Summary of Public Meeting with Firstenergy Nuclear Operating Co. to Discuss the 2007 Perry End-of-Cycle Performance Assessment
ML081150605
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 04/24/2008
From: Jamnes Cameron
NRC/RGN-III/DRP/B6
To:
References
Download: ML081150605 (46)


Text

April 24, 2008 LICENSEE: FirstEnergy Nuclear Operating Company FACILITY: Perry Nuclear Power Station

SUBJECT:

SUMMARY

OF THE APRIL 15, 2008, PUBLIC MEETING TO DISCUSS THE 2007 PERRY END-OF-CYCLE PERFORMANCE ASSESSMENT On April 15, 2008, the Nuclear Regulatory Commission (NRC) held a public meeting at the Quail Hollow Resort in Painesville, Ohio. The meeting was between NRC management and FirstEnergy Nuclear Operating Company representatives to discuss the NRCs 2007 End-of Cycle Assessment of the Perry Nuclear Power Stations safety performance. The results of that assessment were discussed in a letter to the licensee dated March 3, 2008 (ADAMS ML080600303.

The NRC opened the meeting with an overview of the NRC mission, the NRCs Reactor Oversight Process (ROP), the national ROP results, and the Action Matrix. This was followed by a summary of the NRCs assessment of Perry performance in 2007. The slides used during the meeting and a list of principal meeting attendees can be found in the attached enclosures.

Following the NRCs presentation, the licensee presented its perspective on the assessment.

The licensee acknowledged that the NRCs assessment was accurate and provided an overview of actions it is taking to address human performance, equipment issues, and the effectiveness of its corrective action program. The licensees meeting presentation handout is attached as an enclosure to this letter.

At the end of the meeting, members of the public were given the opportunity to ask questions of NRC officials.

/RA/

Jamnes L. Cameron, Chief Projects Branch 6 Division of Reactor Projects Docket No. 50-440 License No. NPF-58

Enclosures:

As stated DISTRIBUTION:

See next page

Memo to FirstEnergy Nuclear Operating Company from J. Cameron dated April 24, 2008

SUBJECT:

SUMMARY

OF THE APRIL 15, 2008, PUBLIC MEETING TO DISCUSS THE 2007 PERRY END-OF-CYCLE PERFORMANCE ASSESSMENT cc w/encls: J. Hagan, President and Chief Nuclear Officer - FENOC J. Lash, Senior Vice President of Operations and Chief Operating Officer - FENOC D. Pace, Senior Vice President, Fleet Engineering - FENOC J. Rinckel, Vice President, Fleet Oversight - FENOC Director, Fleet Regulatory Affairs - FENOC Manager, Fleet Licensing - FENOC Manager, Site Regulatory Compliance - FENOC D. Jenkins, Attorney, FirstEnergy Corp.

Public Utilities Commission of Ohio C. OClaire, Chief, Ohio Emergency Management Agency R. Owen, Ohio Department of Health President, Geauga County Board Director, Department of Emergency Services Geauga County Sheriff President, Ashtabula County Board of Commissioners Ashtabula County Sheriff Director, Ashtabula County Emergency Management Agency Mayor, Village of Genoa Genoa Village Administrator President, Lake County Board of Commissioners Lake County Sheriff Painesville City Manager Lake County Administrator Director, Lake County Emergency Management Agency President, Village of Fairport Harbor Mayor, City of Eastlake Mayor, City of Wickliffe President, Geneva City Council City Manager, Geneva Mayor, City of Kirtland Mayor, City of Mentor City Manager, Mentor Mayor, City of Mentor on the Lake Administrative Director Mayor, City of Willoughby Hills Mayor, City of Willoughby Mayor, City of Willowick Mayor, Village of Madison Village Administrator, Village of Madison Chairman, Board of Madison Township Trustees Mayor, Village of Kirtland Hills Mayor, Village of Geneva-on-the-Lake

Memo to FirstEnergy Nuclear Operating Company from J. Cameron dated April 24, 2008

SUBJECT:

SUMMARY

OF THE APRIL 15, 2008, PUBLIC MEETING TO DISCUSS THE 2007 PERRY END-OF-CYCLE PERFORMANCE ASSESSMENT (Distribution Continued) cc w/encls: Mayor, Lakeline Village Mayor, Village of Timberlake Mayor, Village of Grand River G. Mortensen, INPO

LICENSEE: FirstEnergy Nuclear Operating Company FACILITY: Perry Nuclear Power Station

SUBJECT:

SUMMARY

OF THE APRIL 15, 2008, PUBLIC MEETING TO DISCUSS THE 2007 PERRY END-OF-CYCLE PERFORMANCE ASSESSMENT On April 15, 2008, the Nuclear Regulatory Commission (NRC) held a public meeting at the Quail Hollow Resort in Painesville, Ohio. The meeting was between NRC management and FirstEnergy Nuclear Operating Company representatives to discuss the NRCs 2007 End-of Cycle Assessment of the Perry Nuclear Power Plant's safety performance. The results of that assessment were discussed in a letter to the licensee dated March 3, 2008 (ADAMS ML080600303.

The NRC opened the meeting with an overview of the NRC mission, the NRCs Reactor Oversight Process (ROP), the national ROP results, and the Action Matrix. This was followed by a summary of the NRCs assessment of Perry performance in 2007. The slides used during the meeting and a list of principal meeting attendees can be found in the attached enclosures.

Following the NRCs presentation, the licensee presented its perspective on the assessment.

The licensee acknowledged that the NRCs assessment was accurate and provided an overview of actions it is taking to address human performance, equipment issues, and the effectiveness of its corrective action program. The licensees meeting presentation handout is attached as an enclosure to this letter.

At the end of the meeting, members of the public were given the opportunity to ask questions of NRC officials.

Jamnes L. Cameron, Chief Projects Branch 6 Division of Reactor Projects Docket No. 50-440 License No. NPF-58

Enclosures:

As stated DISTRIBUTION:

See next page DOCUMENT NAME: G:\Branch TSS\ALL EOC\EOC CY 2007\Meeting Letters - Notices\Perry EOC Meeting Summary Letter.doc G Publicly Available G Non-Publicly Available G Sensitive G Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII NAME GWright:dtp JCameron DATE 04/23/08 04/24/08 OFFICIAL RECORD COPY

Memo to FirstEnergy Nuclear Operating Company from J. Cameron dated April 24, 2008

SUBJECT:

SUMMARY

OF THE APRIL 15, 2008, PUBLIC MEETING TO DISCUSS THE 2007 PERRY END-OF-CYCLE PERFORMANCE ASSESSMENT DISTRIBUTION:

TJW2 CSG1 TEB RidsNrrDirslpab JLC1 MAS JKH3 KGO RML2 SRI Perry DRPIII DRSIII PLB1 TXN

LIST OF ATTENDEES Nuclear Regulatory Commission B. Mallett, Deputy Executive Director Reactor and Preparedness Programs J. Caldwell, Regional Administrator J. Cameron, Branch Chief M. Franke, Senior Resident Inspector M. Wilk, Resident Inspector G. Wright, Project Engineer C. Goodwin, Project Manager V. Mitlyng, Public Affairs Officer P. Chandrithil, Public Affairs Officer FENOC Attendees M. Bezilla, Perry Site Vice President F. Cayia, Director, Performance Improvement K. Krueger, Director, Site Operations J. Grabnar, Director, Engineering Other Attendees L. Green, Lake County Emergency Management R. Leidy, Ohio Department of Health J. Wills, Ohio Department of Public Safety Enclosure

Enclosure Enclosure Enclosure Enclosure Enclosure Enclosure Enclosure Enclosure Enclosure Enclosure Enclosure Enclosure Enclosure Enclosure Enclosure Enclosure Enclosure Enclosure Enclosure Enclosure Enclosure Enclosure Enclosure Enclosure Enclosure Enclosure Enclosure Enclosure Enclosure Enclosure Enclosure Enclosure Enclosure Enclosure Enclosure Enclosure Enclosure Enclosure Enclosure Enclosure