Letter Sequence RAI |
---|
EPID:L-2019-LLA-0231, Rulemaking Package: Certificate of Compliance No. 1032, Amendment 6, Model No. HI-STORM FW (Approved, Closed) |
Results
Other: ML20140A191, ML20182A863, ML20182A864, ML20182A865, ML20182A866, ML20182A870, ML20205L597, ML20315A017, ML20356A328, ML20356A330, ML20356A332, ML20356A336, ML21333A141, ML21333A142, ML21333A143, ML22145A407, ML22290A147, ML23041A466, ML23041A467, ML23041A468, ML23041A469
|
MONTHYEARML20140A1912020-05-19019 May 2020 Application for the Model No. Hi-Storm FW: Storage System, Amendment No. 6 - Supplemental Information Needed Project stage: Other ML20182A8622020-06-30030 June 2020 Responses to HI-STORM FW Amd. 6 Requests for Supplemental Information Project stage: Supplement ML20182A8632020-06-30030 June 2020 Attachment 1: HI-STORM FW Amendment 6 Rsi Responses Project stage: Other ML20182A8642020-06-30030 June 2020 Attachment 2: HI-STORM FW Amendment 6 CoC - RSI-Related Changes Project stage: Other ML20182A8652020-06-30030 June 2020 Attachment 3 - HI-STORM FW Amendment 6 CoC, Appendix a - RSI-Related Changes Project stage: Other ML20182A8662020-06-30030 June 2020 Attachment 4: HI-STORM FW Amendment 6 CoC, Appendix B - RSI-Related Changes Project stage: Other ML20182A8702020-06-30030 June 2020 Attachment 8 - Affidavit Project stage: Other ML20205L5972020-08-10010 August 2020 Transmittal Letter: Application for the Model Hi-Storm FW Storage System, Amendment No. 6 - Accepted for Review Project stage: Other ML20267A1662020-09-24024 September 2020 Transmittal Letter and Rais: Application for the Model No. HI-STORM FW Storage System, Amendment No. 6 - Staggered First Request for Additional Information, Thermal Evaluation Project stage: RAI ML20315A0172020-10-31031 October 2020 Fuelsolutions Spent Fuel Management System Certificate of Compliance Renewal Application Project stage: Other ML20280A7412020-11-0606 November 2020 Transmittal Letter: Application for the Model No. Historm FW, Amendment 6 - Structural and Materials Evaluation, Final Staggered Request for Additional Information Project stage: RAI ML20280A7432020-11-0606 November 2020 Enclosure (Rais) to Transmittal Letter: Application for the Model No. Historm FW, Amendment 6 - Structural and Materials Evaluations, Final Staggered Request for Additional Information Project stage: RAI ML20356A3322020-12-21021 December 2020 Attachment 4 - Acceptance Tests and Maintenance Project stage: Other ML20356A3362020-12-21021 December 2020 Affidavit for Kimberly Manzione Project stage: Other ML20356A3302020-12-21021 December 2020 Attachment 2 - SFSC Heat Removal System Project stage: Other ML20356A3292020-12-21021 December 2020 Attachment 1 - Responses to Request for Additional Information Certificate of Compliance No. 1032 Docket No. 72-1032 HI-STORM FW Storage System Amendment No. 6 Project stage: Response to RAI ML20356A3282020-12-21021 December 2020 International Responses to HI-STORM FW Amd. 6 Requests for Additional Information Project stage: Other ML21146A0962021-07-0202 July 2021 Application for the Westinghouse Sentry Dry Storage Cask System, Certificate of Compliance No. 1026, Amendment No. 5 - Request for Additional Information Project stage: RAI ML21214A1322021-08-0202 August 2021 International, Supplemental Responses to HI-STORM FW Amendment 6 Requests for Additional Information Project stage: Supplement ML21333A1392021-11-29029 November 2021 Attachment 1 - HI-STORM FW Amendment 6 RAI Supplemental Responses Revised November 29, 2021 (Non-Proprietary) Project stage: Supplement ML21333A1382021-11-29029 November 2021 International Revised Supplemental Responses for HI-STORM FW Amd. 6 Requests for Additional Information Project stage: Supplement ML21333A1412021-11-29029 November 2021 Attachment 3 - HI-STORM FW FSAR Proposed Revision 7.D Revised November 29, 2021 (Non-Proprietary) Project stage: Other ML21333A1422021-11-29029 November 2021 Attachment 4 - HI-STORM FW Amendment 6 CoC, Appendix a - Revised November 29, 2021 (Non-Proprietary) Project stage: Other ML21333A1432021-11-29029 November 2021 Attachment 5 - Affidavit of Kimberly Manzione Project stage: Other ML22145A4072022-10-13013 October 2022 User Need Memorandum for Rulemaking for the Holtec HI-STORM Flood/Wind Multipurpose Canister Storage System, Amendment No. 6 Project stage: Other ML22145A3132022-10-13013 October 2022, 9 December 2022 Rulemaking Package: Certificate of Compliance No. 1032, Amendment 6, Model No. HI-STORM FW Project stage: Request ML22290A1472022-11-0808 November 2022 Approval of Holtec International Request Withholding Information from Public Disclosure of the Application for Holtec HI-STORM Flood/Wind Multipurpose Canister Storage System, Amendment No. 6 (Docket No. 72-1032) Project stage: Other ML22145A4082022-12-0909 December 2022 Rulemaking Memorandum, Enclosure 1: Draft Certificate of Compliance No. 1032, Amendment No. 6, HI-STORM Flood/Wind Multipurpose Canister Storage System Project stage: Draft Other ML22145A4092022-12-0909 December 2022 Rulemaking Memorandum, Enclosure 2: Draft Appendix a, Technical Specifications, Certificate of Compliance No. 1032, Amendment No. 6, HI-STORM Flood/Wind Multipurpose Canister Storage System Project stage: Draft Other ML22145A4102022-12-0909 December 2022 Rulemaking Memorandum, Enclosure 3: Draft Appendix B, Technical Specifications, Approved Contents and Design Features, CoC No.1032, Amendment No. 6, HI-STORM Flood/Wind Multipurpose Canister Storage System Project stage: Draft Other ML22145A4112022-12-0909 December 2022 Rulemaking Memorandum, Enclosure 4: Preliminary Safety Evaluation Report, Certificate of Compliance. No, 1032, Amendment No. 6, HI-STORM Flood/Wind Multipurpose Canister Storage System Project stage: Approval ML23041A4692023-02-15015 February 2023 Enclosure 3 - Final Appendix B, Technical Specifications, Approved Contents and Design Features, CoC No.1032, Amendment No. 6, HI-STORM Flood/Wind Multipurpose Canister Storage System Project stage: Other ML23041A4702023-02-15015 February 2023 Enclosure 4 - Final Safety Evaluation Report, Certificate of Compliance. No, 1032, Amendment No. 6, HI-STORM Flood/Wind Multipurpose Canister Storage System Project stage: Approval ML23041A4682023-02-15015 February 2023 Enclosure 2 - Final Appendix a, Technical Specifications, Certificate of Compliance No. 1032, Amendment No. 6, HI-STORM Flood/Wind Multipurpose Canister Storage System Project stage: Other ML23041A4672023-02-15015 February 2023 Enclosure 1 - Final Certificate of Compliance No. 1032, Amendment No. 6, HI-STORM Flood/Wind Multipurpose Canister Storage System Project stage: Other ML23041A4662023-02-15015 February 2023 Amendment No. 6 to Certificate of Compliance No. 1032 for the Holtec International Storage Module (Hi-Storm) Flood and Wind (FW) Multipurpose Canister (MPC) Storage System (Docket No. 72-1032, CAC No. 001028, EPID: L-2019-LLA-0231) Project stage: Other 2020-09-24
[Table View] |
|
---|
Category:Letter
MONTHYEARPLA-8148, Registration for the Use of Spent Fuel Storage Casks 311, 308, and 3102024-10-15015 October 2024 Registration for the Use of Spent Fuel Storage Casks 311, 308, and 310 PLA-8142, Registration for the Use of Spent Fuel Storage Casks 306, 309, and 307 - PLA-81422024-09-18018 September 2024 Registration for the Use of Spent Fuel Storage Casks 306, 309, and 307 - PLA-8142 ML24240A1112024-08-27027 August 2024 Registration of Use of Casks to Store Spent Fuel L-24-190, Spent Fuel Storage Cask Registration2024-08-26026 August 2024 Spent Fuel Storage Cask Registration ML24199A2372024-08-13013 August 2024 Letter - Issuance of CoC No. 1032, Amendment 7 for HI-STORM Flood/Wind Multi-Purpose Canister Storage System ML24221A2782024-08-0808 August 2024 Schedule for Responses to HI-STORM FW Amd. 10 Requests for Supplemental Information ML24172A2122024-07-12012 July 2024 Letter - Acceptance Review of Request for Amendment 10 to Certificate of Compliance 1032 for the HI-STORM Flood/Wind Cask System - Request for Supplemental Information ML24138A1242024-07-0909 July 2024 Amendment to List of Approved Spent Fuel Storage Casks: Holtec International, HI-STORM Flood/Wind System Certificate of Compliance No. 1032, Amendment No. 7 ML24191A0612024-07-0606 July 2024 Independent Spent Fuel Storage Installation (ISFSI) - Annual Radioactive Effluent Release Report ML24158A5312024-06-0606 June 2024 Registration of Use of Cask to Store Spent Fuel (MPC-361, -362, -363) ML24100A0282024-04-0808 April 2024 HI-STORM FW Amendment 7 RAI Response Clarifications (Part 5) ML24082A0082024-03-22022 March 2024 Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 ML24109A2502024-03-0101 March 2024 International - HI-STORM FW Amendment 10 Request CNL-24-012, Request for Exemption from Various Part 72 Regulations Resulting from Fuel Basket Design Control Compliance2024-02-28028 February 2024 Request for Exemption from Various Part 72 Regulations Resulting from Fuel Basket Design Control Compliance ML24047A3242024-02-16016 February 2024 International, HI-STORM FW Amendment 7 RAI Response Clarifications (Part 4) ML24016A1902024-01-30030 January 2024 International, Inc. - Notice of Violation; the U.S. Nuclear Regulatory Commission Inspection Report 07201014/2022201 ML24018A1992024-01-18018 January 2024 International, Administrative Change to HI-2200343-A ML23361A1622024-01-0404 January 2024 Application for HI-STORM Flood/Wind Multipurpose Storage System, Amendment No. 9 - Acknowledgement of Withdrawal and Notification of the U.S. Nuclear Regulatory Commission Staff Efforts Closure ML23355A0812023-12-21021 December 2023 International - Withdrawal of HI-STORM FW Multipurpose Canister Storage System Amendment 9 ML23321A2462023-11-17017 November 2023 HI-STORM FW Amendment 7 RAI Response Clarifications (Part 3) ML23289A2132023-10-16016 October 2023 International - Schedule for Responses to HI-STORM FW Amendment 9 Requests for Additional Information ML23229A5172023-10-0404 October 2023 Amendment No. 9 to Certificate of Compliance No. 1032 for the HI-STORM Flood/Wind Multipurpose Canister Storage System - Request for Additional Information ML23271A1662023-09-28028 September 2023 Registration of Spent Fuel Storage Cask Pursuant to 10 CFR 72.212(b)(2) ML23145A1752023-09-12012 September 2023 NRC Choice Letter to Holtec International with Attached Safety Inspection Report, IR 72-1014/2022-201, December 12-15, 2022, Inspection of Holtec International in Camden, New Jersey (Docket Nos.: 72-1014, 72-1032) ML23254A0652023-09-0707 September 2023 Registration of Spent Fuel Storage Cask Pursuant to 10 CFR 72.212(b)(2) ML23254A0012023-09-0505 September 2023 Registration of Use of Casks to Store Spent Fuel ML23227A2492023-08-15015 August 2023 International, HI-STORM FW Amendment 7 RAI 3-10 Response Clarification Call Action Items ML23192A0322023-07-11011 July 2023 International, HI-STORM FW Amendment 7 RAI Responses Part 5 Clarification Corrected Attachments 4 and 5 ML23188A0532023-07-0707 July 2023 Registration of Use of Independent Spent Fuel Storage Installation (ISFSI) Casks NMP2L2846, Nine Mire Point Nuclear Station, Units 1 and 2, General License 30-day Cask Registration Notifications2023-07-0505 July 2023 Nine Mire Point Nuclear Station, Units 1 and 2, General License 30-day Cask Registration Notifications ML23184A1392023-07-0303 July 2023 Registration of Use of Cask to Store Spent Fuel (MPC-295, -296, -297) ML23181A1932023-06-30030 June 2023 International HI-STORM FW Amendment 7 RAI Responses Part 5 Clarification Call Action Items ML23163A1782023-06-12012 June 2023 Registration of Use of Cask to Store Spent Fuel (MPC-292, -293, -294) ML23128A3032023-05-0808 May 2023 International - HI-STORM FW Amendment 7 Responses to Requests for Additional Information Part 5 ML23096A3012023-04-0606 April 2023 International - Schedule for Responses to HI-STORM FW Amendment 7 Requests for Additional Information Part 5 ML23074A1022023-03-23023 March 2023 Letter, Amendment No. 7 to CoC No. 1032 for the HI-STORM_RAI ML23072A4272023-03-13013 March 2023 International, HI-STORM FW Multipurpose Canister Storage System Amendment 9 Obs Responses ML23041A4662023-02-15015 February 2023 Amendment No. 6 to Certificate of Compliance No. 1032 for the Holtec International Storage Module (Hi-Storm) Flood and Wind (FW) Multipurpose Canister (MPC) Storage System (Docket No. 72-1032, CAC No. 001028, EPID: L-2019-LLA-0231) ML23025A3712023-02-10010 February 2023 Acceptance Review of Request for Amendment 9 to Certificate of Compliance No. 1032 for HI-STORM Flood/Wind Multipurpose Canister Storage System ML22300A1512023-02-0303 February 2023 Congressional Letters - Holtec International HI-STORM Flood - Wind Multipurpose Canister Storage System, Certificate of Compliance No. 1032, Amendment No.6 ML23006A2642023-01-0606 January 2023 International HI-STORM FW Amendment 7 Responses to Requests for Additional Information Part 4 L-22-263, Spent Fuel Storage Cask Registration2022-12-12012 December 2022 Spent Fuel Storage Cask Registration ML22326A3612022-12-0707 December 2022 Amendment No. 7 to Certificate of Compliance No. 1032 for the HI-STORM Flood/Wind Multipurpose Canister Storage System Request for Additional Information Batch 4 Letter ML22336A1332022-12-0101 December 2022 HI-STORM FW Amendment 7 RAI 5-2 Response Clarification PLA-8036, Registration for the Use of Spent Fuel Storage Casks 203, 202, and 204, PLA-80362022-11-30030 November 2022 Registration for the Use of Spent Fuel Storage Casks 203, 202, and 204, PLA-8036 PLA-8035, Registration for the Use of Spent Fuel Storage Casks 205, 200, and 201, PLA-80352022-11-0808 November 2022 Registration for the Use of Spent Fuel Storage Casks 205, 200, and 201, PLA-8035 ML22290A1472022-11-0808 November 2022 Approval of Holtec International Request Withholding Information from Public Disclosure of the Application for Holtec HI-STORM Flood/Wind Multipurpose Canister Storage System, Amendment No. 6 (Docket No. 72-1032) ML22276A2822022-10-0303 October 2022 International, HI-STORM FW Amendment 7 Responses to Requests for Additional Information Part 3 ML22265A1732022-09-22022 September 2022 Registration of Use of Casks to Store Spent Fuel ML22258A2512022-09-15015 September 2022 International, HI-STORM FW Amendment 7 RAI Responses Part 1 Clarification Call Action Items 2024-09-18
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24172A2132024-07-12012 July 2024 Enclosure 1 - Non-Proprietary Rsi and Observations FW10 ML23229A5162023-10-0404 October 2023 Enclosure - FW A9 Request for Additional Information ML23216A2192023-08-0303 August 2023 Conversation Record: Discuss Responses to RAI 3-10 for HI-STORM FW Amendment 7, August 3, 2023 ML23216A2182023-08-0303 August 2023 Conversation Record Attachment: Clarification Questions for RAI 3-10 for HI-STORM FW Amendment 7 ML23074A1052023-03-23023 March 2023 Enc - Amendment No. 7 to the HI-Storm Flood/Wind Multipurpose Canister Storage System RAI Batch 5 ML22326A3592022-12-0707 December 2022 Amendment No. 7 to Certificate of Compliance No. 1032 for the HI-STORM Flood/Wind Multipurpose Canister Storage System Request for Additional Information Batch 4 Enclosure 1 ML22172A1932022-06-30030 June 2022 Amendment No. 7 to Certificate of Compliance No. 1032 for the HI-STORM Flood/Wind Multipurpose Canister Storage System Request for Additional Information Batch 2 ML20280A7432020-11-0606 November 2020 Enclosure (Rais) to Transmittal Letter: Application for the Model No. Historm FW, Amendment 6 - Structural and Materials Evaluations, Final Staggered Request for Additional Information ML20280A7412020-11-0606 November 2020 Transmittal Letter: Application for the Model No. Historm FW, Amendment 6 - Structural and Materials Evaluation, Final Staggered Request for Additional Information ML20267A1662020-09-24024 September 2020 Transmittal Letter and Rais: Application for the Model No. HI-STORM FW Storage System, Amendment No. 6 - Staggered First Request for Additional Information, Thermal Evaluation ML19247B7182019-09-0303 September 2019 Letter to J. Tomlinson Amendment No. 5 to Certificate of Compliance No. 1023 for the HI-STORM Flood/Wind Multipurpose Canister Storage System - Request for Additional Information (W/Enclosure 1) ML19046A0642019-02-13013 February 2019 Letter to J. Tomlinson Acceptance Review of Request for Amendment No. 5 to Certificate of Compliance No. 1032 for the HI-STORM Flood/Wind Cask System (W/Enclosure) ML19011A1272019-01-29029 January 2019 Letter to K. Manzione Amendment No. 4 to Certificate of Compliance No. 1032 for the HI-STORM Flood/Wind Multipurpose Canister Storage System - Second Request for Additional Information (W/Enclosure) ML18022A6122018-01-19019 January 2018 Letter to K. Manzione Amendment No. 4 to Certificate of Compliance No. 1032 for the HI-STORM Flood/Wind Multipurpose Canister Storage System-Request for Additional Information 2024-07-12
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 November 6, 2020 Christopher OMullane Licensing Engineer Holtec International Holtec Technology Campus 1 Holtec Blvd.
Camden, NJ 08104
SUBJECT:
APPLICATION FOR THE MODEL NO. HI-STORM FW STORAGE SYSTEM, AMENDMENT NO. 6 - FINAL STAGGERED REQUEST FOR ADDITIONAL INFORMATION
Dear Mr. OMullane:
By letter dated October 2, 2019 [Agencywide Documents Access and Management System (ADAMS) Package Accession No. ML19282C357], and as supplemented on June 30, 2020 (ADAMS Package Accession No. ML20182A860), Holtec International (the applicant) requested to amend Certificate of Compliance (CoC) No. 1032, Model No. HI-STORM FW Storage System. The applicant proposes the following changes:
- 1) Adding an anchored configuration of the HI-STORM FW storage system.
- 2) Allowing non-single failure proof lifting equipment during handling of heavy loads processes (within the 10 CFR Part 72 jurisdictional boundary).
- 3) Revising LCO 3.1.2, SFSC Heat Removal System Operability, to allow an engineering evaluation to be performed in lieu of transferring the multi-purpose canister (MPC) into a transfer cask.
- 4) No longer require the annual submittal of a separate radioactive effluent report for the HI-STORM FW system.
- 5) For the MPC models MPC-37, -89, and -32ML, revise the following:
- a. the allowable contents to clarify the requirements for fuel debris permitted for storage, and
- b. the basket Design Features to clarify that the minimum cell inside dimension (ID) and minimum cell wall thickness are nominal dimensions.
The staff is issuing a final staggered request for additional information (RAI). The staff issued the first staggered RAI on September 24, 2020 (ADAMS Accession No. ML20267A166). In connection with our review, we need the information identified in the enclosure to this letter.
The enclosure contains only the questions related to the structural and materials evaluation.
Additional information requested by this letter should be submitted in the form of revised safety analysis report pages, when applicable. Please provide your complete responses to both requests for additional information within the same submittal. To assist us in scheduling, the staff review of your response, we request that you provide this information 45 calendar days from the date of this letter. Inform us at your earliest convenience, but no later than 15 days
C. OMullane from the date of this letter, if you are not able to provide the information by the timeline specified in this letter. If you are unable to provide a response 45 calendar days from the date of this letter, our review may be delayed.
Please reference Docket No. 72-1032 and EPID No. L-2019-LLA-0231 in future correspondence related to this request. The staff is available to meet and discuss your proposed responses. If you have any questions regarding this matter, I may be contacted at Norma.GarciaSantos@nrc.gov.
Sincerely, Norma Garcia Digitally signed by Norma Garcia Santos Santos Date: 2020.11.06 06:02:00 -05'00' Norma García Santos, Project Manager Storage and Transportation Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards Docket No. 72-1032 EPID No. L-2019-LLA-0231
Enclosure:
Final Staggered RAI