ML20211P344

From kanterella
Jump to navigation Jump to search
Insp Rept 50-298/99-08 on 990711-0821.No Violations Noted. Major Areas Inspected:Initiating Events,Mitigating Systems & Barrier Integrity
ML20211P344
Person / Time
Site: Fort Calhoun 
Issue date: 09/07/1999
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20211P334 List:
References
50-285-99-08, NUDOCS 9909130189
Download: ML20211P344 (8)


See also: IR 05000298/1999008

Text

.

a

-

ENCLOSURE

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

_

Docket No.:

50-285

License No.:

DPR-40

Report No.:

50-285/99-08

Licensee:

Omaha Public Power District

Facility:

Fort Calhoun Station

Location:

Fort Calhoun Station FC-2-4 Adm.

P.O. Box 399, Hwy. 75 - North of Fort Calhoun

Fort Calhoun, Nebraska

Dates:

July 11 through August 21,1999

i

inspectors:

W. Walker, Senior Resident inspector

l

V. Gaddy, Resident inspector

>

'

Approved By:

Charles S. Marschall, Chief, Project Branch C

ATTACHMENT:

Supplemental Information

,

i

t

9909130189 990907

PDR

ADOCK 05000285

O

PM

r

'

.

.

SUMMARY OF FINDINGS

Fort Calhoun Station

NRC Inspection Report 50-298/99-08 (DRP)

The report covers a 6-week period of resident inspection.

Cornerstone: Initiating Events

No findings.

Cornerstone: Mitigating Systems

No findings.

,

Cornerstone: Barrier Integrity

No findings.

i

i

4

i

I

f

.

Report Details

Summarv of Plant Status

The Fort Calhoun Station began this inspection period at 100 percent power and maintained

that level throughout the inspection period.

1.

REACTOR SAFETY

Cornerstones: Initiating Events, Mitigating Systems, Barrier integrity

1R03 Emeraent Work

.1

Diesel Generator

a.

Inspection Scope

inspectors observed emergent work associated with Diesel Generator 1.

b.

Observations and Findinas

On August 11,1999, Diesel Generator 1 was removed from service for monthly

surveillance testing. Prior to testing, a risk assessment was performed. This risk

assessment calculated the change in risk during diesel generator testing. During the

performance of the surveillance test, a metal temperature probe and its attached cable

were inadvertently inserted into the air intake fan that provided cooling to the electrical

generator windings portion of the diesel generator. The diesel generator was

immediately shut down and no abnormal indications were observed locally or in the

control room. The cable was found wrapped around the generator windings cooling fan

blades. The probe was destroyed and pieces were found at the bottom of the generator

windings. Maintenance personnel disassembled the housing around the generator

windings, performed a thorough inspection, and removed any loose parts from the

destruction of the metal temperature probe. Quality assurance personnel were present

during the inspection activities and verified that loose parts had been removed. A

surveillance test was performed on the diesel generator with no abnormal indications

observed and the diesel generator was declared operable.

The inspectors verified that the licensee had performed an additional risk assessment

associated with the repair activities and for other plant conditions. There were no

findings identified and documented during this inspection.

.2

Electrohydraulic Control Pumo Failure

a.

Inspection Scope

inspectors assessed the licensee control of risk associated with failure of

Electrohydraulic Control Pump EHC-38.

.

.g.

.b.

Observations and Findinas -

On August 12,'1999, Electrohydraulic Control Pump EHC-3B failed. Pump EHC-3A

- auto-started as designed. The failed pump was removed from service and sent offsite

for repairs. The pump was returned to service on August 15,1999. The licensee

i

performed maintenance on the failed pump as an emergent work activity, if the second

electrohydraulic control pump had failed, a turbine trip and a reactor trip would have

j

occurred. The inspectors asked if a risk assessment had been performed to evaluate

the new plant configuration. Licensee personnel indicated that their risk model did not

I

model turbine generator and auxiliaries because a turbine trip would not contribute

significantly to an increase in core damage frequency when considered in isolation.

j

The inspectors also noted, however, that, during the time the electrohydraulic control

. pump was out of service, plant staff also took other components out of service for

planned testing. Specifically, on August 13,1999, quarterly inservice testing was

conducted on one train of emergency core cooling. The testing required that plant staff

individually render the low pressure spray injection, the high pressure spray injection,

and the containment spray pumps inoperable. These systems can be important, from a

risk perspective, in mitigating reactor transients. For example, in the event auxiliary

feedwater was lost during a transient, the emergency core cooling system would be

necessary to provide feed and bleed capability and high pressure recirculation to

mitigate a transient. By not performing a risk assessment for the planned activities and

!

taking into consideration the increased likelihood of a reactor transient as a result of the

degraded electrohydraulic control system, the totality of risk was not considered.

When failure of the remaining electrohydraulic control pump would have initisted a

transient (turbine / reactor trip), the licensee did not perform a risk assessment to

consider the total risk prior to removing from service emergency core cooling systema

credited for mitigating a transient. The NRC considered the increased risk from a

postulated failure of the second electrohydraulic pump to be low, but noted that the lack

of a risk assessment that considered both planned and emergent activities by the

licensee was a weakness.

1R04 Eauipment Alianments

a.

Insoection Scoce

During this inspection period, the inspectors performed a partial walkdown to verify

containment integrity using Operating Instruction Ol-CO-5, " Containment Integrity."

b.-

Observations and Findinas

All containment isolation valves and electrical and mechanical penetrations were in the

position required by the procedure. The administrative procedure indicated that the

nitrogen pressure in certain penetrations should be greater than 15 psig. The inspector

noted three penetrations that were below this value. Two of the three had maintenance

requests written. The inspector informed the licensee of the remaining penetration and

a maintenance request was written. During discussions with the system engineer, the

f

.

.

-3-

,

1

inspectors learned that the purpose of the nitrogen pressure was to keep air out of the

penetration, preventing the formation of corrosion. The nitrogen pressure was not

needed for operability. The inspector learned that all penetrations would be tested and

repaired during the upcoming outage. There were no findings identified and

)

documented during this inspection.

l

1R05 Fire Protection

a.

Inspection Scoce

The inspectors verified contingencies and compensatory measures during maintenance

i

on fire protection equipment.

b.

Observations and Findinas

Throughout this inspection period, the licensee performed preventive and corrective

maintenance on fire protection deluge valves throughout the plant. The required various

parts of the fire protection system were to be removed from service. The inspectors

4

verified that proper contingencies were in place and that fire watches had been

established. Additionally, combustibles were adequately controlled and fire protection

system testing was performed as required. There were no findings identified and

documented during this inspection.

1R09 Inservice Testina

a.

insoo.quw. Scope

On Ja 20,1999, the inspectors observed portions of Surveillance Test IC-ST-IA-3009,

" Operability Test of IA-YCV-1045-C and Close Stroke Test of YCV-1045."

b.

Observations and Findinas

Testing was adequate to verify compliance with code requirements. All components

met the acceptance criteria. There were no findings identified and documented during

this inspection.

1R12 Maintenance Rule imolementation

a.

inspection Scope

The inspectors verified proper implementation of the maintenance rule for diesel

generator maintenance,

b.

Observations and Findinas

On August 12,1999, prior to completion of the monthly diesel generator testing, Diesel

Generator 1 was shut down when a temperature probe was inserted in the generator

cooling fan. Diesel Generator 1 remained inoperable. The inspectors used the

!

i

g

!

..

'

-4-

maintenance rule field flow chart and determined that the licensee properly dispositioned

'

the failures. There were no findings identified and documented during this inspection.

1R15' Operability Evaluations

a.

Inspection Scope

l

The inspectors reviewed the operability evaluations associated with the following

j

condition reports:

CR 19901103, " Ventilation Requirements for Safety injection Pump Rooms not

l

in Compliance with Current Basis for Safety injection Room Heating Ventilation

and Air Conditioning Flow Rates and Heat Load," and

CR 199901340, "PORV/ Safety Valve Tailpipe Temperature Circuitry Check."

!

b.

Observations and Findinas

There were no findings identified and documented during this inspection.

1R19 Postmaintenance Testina

i

l

a.

Inspection Scope

!

l

The inspectors observed postmaintenance testing on Diesel Generator 1 and Raw

l

Water Pump AC-100.

!

I

b.

Observations and Findinas

l

The tests were performed correctly and demonstrated that the equipment was functional

l

and operable. There were no findings identified and documented during this inspection.

i

l

1R22 Surveillance Testina

a.

Inspection Scope

,

<

The inspectors observed performance of the following surveillance tests:

l

Surveillance Test Procedure IC-ST-VA-0028, " Verification of Safety injection

i

Pump Room Filter Unit Flow," Revision 2,

Surveillance Test Procedure IC-ST-IA-3009, " Operability Test of IA-YCV-1045C

l

and Close Stroke Test of YCV-1045," and

OP-ST-DG-0002, " Diesel Generator 2 Check."

l

_

.

.

5

b.

Observations and Findinas

The inspectors noted that surveillance tests ensured equipment operability and

demonstrated compliance with Technical Specification requirements. Operations,

engineering, and maintenance personnel were all involved in prejob briefs and testing.

Equipment used was properly calibrated and testing components were returned to their.

j

required position to maintain operability. There were no findings identified and

j

- documented during this inspection.

'

4.

OTHER ACTIVITIES

40A5 Exit Meetina Summary

The inspectors presented the inspection results to members of licensee management at

the conclusion of the inspection of August 20,1999. The licensee acknowledged the

.

findings presented. The licensee did not consider any material examined during the

I

inspection proprietary.

PARTIAL LIST OF PERSONS CONTACTED

Licensee

R. Clemens, Maintenance Manager

)

M. Core, Manager, System Engineering

S. Gambhir, Division Manager, Nuclear Operations

J. Gasper, Manager, Nuclear Projects

B. Hansher, Supervisor, Station Licensing

R. Short, Assistant Plant Manager -

J. Solymossy, Manager, Fort Calhoun Station

J. Spilker, Manager, Corrective Action Group

D. Spires, Manager, Quality Assurance, Quality Control

j

l

,

L_

.~

.

6-

LIST OF BASELINE INSPECTIONS PERFORMED

The following inspectable-area procedures were used to perform inspections during the report

period. Documented findings are contained in the body of the report.

Inspection Procedure

Number

He

Reoort Section

71111-03

Emergency Work

1R03

71111-04

Equipment Alignment

1R04

71111-05

Fire Protection

1R05

4

71111-09

Inservice Testing of Pumps and Valves

1R09

71111-12

Maintenance Rule implementation

1R12

71111-15

Operability Evaluations

1R15

<

71111-22

Surveillance Testing

1R22

(none)

. Management Meetings

40A5

,

a>