|
---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARML20217P3791999-10-21021 October 1999 Forwards NRC Form 396 & NRC Form 398 for Renewal of Licenses SOP-20607-1 & SOP-20610-1.Without Encls ML20217N2521999-10-20020 October 1999 Provides Supplemental Info Re 990405 Containment Insp Program Requests for Relief RR-L-1 & RR-L-2,in Response to 991013 Telcon with NRC ML20217K7541999-10-15015 October 1999 Forwards Rev 1 to Unit 1,Cycle 9 & Unit 2 Cycle 7 Colrs,Iaw Requirements of TS 5.6.5.Figure 5, Axial Flux Difference Limits as Function of Percent of Rated Thermal Power for RAOC, Was Revised for Both Units ML20217G6751999-10-13013 October 1999 Requests Withholding of Proprietary Info Contained in Application for Amend to OLs to Implement Relaxations Allowed by WCAP-14333-P-A,rev 1 ML20217G1071999-10-0707 October 1999 Informs That on 990930,NRC Staff Completed mid-cycle PPR of Vogtle & Did Not Identify Any Areas in Which Performance Warranted More than Core Insp Program.Nrc Plans to Conduct Core Insps at Facility Over Next Six Months ML20216J9041999-10-0101 October 1999 Forwards Response to RAI Re GL 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Motor-Operated Valves ML20216J9161999-10-0101 October 1999 Forwards Response to NRC 990723 RAI Re GL 95-07, Pressure Locking & Thermal Binding of SR Power-Operated Gate Valves ML20217B0141999-10-0101 October 1999 Forwards Insp Repts 50-424/99-06 & 50-425/99-06 on 990725- 0904 at Vogtle Units 1 & 2 Reactor Facilities.Determined That One Violation Occurred & Being Treated as non-cited Violation ML20212E8751999-09-20020 September 1999 Forwards Response to NRC GL 99-02, Lab Testing of Nuclear Grade Activated Charcoal. Description of Methods Used to Comply with Std Along with Most Recent Test Results Encl ML20212E7481999-09-20020 September 1999 Requests Approval Per 10CFR50.55a to Use Alternative Method for Determining Qualified Life of Certain BOP Diaphragm Valves than That Specified in Code Case N-31.Proposed Alternative,Encl ML20212C2191999-09-16016 September 1999 Forwards NRC Form 536, Operator Licensing Exam Data, Which Is Current Need for NRC Operator Licensing Exams for Years 2000 Through 2003 of Plant Vogtle,Per Administrative Ltr 99-03 ML20211Q4801999-09-0101 September 1999 Informs That on 990812-13,Region II Hosted Training Managers Conference on Recent Changes to Operator Licensing Program. List of Attendees,Copy of Slide Presentations & List of Questions Received from Participants Encl ML20211J5291999-08-30030 August 1999 Forwards Snoc Copyright Notice Dtd 990825,re Production of Engineering Drawings Ref in VEGP UFSAR ML20211J5251999-08-30030 August 1999 Forwards Response to NRC 990727 RAI Re GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design Basis Accident Conditions ML20211J7381999-08-27027 August 1999 Informs That Licensee Vessel Data Is Different than NRC Database Based on Listed Info,Per 990722 Request to Review Rvid ML20211E9251999-08-23023 August 1999 Forwards fitness-for-duty Performance Data for Jan-June 1999,as Required by 10CFR26.71(d).Data Reflected in Rept Covers Employees at Vogtle Electric Generating Plant ML20210V0881999-08-16016 August 1999 Forwards Insp Repts 50-424/99-05 & 50-425/99-05 on 990620- 0724.No Violations Noted.Vogtle Facility Generally Characterized by safety-conscious Operations,Sound Engineering & Maintenance Practices ML20210Q4611999-08-0505 August 1999 Informs That NRC Plans to Administer Generic Fundamentals Exam Section of Written Operator Licensing Exam on 991006 for Vogtle.Requests Info Re Individuals Who Will Take Exam. Sample Registration Ltr Encl ML20210L2181999-08-0202 August 1999 Forwards NRC Form 396 & Form 398 for Renewal of Listed Licenses,Iaw 10CFR55.57.Without Encl ML20210N1191999-08-0202 August 1999 Discusses 990727 Telcon Between Rs Baldwin & R Brown Re Administration of Licensing Exam at Facility During Wk of 991213 ML20210G3351999-07-27027 July 1999 Forwards Second Request for Addl Info Re GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design Basis Accident Conditions ML20210E0121999-07-23023 July 1999 Forwards Second Request for Addl Info Re GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves ML20210D9341999-07-22022 July 1999 Discusses Closure of TACs MA0581 & MA0582,response to Requests for Info in GL 92-01,rev 1,suppl 1, Reactor Vessel Structural Integrity ML20210C8011999-07-21021 July 1999 Provides Response to NRC AL 99-02,which Requests That Addressees Submit Info Pertaining to Estimates of Number of Licensing Actions That Will Be Submitted for NRC Review for Upcoming Fy 2000 & 2001 ML20210E0431999-07-15015 July 1999 Forwards Insp Repts 50-424/99-04 & 50-425/99-04 on 990502- 0619.Two Violations of NRC Requirements Identified & Being Treated as non-cited Violations Consistent with App C of Enforcement Policy ML20209H3881999-07-14014 July 1999 Forwards Revs 1 & 2 to ISI Program Second 10-Year Interval Vogtle Electric Generating Plant Unit 1 & 2 ML20209C4041999-07-0101 July 1999 Forwards Rev 29 to VEGP Units 1 & 2 Emergency Plan.Rev 29 Incorporates Design Change Associated with Consolidation of Er Facilities Computer & Protues Computer.Justifications for Changes & Insertion Instructions Are Encl ML20196H8081999-06-28028 June 1999 Discusses 990528 Meeting Re Results of Periodic PPR for Period of Feb 1997 to Jan 1999.List of Attendees Encl ML20212J2521999-06-21021 June 1999 Responds to NRC RAI Re Yr 2000 Readiness at Nuclear Power Plants.Gl 98-01 Requested Response on Status of Facility Y2K Readiness by 990701 ML20196F9171999-06-21021 June 1999 Forwards Owner Rept for ISI for Vogtle Electric Generating Plant,Unit 1 Eighth Maint/Refueling Outage. Separate Submittal Will Not Be Made to NRC on SG Tubes Inspected During Subj Outage ML20195F8031999-06-11011 June 1999 Forwards Changes to VEGP Unit 1 Emergency Response Data Sys (ERDS) Data Point Library.Changes Were Completed on 990308 While Unit 1 Was SD for Refueling Outage ML20207E7421999-06-0303 June 1999 Refers to from NRC Which Issued Personnel Assignment Ltr to Inform of Lm Padovan Assignment as Project Manager for Farley Npp.Reissues Ltr with Effective Date Corrected to 990525 ML20207F6201999-06-0202 June 1999 Sixth Partial Response to FOIA Request for Documents.Records in App J Encl & Will Be Available in Pdr.App K Records Withheld in Part (Ref FOIA Exemptions 7) & App L Records Completely Withheld (Ref FOIA Exemption 7) ML20207D9861999-05-28028 May 1999 Informs That,Effective 990325,LM Padovan Was Assigned as Project Manager for Plant,Units 1 & 2 ML20207D2701999-05-19019 May 1999 Forwards Insp Repts 50-424/99-03 & 50-425/99-03 on 990321- 0501.One Violation of NRC Requirements Identified & Being Treated as non-cited Violation Consistent with App C of Enforcement Policy ML20206M5141999-05-11011 May 1999 Informs That NRC Ofc of Nuclear Regulation Reorganized Effective 990328.As Part of Reorganization,Div of Licensing Project Mgt Created.Rl Emch Section Chief for Vogtle. Reorganization Chart Encl ML20206U4061999-05-11011 May 1999 Confirms Telcon with J Bailey Re Mgt Meeting Scheduled for 990528 to Discuss Results of Periodic Plant Performance Review for Plan Nuclear Facility Fo Period of Feb 1997 - Jan 1999 05000424/LER-1998-006, Forwards LER 98-006-03 Re Motor Control Ctr Breaker Buckets Not Being Seismically Qualified.Rev Is Submitted to Document Results of Seismic Testing That Demonstrated That No Condition Outside Design Basis of TS Requirements Exi1999-05-10010 May 1999 Forwards LER 98-006-03 Re Motor Control Ctr Breaker Buckets Not Being Seismically Qualified.Rev Is Submitted to Document Results of Seismic Testing That Demonstrated That No Condition Outside Design Basis of TS Requirements Existed ML20206D6411999-04-29029 April 1999 Forwards Vogtle Electric Generating Plant Radiological Environ Operating Rept for 1998 & Vogtle Electric Generating Plant Units 1 & 2 1998 Annual Rept Annual Radioactive Effluent Release Rept ML20206D5881999-04-29029 April 1999 Forwards Rept Which Summarizes Effects of Changes & Errors in ECCS Evaluation Models on PCT for 1998,per Requirements of 10CFR50.46(a)(3)(ii).Rept Results Will Be Incorporated Into Next FSAR Update ML20206D6951999-04-28028 April 1999 Provides Update of Plans for VEGP MOV Periodic Verification Program Re GL 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Movs ML20206C2241999-04-21021 April 1999 Forwards Revised Monthly Operating Repts for Mar 1999 for Vogtle Electric Generating Plant,Units 1 & 2.Page E2-2 Was Iandvertently Omitted from Previously Submitted Rept on 990413 ML20206A6371999-04-21021 April 1999 Forwards SE Authorizing Licensee Re Rev 9 to First 10-yr ISI Interval Program Plan & Associated Requests for Relief (RR) 65 from ASME Boiler & Pressure Vessel Code ML20205Q3351999-04-15015 April 1999 Forwards Insp Repts 50-424/99-02 & 50-425/99-02 on 990214-0320.Three Violations Identified & Being Treated as Non-Cited Violations ML20205T2351999-04-0909 April 1999 Informs That on 990317,B Brown & Ho Christensen Confirmed Initial Operator Licensing Exam Scheduled for Y2K.Initial Exam Date Scheduled for Wk of 991213 for Approx 10 Candidates ML20205K7501999-04-0505 April 1999 Informs That Effective 990329,NRC Project Mgt Responsibility for Plant Has Been Transferred from Dh Jaffe to R Assa ML20209A3741999-04-0505 April 1999 Submits Several Requests for Relief for Plant from Code Requirements Pursuant to 10CFR50.55a(a)(3) & (g)(5)(iii).NRC Is Respectfully Requested to Approve Requests Prior to Jan 1,2000 ML20205H3481999-03-31031 March 1999 Forwards Georgia Power Co,Oglethorpe Power Corp,Municipal Electric Authority of Ga & City of Dalton,Ga Status of Decommissioning Funding for Each Reactor or Part of Reactor Owned for OLs NPF-68 & NPF-81 ML20205F9091999-03-29029 March 1999 Submits Rept of Number of SG Tubes Plugged During Plant Eighth Maintenance/Refueling Outage (1R8).Inservice Insps Were Completed on SGs 1 & 4 on 990315.No Tubes Were Plugged ML20205G0761999-03-26026 March 1999 Provides Results of Individual Monitoring for 1998.Encl Media Contains All Info Required by Form NRC 5.Without Encl 1999-09-20
[Table view] Category:OUTGOING CORRESPONDENCE
MONTHYEARML20217G1071999-10-0707 October 1999 Informs That on 990930,NRC Staff Completed mid-cycle PPR of Vogtle & Did Not Identify Any Areas in Which Performance Warranted More than Core Insp Program.Nrc Plans to Conduct Core Insps at Facility Over Next Six Months ML20217B0141999-10-0101 October 1999 Forwards Insp Repts 50-424/99-06 & 50-425/99-06 on 990725- 0904 at Vogtle Units 1 & 2 Reactor Facilities.Determined That One Violation Occurred & Being Treated as non-cited Violation ML20211Q4801999-09-0101 September 1999 Informs That on 990812-13,Region II Hosted Training Managers Conference on Recent Changes to Operator Licensing Program. List of Attendees,Copy of Slide Presentations & List of Questions Received from Participants Encl ML20210V0881999-08-16016 August 1999 Forwards Insp Repts 50-424/99-05 & 50-425/99-05 on 990620- 0724.No Violations Noted.Vogtle Facility Generally Characterized by safety-conscious Operations,Sound Engineering & Maintenance Practices ML20210Q4611999-08-0505 August 1999 Informs That NRC Plans to Administer Generic Fundamentals Exam Section of Written Operator Licensing Exam on 991006 for Vogtle.Requests Info Re Individuals Who Will Take Exam. Sample Registration Ltr Encl ML20210N1191999-08-0202 August 1999 Discusses 990727 Telcon Between Rs Baldwin & R Brown Re Administration of Licensing Exam at Facility During Wk of 991213 ML20210G3351999-07-27027 July 1999 Forwards Second Request for Addl Info Re GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design Basis Accident Conditions ML20210E0121999-07-23023 July 1999 Forwards Second Request for Addl Info Re GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves ML20210D9341999-07-22022 July 1999 Discusses Closure of TACs MA0581 & MA0582,response to Requests for Info in GL 92-01,rev 1,suppl 1, Reactor Vessel Structural Integrity ML20210E0431999-07-15015 July 1999 Forwards Insp Repts 50-424/99-04 & 50-425/99-04 on 990502- 0619.Two Violations of NRC Requirements Identified & Being Treated as non-cited Violations Consistent with App C of Enforcement Policy ML20196H8081999-06-28028 June 1999 Discusses 990528 Meeting Re Results of Periodic PPR for Period of Feb 1997 to Jan 1999.List of Attendees Encl ML20207E7421999-06-0303 June 1999 Refers to from NRC Which Issued Personnel Assignment Ltr to Inform of Lm Padovan Assignment as Project Manager for Farley Npp.Reissues Ltr with Effective Date Corrected to 990525 ML20207F6201999-06-0202 June 1999 Sixth Partial Response to FOIA Request for Documents.Records in App J Encl & Will Be Available in Pdr.App K Records Withheld in Part (Ref FOIA Exemptions 7) & App L Records Completely Withheld (Ref FOIA Exemption 7) ML20207D9861999-05-28028 May 1999 Informs That,Effective 990325,LM Padovan Was Assigned as Project Manager for Plant,Units 1 & 2 ML20207D2701999-05-19019 May 1999 Forwards Insp Repts 50-424/99-03 & 50-425/99-03 on 990321- 0501.One Violation of NRC Requirements Identified & Being Treated as non-cited Violation Consistent with App C of Enforcement Policy ML20206M5141999-05-11011 May 1999 Informs That NRC Ofc of Nuclear Regulation Reorganized Effective 990328.As Part of Reorganization,Div of Licensing Project Mgt Created.Rl Emch Section Chief for Vogtle. Reorganization Chart Encl ML20206U4061999-05-11011 May 1999 Confirms Telcon with J Bailey Re Mgt Meeting Scheduled for 990528 to Discuss Results of Periodic Plant Performance Review for Plan Nuclear Facility Fo Period of Feb 1997 - Jan 1999 ML20206A6371999-04-21021 April 1999 Forwards SE Authorizing Licensee Re Rev 9 to First 10-yr ISI Interval Program Plan & Associated Requests for Relief (RR) 65 from ASME Boiler & Pressure Vessel Code ML20205Q3351999-04-15015 April 1999 Forwards Insp Repts 50-424/99-02 & 50-425/99-02 on 990214-0320.Three Violations Identified & Being Treated as Non-Cited Violations ML20205T2351999-04-0909 April 1999 Informs That on 990317,B Brown & Ho Christensen Confirmed Initial Operator Licensing Exam Scheduled for Y2K.Initial Exam Date Scheduled for Wk of 991213 for Approx 10 Candidates ML20205K7501999-04-0505 April 1999 Informs That Effective 990329,NRC Project Mgt Responsibility for Plant Has Been Transferred from Dh Jaffe to R Assa ML20205B9601999-03-24024 March 1999 Seventh Partial Response to FOIA Request for Documents. Records in App N Already Available in Pdr.App O Records Being Released in Entirety & App P Records Being Withheld in Part (Ref FOIA Exemptions 7C,2 & 5) ML20205A2771999-03-19019 March 1999 Advises of NRC Planned Insp Effort Resulting from Vogtle PPR on 990208.PPR for Plant Involved Participation of All Technical Divs in Evaluating Insp Results & Safety Performance Info for Period of Dec 1997 - Jan 1999 ML20207L8281999-03-0808 March 1999 Forwards Partially Withheld Insp Repts 50-424/99-01 & 50-425/99-01 & Notice of Violation ML20207J0431999-03-0303 March 1999 Forwards Insp Repts 50-424/98-10 & 50-425/98-10 on 981227- 990213.No Violations Noted.Licensee Conduct of Activities at Vogtle Facility Generally Characterized by safety-conscious Operations,Sound Engineering & Maint Practices ML20203G5691999-02-0505 February 1999 Informs That NRC Plans to Administer Generic Fundamentals Exam Section of Written Operator Licensing Exam on 990407. Representative of Facility Must Submit Ltr Indicating No Candidates or Ltr Listing Names of Candidates for Exam ML20202H9691999-01-29029 January 1999 Forwards Safety Evaluation Authorizing Rev 8 to First 10-year Interval Inservice Insp Program & Associated Requests for Relief for Vogtle Electric Generating Plant, Unit 1 ML20199J7931999-01-20020 January 1999 Forwards Insp Repts 50-424/98-09 & 50-425/98-09 on 981115-1226 at Vogtle Units 1 & 2.No Violations Were Identified.Conduct of Activities at Vogtle Was Generally Characterized by safety-conscious Operations ML20199K1381999-01-12012 January 1999 Informs That on 990117,Region II Implemented Staff Reorganization as Part of agency-wide Streamlining Effort, Due to Staffing Reductions in FY99 Budget.Organization Charts Encl ML20198S1601998-12-31031 December 1998 Forwards SER of Licensee Second 10-year Interval Inservice Insp Program Plan & Associated Requests for Relief for Vogtle Electric Generating Plant Submitted on 970529. INEEL/EXT-98-01007 Rept Also Encl ML20199E4741998-12-23023 December 1998 Provides Summary of 981105 Training Managers Conference Held in Atlanta,Georgia.Conference Agenda,List of Conference Attendees,Presentation Slides & Preliminary Schedule for FY99 & FY00 Encl ML20199J9781998-12-22022 December 1998 Responds to 981209 Meeting Re Installation of Seismic Clips on Cutler Hammer Electrical Circuit Breakers.Forwards List of Attendees & Handouts ML20198F6711998-12-11011 December 1998 Forwards Insp Repts 50-424/98-08 & 425/98-08 on 980927-1114. No Violations Identified ML20198N9431998-12-10010 December 1998 Ack Receipt of Response, to NOV Issued on 980112 Re Surveillance Testing of Reactor Trip Sys P-4 Interlock Feature at Licensee Facility.Nrc Agrees That Surveillance Testing Not Required ML20196J2181998-12-0101 December 1998 Advises of Planned Insp Effort Resulting from 981102 Insp Planning Meeting.Historical Listing of Plant Issues Called Plant Issues Matrix & Insp Plan,Including Specific Insps Such as in Security & Radiological Protection Areas Encl ML20196J2581998-12-0101 December 1998 Confirms Arrangements Made Between J Bailey & B Holbrook, Re Info Meeting Scheduled for 990210 to Discuss Licensee Performance,New Initiatives & Other Regulatory Issues Pertaining to Listed Facilities ML20196B1231998-11-23023 November 1998 Confirms Telephone Conversation Between J Bailey & P Skinner on 981120 Re Info Meeting Which Has Been Scheduled for 981209 in Atlanta,Ga,To Discuss Issues Re Seismic Retainer Clips ML20196D4981998-11-13013 November 1998 Informs That on 981007,NRC Administered Gfes of Written Operator Licensing Examination.Copy of Answer Key & Master Bw/Pwr GFE Encl,Even Though Facility Did Not Participate in Exam.Without Encl ML20195B3391998-11-0909 November 1998 Forwards Partially Withheld Insp Repts 50-424/98-12 & 50-425/98-12 on 981005-09 (Ref 10CFR73.21).No Violations Noted.Conduct of Activities Generally Characterized by safety-conscious Operations & Sound Engineering ML20155H2501998-10-21021 October 1998 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Repts 50-424/98-05 & 50-425/98-05 Issued on 980723.Concluded for Reasons Stated That Example 2 Violation Occurred as Stated in NOV ML20155A7491998-10-15015 October 1998 Forwards Insp Repts 50-424/98-07 & 50-425/98-07 on 980816-0926 & Nov.Insp Generally Characterized by Safety Conscious Operations,Sound Engineering & Maint Practices & Appropriate Radiological Controls ML20155B7771998-10-0909 October 1998 Extends Invitation to Attend Training Manager Conference on 981105 in Atlanta,Georgia.Conference Designed to Inform Regional Training & Operations Mgt of Issues & Policies That Effect Licensing of Reactor Plant Operators ML20155B4621998-09-25025 September 1998 Discusses OI Investigation Which Completed on 980728. Investigation Reviewed Circumstances Surrounding Apparent Disabling of Fire Computer Trouble Alarm by Unit Shift Supervisor.Concludes Enforcement Discretion Warranted ML20153B0401998-09-17017 September 1998 Responds to 980904 e-mail Message Making Certain Observations Re Apparent Increase in Reactor Trips at Plant, Units 1 & 2.NRC Concluded That Licensee post-trip Reviews Adequately Conducted & That No Adverse Trends,Apparent ML20153B9311998-09-16016 September 1998 Forwards RAI Re GL 97-01, Degradation of Crdm/Cedm Nozzle & Other Vessel Closure Head Penetrations, Responses for Plant,Units 1 & 2 ML20153F7081998-09-11011 September 1998 Provides Summary of 980909 Meeting Held to Discuss TS & Other Regulatory Issues Re Vogtle Electric Generating Plant. List of Meeting Attendees & Copy of Presentation Slides Encl ML20154C4871998-09-10010 September 1998 Forwards Insp Repts 50-424/98-06 & 50-425/98-06 on 980628-0815 & Nov.One Violation Involved Failure to Implement Adequate C/As for Repeated Failures to Enter Applicable TS Limiting Conditions for Operation ML20151U7901998-09-0909 September 1998 Discusses 980615 Request for Exemption from Requirement of 10CFR73.55(e)(1) & (f)(1) to Provide Continuous Staffing of Plant CAS During Contingency Events.Request Denied ML20151S7291998-09-0202 September 1998 Discusses Evaluation of Util Response to GL 97-05 for Plant, Units 1 & 2.NRC Did Not Identify Any Concerns W/Sg Tube Insp Techniques Employed at Plant ML20239A4251998-08-27027 August 1998 Informs of Change Being Implemented by Region II Re Administrative Processing of Licensee Responses to Nov.Nov Responses Will Be Formally Ack as Part of Periodically Issued Integrated Insp Repts 1999-09-01
[Table view] |
Text
_ _ _ _ _ _ _ _ - _ _ _ _ _ _ _
Mr. B. Be:sley August 10, 1998
. Vice Pr:sident South rn Nuclar Oper; ting Company, Inc.
Post Office Box 1295 Birmingham, Alabama 35201-1295
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION CONCERNING GENERIC LETTER (GL) 96-06, " ASSURANCE OF EQUIPMENT OPERABILITY AND CONTAINMENT INTEGRITY DURING DESIGN-BASIS ACCIDENT CONDITIONS"- VOGTLE ELECTRIC GENERATING PLANT (VEGP), UNITS 1 AND 2 (TAC NCS. MG6881 AND M96882)
Dear Mr. Beasley:
In the course of reviewing your January 27,1997, response to GL 96-06 for VEGP, the staff has identified the need for additional information. The enclosed request for additional information has been discussed with Jim Bailey of your staff. A target date for your response has been agreed upon to be November 1,1998. Should a situation occur which prevents you from meeting the due date, please contact me at (301) 415-1439.
Sincerely, ORIGINAL SIGNED BY:
David H. Jaffe, Senior Projeci h anaer Project Directorate 11-2 Division of Reactor Projects - 1/11 Office of Nuclear Reactor Regulation Docket Nos. 50-424 emiS0-425
Enclosure:
Request for Additional Information cc w/ encl: See next page '
DISTRIBUTION: l Docket File J. Tatum, NRR PUBLIC ACRS f
g PD 11-2 Rdg. PSkinner, Ril l JZwolinski
)
HBerkow ,g\ 4 DJaffe pI LBerry j LPlisco, Rll . ng i OGC M tLp3 i N'". m,.3 p?
, , _ _ ,}
g\ m m eno p'u !T7 l DOCUMENT NAME: G:\VOGTLE\RFl9606.WP l
To receive a copy of this document, indicate in the box: "C" = Copy without enclosures "E" = Copy with !
cnclosures "N" = No cogt s l
7 OFFICE PM:PDll-$ r(\ / LA:PDil-2\ O V D:PDllM l l NAME DJaffe:cr$J/j V
LBerry %\/ HiiferkM / i f DATE Q/lV98 4 /K/98 ~\ did98/"
9808120311 980810
~
OFFICIAL RECORD COPY i PDR ADOCK 05000424 e P PDR j
.
[j t UNITED STATES '
g j 2
NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 'annan nani
% . . . . . p' August 10, 1998 Mr. B. Beasley Vice President i
Southern Nuclear Operating l
Company, Inc.
Post Office Box 1295 Birmingham, Alabama 35201-1295
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION CONCERNING GENERIC LETTER (GL) 96-06, " ASSURANCE OF EQUIPMENT OPERABILITY AND CONTAINMENT INTEGRITY DilRING DESIGN-BASIS ACCIDENT CONDITIONS' - VOGTLE ELEC.TRIC GENERATING PLANT (VEGP), UNITS 1 AND 2 (TAC NOS. M96881 ANC, M96882)
Dear Mr. Beasley:
In the course of reviewing your January 27,1997, response to GL 96-06 for VEGP, the staff has identified the need for additionalinformation. The enclosed request for additional information has been discussed with Jim Bailey of your staff. A target date for your response has been agreed upon to be November 1,1998. Should a situation occur which prevents you
' from meeting the due date, please contact me at (301) 415-1439.
Sincerely,
\
David H. , Senior Project Manager Project Directorate ll-2 Division of Reactor Projects - l/II Office of Nuclear Reactor Regulation Docket Nos. 50-424 and 50-425
Enclosure:
Request for Additional Information cc w/ encl: See next page u_______.___--- - - - - -
7 l
Vogtle Electric Generating Plant I cc: Harold Reheis, Director Mr. J. A. Bailey Department of Natural Resources
, Manager, Licensing _
205 Butler Street, SE. Suite 1252
)
i Southem Nuclear Operating Atlanta, Georgic 30334 Company, Inc.
P. O. Box 1295 Attomey General Birmingham, Alabama 35201-1295 Law Department l
- - 132 Judicial Building l Mr. J. Gasser Atlanta, Georgia 30334 l General Manager, Vogtle Electric Generating Plant Mr. R. D. Barker i Southern Nuclear Operating Program Manager Company, Inc. Fossil & Nuclear Operations P. O. Box 1600 Oglethorpe Power Corporation
- Waynesboro, Georgia 30830 2100 East Exchange Place ;
P. O. Box 1349 Regional Administrator, Region ll Tucker, Georgia 30085-1349 U. S. Nuclear Regulatory Commission Charles A. Patrizia, Esquire
. Atlanta Federal Center Paul, Hastings, Janofsky & Walker l j 61 Forsyth Street, SW., Suite 23T85 10th Floor
- Atlanta, Georgia 30303 1299 Pennsylvania Avenue Washington, DC 20004-9500 Office of Planning and Budget Room 615B Arthur H. Domby, Esquire 270 Washington Street, SW. Troutman Sanders l Atlanta, Georgia 30334 NationsBank Plaza l 600 Peachtree Street, NE.
Mr. J. D. Woodard Suite 5200 i Executive Vice President Atlanta, Georgia 30308-2216
! Southern Nuclear Operating Company, Inc. Resident inspector
- P. O. Box 1295 Vogtle Plant
! Birmingham, Alabama 35201-1295 8805 River Road i Waynesboro, Georgia 30830 -
Steven M. Jackson Senior Engineer - Power Supply Office of the County Commissioner Municipal Electric Authority Burke County Commission l
of Georgia Waynesboro, Georgia 30830 1470 Riveredge Parkway, NW.
Atlanta, Georgia 30328-4684
1 l
REQUEST FOR ADDITIONAL INFORMATION FOR RESOLUTION OF 4 GENERIC LETTER 96-06 ISSUES AT VOGTLE 1 AND 2 (TAC NOS. M96881 AND M96882)
Generic Letter (GL) 96-06, " Assurance of Equipment Operability and Containment Integrity During Design-Basis Accident Conditions," dated September 30,1996, included a request for licensees to evaluate cooling water systems that serve containment air coolers to assure that they are not vulnerable to waterhammer and two-phase flow conditions. Georgia Power Company (the licer,see) provided its assessment of the waterhammer and two-phase flow issues for Vogtle 1 and 2 in a letter dated January 27,1997. The licensee has concluded that existing flow orifices will prevent two-phase flow situations from occurring in the nuclear service cooling water (NSCW) system, which provides cooling water for the containment air coolers (CACs), the auxiliary containment air coolers, and the reactor cavity coolers. The licensee also concluded that the NSCW system is susceptible to waterhammer, and that pressure spikes could exceed system design pressure. However, the licensee determined that allowable piping stresses for the system would not be exceeded. In order to assess the licensee's resolution of these issues, the following additional information is requested:
Notes: a. Information that has been submitted previously may be referred to and supplemented as necessary to provide a complete response to the staff's questions.
- b. To the extent that positive measures are implemented to eliminate the potential for waterhammer and two-phase flow conditions, question number 3 may not be applicable.
- c. ~ The following questions are applicable to the system configuration and analyses that are credited for the final resolution of the waterhammer and two-phase flow issues.
- 1. Provide a detailed description of the " worst case" scenarios for waterhammer and two-phase flow, taking into consideration the complete range of event possibilities, system configurations, and parameters. For example, all waterhammer types and water slug scenarios should be considered, as well as temperatures, pressures, flow rates, load combinations, and potential component failures. To the extent that the possibility for waterhammer and two-phase flow to occur is eliminated, describe the minimum margin to boiling that will exist.
- 2. If a methodology other than that discussed in NUREG/CR-5220, " Diagnosis of Condensation-induced Waterhammer," was used in evaluating the effects of waterhammer, describe this alternate methodology in detail. Also, explain why this methodology is applicable and gives conservative results (typically accomplished through rigorous plant-specific modeling, testing, and analysis).
1 Enclosure
l
- 3. Identify any computer codes that were used in the waterhammer and two-phase flow analyses and describe the methods used to validate and benchmark the codes for the .
specific application and loading conditions involved. '
- 4. Describe and justify all assumptions and input parameters (including those used in any computer codes) that were used in the waterhammer and two-phase flow analyses, and ~
provide justification for omitting any effects that may be relevant to the analyses (e.g., fluid structure interaction, fl~v induced vibration, erosion). Confirm that these assumptions and input parameters are consistent with the existing design and licensing basis of the plant.
Any exceptions should be explained and justified.
- 5. Explain why voiding in the CACs is limited to the two top coils (i.e., is this an assumption or is it based on heat transfer considerations).
- 6. The January 27,1997, response indicated that additional analyses would be completed to determine if modifications or system operational changes would be required to reduce waterhammer stresses. Describe the additional analyses that were completed and conclusions that were reached.
- 7. Explain and justify all uses of " engineering judgement" that were credited in the
. waterhammer and two-phase flow analyses.
- 8. Discuss specific system operating parameters and other operating restrictions that must be maintained to assure that the waterhammer and two-phase flow analyses remain valid, and explain why it would not be appropriate to establish technical specification requirements to acknowledge the importance of these parameters and operating restrictions. Also, describe and justify use of any nonsafety-related instrumentation and controls for maintaining these parameters.
- 9. Implementing measures to minimize or eliminate waterhammer and two-phase flow conditions may be a viable approach for addressing these issues. However, all scenarios must be considered to assure that the vulnerability to waterhammer and two-phase flow has been eliminated. Confirm that all scenarios have been considered, including those where the affected containment penetrations are not isolated (if this is a possibility), such that the measures that have been established (or will be established) are adequate to address the waterhammer and two-phase flow concems during (and following) all applicable accident scenarios.
l 10. Confirm that the waterhammer and two-phase flow analyses included a complete failure l modes and effects analysis (FMEA) for all components (including electrical and pneumatic failures) that could impact performance of the cooling water system and confirm that the FMEA is documented and available for review, or explain why a complete and fully documented FMEA was not performed.
- 11. Describe the uncertainties that exist in the waterhammer and two-phase flow analyses, including uncertainties and shortcomings associated with the use of any computer codes,
l l
l l end explain how these uncertainties were accounted for in the analyses to assure
- conservative results, i
- 12. The waterhammer and two-phase flow analyses assume that there is no back flow through i the containment supply check valves. Describe measures that exist that assure that these j valves will remain leak-tight over the life of the plant. 1 l
- 13. The response seems to indicate that two-phase flow due to fluid conditions in concert with the pressure drop associated with various system components was not considered.
Confirm that the potential for two-phase flow throughout the affected system was l evaluated and that two-phase flow conditions do not exist for any of the applicable accident scenarios. If it is determined that two-phase flow does exist, then heat transfer, structural, and system integrity concems must be addressed. For example, the following i two-phase flow effects would be relevant:
a the effects of void fraction on flow balance and heat transfer; the consequences of steam formation, transport, and accumulation; cavitation, resonance, and fatigue effects; and
+
erosion considerations.
Licensees may find NUREG/CR-6031, " Cavitation Guide for Control Valves," helpful in addressing some aspects of the two-phase flow analyses.
- 14. The waterhammer analysis was based on analyses of the NSCW system associated with l Unit 1, Train A. Confirm that the analyses that were completed are bounding for the other NSCW trains for both of the Vogtle units.
- 15. Provide a simplified diagram of the affected system, showing major components, active components, relative elevations, lengths of piping runs, and the location of any orifices and flow restrictions.
l 16. Descrite in detail any plant modifications or procedure changes that have been made or f j are planned to be made to resolve the waterhammer and two-phase flow issues, including j schedules for completion. j 1
I
!