Responds to NRC 790921 Ltr Re Position That Facility Could Not Provide Independent Review of ASME Boiler & Pressure Vessel Code Section XI Program.Will Use Third Party for Future Insp Programs
ML19254C732
Person / Time
Site: Sequoyah  Tennessee Valley Authority icon.png
Issue date: 10/12/1979
From: Mills L
TENNESSEE VALLEY AUTHORITY
To: Rubenstein L
Office of Nuclear Reactor Regulation
References
NUDOCS 7910170279
Download: ML19254C732 (1)


Text

TENNESSEE VALLEY AUTHORITY CH ATTANOOGA. TENNESSEE 374o1 400 Chestnut Street Tower II October 12, 1979 Director of a.aclear Reactor Regulation Attention: Mr. L. S. Rubenstein Acting Chief Light Water Reactors Branch No. 4 Division of Project Management U.S. Nuclear Regulatory Commission Washington, DC 20555

Dear Mr. Rubenstein:

In the Matter of the Application of ) Docket Nos. 50-327 Tennessee Valley Authority ) 50-328 In your letter to H. G. Parris dated September 21, 1979, it was stated that the NRC did not agree with the position that TVA could provide its own independent review of the Section XI program. It was also stated that TVA was not exempt from the requirements of 10 CFR Part 50, Section 50.55a(g)(4) concerning the ASME Boiler and Pressure Vessel Code. Since it was the NRC's position that TVA could not provide its own inspection services on the basis that it is a federal agency, TVA was required to institute a third party inspection system for the Sequoyah Nuclear Plant.

The preservice inspection work for unit 1 is essentially complete, and we do not believe it is practical to bring in a third party at thir time.

The NRC has been auditing the unit 1 inspection work as it has a .

progressing. TVA has been working under the exception nc*ed in tue answer to Q5.19 dated November 27, 1974, of the Sequoyah final Safety Analysis Report.

We will use the th_ird party inspector for future preservice inspection work for Sequoyah unit 2 and future inservice inspection and testing for both units 1 ano 2.

Very truly yours, TENNESSEE VALLEY AUTHORITY L. M. Mills, Manager Nucl.sr Regulation and Safety 1157 J51 -

1910170 104' A