UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 January 22, 2009 LICENSEE: FirstEnergy Nuclear Operating Company FACILITIES: Beaver Valley, Davis-Besse, and Perry Nuclear Power Plants

SUBJECT:

SUMMARY

OF THE JANUARY 14, 2009, PUBLIC MEETING TO DISCUSS FENOC FLEET PERFORMANCE On January 14, 2009, the Nuclear Regulatory Commission (NRC) held a public meeting at the Perry Schools Manchester West Training Center, Perry, Ohio. The meeting was between NRC Regions I and III, and FirstEnergy Nuclear Operating Company (FENOC) management to discuss fleet performance. The meeting notice and licensee presentation can be found in the Agencywide Documents Access and Management System (ADAMS) as ML083590148 and ML090210169, respectively. A list of principal NRC and licensee meeting participants is enclosed.

The NRC began the meeting with a brief introduction, then FENOC management discussed individual plant performance, their fleet-wide approach to sustaining performance improvements, and improving site performance at the Beaver Valley, Davis-Besse, and Perry Nuclear Power Plants. At the end of the meeting, members of the public were given the opportunity to ask questions of NRC officials.

The meeting provided a useful forum to discuss common themes at the FENOC plants with the NRC Regions and the Office of Nuclear Reactor Regulation. The meeting concluded with a discussion of plans to continue these meetings involving the NRC regions and program offices and all plants in the FENOC fleet on an annual basis.

/RA/

Jamnes L. Cameron, Chief Branch 6 Division of Reactor Projects Docket Nos. 50-334, 50-412, 50-346, and 50-440 License Nos. DPR-66, NPF-73, NPF-3, NPF-58

Enclosure:

As Stated DISTRIBUTION:

See next page

LICENSEE: FirstEnergy Nuclear Operating Company FACILITIES: Beaver Valley, Davis-Besse, and Perry Nuclear Power Plants

SUBJECT:

SUMMARY

OF THE JANUARY 14, 2009, PUBLIC MEETING TO DISCUSS FENOC FLEET PERFORMANCE On January 14, 2009, the Nuclear Regulatory Commission (NRC) held a public meeting at the Perry Schools Manchester West Training Center, Perry, Ohio. The meeting was between NRC Regions I and III, and FirstEnergy Nuclear Operating Company (FENOC) management to discuss fleet performance. The meeting notice and licensee presentation can be found in the Agencywide Documents Access and Management System (ADAMS) as ML083590148 and ML090210169, respectively. A list of principal NRC and licensee meeting participants is enclosed.

The NRC began the meeting with a brief introduction, then FENOC management discussed individual plant performance, their fleet-wide approach to sustaining performance improvements, and improving site performance at the Beaver Valley, Davis-Besse, and Perry Nuclear Power Plants. At the end of the meeting, members of the public were given the opportunity to ask questions of NRC officials.

The meeting provided a useful forum to discuss common themes at the FENOC plants with the NRC Regions and the Office of Nuclear Reactor Regulation. The meeting concluded with a discussion of plans to continue these meetings involving the NRC regions and program offices and all plants in the FENOC fleet on an annual basis.

Jamnes L. Cameron, Chief Branch 6 Division of Reactor Projects Docket Nos. 50-334, 50-412, 50-346, and 50-440 License Nos. DPR-66, NPF-73, NPF-3, NPF-58

Enclosure:

As Stated DISTRIBUTION:

See next page DOCUMENT NAME: G:\FENOC\2009 All FENOC public meeting.doc G Publicly Available G Non-Publicly Available G Sensitive G Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII NAME RMurray:dtp JCameron DATE 01/22/09 01/22/09 OFFICIAL RECORD COPY

PRINCIPAL MEETING PARTICIPANTS Nuclear Regulatory Commission S. Collins, Regional Administrator, RI J. Caldwell, Regional Administrator, RIII J. Wiggins, Deputy Director, Office of Nuclear Reactor Regulation (NRR)

G. Shear, Deputy Director, Division of Reactor Projects, RIII Robert Nelson, Deputy Director, Division of Reactor Licensing, NRR D. Werkheiser, SRI, Beaver Valley M. Franke, SRI, Perry J. Rutkowski, SRI, Davis-Besse FirstEnergy Nuclear Operating Company J. Hagan, President and Chief Nuclear Officer J. Lash, Senior Vice President and Chief Operating Officer D. Pace, Senior Vice President, Engineering K. Fili, Vice President, Fleet Oversight P. Harden, Vice President, Nuclear Support P. Sena, Site Vice President, Beaver Valley B. Allen, Vice President, Davis Besse M. Bezilla, Vice president, Perry G. Halnon, Dierector, Fleet Regulatory Affairs

Letter to FirstEnergy Nuclear Operating Company from J. Cameron dated January 22, 2009.

SUBJECT:

SUMMARY

OF THE JANUARY 14, 2009, PUBLIC MEETING TO DISCUSS FENOC FLEET PERFORMANCE cc w/encl:

J. Lash, Senior Vice President of Operations and Chief Nuclear Officer D. Pace, Senior Vice President, Fleet Engineering D. Jenkins, Attorney Manager, Fleet Licensing P. Harden, Vice President Nuclear Support K. Fili, Vice President, Fleet Oversight Gregory Halnon, Director, Fleet Regulatory Affairs C. OClaire, State Liaison to the NRC, State of Ohio Z. Clayton, EPA-DERR, State of Ohio Director, Utilities Department, Public Utilities Commission, State of Ohio R. Owen, Ohio Department of Health G. Mortensen, INPO The Honorable Dennis Kucinich B. Allen, Site Vice President Manager, Site Regulatory Compliance President, Lucas County Board of Commissioners President, Ottawa County Board of Commissioners Ottawa County Sheriff Director, Ottawa County EMA Lucas County Sheriff Director, Lucas County EMA Genoa Village Administrator Mayor of Clay Center Mayor of Elmore Mayor of Genoa Mayor of Oak Harbor Mayor of Toledo Mayor of Port Clinton Mayor of Marblehead Mayor of Rocky Ridge Village Administrator of Oak Harbor Mayor of Put-in-Bay M. Bezilla, Site Vice President Manager, Site Regulatory Compliance President, Geauga County Board Director, Department of Emergency Services Geauga County Sheriff President, Ashtabula County Board of Commissioners Ashtabula County Sheriff Director, Ashtabula County Emergency Management Agency President, Lake County Board of Commissioners Lake County Sheriff Painesville City Manager

(Distribution continued)

Lake County Administrator Director, Lake County Emergency Management Agency President, Village of Fairport Harbor Mayor, City of Eastlake Mayor, City of Wickliffe President, Geneva City Council City Manager, Geneva Mayor, City of Kirtland Mayor, City of Mentor City Manager, Mentor Mayor, City of Mentor on the Lake Administrative Director Mayor, City of Willoughby Hills Mayor, City of Willoughby Mayor, City of Willowick Mayor, Village of Madison Village Administrator, Village of Madison Chairman, Board of Madison Township Trustees Mayor, Village of Kirtland Hills Mayor, Village of Geneva-on-the-Lake Mayor, Lakeline Village Mayor, Village of Timberlake Mayor, Village of Grand River P. Sena, Site Vice President K. Ostrowski, Director, Site Operations E. Hubley, Director, Maintenance M. Manoleras, Director, Engineering R. Brosi, Director, Site Performance Improvement C. Keller, Manager, Site Regulatory Compliance M. Clancy, Mayor, Shippingport, PA D. Allard, Director, PADEP D. Hill, Chief, Radiological Health Program, State of West Virginia J. Lewis, Commissioner, Division of Labor, State of West Virginia W. Hill, Beaver County Emergency Management Agency J. Johnsrud, National Energy Committee, Sierra Club J. Powers, Director, PA Office of Homeland Security R. French, Director, PA Emergency Management Agency

Letter to FirstEnergy Nuclear Operating Company from J. Cameron dated January 22, 2009.

SUBJECT:

SUMMARY

OF THE JANUARY 14, 2009, PUBLIC MEETING TO DISCUSS FENOC FLEET PERFORMANCE DISTRIBUTION:

RidsNrrDirslpab Resource James Caldwell Mark Satorius Jared Heck Kenneth Obrien Allen Barker DRPIII DRSIII Patricia Buckley Tammy Tomczak ROPreports@nrc.gov RidsNrrPMPerry RidsNrrDorlLpI3-2 Thomas Wengert Tamara Bloomer RidsNrrDorlLpl3-2 RidsNrrPMDavisBesse Resource S. Collins, RA M. Dapas, DRA D. Lew, DRP J. Clifford, DRP R. Bellamy, DRP S. Barber, DRP C. Newport, DRP S. Williams, RI OEDO R. Nelson, NRR N. Morgan, NRR, PM R. Guzman, NRR Backup D. Werkheiser, Senior Resident Inspector D. Spindler, RI P. Garrett, Resident OA RIDSRGN1MAILCENTER RESOURCES