| | | Reporting criterion |
|---|
| 05000245/LER-1998-001, Forwards LER 98-001-00,re Event Which Occurred on 980109 at Millstone Unit 1.Commitments Made within Ltr,Encl | Forwards LER 98-001-00,re Event Which Occurred on 980109 at Millstone Unit 1.Commitments Made within Ltr,Encl | 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition |
| 05000245/LER-1998-001-02, :on 980109,MRP Determined That There Have Been Periods During Power Operation When Backup Pressure Regulator Was Oos.Caused by Inadequate Understanding of Safety Analysis.Evaluation Will Be Performed |
- on 980109,MRP Determined That There Have Been Periods During Power Operation When Backup Pressure Regulator Was Oos.Caused by Inadequate Understanding of Safety Analysis.Evaluation Will Be Performed
| 10 CFR 50.73(a)(2) |
| 05000423/LER-1998-001-01, :on 980106,discovered Motor Pinion Gear Keys Sheared for Valve Actuators.Caused by Improper Installation of Key Matl That Was Weaker than Required for Function. Replaced Sheared Keys W/Stronger 4140 Matl |
- on 980106,discovered Motor Pinion Gear Keys Sheared for Valve Actuators.Caused by Improper Installation of Key Matl That Was Weaker than Required for Function. Replaced Sheared Keys W/Stronger 4140 Matl
| |
| 05000423/LER-1998-001, Forwards LER 98-001-00,documenting Condition Determined Reportable at Millstone,Unit 3,on 980106.Commitments Made by Util,Encl | Forwards LER 98-001-00,documenting Condition Determined Reportable at Millstone,Unit 3,on 980106.Commitments Made by Util,Encl | 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2) |
| 05000336/LER-1998-001, :on 980108,ongoing Engineering Evaluations of Fault Clearing & Fuse Coordination for Vital 120 Volt AC Sys Occurred.Caused by Incomplete Engineering Evaluation of Fault Clearing.Changes Will Be Implemented |
- on 980108,ongoing Engineering Evaluations of Fault Clearing & Fuse Coordination for Vital 120 Volt AC Sys Occurred.Caused by Incomplete Engineering Evaluation of Fault Clearing.Changes Will Be Implemented
| 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2)(viii) 10 CFR 50.73(a)(2) |
| 05000245/LER-1998-002-02, :on 980211,seal Welding Activities W/O Repair/ Replacement Plan Were Noted.Caused by Inappropriate Decision Making by ISI Coordinator.Evaluation of Each of Nine Seal Welds Was Performed |
- on 980211,seal Welding Activities W/O Repair/ Replacement Plan Were Noted.Caused by Inappropriate Decision Making by ISI Coordinator.Evaluation of Each of Nine Seal Welds Was Performed
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2)(viii) |
| 05000245/LER-1998-002, Forwards LER 98-002-00,documenting Condition That Was Discovered at Millstone,Unit 1 on 980211.Util Commitments Made within Ltr,Listed | Forwards LER 98-002-00,documenting Condition That Was Discovered at Millstone,Unit 1 on 980211.Util Commitments Made within Ltr,Listed | 10 CFR 50.73(a)(2)(i) |
| 05000423/LER-1998-002-01, :on 980112,verification of ECCS Piping Full of Water Per TS 4.5.2.b.1 Was Not Being Met.Caused by Personnel Not Considering ECCS cross-tie Piping as Discharge Piping. Revised ECCS Venting Sp |
- on 980112,verification of ECCS Piping Full of Water Per TS 4.5.2.b.1 Was Not Being Met.Caused by Personnel Not Considering ECCS cross-tie Piping as Discharge Piping. Revised ECCS Venting Sp
| 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications |
| 05000336/LER-1998-002-01, Forwards LER 98-002-01,re ECC Sys Single Failure Vulnerability on 980109.LER Suppl Provides Info on Addl Discrepancies,Identified During Investigation of Condition & During Implementation of Associated Corrective Actions | Forwards LER 98-002-01,re ECC Sys Single Failure Vulnerability on 980109.LER Suppl Provides Info on Addl Discrepancies,Identified During Investigation of Condition & During Implementation of Associated Corrective Actions | 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition |
| 05000423/LER-1998-002, Informs of Revised Completion Date to Complete Commitment Contained in LER 98-002-00, Verification of ECCS Piping Full of Water Per TS 4.5.2.b.1 Not Being Met. New Commitment Made by Util,Encl | Informs of Revised Completion Date to Complete Commitment Contained in LER 98-002-00, Verification of ECCS Piping Full of Water Per TS 4.5.2.b.1 Not Being Met. New Commitment Made by Util,Encl | |
| 05000336/LER-1998-003, Forwards LER 98-003-00,documenting Event That Occurred at Unit 2 on 980113.Util Commitments Made within Ltr Included in Attachment 1 | Forwards LER 98-003-00,documenting Event That Occurred at Unit 2 on 980113.Util Commitments Made within Ltr Included in Attachment 1 | 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition |
| 05000336/LER-1998-003-02, :on 980113,inadequate Evaluation Between Reactor Internals & Rv Occurred.Caused by Inadequate Design Review.Appropriate Structural Analyses Revised |
- on 980113,inadequate Evaluation Between Reactor Internals & Rv Occurred.Caused by Inadequate Design Review.Appropriate Structural Analyses Revised
| 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(x) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2)(viii) 10 CFR 50.73(a)(2) |
| 05000423/LER-1998-003, :on 980114,ISI Pressure Tests for Class 2 & 3 Sys Were Missed.Caused by Historical Program Interface Deficiencies.Procedure for Sys Pressure Tests Has Been Revised to Reflect Sys within Scope of ISI Program |
- on 980114,ISI Pressure Tests for Class 2 & 3 Sys Were Missed.Caused by Historical Program Interface Deficiencies.Procedure for Sys Pressure Tests Has Been Revised to Reflect Sys within Scope of ISI Program
| |
| 05000336/LER-1998-004-02, :on 980316,auxiliary Feedwater Pump Performance Was Degraded.Cause of Condition Is Unknown.Pump Will Be Returned to Operable Status Prior to Mode 3 from Current Outage |
- on 980316,auxiliary Feedwater Pump Performance Was Degraded.Cause of Condition Is Unknown.Pump Will Be Returned to Operable Status Prior to Mode 3 from Current Outage
| 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2)(iii) |
| 05000245/LER-1998-004-01, :on 980311,failure to Recognize Rod Block Monitor Inoperable Occurred.Caused by Personnel Error. Procedures Will Be Revised to Require & Document Monitoring of Local Power Range Monitor |
- on 980311,failure to Recognize Rod Block Monitor Inoperable Occurred.Caused by Personnel Error. Procedures Will Be Revised to Require & Document Monitoring of Local Power Range Monitor
| 10 CFR 50.73(a)(2)(i) |
| 05000245/LER-1998-004, Forwards LER 98-004-00,documenting Condition That Was Discovered at Unit 1 on 980311.Util Commitments Made within Rept,Encl | Forwards LER 98-004-00,documenting Condition That Was Discovered at Unit 1 on 980311.Util Commitments Made within Rept,Encl | 10 CFR 50.73(a)(2)(i) |
| 05000423/LER-1998-004, :on 980114,EDG Intercoolant Coolers Were Not Capable of Meeting Design Criteria.Caused by Inadequate Implementation of GL 89-13 Section II Testing.Diesels Operability in Modes 5 & 6 Was Documented Via CAP |
- on 980114,EDG Intercoolant Coolers Were Not Capable of Meeting Design Criteria.Caused by Inadequate Implementation of GL 89-13 Section II Testing.Diesels Operability in Modes 5 & 6 Was Documented Via CAP
| 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition |
| 05000336/LER-1998-004-01, Forwards LER 98-004-01,re Event Determined Reportable on 980316 at Millstone Unit 2.Commitments Made by Util,Encl | Forwards LER 98-004-01,re Event Determined Reportable on 980316 at Millstone Unit 2.Commitments Made by Util,Encl | 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition |
| 05000245/LER-1998-005-02, :on 980330,loss of S1 & S2 Power Supply Were Noted Due to Single Failure.Caused by Inadequate Design & Indequate Mod Review.Abt & Breaker Configuration for MCC EF3 & MCC FE3 Will Be Evaluated |
- on 980330,loss of S1 & S2 Power Supply Were Noted Due to Single Failure.Caused by Inadequate Design & Indequate Mod Review.Abt & Breaker Configuration for MCC EF3 & MCC FE3 Will Be Evaluated
| 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2)(x) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2)(viii) |
| 05000245/LER-1998-005, Forwards LER 98-005-00,documenting Event That Occurred at Millstone Nuclear Power Station,Unit 1 on 980330.LER Being Submitted Per 10CFR50.73(a)(2)(ii).Util Commitments Made within Ltr,Listed | Forwards LER 98-005-00,documenting Event That Occurred at Millstone Nuclear Power Station,Unit 1 on 980330.LER Being Submitted Per 10CFR50.73(a)(2)(ii).Util Commitments Made within Ltr,Listed | 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition |
| 05000336/LER-1998-005-01, Forwards LER 98-005-01 Re HELB Deficiencies for Piping Inside Containment on 980318.Commitments,encl | Forwards LER 98-005-01 Re HELB Deficiencies for Piping Inside Containment on 980318.Commitments,encl | 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition |
| 05000336/LER-1998-005-02, Forwards LER 98-005-02,re HELB Deficiencies for Piping Inside Containment Identified on 980318.Commitments Made by Util Also Encl | Forwards LER 98-005-02,re HELB Deficiencies for Piping Inside Containment Identified on 980318.Commitments Made by Util Also Encl | 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition |
| 05000423/LER-1998-005, :on 980116,AMSE Section XI Code Requirements Not Met in Scheduling & Performing Inspections of Pipe Supports or Welds Were Noted.Caused by Misinterpretation of Info.Isi Surveillance Procedure Was Revised |
- on 980116,AMSE Section XI Code Requirements Not Met in Scheduling & Performing Inspections of Pipe Supports or Welds Were Noted.Caused by Misinterpretation of Info.Isi Surveillance Procedure Was Revised
| |
| 05000336/LER-1998-005, :on 980318,HELB Deficiencies for Piping Inside Containment Was Noted.Caused by Inadequate Consideration of HELB Requirements.Rept Was Submitted to NRC Discussing Applicability of leak-before-break Methodology |
- on 980318,HELB Deficiencies for Piping Inside Containment Was Noted.Caused by Inadequate Consideration of HELB Requirements.Rept Was Submitted to NRC Discussing Applicability of leak-before-break Methodology
| 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2)(viii) |
| 05000336/LER-1998-006-01, :on 980327,reactor Bldg Closed Cooling Water Sys Outside Design Upon Loss of Svc Water Occurred.Caused by Inadequate Consideration of All Postulated Single Failure Events.Procedures Will Be Implemented |
- on 980327,reactor Bldg Closed Cooling Water Sys Outside Design Upon Loss of Svc Water Occurred.Caused by Inadequate Consideration of All Postulated Single Failure Events.Procedures Will Be Implemented
| 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition |
| 05000336/LER-1998-006, Forwards LER 98-006-00,documenting Event That Occurred at Millstone Nuclear Power Station,Unit 2 on 980327.LER Being Submitted Per 10CFR50.73(a)(2)(ii).NNECOs Commitments Made within Ltr Listed | Forwards LER 98-006-00,documenting Event That Occurred at Millstone Nuclear Power Station,Unit 2 on 980327.LER Being Submitted Per 10CFR50.73(a)(2)(ii).NNECOs Commitments Made within Ltr Listed | 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition |
| 05000423/LER-1998-006, Forwards LER 98-006-00,documenting Condition Determined Reportable at Unit 3 on 980115.Util Commitments in Response to Event Contained within Attachment 1 to Ltr | Forwards LER 98-006-00,documenting Condition Determined Reportable at Unit 3 on 980115.Util Commitments in Response to Event Contained within Attachment 1 to Ltr | 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2)(viii) |
| 05000336/LER-1998-007-02, :on 980408,reanalysis of Ms Line Break Indicated Possible Fuel Failures.Cause Is Under Investigation.Siemens Analysis Will Be Completed Prior to Entering Mode 4 from Current Outage |
- on 980408,reanalysis of Ms Line Break Indicated Possible Fuel Failures.Cause Is Under Investigation.Siemens Analysis Will Be Completed Prior to Entering Mode 4 from Current Outage
| 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(viii) 10 CFR 50.73(a)(2) |
| 05000423/LER-1998-007, :on 980129,containment Bypass Leakage Was in Excess of TS Limits.Caused by non-conservative Decision Making (W/Respect to NRC Branch Technical Position). Calculation Review & Approval Has Been Improved |
- on 980129,containment Bypass Leakage Was in Excess of TS Limits.Caused by non-conservative Decision Making (W/Respect to NRC Branch Technical Position). Calculation Review & Approval Has Been Improved
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2)(viii) |
| 05000423/LER-1998-007-01, Forwards LER 98-007-01,documenting Condition That Was Orginally Determined at Millstone,Unit 3 on 980129.LER Being Submitted Pursuant to 10CFR50.73(a)(2)(i)(B).NNECO Commitments Contained within Attachment 1 to Ltr | Forwards LER 98-007-01,documenting Condition That Was Orginally Determined at Millstone,Unit 3 on 980129.LER Being Submitted Pursuant to 10CFR50.73(a)(2)(i)(B).NNECO Commitments Contained within Attachment 1 to Ltr | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications |
| 05000336/LER-1998-007-01, :on 980408,noted That non-conservative Assumptions May Result in Violation of Fuel Centerline Temp Fuel Design Limit.Caused Indeterminate.Will Complete Siemens Analysis Prior to Entering Mode 4 from Current Outage |
- on 980408,noted That non-conservative Assumptions May Result in Violation of Fuel Centerline Temp Fuel Design Limit.Caused Indeterminate.Will Complete Siemens Analysis Prior to Entering Mode 4 from Current Outage
| 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(viii) |
| 05000336/LER-1998-007, Forwards Corrected LER 98-007-00,documenting Event Which Occurred at Millstone Unit 2 on 980408.LER Is Being Resubmitted Due to Omission of Rept Date on Original Submittal.Commitments Made within Ltr,Encl | Forwards Corrected LER 98-007-00,documenting Event Which Occurred at Millstone Unit 2 on 980408.LER Is Being Resubmitted Due to Omission of Rept Date on Original Submittal.Commitments Made within Ltr,Encl | 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition |
| 05000336/LER-1998-008-01, :on 980423,TS Violations Were Noted.Caused by Failure to Achieve Compliance to TS Requirements.Revised Appropriate Surveillance Procedures |
- on 980423,TS Violations Were Noted.Caused by Failure to Achieve Compliance to TS Requirements.Revised Appropriate Surveillance Procedures
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition |
| 05000336/LER-1998-008, Forwards LER 98-008-00,re Event Which Occurred at Millstone Unit 2,on 980423,per 10CFR50.73(a)(2)(i).Commitments Made within Ltr,Encl | Forwards LER 98-008-00,re Event Which Occurred at Millstone Unit 2,on 980423,per 10CFR50.73(a)(2)(i).Commitments Made within Ltr,Encl | 10 CFR 50.73(a)(2)(i) |
| 05000423/LER-1998-008, :on 980210,RS Sys Historically Outside of Design Basis as Result of Design Change.Caused by Inadequate Historical SE Program Design When Compared W/Current Standards.Lar Was Prepared & Submitted on 980303 |
- on 980210,RS Sys Historically Outside of Design Basis as Result of Design Change.Caused by Inadequate Historical SE Program Design When Compared W/Current Standards.Lar Was Prepared & Submitted on 980303
| 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2)(viii) 10 CFR 50.73(a)(2) |
| 05000423/LER-1998-009, Forwards Revised Commitments Contained in LER 98-009-00 for Mnps,Unit 3, Containment Radiation Monitor CMS*22 Setpoints Non-Conservative W/Respect to Conforming W/Commitments Made to Reg Guide 1.45 within Fsar | Forwards Revised Commitments Contained in LER 98-009-00 for Mnps,Unit 3, Containment Radiation Monitor CMS*22 Setpoints Non-Conservative W/Respect to Conforming W/Commitments Made to Reg Guide 1.45 within Fsar | |
| 05000336/LER-1998-009-01, :on 980501,LBLOCA Analysis Indicates Peak Clad Temp Could Exceed 2200 Degrees F.Caused by Failure to Identify Excessive Variability.Reanalyzed LBLOCA Using Current & Corrected Evaluation Models |
- on 980501,LBLOCA Analysis Indicates Peak Clad Temp Could Exceed 2200 Degrees F.Caused by Failure to Identify Excessive Variability.Reanalyzed LBLOCA Using Current & Corrected Evaluation Models
| 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(x) 10 CFR 21.21(a)(2), Interim Report for Comply or Defect in Component 10 CFR 50.73(a)(2)(viii) |
| 05000336/LER-1998-009, Forwards LER 98-009-00,documenting Event Which Occurred at Millstone Unit 3 on 980501.Commitments Made within Ltr,Encl | Forwards LER 98-009-00,documenting Event Which Occurred at Millstone Unit 3 on 980501.Commitments Made within Ltr,Encl | 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition |
| 05000336/LER-1998-010, Forwards LER 98-010-00,documenting Event That Occurred at Unit 2 on 980508.Util Commitments Made within Ltr Included in Attachment 1 | Forwards LER 98-010-00,documenting Event That Occurred at Unit 2 on 980508.Util Commitments Made within Ltr Included in Attachment 1 | 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition |
| 05000336/LER-1998-010-01, :on 980508,discovered That Encl Bldg Surveillance Procedure Did Not Adequately Verify Leak Integrity of Encl B.Caused by Inadequate Evaluation of Phenomenon Described in NRC Info Notice.Amend Implemented |
- on 980508,discovered That Encl Bldg Surveillance Procedure Did Not Adequately Verify Leak Integrity of Encl B.Caused by Inadequate Evaluation of Phenomenon Described in NRC Info Notice.Amend Implemented
| 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.73(a)(2)(viii) |
| 05000423/LER-1998-010, :on 980211,failed to Meet TS Definition of Analog Channel Operational Test of Unit 1 Main Stack Noble Gas Activity Monitor.Caused by Inadequate Verification of Compliance W/Unit 3 Ts.Procedures Will Be Revised |
- on 980211,failed to Meet TS Definition of Analog Channel Operational Test of Unit 1 Main Stack Noble Gas Activity Monitor.Caused by Inadequate Verification of Compliance W/Unit 3 Ts.Procedures Will Be Revised
| 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(iii) 10 CFR 50.73(a)(2)(viii) |
| 05000336/LER-1998-011-01, :on 980519,determined That Valves Had Been Closing Completely Under No Flow Conditions.Caused by Improper Valve Setup & Failure to Verify Adequate Valve Closure.Valves Disassembled |
- on 980519,determined That Valves Had Been Closing Completely Under No Flow Conditions.Caused by Improper Valve Setup & Failure to Verify Adequate Valve Closure.Valves Disassembled
| 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(x) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2)(viii) |
| 05000336/LER-1998-011, Forwards LER 98-011-00,documenting Event That Occurred at Unit 2 on 980502.Util Commitments Made within Ltr Included in Attachment 1 | Forwards LER 98-011-00,documenting Event That Occurred at Unit 2 on 980502.Util Commitments Made within Ltr Included in Attachment 1 | 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition |
| 05000423/LER-1998-011, :on 980218,failed to Adequately Test Turbine Driven Auxiliary Feedwater Pump.Caused by Inadequate Interface Among Organization.Tdafw Pump Will Be Tested |
- on 980218,failed to Adequately Test Turbine Driven Auxiliary Feedwater Pump.Caused by Inadequate Interface Among Organization.Tdafw Pump Will Be Tested
| 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications |
| 05000423/LER-1998-012-01, Forwards LER 98-012-01,documenting Addl Info Pertaining to Condition That Was Determined Reportable on 980218. Attachment 1 Contains Commitments in Response to Event | Forwards LER 98-012-01,documenting Addl Info Pertaining to Condition That Was Determined Reportable on 980218. Attachment 1 Contains Commitments in Response to Event | 10 CFR 50.73(a)(2)(v), Loss of Safety Function |
| 05000336/LER-1998-012, Forwards LER 98-012-00,re Event Which Occurred at Millstone Unit 2 on 980521.Commitments Made within Ltr,Encl | Forwards LER 98-012-00,re Event Which Occurred at Millstone Unit 2 on 980521.Commitments Made within Ltr,Encl | 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition |
| 05000423/LER-1998-012, :on 980218,potential Failure of Rhrps Due to Loss of Mim Flow Protection,Was Reported.Caused by Lack of Documented Review & Analysis of Historical Design Deficiency.Performed DCR M3-98013 |
- on 980218,potential Failure of Rhrps Due to Loss of Mim Flow Protection,Was Reported.Caused by Lack of Documented Review & Analysis of Historical Design Deficiency.Performed DCR M3-98013
| 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(iv), System Actuation 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2)(viii) |
| 05000336/LER-1998-012-01, :on 980521,nonconservative Assumptions in Facility Loss of Normal FW Analysis Was Noted.Caused by Incorrect Calculation of SG Inventory During Lonf Event. Reanalysis of FSAR Loss of Normal FW Analysis Was Completed |
- on 980521,nonconservative Assumptions in Facility Loss of Normal FW Analysis Was Noted.Caused by Incorrect Calculation of SG Inventory During Lonf Event. Reanalysis of FSAR Loss of Normal FW Analysis Was Completed
| 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition |
| 05000336/LER-1998-013, Forwards LER 98-013-00,re Event Which Occurred at Millstone Unit 2 on 980526.Commitments Made within Ltr,Encl | Forwards LER 98-013-00,re Event Which Occurred at Millstone Unit 2 on 980526.Commitments Made within Ltr,Encl | 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition |
| 05000336/LER-1998-013-01, :on 980526,shutdown Cooling Sys Was Over Pressurized by Inadvertent Hpsip Start.Caused by Inadequate Evaluation in Original Plant Design.Appropriate Actions Were Taken to Ensure Sys Complies W/Design & Licensing Basis |
- on 980526,shutdown Cooling Sys Was Over Pressurized by Inadvertent Hpsip Start.Caused by Inadequate Evaluation in Original Plant Design.Appropriate Actions Were Taken to Ensure Sys Complies W/Design & Licensing Basis
| 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition 10 CFR 50.73(a)(2)(viii) |