ML19326C628

From kanterella
Revision as of 23:20, 31 January 2020 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search
Documents 780707 Telcon & Submits Fire Protection Plan Implementing Five Man Brigade.Plan to Be Implemented 90 Days After SER Issuance
ML19326C628
Person / Time
Site: Arkansas Nuclear Entergy icon.png
Issue date: 07/07/1978
From: David Williams
ARKANSAS POWER & LIGHT CO.
To: Reid R, Stolz J
Office of Nuclear Reactor Regulation
References
1-078-4, 1-78-4, NUDOCS 8004240569
Download: ML19326C628 (5)


Text

- A 3/nht (

t

  • REGULATORY INFORMATION DISTRIBUTION SYSTEM (RIDS DISTRIDUTION FOR INCOMING MATERIAL 50-319 368 REC: STOLZ J F ORG: WILLIAMS D H DOCDATE: 07/07/78 NRC AR PWR & LIGHT DATE RCVD: 07/14/78 DOCTYPE: LETTER NOTARIZED: NO COPIES RECEIVED

SUBJECT:

LTR 4 ENCL 40 SUBMISSION OF FIRE PROTECTION PLAN IMPLEMENTING A FIVE MAN FIRE BRIGADE.

[@ 7*7-7f TELECW m)/ apt-l.4, .. . W/ ATC / -wr xmane immm in SAF6tY AEl.ATED gpA)CS.

PLANT NAME: ARKANOAS - UNIT 1 REVIEWER INITI AL: XRS ARKANSAS 1 - UNIT 2 DISTRIBUTER INITIAL: p oooo*o*********** DISTRIBUTION OF THIS MATERIAL IS AS FOLLOWS ******************

FIRE PROTECTION (PRIOR TO ISSUANCE OF OL).

(DISTRIBUTION CODE BOO 2)

FOR ACTION: BR CHIEF ORBH4 BC**W/ ENCL PROJ MGR VISSING**W/ ENCL L r ^5T '"" 4 LA**La%If0NLOL INTERNAL: _ REG FILE **W/ ENCL 'l NRC PDR**W/ ENCL UELU**L i n urat Y I & E**W/3 ENCL DIRECTOR DPM**LTR ONLY DE YOUNG **LT' G.?

VASGALLO**LTR ONLY DIRECTOR DSF**W/ ENCL AD FOR PLANT SYSTEMS **W/ ENCL AUXILIARY SYS BR**W/2 ENCL I & C SYSTEMS BR**LTR ONLY AD FOR QA & O**LTR ONLY QAB**W/ ENCL R. MURANAKA**LTR ONLY HANAUER**W/ ENCL STOL L Wll M EXTERNAL: LPDR'S g gp) o;/EMC(

RUSSELLVILLE, AR**W/ ENCL fiYAfDA>ol/A M TERA **W/ ENCL NSIC**W/ ENCL POWER SYS BR**W/ ENCL PLANT SYSTEMS BR**W/2 ENCL AD FOR SYS & PROJ**LTR ONLY DIRECTOR DOR **LTR ONLY OPERATOR LIC BR**W/ ENCL THIS DOCU AENT CONTAINS ACRS CAT B4*W/16 ENCL POOR Qi'AI.iTY PAGES l

N 50 40 NBUTION: LTR % ENCL C.4. CONTRGL NBR:7&I90vi90 )

VP+1P g

'w************************** THE END **********************************O

', 8004240@ f

.s- -

(

F MGLlTORY B0CKET RJ.&

ARKANSAS POWER & LIGHT COMPANY POST OFFICE BOX 551 LRTLE ROCK. ARKANSAS 72203 (501) 371-4000 July 7, 1978 o $i G l-078-4 G 2-078-6 h'.- 40

.p?

. . . on Director of Nuclear Reactor Regulation .

.c i M 23 ATTN: Mr. J. F. Stolz, Chief ;t Light Water Reactor Branch #1 "

"Si h E Mr. Robert W. Reid, Chief C U ~

Operating Reactor Branch #4 U. S. Nuclear Regulatory Commission Washington, D. C. 20555

Subject:

Arkansas Nuclear One-Units 1 & 2 Docket No. 50-313 & 50-368 License No. DPR - 51 Fire Protection (File: 1510 2040 2-1510 2-2040)

Gentlemen:

The following is provided to document the telecon of July 7, 1978, between Mr. Bob Reed et al. of NRC and Mr. Don Rueter et al. of AP&L.

As agreed in the telecon, we will implement a five (5) man Fire Brigade. The Brigade will consist of three (3) personnel who have received the full training as outlined in the Fire Protection Plan and whose primary responsibility is fire fighting and two (2) personnel (Support Personnel) whose primary responsibility is a support role to the three (3) fire fighting personnel. The Support Personnel will be trained the same as the three (3) fire fighting personnel (in accordance with the Fire Protection Plan) with the following exceptions:

1. Installed Plant Fire Protection Systems.

The training for the Support Personnel will not include l strategy as it applies to the actuation of installed l

automatic systems. The Support Personnel will actuate an installed automatic system only under direct order from a fully trained Fire Brigade Member who will make the decision for the necessity of the actuation of that l

system based on his training in the strategy of fight- l ing fires.

V l

- 7sivege~ g 4ff)b o

( (

1-078-4 2-078-6 .

Mr. J. F. Stolz &

Mr. R. W. Reid July 7, 1978

2. Fire Fighting Strategy.

The Support Personnel will of how to approach and extinguish differentbe trainedtypesin the basics of fires but fighting will not be trained in detailed fire strategies. They will receive training in how to read and interpret the Pre Fire Plans. The plans, Personnelhowever, will not in detailed s trabetegy.

used to train the Support The above information should supersede our letter of June 29 1978, and will be incorporated in our Fire Protection Plan. ,

As also discussed in the above telecon, the following implemen-tation schedules are provided, letter in which the commitment to implementlisted under the date of our was made. the modification

_0ctober 26, 1977 next (1st) ANO-2 refueling outage.The modification to zone 2136-February 3, 1978 Modifications next (3rd) ANO-1to zones 99-M refueling and 100-N will be completed by the outage.

i The modification to zone 73-W will be complete by July, 1979.

For zone 2096-M, December, 1978. the cable tray barriers will be provided by The smske detectors will be provided by the h end of the next (1st) ANO-2 refueling outage. j Modification next (1s t) ANO-2to zone 2109-U will be provided by the end of the refueling outage. ,

_Ap r i l 12, 1978 provided by March 31,1979. Item 32 (fixed repeaters and portable communicatio April 26, 1978 fica tions are required, Item PF.5 (ANO-1 cab'e penetration fire s top testin If modi-4th (1980) ANO-1 refueling they will be completed by the end of the outage. This delay is required due to form testing, evaluatethe amount cf time necessary to compile information and/o fications are necessary.results, and engineer new designs if modi-

(

l-078-4 2-078-6 Mr.J. E. Stolz &

Mr. R. W. Reid Jui? ' , 1978 Item PF.13 (Portable water or halon extinguisher in the Control Rooms). This modification will be provided by November 15, 1978.

Item PF.19 (Control of Fire Doors).

by March 31, 1979.

This item will be implemented June 29, 1978 Item PF.20 (RCP Oil Collection System). Modifications (if re-quired) will be provided by the end of the 4th (1980) ANO-1 re-fueling outage for ANO-1 and by the next refueling outage for ANO-2.

Item 8b. Associated Circuitry. Modifications (if required) will be provided by the end of the 4th ANO-1 refueling outage (1980).

Item 8h (PF.21) (Smoke Detectors in Safety Related Zones)

As agreed in the above telecon, our response to this item re-quires a few changes. These changes are discussed below and a new list (Attachment I) is provided. This information should supersede our response of June 29, 1978.

Zone 144-D has been deleted as smoke detectors are presently installed in this zone.

Zone 2E has been deleted as there are no combustibles in the zone and the zone is outside (open to the atmosphere).

Zone 10 EE is added to the list as it contains one (1) channel of safety circuitry and low combustibles.

As agreed with the Staff in the above telecon, the Fire Protection Plan will be implemented 90 days af ter the issuance of the SER.

Very ruly yours,

/

  1. 11 Daniel H. Williams Manager, Licensing DHW/JTE/ew Attachment

r- -

' (

ATTACHMENT 1 Smoke Detector Installation in Safety Related Zones ANO-1 ANO-2 159-B 2156-A 167-B 2114-I 128-E 2115-I 68-P 2136-I 104-S 2107-N 79-U 2106-R 77-V 2109-U 73-W 2068-DD 76-W 2073-DD 20-Y 2084-DD 34-Y 2076-HH 40-Y ' 2081-HH 46-Y 2024-JJ 47-Y 2025-JJ 53-Y 2040-JJ 10-EE 2055-JJ 14-EE 2223-KK

, ANO-1 Intake 2006-LL 2007-LL 2010-LL 2011-LL 2014-LL 2200-MM ANO-2 Intake 1

\;

-\

\

\.

N'y

. . . . _ . . - , . _ , _ _ . _ . - - . - . . _ . _ _ _ . .