Notice of Violation from Insp on 980412-0523.Violation Noted:On 980402,licensee Did Not Have Adequate Procedure for Performing Activity That Affected Quality
ML20249A617
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 06/15/1998
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20249A616 List:
References
50-285-98-09, 50-285-98-9, NUDOCS 9806170150
Download: ML20249A617 (2)


Text

- - - - - - - _ _

ENCLOSURE 1 NOTICE OF VIOLATION I

i Omaha Public Power District Docket No.: 50-285 i Fort Calhoun Station License No.: DPR-40 During an NRC inspection conducted on April 12 through May 23,1998, one violation of NRC requirements was identi0ed. In accordance with the " General Statement of Policy and Procedure for NRC Enforcement Actions," NUREG-1600, the violation is listed below- .

i 10 CFR Part 50, Appendix B, Criterion V, states, in part, that activities affecting quality shall be prescribed by documented instructions, procedures, or drawings of a type appropriate to the circumstances and shall be accomplished in accordance with these instructions, procedures, or drawings.

Contrary to the above on April 2,1998, it was determined that the licensee did not have an adequate procedure for performing an activity that affected quality. Specifically, Procedure OP-3A, " Plant Shutdown," Revision 19, directed operators to use pressurizer steam space temperature indication to monitor plant cooldown when, in fact, pressurizer liquid space temperature should have been utilized. This resulted in operations personnel allowing reactor coolant system pressure to decrease below the minimum required pressure for maintaining net positive suction head for the operating reactor coolant pump.

This is a Severity Level IV violation (Supplement 1) (50-285/9809- 01).

Pursuant to the provisions of 10 CFR 2.201, Omaha Public Power District is hereby required to l submit a written statement or explanation to the U.S. Nuclear Regulatory Commission, ATTN: j Document Control Desk, Washington, D.C. 20555 with a copy to the Regional Adrainistrator, Region IV,611 Ryan Plaza Drive, Suite 400, Arlington, Texas 76011, and a copy to the NRC Resident inspector at the facility that is the subject of this Notice, within 30 days of the date of the letter transmitting this Notice of Violation (Notice). This reply should be clearly marked as a ,

" Reply to a Notice of Violation" and should include for each violation. (1) the reason for the l violation, or, if contested, the basis for disputing the violation or severity level, (2) the corrective ,

steps that have been taken and the results achieved, (3) the corrective steps that will be taken to i avoid further violations, and (4) the date when full compliance will be achieved. Your response may reference or include previous docketed correspondence, if the correspondence adequately addresses the required response. If an adequate reply is not received within the time specified in this Notice, an order or a Demand for Information may be issued as to why the license should not be modified, suspended, or revoked, or why such other action as may be proper should not be taken. Where good cause is shown, consideration will be given to extending the response

. time.

If you contest this enforcement action, you should also provide a copy of your response to the Director, Office of Enforcement, United States Nuclear Regulatory Commission, Washington, DC 20555-0001.

9906170150 990615 PDR ADOCK 05000205 G PDR

1 2

J Because your response will be placed in the NRC Public Document Room (PDR), to the extent possible, it should not include any personal privacy, proprietary, or safeguards information so that it can be placed in the PDR without redaction. If personal privacy or proprietary information is necessary to provide an acceptable response, then please provide a bracketed copy of your response that identifies the information that should be protected and a redacted copy of your response that deletes such information. If you request withholding of such material, you must specifically identify the portions of your response that you seek to have withheld and provide in detail the bases for your claim of withholding (e.g., explain why the disclosure of information will create an unwarranted invasion of personal privacy or provide the information required by 10 CFR 2.790(b) to support a request for withholding confidential commercial or financial i information). If safeguards information is necessary to provide an acceptable response, please provide the level of protection described in 10 CFR 73.21.