IR 05000219/2012006

From kanterella
Revision as of 06:55, 12 May 2019 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
Jump to navigation Jump to search
Mid-Cycle Performance Review and Inspection Plan 2012 - Oyster Creek Nuclear Generating Station (Report 05000219/2012006)
ML12240A257
Person / Time
Site: Oyster Creek
Issue date: 09/04/2012
From: Hunegs G K
NRC/RGN-I/DRP/PB6
To: Pacilio M J
Exelon Nuclear Generation Corp
HUNEGS, GK
References
IR-12-006
Download: ML12240A257 (5)


Text

September 4, 2012

Mr. Michael Senior Vice President, Exelon Generation Company, LLC President and Chief Nuclear Officer, Exelon Nuclear

4300 Winfield Rd.

Warrenville, IL 60555

SUBJECT: MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN - OYSTER CREEK NUCLEAR GENERATING STATION (REPORT 05000219/2012006)

Dear Mr. Pacilio:

On August 16, 2012, the U. S. Nuclear Regulatory Commission (NRC) completed its mid-cycle performance review of Oyster Creek Nuclear Generating Station. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from July 1, 2011 through June 30, 2012. This letter informs you of the NRC's assessment of your facility during this period and its plans for future inspections at your facility.

This assessment reflects the integration of the Security Cornerstone into the ROP performance assessment program governed by IMC 0305, "Operating Reactor Assessment Program."

The NRC determined the performance at Oyster Creek during the most recent quarter was within the Licensee Response Column of the NRC

=s Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., green).

Therefore, the NRC plans to conduct ROP baseline inspections at your facility.

The enclosed inspection plan lists the inspections scheduled through December 31, 2013. Routine inspections performed by resident inspectors are not included in the inspection plan. In addition to the baseline inspections, consistent with the Agency's actions related to Fukushima, the NRC will perform TI-187, "Inspection of Near Term Task Force Recommendation 2.3 Flooding Walkdowns" and TI-188, "Inspection of Near Term Task Force Recommendation 2.3 Seismic Walkdowns." Additionally, inspections will be performed for the operation of your Independent Spent Fuel Storage Installation and a follow up inspection for three or more severity level IV traditional enforcement violations in the same area in a 12 month period. The inspections listed during the last nine months of the inspection plan are tentative and may be

revised at the end-of-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence.

In accordance with 10 CFR 2.390 of the NRC

=s A Rules of Practice,@ a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide Document Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room.

Please contact me at 610-337-5046 with any questions you have regarding this letter.

Sincerely,

/RA/ Gordon K. Hunegs, Chief Projects Branch 6

Division of Reactor Projects Docket Nos.: 50-219 License Nos.: DPR-16

Enclosure: Oyster Creek Inspection/Activity Plan

cc w/encl: Distribution via ListServ

ML12240A357 SUNSI Review Non-Sensitive Sensitive Publicly Available Non-Publicly Available OFFICE RI/DRP RI/DRP NAME ADugandzic/ AD GHunegs/ GKH DATE 08/23 /12 08/27/12

Page 1 of 2 08/27/2012 08:55:50 Report 22 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Oyster Creek Inspection / Activity Plan 07/01/2012

-12/31/2013 71124-RAD MONT INSTRUMENTION & TI 2515/185 GW 1 1 IP Follow-up on the Industry's Ground Water Protection Initiative 2515/185 08/06/2012 08/09/2012 1 IP Radiation Monitoring Instrumentation 71124.05 08/06/2012 08/09/2012 71152B-PI&R 4 1 IP Problem Identification and Resolution 71152B 08/13/2012 08/17/2012 1 IP Problem Identification and Resolution 71152B 08/27/2012 08/31/2012 2515/187-FLOODING WALKDOWNS 2 1 IP Inspection of Near-Term Task Force Recommendation 2.3 Flooding Walkdowns 2515/187 08/16/2012 09/06/2012 2515/188-SEISMIC WALKDOWNS 3 1 IP Inspection of Near-Term Task Force Recommendation 2.3 Seismic Walkdowns 2515/188 08/20/2012 08/24/2012 71124-RAD HAZARD ALARA AIRBORNE & DOSE ASSESSM 1 1 IP Radiological Hazard Assessment and Exposure Controls 71124.01 08/20/2012 08/24/2012 1 IP Occupational ALARA Planning and Controls 71124.02 08/20/2012 08/24/2012 1 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 08/20/2012 08/24/2012 1 IP Occupational Dose Assessment 71124.04 08/20/2012 08/24/2012 60855-ISFSI OPERATIONAL INSPECTION 1 1 IP Operation Of An ISFSI 60855 10/03/2012 10/03/2012 1 IP Operation of an Independent Spent Fuel Storage Installation at Operating Plants 60855.1 10/03/2012 10/03/2012 71124- HP INSPECTION 01 02 03 04 1 1 IP Radiological Hazard Assessment and Exposure Controls 71124.01 10/22/2012 10/26/2012 1 IP Occupational ALARA Planning and Controls 71124.02 10/22/2012 10/26/2012 1 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 10/22/2012 10/26/2012 1 IP Occupational Dose Assessment 71124.04 10/22/2012 10/26/2012 EP PROGR-EP PROGRAM INSPECTION 1 1 IP A lert and Notification System Testing 7111402 10/29/2012 11/09/2012 1 IP Emergency Preparedness Organization Staffing and Augmentation System 7111403 10/29/2012 11/09/2012 1 IP Correction of Emergency Preparedness Weaknesses and Deficiencies 7111405 10/29/2012 11/09/2012 7111108G-INSERVICE INSPECTION 1 1 IP Inservice Inspection Activities - BWR 7111108G 10/29/2012 11/02/2012 71124-71124.06 RAD EFFLUENT MONT TREATMENT 1 1 IP Radioactive Gaseous and Liquid Effluent Treatment 71124.06 01/28/2013 02/01/2013 60855-ISFSI LOADING INSPECTION 1 1 IP Operation Of An ISFSI 60855 03/01/2013 05/24/2013 1 IP Operation of an Independent Spent Fuel Storage Installation at Operating Plants 60855.1 03/01/2013 05/24/2013 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Page 2 of 2 08/27/2012 08:55:50 Report 22 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Oyster Creek Inspection / Activity Plan 07/01/2012

-12/31/2013 7111111B-OYSTER CREEK REQL INSP WITH P/F RESULTS 2 1 IP Licensed Operator Requalification Program 7111111Q 05/27/2013 05/31/2013 71124-OC IP 71124.07 REMP 1 1 IP Radiological Environmental Monitoring Program 71124.07 06/10/2013 06/14/2013 7111121-CDBI 6 1 IP Component Design Bases Inspection 7111121 09/09/2013 09/13/2013 1 IP Component Design Bases Inspection 7111121 09/23/2013 09/27/2013 1 IP Component Design Bases Inspection 7111121 10/07/2013 10/11/2013 EP EX-EP EXERCISE EVALUATION 5 1 IP Exercise Evaluation 7111401 10/07/2013 10/11/2013 1 IP Emergency Action Level and Emergency Plan Changes 7111404 10/07/2013 10/11/2013 TI-182-DEGRAD UNDERGROUND PIPING - PHASE 2 1 1 IP Review of the Implementation of the Industry Initiative to Control Degradation of Underground Piping 2515/182 10/28/2013 11/01/2013 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.