region II .g ;9 101 Marietta Street, N. W. g .

Suite 3100 ..

~

Atlanta, GA 30303 m es J. M. Farley Nuclear Plant - Unit 1 Containment Post Tensioning System Testing and Inspection Licensee Event Report No. LER 80-58/03L-1 -

Dear Mr. O'Reilly:

Alabama Power Company herewith submits a description of actions taken subsequent to the Farley Nuclear Plant Unit 1 initial three year Contain-ment Post Tensioning System testing and inspection.

The five year tendon surveillance was completed in April,1982. All liftoff forces measured were within predicted limits specified in the Unit 1 Technical Specifications. Results of the visual inspections performed during the five year tendon surveillance were within the acceptance cri-teria of procedure FNP-1-STP-609.0 and were within the acceptance criteria of the Inland Ryerson Field Installation and Quality Control Manual used during initial installation of the tendons. These results have been docu-mented in the Five Year Tendon Surveillance Report submitted to the NRC, j Region II by our letter number 'NT-82-2353 of July 7,1982.

1 Concurrent with the five year tendon surveillance, all tendons from the original three year tendon surveillance sample were visually inspected and had their liftoff forces re-checked. The visual inspection results showed no significant change from the conditions reported in the original l Three Year Tendon Surveillance Report. All liftoff forces checked during the resurveillance were found to be within the predicted limits specified in the Unit 1 Technical Specifications. Furthermore, the liftoff forces measured during the resurveillance were higher than the lockoff forces calculated using the July 10, 1980 calibration equations as reported in l the original Three Year Tendon Surveillance Report. This indicates the calibration methods and equations that were used to derive the three year lockoff and liftoff force values (based on the July 10, 1980 calibration) yielded lower liftoff force values than actually existed in the tendons.

8208020074 820720 3 MN PDR ADOCK 05000348 --

S PDR

{W hU

J. M. Farley Nuclear Plant - Unit 1 Containment Post Tensioning System Testing and Inspection License Event Report No. LER 80-58/03L-1 July 20, 1982 Page 2 Therefore, it has been determined that the liftoff values reported in the original Three Year Tendon Surveillance Report are unrealistically low.

These results have been documented in the Resurveillance Report on Three Year Surveillance Tendons submitted to the NRC, Region II by our letter number NT-82-2354 of July 7,1982.

Calibrations of the rams used in both the three year tendon resurveil-lance and the five year tendon surveillance were conducted before, during (up to five times), and after completion of surveillance activities. Each ram calibration was perfonned in accordance with procedure FNP-1-STP-609.0, Appendix B, Stressing Ram Calibration Procedure. All ram calibrations utilized a single load cell. This load cell was calibrated (traceable to the National Bureau of Standards) before the start of the three year tendon resurveillance and after completion of the five year tendon surveillance.

Load cell calibrations were performed in accordance with procedure FNP STP-609.0, Appendix A, Load Cell Calibration Procedure. All ram and load cell calibration results were within the maximum deviations allowed by the procedures. These results are documented in Appendix 3 of the Resurveil-lance Report on Three Year Surveillance Tendons and Appendix 4 of the Five Year Tendon Surveillance Report.

Since no liftoff force anomalies were observed from the three year tendon resurveillance or from the five year tendon surveillance; since all liftoff forces measured were within the predicted limits specified in the Unit 1 Technical Specifications; since the results of the three year tendon resurveillance indicate that the liftoff values based on the July 10, 1980 calibration were unrealistically low; since the visual inspection data from the three year tendon resurveillance showed no significant changes from the results reported in the original Three Year Tendon Surveillance Report; and since the five year tendon surveillance visual inspection data was within the acceptance standards of procedure FNP-1-STP-609.0 and the original OC acceptance criteria, it is concluded that the FNP Unit 1 Containment Post Tensioning System is performing its design function with a margin of safety, and that no additional action, such as sample size expansion, is necessa ry.

The corrective actions taken and the favorable results found and docu-mented during the surveillance fulfill all of the commitments stated in Licensee Event Report No. LER 80-58/03L-1 and Alabama Power Company con-siders this item complete.

Yours truly, YO F. L. Clayto Jr.

STB:bs cc: Mr. R. A. Thomas Mr. G. F. Trowbridge Mr. S. A. Varga Mr. E. A. Reeves Mr. W. H. Bradford