|
---|
Category:INSPECTION REPORT
MONTHYEARIR 05000285/20240032024-10-29029 October 2024 NRC Inspection Report 05000285/2024003 IR 05000285/20240022024-08-21021 August 2024 NRC Inspection Report 05000285/2024002 IR 05000285/20240012024-06-0505 June 2024 NRC Inspection Report 05000285/2024001 IR 05000285/20230062023-12-21021 December 2023 NRC Inspection Report 05000285/2023006 IR 05000285/20230052023-11-0202 November 2023 NRC Inspection Room 05000285/2023005 IR 05000285/20230042023-09-13013 September 2023 NRC Inspection Report 05000285/2023-004 IR 05000285/20230032023-07-10010 July 2023 – NRC Inspection Report 05000285/2023003 IR 05000285/20230022023-06-0505 June 2023 NRC Inspection Report 05000285/2023002 IR 05000285/20230012023-02-24024 February 2023 NRC Inspection Report 05000285/2023001 IR 05000285/20220062023-01-0505 January 2023 NRC Inspection Report 05000285/2022-006 IR 05000285/20220052022-10-26026 October 2022 NRC Inspection Report 05000285/2022-005 IR 05000285/20220042022-09-14014 September 2022 NRC Inspection Report 05000285/2022004 IR 05000285/20220032022-06-15015 June 2022 NRC Inspection Report 05000285/2022003 IR 05000285/20220022022-04-28028 April 2022 NRC Inspection Report 050-00285/2022-002 IR 05000285/20220012022-02-25025 February 2022 NRC Inspection Report 050-00285/2022-001 IR 05000285/20210042021-11-18018 November 2021 NRC Inspection Report 050-00285/2021-004 IR 05000285/20210032021-08-11011 August 2021 NRC Inspection Report 050-00285/2021-003 (Public) IR 05000285/20210022021-05-0707 May 2021 NRC Inspection Report 05000285/2021002 IR 05000285/20210012021-02-17017 February 2021 NRC Inspection Report 05000285/2021001 IR 07200054/20204012020-10-29029 October 2020 Independent Spent Fuel Storage Installation Physical Security Requirements for Independent Spent Fuel Storage Installations Inspection Report 07200054/2020401 IR 05000285/20200022020-09-22022 September 2020 NRC Inspection Report 05000285/2020002 IR 05000285/20190052020-03-12012 March 2020 Independent Spent Fuel Storage Installation (ISFSI) - NRC Inspection Report 050-00285/2019-005 and 072-00054/2019-001 IR 05000206/20190042020-02-20020 February 2020 Independent Spent Fuel Storage Installation (ISFSI) - NRC Inspection Report 05000206/2019 004; 05000361/2019 007; 05000362/2019 007; and 07200054/2019-002 IR 05000285/20190042019-11-26026 November 2019 Inspection Report 050-00285/2019-004 IR 05000285/20190032019-09-13013 September 2019 NRC Inspection Report 050-00285/2019-003 IR 05000285/20190022019-07-23023 July 2019 NRC Inspection Report 05000285/2019002 IR 05000285/20194042019-07-11011 July 2019 NRC Security Baseline Inspection Report 05000285/2019404 IR 05000285/20194032019-06-0404 June 2019 NRC Security Baseline Inspection Report 05000285/2019403 IR 05000285/20190012019-02-12012 February 2019 NRC Inspection Report 050-00285/2019-001 IR 05000285/20180042018-11-19019 November 2018 Omaha Public Power District; Fort Calhoun Station - NRC Inspection Report 05000285/2018-004 IR 05000285/20180032018-09-27027 September 2018 NRC Inspection Report 05000285/2018003 IR 05000285/20184102018-05-17017 May 2018 NRC Security Baseline Inspection Report 05000285/2018410 IR 05000285/20184032018-05-17017 May 2018 NRC Physical Security Inspection Report 05000285/2018403 IR 05000285/20180012018-04-13013 April 2018 NRC Inspection Report 05000285/2018001 IR 05000285/20174032018-04-10010 April 2018 Cancellation of NRC Inspection Report 05000285/2017403 IR 05000285/20170112018-02-0101 February 2018 NRC Inspection Report 05000285/2017-011 IR 05000285/20170022017-11-0909 November 2017 NRC Inspection Reports 05000285/2017002 Through 05000285/2017007 IR 05000285/20170122017-11-0808 November 2017 NRC Inspection Report 05000285/2017-012 IR 05000285/20160062017-09-18018 September 2017 NRC Inspection Report 05000285/2016006 IR 05000285/20170092017-08-0404 August 2017 NRC Inspection Report 05000285/2017-009 IR 05000285/20174062017-06-26026 June 2017 NRC Security Baseline Inspection Report 05000285/2017406 IR 05000285/20174052017-06-26026 June 2017 NRC Security Inspection Report 05000285/2017405 and NRC Investigation Report 4-2015-030 IR 05000285/20170102017-06-15015 June 2017 Independent Spent Fuel Storage Installation Inspection Report 05000285/2017010 and 07200054/2017001 IR 05000285/20170012017-05-0808 May 2017 NRC Inspection Report 05000285/2017001 and 05000285/2017008 IR 05000285/20160042017-01-18018 January 2017 NRC Integrated Inspection Report 05000285/2016004 IR 05000285/20165012017-01-17017 January 2017 NRC Emergency Preparedness Annual Inspection Report 05000285/2016501 IR 05000285/20160032016-11-0808 November 2016 NRC Integrated Inspection Report Number 05000285/2016003 IR 05000285/20164042016-10-28028 October 2016 NRC Security Baseline Inspection Report 05000285/2016404 IR 05000285/20160082016-09-22022 September 2016 NRC Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications Baseline Inspection Report 05000285/2016008 IR 05000285/20160052016-09-12012 September 2016 Errata for Mid-Cycle Assessment Letter for Fort Calhoun Station (Report 05000285/2016005) 2024-08-21
[Table view] Category:NRC-GENERATED
MONTHYEARIR 05000285/19990101999-10-15015 October 1999 Insp Rept 50-285/99-10 on 990913-17.One NCV Noted.Major Areas Inspected:Mitigating Sys,Reactor Safety IR 05000285/19990091999-10-14014 October 1999 Insp Rept 50-285/99-09 on 990913-17.No Violations Noted. Major Areas Inspected:Effective Implementation of Protective Strategy When Required to Respond to Contingency Events ML20211P3441999-09-0707 September 1999 Insp Rept 50-298/99-08 on 990711-0821.No Violations Noted. Major Areas Inspected:Initiating Events,Mitigating Systems & Barrier Integrity IR 05000285/19990061999-09-0303 September 1999 Insp Rept 50-285/99-06 on 990809-12.No Violations Noted. Major Areas Inspected:Cornerstone Area of Reactor Safety, Emergency Preparedness.Insp Included Review of Licensee Program for Problem Identification & Resolution IR 05000285/19990071999-08-13013 August 1999 Insp Rept 50-285/99-07 on 990719-23.No Violations Noted. Major Areas Inspected:Accuracy & Operability of Radiation Monitoring Instrumentation Used for Protection of Occupational Workers IR 05000285/19990051999-07-19019 July 1999 Insp Rept 50-285/99-05 on 990601-0710.No Violations Noted. Major Areas Inspected:Broad Categories of Reactor Safety, Emergency Preparedness & Other Activities ML20195J2591999-06-11011 June 1999 Insp Rept 50-285/99-04 on 990425-0531.Noncited Violations Identified.Major Areas Inspected:Operations,Maint & Plant Support IR 05000285/19990031999-05-18018 May 1999 Insp Rept 50-285/99-03 on 990314-0424.Noncited Violations Noted.Major Areas Inspected:Operations,Maintenance, Engineering & Plant Support IR 05000285/19990021999-04-0202 April 1999 Insp Rept 50-285/99-02 on 990131-0313.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000285/19990011999-03-11011 March 1999 Insp Rept 50-285/99-01 on 990208-26.One Noncited Violation Was Identified.Major Areas Inspected:Evaluation of Cumulative Effect of Operator Workarounds at Plant Reactor Facility IR 05000285/19980191999-01-0808 January 1999 Insp Rept 50-285/98-19 on 981005-23 & 1211.Violations Noted. Major Areas Inspected:Corrective Action Program in Identifying Evaluation,Correcting & Preventing Problems That Affect Safe Operation of Facility IR 05000285/19980231999-01-0707 January 1999 Insp Rept 50-285/98-23 on 981108-1219.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000285/19980251998-12-30030 December 1998 Insp Rept 50-285/98-25 on 981130-1204.No Violations Noted. Major Areas Inspected:Licensee Emergency Preparedness Program IR 05000285/19980261998-12-17017 December 1998 Insp Rept 50-285/98-26 on 981131-1204.Deviations Noted. Major Areas Inspected:Plant Support Activities IR 05000285/19980131998-12-16016 December 1998 Insp Rept 50-285/98-13 on 981130-1204.No Violations Noted. Major Areas Inspected:Review Implementation of Liquid & Gaseous Radwaste Effluent Mgt Program IR 05000285/19980241998-11-20020 November 1998 Insp Rept 50-285/98-24 on 981102-06.Violations Noted.Major Areas Inspected:Plant Support IR 05000285/19980211998-11-13013 November 1998 Insp Rept 50-285/98-21 on 980927-1107.No Violations Noted. Major Areas Inspected:Operations,Maintenance,Engineering & Plant Support IR 05000285/19980171998-10-28028 October 1998 Insp Rept 50-285/98-17 on 980928-1002.No Violations Noted. Major Areas Inspected:Licensee Operator Requalification Program to Determine Whether Program Incorporated Appropriate Requirements IR 05000285/19980181998-10-0808 October 1998 Insp Rept 50-285/98-18 on 980831-0902.No Violations Noted. Major Areas Inspected:Changes to Fort Calhoun Station Radiological Emergency Action Levels IR 05000285/19980201998-10-0505 October 1998 Insp Rept 50-285/98-20 on 980816-0926.No Violations Noted. Major Areas Inspected:Operations,Maint & Engineering IR 05000285/19980221998-09-29029 September 1998 Insp Rept 50-285/98-22 on 980914-18.No Violations Noted. Major Areas Inspected:Routine,Announced Insp Reviewed Implementation of Radiological Environ & Meteorological Monitoring Programs IR 05000285/19980141998-08-28028 August 1998 Insp Rept 50-285/98-14 on 980705-0815.No Violations Noted. Major Areas Inspected:Operations,Maintenance,Engineering & Plant Support IR 05000285/19980121998-08-17017 August 1998 Insp Rept 50-285/98-12 on 980601-05 (on Site) & 980811 (in Ofc).One Noncited Violation Noted.Major Areas Inspected: Operations,Maint & Engineering.Root Cause Assessment, Performed as Result of 980527 Pump FW-10 Occurrence IR 05000285/19980151998-08-0606 August 1998 Insp Rept 50-285/98-15 on 980727-31.No Violations Noted. Major Areas Inspected:Testing & Maint,Protected Area Barrier & Detection Aids,Vital Area Barriers & Detection Aids, Security Event Logs & Security Training & Qualifications IR 05000285/19980101998-07-21021 July 1998 Insp Rept 50-285/98-10 on 970524-0704.Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000285/19980111998-07-0808 July 1998 Insp Rept 50-285/98-11 on 980521-0605.Violations Noted.Major Areas Inspected:Operations,Maint & Engineering ML20249A6181998-06-15015 June 1998 Insp Rept 50-285/98-09 on 980412-0523.Violations Noted:Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000285/19980061998-04-30030 April 1998 Insp Rept 50-285/98-06 on 980406-10.Violations Noted.Major Areas Inspected:Plant Support IR 05000285/19980051998-04-22022 April 1998 Insp Rept 50-285/98-05 on 980301-0411.Violations Noted. Major Areas Inspected:Operation,Maint,Engineering & Plant Support IR 05000285/19980011998-04-0606 April 1998 Insp Rept 50-285/98-01 on 980120-23 & 26-0306.No Violations Noted.Major Areas Inspected:Plant Support,Including Fire Protection Program IR 05000285/19980031998-03-27027 March 1998 Insp Rept 50-285/98-03 on 980223-27 & 0311-18.No Violations Identified.Major Areas Inspected:Licensee Physical Security Program,Access Authorization,Alarm Stations,Communications, Access Control of Event Logs & Mgt Support IR 05000285/19980021998-03-25025 March 1998 Insp Rept 50-285/98-02 on 980209-13 W/In Ofc Insp Until 980302.Violations Noted.Major Areas Inspected:Operations & Engineering IR 05000285/19980041998-03-12012 March 1998 Insp Rept 50-285/98-04 on 980118-0228.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000285/19970201998-02-27027 February 1998 Errata to Insp Rept 50-285/97-20 Issued on 980128.Noncited Violation Withdrawn.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support ML20199H8611998-01-28028 January 1998 Insp Rept 50-285/97-20 on 971207-980117.Violations Noted. Major Areas Inspected:Operation,Maint,Engineering & Plant Support IR 05000285/19970191997-12-19019 December 1997 Insp Rept 50-285/97-19 on 971026-1206.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000285/19970141997-11-18018 November 1997 Informs That Insp Rept 50-285/97-14 Has Been Cancelled.No Insp Rept Will Be Issued for Rept Number IR 05000285/19970171997-09-19019 September 1997 Insp Rept 50-285/97-17 on 970825-29.Violations Being Considered for Escalated Ea.Major Areas Inspected: Operations & Engineering IR 05000285/19970151997-08-15015 August 1997 Insp Rept 50-285/97-15 on 970615-0802.Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support Re Fire Sprinkler Sys IR 05000285/19970051997-08-0101 August 1997 Insp Rept 50-285/97-05 on 970714-18.No Violations Noted. Major Areas Inspected:Plant Support IR 05000285/19970121997-07-25025 July 1997 Paritally Withheld Insp Rept 50-285/97-12 on 970623-0710 (Ref 10CFR73.21).Violation Noted.Major Areas Inspected: Licensee Implementation of Land Vehicle Control Measures & Security Surveillance IR 05000285/19970041997-07-0202 July 1997 Insp Rept 50-285/97-04 on 970602-06.Unresolved Items Identified.Major Areas Inspected:Licensee Performance & Capabilities in Control Room Simulator,Technical Support Ctr,Operations Support Ctr & Emergency Operations Facility ML20141E2441997-06-27027 June 1997 Insp Rept 50-285/97-06 on 970414-18 & 0428-0502.Violations Noted.Major Areas Inspected:Current Effectiveness of Licensee Plant & Design Engineering Organizations to Respond to Routine & Reactive Site Activities IR 05000285/19970101997-06-20020 June 1997 Insp Rept 50-285/97-10 on 970504-0614.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support ML20149D5961997-06-17017 June 1997 Insp Rept 50-285/97-09 on 970423-0610.Violations Noted But Not Cited & Being Considered for Escalated Enforcement Action.Major Areas Inspected:Operations,Maintenance, Engineering & Mgt Meeting IR 05000285/19970081997-06-0505 June 1997 Insp Rept 50-285/97-08 on 970512-16.Violations Noted.Major Areas Inspected:Records & Repts,Testing & Maint,Barriers & Dection Aids,Assessment Aids,Alarm Stations,Communications, Security Sys Power Supply & Security ML20140C3301997-06-0404 June 1997 Insp Rept 50-285/97-11 on 970519-23.Violations Noted. Major Areas Inspected:Implementation & Maint of TS Program & Events Associated W/Control Rod Withdrawal to Bring Reactor to Critical Condition on 970512 IR 05000285/19970021997-06-0303 June 1997 Insp Rept 50-285/97-02 on 970505-09.Violations Noted.Major Areas Inspected:Licensees Emergency Preparedness Program. Emphasis Placed on Changes That Occurred Since Last Routine Emergency Prepardness Insp IR 05000285/19970011997-05-21021 May 1997 Insp Rept 50-285/97-01 on 970414-0506.No Violations Noted. Major Areas Inspected:Competency of Seven Senior Reactor Operator License Applicants for Issuance of Senior Reactor Operator Licenses ML20141H0811997-05-19019 May 1997 Insp Rept 50-285/97-07 on 970323-0503.Violations Noted. Major Areas Inspected:Operations,Maintenance,Engineering & Plant Support 1999-09-07
[Table view] Category:TEXT-INSPECTION & AUDIT & I&E CIRCULARS
MONTHYEARPNO-IV-99-048, on 991026,Fort Calhoun Station Operators Reported Alert Because 4160 Volt Vital Buses 1A4 Were Deenergized for Approx 2 Minutes.Electrical Maint Personnel Have Inspected Electrical Equipment Inside & Outside Plant1999-10-26026 October 1999 PNO-IV-99-048:on 991026,Fort Calhoun Station Operators Reported Alert Because 4160 Volt Vital Buses 1A4 Were Deenergized for Approx 2 Minutes.Electrical Maint Personnel Have Inspected Electrical Equipment Inside & Outside Plant IR 05000285/19990101999-10-15015 October 1999 Insp Rept 50-285/99-10 on 990913-17.One NCV Noted.Major Areas Inspected:Mitigating Sys,Reactor Safety IR 05000285/19990091999-10-14014 October 1999 Insp Rept 50-285/99-09 on 990913-17.No Violations Noted. Major Areas Inspected:Effective Implementation of Protective Strategy When Required to Respond to Contingency Events ML20211P3441999-09-0707 September 1999 Insp Rept 50-298/99-08 on 990711-0821.No Violations Noted. Major Areas Inspected:Initiating Events,Mitigating Systems & Barrier Integrity IR 05000285/19990061999-09-0303 September 1999 Insp Rept 50-285/99-06 on 990809-12.No Violations Noted. Major Areas Inspected:Cornerstone Area of Reactor Safety, Emergency Preparedness.Insp Included Review of Licensee Program for Problem Identification & Resolution IR 05000285/19990071999-08-13013 August 1999 Insp Rept 50-285/99-07 on 990719-23.No Violations Noted. Major Areas Inspected:Accuracy & Operability of Radiation Monitoring Instrumentation Used for Protection of Occupational Workers IR 05000285/19990051999-07-19019 July 1999 Insp Rept 50-285/99-05 on 990601-0710.No Violations Noted. Major Areas Inspected:Broad Categories of Reactor Safety, Emergency Preparedness & Other Activities ML20195J2591999-06-11011 June 1999 Insp Rept 50-285/99-04 on 990425-0531.Noncited Violations Identified.Major Areas Inspected:Operations,Maint & Plant Support IR 05000285/19990031999-05-18018 May 1999 Insp Rept 50-285/99-03 on 990314-0424.Noncited Violations Noted.Major Areas Inspected:Operations,Maintenance, Engineering & Plant Support PNO-IV-99-025, on 990513,possible Stop Work in Response to Contract Dispute Occurred.Union Maint Personnel May Participate,But Operators & Security Personnel Will Not Participate.No Press Release Is Planned1999-05-14014 May 1999 PNO-IV-99-025:on 990513,possible Stop Work in Response to Contract Dispute Occurred.Union Maint Personnel May Participate,But Operators & Security Personnel Will Not Participate.No Press Release Is Planned IR 05000285/19990021999-04-0202 April 1999 Insp Rept 50-285/99-02 on 990131-0313.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000285/19990011999-03-11011 March 1999 Insp Rept 50-285/99-01 on 990208-26.One Noncited Violation Was Identified.Major Areas Inspected:Evaluation of Cumulative Effect of Operator Workarounds at Plant Reactor Facility IR 05000285/19980191999-01-0808 January 1999 Insp Rept 50-285/98-19 on 981005-23 & 1211.Violations Noted. Major Areas Inspected:Corrective Action Program in Identifying Evaluation,Correcting & Preventing Problems That Affect Safe Operation of Facility ML20206R1601999-01-0808 January 1999 Notice of Violation from Insp on 981005-23 & 1211.Violations noted:licensee-established Measures Failed to Assure Prompt Identification & Effective Corrective Action to Address Potential for Core Reactivity Change IR 05000285/19980231999-01-0707 January 1999 Insp Rept 50-285/98-23 on 981108-1219.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000285/19980251998-12-30030 December 1998 Insp Rept 50-285/98-25 on 981130-1204.No Violations Noted. Major Areas Inspected:Licensee Emergency Preparedness Program IR 05000285/19980261998-12-17017 December 1998 Insp Rept 50-285/98-26 on 981131-1204.Deviations Noted. Major Areas Inspected:Plant Support Activities ML20198J2051998-12-17017 December 1998 Notice of Deviation from Insp on 981131-1204.Deviation Noted:Licensee Quality Assurance Dept Conducted Biennial Audits of All Transfer,Packaging & Transport Activities Involving Radioactive Matl IR 05000285/19980131998-12-16016 December 1998 Insp Rept 50-285/98-13 on 981130-1204.No Violations Noted. Major Areas Inspected:Review Implementation of Liquid & Gaseous Radwaste Effluent Mgt Program IR 05000285/19980241998-11-20020 November 1998 Insp Rept 50-285/98-24 on 981102-06.Violations Noted.Major Areas Inspected:Plant Support ML20195H8021998-11-20020 November 1998 Notice of Violation from Insp on 981102-06.Violation Noted: from 4:45 to 11:45 Am on 980423,room 13 on Elevation 989 Ft of Auxiliary Building Not Posted as Airborne Radioactivity Area When Sample Results Showed Excess Radioactivity IR 05000285/19980211998-11-13013 November 1998 Insp Rept 50-285/98-21 on 980927-1107.No Violations Noted. Major Areas Inspected:Operations,Maintenance,Engineering & Plant Support IR 05000285/19980171998-10-28028 October 1998 Insp Rept 50-285/98-17 on 980928-1002.No Violations Noted. Major Areas Inspected:Licensee Operator Requalification Program to Determine Whether Program Incorporated Appropriate Requirements IR 05000285/19980181998-10-0808 October 1998 Insp Rept 50-285/98-18 on 980831-0902.No Violations Noted. Major Areas Inspected:Changes to Fort Calhoun Station Radiological Emergency Action Levels IR 05000285/19980201998-10-0505 October 1998 Insp Rept 50-285/98-20 on 980816-0926.No Violations Noted. Major Areas Inspected:Operations,Maint & Engineering IR 05000285/19980221998-09-29029 September 1998 Insp Rept 50-285/98-22 on 980914-18.No Violations Noted. Major Areas Inspected:Routine,Announced Insp Reviewed Implementation of Radiological Environ & Meteorological Monitoring Programs IR 05000285/19980141998-08-28028 August 1998 Insp Rept 50-285/98-14 on 980705-0815.No Violations Noted. Major Areas Inspected:Operations,Maintenance,Engineering & Plant Support IR 05000285/19980121998-08-17017 August 1998 Insp Rept 50-285/98-12 on 980601-05 (on Site) & 980811 (in Ofc).One Noncited Violation Noted.Major Areas Inspected: Operations,Maint & Engineering.Root Cause Assessment, Performed as Result of 980527 Pump FW-10 Occurrence IR 05000285/19980151998-08-0606 August 1998 Insp Rept 50-285/98-15 on 980727-31.No Violations Noted. Major Areas Inspected:Testing & Maint,Protected Area Barrier & Detection Aids,Vital Area Barriers & Detection Aids, Security Event Logs & Security Training & Qualifications ML20236W2931998-07-29029 July 1998 Notice of Violation from Insp on 980606-10.Violation Noted: Licensee Did Not Take Dry Active Samples Annually.Dry Active Waste Stream Samples Were Collected in June 1995 & Aug 1997 IR 05000285/19980101998-07-21021 July 1998 Insp Rept 50-285/98-10 on 970524-0704.Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000285/19980111998-07-0808 July 1998 Insp Rept 50-285/98-11 on 980521-0605.Violations Noted.Major Areas Inspected:Operations,Maint & Engineering ML20236M7531998-07-0808 July 1998 Notice of Violation from Insp on 980521-0605.Violation Noted:On 980520,licensee Personnel Did Not Write Maint Work Document to Document Deficiency W/Valve FP-230 Following Manipulation of Valve ML20249A6181998-06-15015 June 1998 Insp Rept 50-285/98-09 on 980412-0523.Violations Noted:Major Areas Inspected:Operations,Maint,Engineering & Plant Support ML20249A6171998-06-15015 June 1998 Notice of Violation from Insp on 980412-0523.Violation Noted:On 980402,licensee Did Not Have Adequate Procedure for Performing Activity That Affected Quality PNO-IV-98-021A, on 980526,update to Loss of Offsite Power Made.Components Have Been Replaced & Sys Functioning Properly.Correction Should Be Made to Info in Original Pn. Nonvital Buses 1A1 & 1A2 Continuously Energized1998-05-26026 May 1998 PNO-IV-98-021A:on 980526,update to Loss of Offsite Power Made.Components Have Been Replaced & Sys Functioning Properly.Correction Should Be Made to Info in Original Pn. Nonvital Buses 1A1 & 1A2 Continuously Energized ML20249C1431998-05-24024 May 1998 Notice of Violation from Insp on 980415-24.Violation Noted: Inspectors Identified That Licensee Had Not Submitted in 1984 & 1994 Relief Requests for Code Class Welds That Did Not Receive Full Exam Coverage During 10-yr ISI Intervals PNO-IV-98-021, on 980520,loss of Offsite Power Occurred as Result of Fault on Transformer T1A-3,161 Kv to 4 Kv Transformer Which Supplies Power to One of Two Vital Electrical Buses.Special Followup Initiated on 9805211998-05-21021 May 1998 PNO-IV-98-021:on 980520,loss of Offsite Power Occurred as Result of Fault on Transformer T1A-3,161 Kv to 4 Kv Transformer Which Supplies Power to One of Two Vital Electrical Buses.Special Followup Initiated on 980521 ML20217N0931998-04-30030 April 1998 Notice of Violation from Insp on 980406-10.Violation Noted: on 980407,individual Working in Accordance W/Radiation Work Permit 98-0011 Entered Restricted High Radiation Area in Steam Generator Bay B W/O Radiation Protection Coverage IR 05000285/19980061998-04-30030 April 1998 Insp Rept 50-285/98-06 on 980406-10.Violations Noted.Major Areas Inspected:Plant Support ML20217E0061998-04-22022 April 1998 Notice of Violation from Insp on 980301-0411.Violation Noted:Inspectors Identified That Licensee Did Not Have Procedure for Performing an Activity That Affected Quality IR 05000285/19980051998-04-22022 April 1998 Insp Rept 50-285/98-05 on 980301-0411.Violations Noted. Major Areas Inspected:Operation,Maint,Engineering & Plant Support IR 05000285/19980011998-04-0606 April 1998 Insp Rept 50-285/98-01 on 980120-23 & 26-0306.No Violations Noted.Major Areas Inspected:Plant Support,Including Fire Protection Program IR 05000285/19980031998-03-27027 March 1998 Insp Rept 50-285/98-03 on 980223-27 & 0311-18.No Violations Identified.Major Areas Inspected:Licensee Physical Security Program,Access Authorization,Alarm Stations,Communications, Access Control of Event Logs & Mgt Support IR 05000285/19980021998-03-25025 March 1998 Insp Rept 50-285/98-02 on 980209-13 W/In Ofc Insp Until 980302.Violations Noted.Major Areas Inspected:Operations & Engineering ML20217D4471998-03-25025 March 1998 Notice of Violation from Insp on 980209-13 W/In Ofc Insp Until 980302.Violation Noted:Since Aug 1994 QA Lead Auditor Had Not Satisfied or Completed QA Qualification Manual Requirements Prior to Conducting Lead Auditor Functions IR 05000285/19980041998-03-12012 March 1998 Insp Rept 50-285/98-04 on 980118-0228.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000285/19970201998-02-27027 February 1998 Errata to Insp Rept 50-285/97-20 Issued on 980128.Noncited Violation Withdrawn.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support ML20199H8241998-01-28028 January 1998 Notice of Violation from Insp on 971207-980117.Violations Noted:Changes to Operating Procedures Affecting Nuclear Safety Were in Effect,Implemented,Via Five Different Operations Memos W/O Performed Requirements of TS ML20199H8611998-01-28028 January 1998 Insp Rept 50-285/97-20 on 971207-980117.Violations Noted. Major Areas Inspected:Operation,Maint,Engineering & Plant Support 1999-09-07
[Table view] |
See also: IR 05000285/1999004
Text
,
.
ENCLOSURE
U.S. NUCLEAR REGULATORY COMMISSION
REGION IV
Docket No.:
50-285
License No.:
DPR-40
Report No.:
50-285/99-04
Licensee:
Omaha Public Power District
Facility:
Fort Calhoun Station
Location:
Fort Calhoun Station FC-2-4 Adm., P.O. Box 399,
Hwy. 75 - North of Fort Calhoun
Fort Calhoun, Nebraska
Dates:
April 25 through May 31,1999
Inspectors:
W. C. Walker, Senior Resident inspector
V. G. Gaddy, Resident inspector
R. V. Azua, Project Engineer
R. A. Kopriva, Project Engineer
i
Approved By:
C. S. Marschall, Chief, Project Branch C
ATTACHMENT:
Supplemental Information
f
9906100154 9906'il
PDR
ADOCK 05000285
O
PDR
j
,
i
'4
mq'
..
EXECUTIVE SUMMARY '
Fort Calhoun Station .
NRC Inspection Report No. 50-285/99-04
kOperations '
The inspectors reviewed licensee Procedure NOD-OP-36," Control of Switchyard at
FCS," and verified that appropriate controls were being maintained over construction
activities in the switchyard and that offsite power sources had been appropriately.-
protected (Section O6.1).
Maintenance
During the replacement of the east raw water supply header flow indicator, maintenance
personnel noted that the replacement flow indicator would not fit into the pipe.
Engineering personnel determined that the plant drawing used to develop the
modification package was incorrect. Because the drawing was incorrect, licensee
personnel exercised conservative decision making by stopping the activity until
engineers performed a thorough evaluation of the changes needed to successfully
comp!ste the activity.(Sectioa M1.3).
Plant Sucoort
A member of the engineering department improperly entered a restricted high radiation
area. The engineer's failure to sign in on the proper radiation work permit was in
.
noncompliance with Standing Order SO-G-101 and, therefore, in violation of Technical
Specification 5.8.1. This Severity Level IV violation is being treated as a noncited
violation, consistent with Appendix C of the Enforcement Policy. This deficiency was
included in the corrective action program as Condition Report 19990077. Licensee
personnel responded appropriately to this occurrence (Section R4.1).
Durint a spent resin transfer, licensee personnel failed to identify adequate contingency
actions for the potential to clog system piping with resin. This resulted in operations
personnel receiving approximately 20 percent more dose thar: anticipated, but all doses
were within the radiation work permit limits. The procedures used during a transfer of
resin from the Spent Fuel Pool Demineralizer Tank AC-7 were clear and concise. The
associated briefings were informative (Section R4.2).
i
j
r
-]
-
9
.
c
Report Details
I
' Summarv of Plant Status
The Fort Calhoun Station began this inspection report period at 100 percent power and
maintained that level throughout the inspection period.
1. Operations
01
Conduct of Operations:
1
- O1.1 General Comments (71707)
. The inspectors conducted frequent reviesa of ongoing plant operations, in general, the
conduct of operations was professional and safety-conscious.; Plant status, operating
problems, and work plans were appropriately addressed during daily turnover and
f
plan-of-the-day meetings. Plant testing and maintenance requiring control room
. coordination were properly controlled. The inspectors observed several shift tumovers
and noted no problems.
02' : Operational Status of Facilities and Equipment
~ O2.1 Safety Iniection System Walkdown (71707)
-
The_ inspectors walked down those accessible portions of the safety injection system
located in the auxiliary building. All valves observed were in the appropriate position for
full power operations as indicated in Operations Instruction OI-SI-1, " Safety injection-
.
Normal Operation," Revision 39. The overall observable material condition of the
equipment was found to be very good, with only a few instances noted where small
amounts of boric acid crystals were visible.
- 06'
Operations Organization and Administration .
06.1 - Control of Switchvard Activities (71707)
The inspectors reviewed licensee Procedure NOD-OP-36, " Control of Switchyard at
~ FCS," and verified that appropriate controls were being maintained over construction
activities in the switchyard and that appropriate offsite power sources had been
appropriately protected.
4-
II. Maintenance
M1-
Conduct of Maintenance
M1.1 - General Comments - Maintenancg
ac
. Insoection Scoce (62707)
The inspectors observed or reviewed portions of the following work activities:
b
.
-2-
Work Order 98-0030 Replacement of east raw water supply header flow
indicator
Work Order 22677
Clean, inspect, lubricate, adjust 4160V breaker for raw
water Pump AC-10C
b.
Observations and Findinos
With the exception of the maintenance described in Section M1.4, the inspectors
identified no substantive concerns. Workers performed all observed activities with the
work packages present and in active use. The inspectors frequently observed
supervisors and system engineers monitoring job progress, and quality control
personnel were present when required.
c.
Conclusions
The maintenance activities observed were conducted in a controlled and professional
manner.
M1.2 Surveillance Tests
a.
Insoection Scope (61726)
The inspectors observed or reviewed all or portions of the following surveillance
activities:
OP-ST-DG-0002," Diesel Generator 2 Check," Revision 27
IC-ST-RPS-0003," Quarterly Functional Test of Power Range Safety Channel B
Trip Unit," Revision 2
OP-PM-AFW-0004, " Third Auxiliary Feedwater Pump Operability Verification,"
Revision 19
b.
Observations and Findinas
The plant staff conducted surveillance testing satisfactorily in accordance with the
licensee's approved programs and the Technical Specifications.
c.
Conclusions
Surveillance activities were completed thoroughly and professionally.
.
!
. .
' 3-
-
.
M1.3 - East Raw Water Suoolv Header Flow Indicator Reolacement
=a.
-Insoection Scope (62707)
.
The inspectors followed up to determine why maintenance on the east raw water supply
header flow indicator could not be performed as expected.
b.-
Observations and Findinas -
!
On May.5,1999, maintenance personnel attempted to replace the existing east raw
'
water supply header flow indicator with a new magnetic flow sensor. Although still
operable, the original flow indicator was degraded. The work was performed under
Modification Package 97-025.. Operators were required to remove the raw water system
from service for the replacement of the flow indicator.
~ The original flow indicator was removed from the supply header without incident. When
maintenance personnel attempted to insert the new magnetic flow sensor into the
header, it would not fit. The flow sensor was larger than the existing pipe-spool's inside
diameter. Plant drawings indicated that the bore measured 3.068 inches. However, the
actual bore measured 2.325 inches. The new flow sensor required a minimum opening -
of 2.6 inches.
Because the new flow sensor would not fit, licensee personnel considered counterboring
the existing fitting to enlarge the opening. This method would have required an
engineering analysis. Other methods of resolving the situation within the limiting
conoition for operation were evaluated and considered impractical. As a result,
maintenance personnel reinstalled the original flow indicator and the system was
retumed to service.
'
. c.
Conclusions
During the replacement of the east raw water supply header flow indicator, maintenance
i
personnel noted that the replacement flow indicator would not fit into the pipe.
'
Engineering personnel determined that the plant drawing used to develop the
modification package was incorrect. Because the drawing was incorrect, licensee
personnel exercised conservative decision making by stopping the activity until
engineers performed a thorough evaluation of the changes needed to successfully
complete the activity.
~
M2
Maintenance and Material Condition of Facilities and Equipment
M2.1 Review of Material Condition Durina Plant Tours
a.
Insoection Scope (62707)
,
The inspectors performed routine plant tours to evaluate plant material condition.
o
1
j
1
i
lC
4
b. -
Observations and Findinas '
i
'
The inspectors observed that the material condition and housekeeping of accessible
. areas in the auxiliary building, the radwaste building, the intake structure, and most
'
areas of the turbine building were good.
!
During a tour of the turbine building,.the inspectors identified a pin-hole leak in the area
i
_ of the weld seam on a 4-inch section of fire protection system piping. The inspectors
!
discussed this with the fire protection system engineer to verify that workers were
.
continuing to implement Preventive Maintenance Order 9803041. This order required a
'
complete walkdown of the. fire protection system 4- and 5-inch piping, at 6-month
intervals to determine if further erosion / corrosion of the system was occurring.
' The inspectors verified that a condition report was written to document the additional
. leak and that a deficiency tag was placed to ensure a work request for repair of the leak
l
would be initiated.
c.
Qgnclusions
'
The inspectors concluded that the observable material condition of plant structures and
j
equipment was good and verified that an action plan was in place to continue monitoring
{
the condition of the fire protection system.
j
l
j
M8
Miscellaneous Maintenance issues (92902) ,
1
M8.1 (Closed) Unresolved item 50-285/99003-02: mechanical agitation of volume control
tank makeup inlet Check Valve CH-151. This item had remained open pending the
l
completion of an analysis to evaluate whether the check valve should remain within the -
scope of the inservice testing program.
-
-
!
As documented in NRC Inspection Report 50-285/99-03, the check valve failed to meet
I
its acceptance criteria for backleakage and was declared inoperable as required by the
j
surveillance procedure. The valve was mechanically agitated with a sledge hammer,
passed subsequent testing,~ and was declared operable. As corrective action, the check
'
valve was retested and again failed its acceptance criteria. The valve was again
,
declared inoperable as required by the surveillance test.
j
On May 5,1999, engineers completed their evaluation and concluded that Check
'
Valve CH-151 did not perform a safety function and was not required to prevent back
leakage from the volume control tank. The evaluation also referenced Updated Safety
Analysis Report Section 6.1.2.3 stating that the chemical and volume control system
was not required to mitigate the consequences of a design basis accident.
!
This evaluation was documented in Memorandum NE-CTD-99-024. Because no safety
function was performed by the valve, the engineers recommended that the current
quarterly test be deleted from the inservice testing program and also from Surveillance
Test Procedure OP-ST-CH-3002, " Chemical and Volume Control System (CVCS)
_
~ Category C Valve Exercise Test." The inspectors concluded that the check valve was
,
i
V,,
,
,
5-
not required to be within the scope of the inservice testing program and no violation of :
the inservice. testing program had occurred.
IV, Plant Support
R1
Radiological Protection and Chemistry Controls
R1.1 - General Comments (71750)
The inspectors observed health physics personnel, including supervisors, routinely
touring the radiologically controlled areas. Licensee personnel working in radiologically
controlled areas exhibited good radiation worker practices.
Contaminated areas and high radiation areas were properly posted. Area surveys
posted outside rooms in the auxiliary building were current. The inspectors checked a
sample of doors required to be locked for the purpose of radiation protection and found
no problems.
R4
Staff Knowledge and Performance
R4.1
Imorocer Entrv Into a Restricted Hiah Radiation Area
a.
Insoection Scooe (71750)
On April 29,1999, a member of the system engineering department entered a restricted
high radiation area without signing onto the proper radiation work permit. The
inspectors reviewed the circumstances surrounding this event.
b.
Observations and Findinas
The engineer entered the spent fuel pool cooling pump room (Room 5), posted as a
restricted high radiation area, during the resin transfer discussed in Section M1.4. The
door to Room 5 had been propped open to allow passing of hoses into the room. The
supervisor for this radiological operation had made the decision to post the room at the
open doorway. The room had been barricaded with a suspended rope bearing an
,
appropriate posting, in addition, a radiological protection technician was assigned to
provide positive control of access to the room.
In support of the job, the engineer entered the room to observe the resin transfer. The
radiation work permit that the engineer was signed in on did not allow access into a
restricted high radiation area. .The engineer entered the room while the radiation
protection technician was observing work inside the room with a remote camera. As
soon as the engineer passed the technician, the radiation protection technician
immediately directed the engineer to exit the area.
i
1
I
i
/
-6-
The engineer's electronic dosimetry recorded a maximum dose rate of 58 mrem /hr, and
his recorded dose for the entire duration of his radiological cont,olled area entry was
,
2 mrem. The maximum measured radiation dose rate in the room where the engineer
stood was 80 mrem /hr.
i
Radiation protection technicians initiated Condition Report 199900771 to document this
event, and the engineer was excluded from the radiologically controlled area. The
circumstances that resulted in the incident were discussed with all radiation protection
personnel.
The inspector reviewed Standing Order SO-G-101, " Radiation Worker Practices," and
noted that it required personnel to sign onto the proper radiation work permit prior to
entering into a restricted high radiation area. The failure of the engineer to follow this
standing order was in violation of Technical Specification 5.8.1 (50-285/99004-02). This
Severity Level IV violation is being treated as a noncited violation, consistent with
Appendix C of the Enforcement Policy. This deficiency was included in the corrective
action program as Condition Report 199900771.
c.
Conclusions
A member of the engineering department improperly entered a restricted high radiation
area. The engineer's failure to sign in on the proper radiation work permit was in
noncompliance with S anding Order SO-G-101 and, therefore, in violation of Technical
Specification 5.8.1. Licensee personnel responded appropriately to this occurrence.
R4.2 Removina Resin from Soent Fuel Pool Demineralizer Tank AC-7
a.
Insoection Scope (62707)
The inspectors monitored efforts to remove resin from Spent Fuel Pool Demineralizer
Tank AC-7. Prejob briefings, equipment setup, resin transfer, and job critiques were
observed. In addition, the inspectors reviewed the work orders, work instructions, and
radiation work permits used to perform this effort.
b.
Observations and Findinos
The inspectors found that the prejob 6defing and the as low as reasonably achievable
briefing were both comprehensive and engaging, elicitiiig a number of questions and
suggestions by licensee personnel involved. Licensee efforts were appropriately
focused on minimizing personnel exposure during the high radiation conditions. The
work orders, work instructions and associated radiation work permits were clear and
!
concise and had been reviewed and approved as noted by the appropriate signatures.
Overall, the work was performed in accordance with the work instructions and personnel
involved adhered to good radiation work practices. Health physics technicians closely
1
monitored the radiation exposure received by the operations personnelinvolved in
manipulating the system valves and radiation levels emanating from Tank AC-7 and the
associated drainage piping.
1
i
\\
__-
_ _ - _ _ ____-______ _ _
---
4:
1 '
7-
At one point during this activity, the system drainage piping became clogged with resin.
Licensee personnel had not prepared adequate contingency plans to address this issue.
As a result, operators had to stop the activity to determine the next course of action.
,
This delayed the completion of the activity and prolonged the time that some of the -
. operators had to remain in areas with elevated radiation levels. During this time an
engineer involved in developing a method for dislodging the clogged resin entered the
spent fuel pool cooling room to observe the position of the piping. This room had been
- designated as a restricted high radiation area. However, the engineer was signed in on
Radiation Work Permit 1014 that did not allow access into restricted high radiation areas
as documented in Section R4 of this inspection report.
Licensee engineers made a' decision to mechanically agitate the clogged section of
pipe. However, the line clogged again. As a result, the activity was suspended.
Operators issued Condition Report 199900772 to evaluate the poor planning for
potential resin clogging of the line. Delays in the activity resulted in operations
personnel receiving approximately 20 percent more dose than anticipated. However, all
doses were within the radiation work permit limits.
The job critique was very thorough and candid. The personnel involved clearly identified -
errors and made some good suggestions for improvement, Two condition reports were
issued during the meeting.
c.
Conclusions
During a resin transfer, licensee personnel failed to identify adequate contingency
actions for the potential to clog system piping with resin. This resulted in operations
personnel receiving approximately 20 percent more dose than anticipated, but all doses
were within the radiation work permit limits. The procedures used during a transfer of
resin from Spent Fuel Pool Demineralizer Tank AC-7 were clear and concise. The
associated briefings were informative.
V. Manaaement Meetinas
.
X1
Exit Meeting Summary
The inspectors presented the inspection results to members of licensee management at
the exit meeting on May 28,1999. The licensee acknowledged the finding as
presented.
The inspectors asked the licensee whether any materials examined during the
inspection should be considerad proprietary. No proprietary information was identified.
t
.
..
.
. ..
..
.
..
..
)
r
ATTACHMENT
SUPPLEMENTAL INFORMATION
PARTIAL LIST OF PERSONS CONTACTED
i
Licensee
D. Bannister, Operations Supervisor
M. Core, Manager, System Engineering
M. Frans, Licensing Manager
j
M. Puckett, Manager, Radiation Protection
R. Short, Assistant Plant Manager
J. Skiles, Manager, Design Engineering
J. Solymossy, Manager, Fort Calhoun Station
R. Clemens, Manager, Maintenance
'
INSPECTION PROCEDURES USED
37551
Onsite Engineering
61726
Surveillance Observations
62707
Maintenance Observations
71707
Plant Operations
71750
Plant Support Activities
92700
Onsite Followup of Written Reports of Nonroutine Events at Power Reactor
Facilities
92902
Followup - Maintenance
92903
Followup - Engineering
ITEMS OPENED AND CLOSED
.
Opened
j
99004-01
NCV
Improper entry into a restricted high radiation area
(Section R4.1).
99004-02
NCV
Low pressure safety injection in an unanalyzed condition due
to potential for voiding (Section R4.2).
p;;9 --
-
..
>.
2-
Closed
99003-02
URI '
' Mechanical agitation of volume control tank makeup inlet
check valve (Section M8.1).
.97010-03
-lFl
Low pressure safety injection in an unanalyzed condition due
to potential for voiding (Section E8.1).
97017;
'LER
Low pressure safety injection in an unanalyzed condition due -
to potential for voiding (Section E8.1).
99004-01.
NCV.
Low pressure safety injection in an unanalyzed condition due
to potential for voiding (Section E8.1).
99004-02
- NCV
!mproper entry into a restricted high radiation area
(Section R4.1).
i
,
,
i