ML14086A059

From kanterella
Revision as of 01:45, 2 July 2018 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search
3/18/14 Summary of Public Meeting to Discuss the 2013 Perry End-of-Cycle Performance Assessment
ML14086A059
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 03/26/2014
From: Kunowski M A
NRC/RGN-III/DRP/B5
To:
FirstEnergy Nuclear Operating Co
References
Download: ML14086A059 (4)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE RD. SUITE 210 LISLE, IL 60532-4352 March 26, 2014

LICENSEE: FirstEnergy Nuclear Operating Company FACILITY: Perry Nuclear Power Plant

SUBJECT:

SUMMARY OF THE MARCH 18, 2014, PERRY PUBLIC MEETING On March 18, 2014, the U.S. Nuclear Regulatory Commission (NRC) held a public meeting at the Quail Hollow Resort in Painesville, Ohio, to discuss the 2013 annual assessment results for Perry. Enclosure 1 is a list of attendees for the meeting. A copy of the slides used by the NRC's staff during the meeting is located in ADAM S at Accession Number ML14079A091.

At the meeting, the NRC provided an overview of the reactor oversight program, the results of the 2013 annual assessment for Perry, and the NRC's inspection plans for 2014. The NRC's presentation was followed by statements from the Perry Site Vice-President and the Director of Site Operations which included information on the performance and accomplishments for 2013, the plant priorities for 2014, a 40-million dollar financial commitment to post-Fukushima efforts, the continued focus on improving occupational radiation safety, and on the planning for the 2015 refueling outage. Cynthia Pederson, the Regional Administrator for the NRC's Region III Office, acknowledged the information provided by the Perry officials and emphasized the importance of Perry continuing in 2014 the improvement in performance seen in 2013 that resulted in the NRC moving Perry from the Degraded Cornerstone Colum n (Column 3) of the NRC's Action Matrix to the Licensee Response Column (Column 1).

After the business part of the meeting ended, NRC and Perry representatives listened to comments and attempted to address several questions from the public. The questions were related to tritium releases at Perry, the number and manufacturer of the spent fuel dry cask storage units used at Perry, an overview of post-Fukushima efforts taken by Perry, and the use by Perry of a local vendor for transfer of radioactively contaminated material. NRC representatives provided additional information to a member of the public after the meeting.

/RA/______________________

Michael A. Kunowski, Chief Branch 5

Division of Reactor Projects Docket No. 50-440 License No. NPF-58

Enclosure:

Meeting Attendance List

cc w/encl: Distribution via List Serv TM PERRY 2013 PERFORMANCE ASSESSMENT MEETING March 18, 2014 MEETING ATTENDANCE LIST NRC Attendees

Cynthia Pederson, Regional Administrator Anne Boland, Director, Division of Reactor Projects Billy Dickson, Chief, Health Physics and Incident Response Branch Mark Marshfield, Perry Senior Resident Inspector Jim Nance, Perry Resident Inspector Diane Flowers, Perry Office Administrative Assistant Prema Chandrathil, Public Affairs Officer Michael Kunowski, Chief, Branch 5, Division of Reactor Projects FirstEnergy Nuclear Operating Company Attendees

Ernest Harkness, Perry Site Vice-President David Hamilton, Perry Director of Site Operations Other Perry Plant/FirstEnergy Employees

Members of the Public

Ed Klco, Mayor, North Perry Village Connie Kline, Ohio CARE - Citizens Against a Radioactive Environment Janet Jodlowski, Ohio CARE

John Laituri

Milly Laituri

Enclosure March 26, 2014 LICENSEE: FirstEnergy Nuclear Operating Company FACILITY: Perry Nuclear Power Plant

SUBJECT:

SUMMARY OF THE MARCH 18, 2014, PERRY PUBLIC MEETING On March 18, 2014, the U.S. Nuclear Regulatory Commission (NRC) held a public meeting at the Quail Hollow Resort in Painesville, Ohio, to discuss the 2013 annual assessment results for Perry. is a list of attendees for the meeting. A copy of the slides used by the NRC's staff during the meeting is located in ADAMS at Accession Number ML14079A091.

At the meeting, the NRC provided an overview of the reactor oversight program, the results of the 2013 annual assessment for Perry, and the NRC's inspection plans for 2014. The NRC's presentation was followed by statements from the Perry Site Vice-President and the Director of Site Operations which included information on the performance and accomplishments for 2013, the plant priorities for 2014, a 40-million dollar financial commitment to post-Fukushima efforts, the continued focus on improving occupational radiation safety, and on the planning for the 2015 refueling outage. Cynthia Pederson, the Regional Administrator for the NRC's Region III Office, acknowledged the information provided by the Perry officials and emphasized the importance of Perry continuing in 2014 the improvement in performance seen in 2013 that resulted in the NRC moving Perry from the Degraded Cornerstone Column (Column 3) of the NRC's Action Matrix to the Licensee Response Column (Column 1).

After the business part of the meeting ended, NRC and Perry representatives listened to comments and attempted to address several questions from the public. The questions were related to tritium releases at Perry, the number and manufacturer of the spent fuel dry cask storage units used at Perry, an overview of post-Fukushima efforts taken by Perry, and the use by Perry of a local vendor for transfer of radioactively contaminated material. NRC representatives provided additional information to a member of the public after the meeting.

/RA/______________________

Michael A. Kunowski, Chief Branch 5

Division of Reactor Projects Docket No. 50-440 License No. NPF-58

Enclosure:

Meeting Attendance List cc w/encl: Distribution via List Serv TM DISTRIBUTION

See next page DOCUMENT NAME: Summary of the March 18, 2014, Perry Public Meeting Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII NAME MKunowski DATE 03/26/14 OFFICIAL RECORD COPY Letter to FirstEnergy Nuclear Operating Company for Michael Kunowski dated March 26, 2014

SUBJECT:

SUMMARY OF THE MARCH 18, 2014, PERRY PUBLIC MEETING DISTRIBTUION

Ernesto Quinones RidsNrrPMPerry Resource RidsNrrDorlLpl3-2 Resource

RidsNrrDirsIrib Resource Cynthia Pederson Darrell Roberts Steven Orth

Allan Barker

Carole Ariano Linda Linn DRPIII DRSIII Patricia Buckley ROPassessment.Resource@nrc.gov