MONTHYEARML23291A0572023-10-25025 October 2023 Environmental Scoping Meeting Related to the Perry Nuclear Power Plant, Unit 1 License Renewal Application - Virtual Meeting Slides ML23291A0702023-10-18018 October 2023 Environmental Scoping Meeting Related to the Perry Nuclear Power Plant, Unit 1 License Renewal Application - In-person Meeting Slides ML23044A2122023-02-14014 February 2023 February 14, 2023, Second Perry Nuclear Power Plant License Renewal Environmental Pre-application Public Meeting - Energy Harbor Slides ML23044A2082023-02-14014 February 2023 February 14, 2023, Second Perry Nuclear Power Plant License Renewal Environmental Pre-application Public Meeting - NRC Slides ML22199A0352022-07-21021 July 2022 July 21, 2022, Perry Nuclear Power Plant License Renewal Environmental Pre-application Public Meeting - Energy Harbor Slides ML22199A0232022-07-21021 July 2022 July 21, 2022, Perry Nuclear Power Plant License Renewal Environmental Pre-application Public Meeting - NRC Slides ML22200A2222022-07-21021 July 2022 License Renewal Application - Safety Pre-Application Meeting July 21, 2022 (Perry Slides) ML22201A0052022-07-19019 July 2022 License Renewal Application - Safety Pre-Application Meeting July 21, 2022 (NRC Slides) ML21176A1992021-06-25025 June 2021 Slideshow Presentation for 2020 End -of-Cycle Public Meeting for Davis-Besse and Perry ML21047A1522021-02-16016 February 2021 Slides - Perry Pre-Application Flooding 2/16/2021 Meeting Slides (L-2021-LRM-10016) ML20210M0712020-07-27027 July 2020 Combined End-of-Cycle 2019 Public Meeting Slide Presentation ML18310A1772018-11-0909 November 2018 Slides Presentation for November 9, 2018, Pre-Submittal Teleconference Call Regarding Changes to Emergency Plan ML18054B6002018-02-21021 February 2018 Drywell General Area Heat Detectors License Amendment Request - Pre-Submittal Meeting, Perry Nuclear Power Plant, February 21, 2018 ML17187A5742017-06-29029 June 2017 FENOC - NRC Pre-Submittal Meeting, Proposed Request for Licensing Action, Perry Flood Hazards Public Meeting Handout ML16307A4052016-09-14014 September 2016 R-III Rug 15 Sep 16 Presentation ML16047A1332016-02-0909 February 2016 February 9, 2016, Public Meeting Slides for License Amendment Request for Drain Down of Upper Containment Pool in Mode 3 ML14079A0912014-03-18018 March 2014 NRC - Perry 2013 Annual Assessment Public Meeting Slides ML13294A5972013-10-21021 October 2013 FENOC Presentation Slides for Public Meeting September 24, 2013 ML13281A5302013-10-15015 October 2013 Meeting Slide for FENOC - NRC Pre-Submittal Meeting Request for Licensing Action ML13101A1432013-04-10010 April 2013 NRC 2012 Annual Assessment Presentation ML12269A0612012-09-26026 September 2012 FENOC Presentation for 2012-09-26 Public Meeting ML12094A2932012-04-0303 April 2012 Licensee Slides for Annual Assessment Meeting ML1122408232011-08-11011 August 2011 Annual Assessment Meeting, 2010 Reactor Oversight Program ML1021500692010-07-28028 July 2010 NRC Slides for Perry, July 28, 2010; Annual Assessment Meeting ML1021500852010-07-28028 July 2010 Licensee Slides for Perry; July 28, 2010; Annual Assessment Meeting ML0932005842009-11-12012 November 2009 FENOC Presentation for NRC Public Meeting ML0920900792009-07-21021 July 2009 Licensee Slides from End of Cycle - Public Meeting ML0708602352007-03-21021 March 2007 Slides, Perry Confirmatory Action Letter Closure Meeting. ML0708602302007-03-21021 March 2007 Slides, Perry Annual Assessment Meeting Reactor Oversight Process - Cy 2006. ML0706501602007-02-28028 February 2007 Meeting Handout on MP2 SPAR Model ML0634900272006-12-13013 December 2006 NRC Slides from Public Meeting to Discuss Results of NRC Confirmatory Action Letter Follow-Up Inspections ML0623001242006-08-15015 August 2006 Licensee Public Meeting Slides ML0607507382006-03-14014 March 2006 NRC Perry CAL Inspections IP 95002 CAP Action Item Slides ML0607507342006-03-14014 March 2006 NRC Perry Annual Assessment Meeting Slides ML0607507312006-03-14014 March 2006 March 14 Public Meeting Annual Assessment Final Slides ML0603002272006-01-10010 January 2006 Multi-Regional NRC Public Meeting Licensee (FENOC) Slide Presentation ML0529201782005-10-12012 October 2005 Slides for CAL Public Meeting Summary 10-12-05, Perry Nuclear Power Plant ML0513701772005-05-12012 May 2005 Attachment 3 - Licensee Presentation (Ginna, Perry, Peach Bottom, LaSalle, and Quad Cities) - Public Meeting Summary on FAQ Appeal Meeting May 12, 2005 ML0509404132005-04-0404 April 2005 Fenoc'S EOC Public Meeting Slides for Perry ML0430901982004-10-28028 October 2004 Licensee Slides from Perry Nuclear Power Plant Public Meeting ML0412602572004-04-20020 April 2004 Public Meeting Licensee Slides, Perry 2003 End - of - Cycle Assessment ML0336503762003-12-23023 December 2003 Meeting Handout Material, Emergency Service Water (ESW) Pump Coupling Failure. ML0335002242003-12-0909 December 2003 Slides from December 9, 2003 Regulatory Conference Re April 24, 2003 Alert ML0324812782003-09-10010 September 2003 Agenda and Handout for Public Meeting Between NRC and Firstenergy Nuclear Operating Company Davis-Besse Nuclear Power Station ML0309204812003-04-0707 April 2003 Summary of Meeting with Firstenergy Nuclear Operating Company to Present Results of NRC End of Cycle Assessment for Perry Nuclear Power Plant. NRC Presentation Slides ML0220407282002-07-16016 July 2002 Meeting Handout with FENOC Re IMC 0350 Restart Oversight Panel Public Meeting - July 16, 2002 ML0210002192002-04-0303 April 2002 EOC Meeting Slides 2023-02-14
[Table view] Category:Slides and Viewgraphs
MONTHYEARML23291A0572023-10-25025 October 2023 Environmental Scoping Meeting Related to the Perry Nuclear Power Plant, Unit 1 License Renewal Application - Virtual Meeting Slides ML23291A0702023-10-18018 October 2023 Environmental Scoping Meeting Related to the Perry Nuclear Power Plant, Unit 1 License Renewal Application - In-person Meeting Slides ML23046A1682023-02-16016 February 2023 License Renewal Application - 2nd Safety Pre-Application Meeting, February 16, 2023 (Perry Slides) ML23044A2122023-02-14014 February 2023 February 14, 2023, Second Perry Nuclear Power Plant License Renewal Environmental Pre-application Public Meeting - Energy Harbor Slides ML23044A2082023-02-14014 February 2023 February 14, 2023, Second Perry Nuclear Power Plant License Renewal Environmental Pre-application Public Meeting - NRC Slides ML22200A2222022-07-21021 July 2022 License Renewal Application - Safety Pre-Application Meeting July 21, 2022 (Perry Slides) ML22199A0232022-07-21021 July 2022 July 21, 2022, Perry Nuclear Power Plant License Renewal Environmental Pre-application Public Meeting - NRC Slides ML22199A0352022-07-21021 July 2022 July 21, 2022, Perry Nuclear Power Plant License Renewal Environmental Pre-application Public Meeting - Energy Harbor Slides ML22201A0052022-07-19019 July 2022 License Renewal Application - Safety Pre-Application Meeting July 21, 2022 (NRC Slides) ML21176A1992021-06-25025 June 2021 Slideshow Presentation for 2020 End -of-Cycle Public Meeting for Davis-Besse and Perry ML21047A1522021-02-16016 February 2021 Slides - Perry Pre-Application Flooding 2/16/2021 Meeting Slides (L-2021-LRM-10016) ML20210M0712020-07-27027 July 2020 Combined End-of-Cycle 2019 Public Meeting Slide Presentation ML18054B6002018-02-21021 February 2018 Drywell General Area Heat Detectors License Amendment Request - Pre-Submittal Meeting, Perry Nuclear Power Plant, February 21, 2018 ML17205A0362017-07-19019 July 2017 Presentation for 2016 Perry EOC Open House ML16307A4052016-09-14014 September 2016 R-III Rug 15 Sep 16 Presentation ML16047A1332016-02-0909 February 2016 February 9, 2016, Public Meeting Slides for License Amendment Request for Drain Down of Upper Containment Pool in Mode 3 ML14079A0912014-03-18018 March 2014 NRC - Perry 2013 Annual Assessment Public Meeting Slides ML13294A5972013-10-21021 October 2013 FENOC Presentation Slides for Public Meeting September 24, 2013 ML13281A5302013-10-15015 October 2013 Meeting Slide for FENOC - NRC Pre-Submittal Meeting Request for Licensing Action ML13101A1432013-04-10010 April 2013 NRC 2012 Annual Assessment Presentation ML13101A1522013-04-10010 April 2013 2012 Annual Assessment Presentation ML12269A0612012-09-26026 September 2012 FENOC Presentation for 2012-09-26 Public Meeting ML12094A2932012-04-0303 April 2012 Licensee Slides for Annual Assessment Meeting ML12086A2002012-03-26026 March 2012 NRC Slides Regarding Perry Nuclear Plant EOC Meeting for Cy 2011 ML1122408232011-08-11011 August 2011 Annual Assessment Meeting, 2010 Reactor Oversight Program ML1122805732011-08-11011 August 2011 Licensee Presentation Slides from 2010 EOC Meeting 8/11/11 ML1117303602011-06-21021 June 2011 FENOC Licensee Slides for 6-21-11 All FENOC Meeting ML1021500852010-07-28028 July 2010 Licensee Slides for Perry; July 28, 2010; Annual Assessment Meeting ML1021500692010-07-28028 July 2010 NRC Slides for Perry, July 28, 2010; Annual Assessment Meeting ML1009102662010-03-31031 March 2010 Slides FENOC and NRC Senior Management Briefing, 3-31-10 ML0932101992009-11-12012 November 2009 NRC Slides from Public Meeting with Firstenergy Nuclear Operating Company ML0932005842009-11-12012 November 2009 FENOC Presentation for NRC Public Meeting ML0920900792009-07-21021 July 2009 Licensee Slides from End of Cycle - Public Meeting ML0920900682009-07-21021 July 2009 Slides for Perry Nuclear Power Plant Annual Assessment Meeting, Reactor Oversight Program - Cy 2008 ML0811506052008-04-24024 April 2008 Summary of Public Meeting with Firstenergy Nuclear Operating Co. to Discuss the 2007 Perry End-of-Cycle Performance Assessment ML0801604842008-01-0909 January 2008 Slides - FENOC Public Meeting, Senior Management Briefing, January 9, 2008 ML0708602462007-03-21021 March 2007 Perry EOC Cy 2006 Slides FENOC (CAL Closure - Public Meeting) ML0708602302007-03-21021 March 2007 Slides, Perry Annual Assessment Meeting Reactor Oversight Process - Cy 2006. ML0708602352007-03-21021 March 2007 Slides, Perry Confirmatory Action Letter Closure Meeting. ML0708602382007-03-21021 March 2007 Perry EOC Cy 2006 Slides FENOC (EOC-Public Meeting) ML0701205622007-01-10010 January 2007 Public Meeting - FENOC Meeting Slides ML0634900242006-12-13013 December 2006 FENOC Slides from Perry Public Meeting to Discuss Results of NRC Confirmatory Action Letter Followup Inspections ML0634900272006-12-13013 December 2006 NRC Slides from Public Meeting to Discuss Results of NRC Confirmatory Action Letter Follow-Up Inspections ML0623001242006-08-15015 August 2006 Licensee Public Meeting Slides ML0623001332006-08-15015 August 2006 NRC Perry 8-15-06 Public Meeting Slides ML0733408162006-07-14014 July 2006 Michael Johnson Ltr. Confirmatory Order (EA-01-082, EA-04-172) ML0619303972006-07-11011 July 2006 NRC CAL Followup Inspection Public Meeting Presentation Slides for Perry ML0619304062006-07-11011 July 2006 FENOC CAL Followup Inspection Public Meeting Presentation Slides ML0615106012006-05-23023 May 2006 EPRI HRA Users Group Review of Draft NUREG-1842 ML0607507312006-03-14014 March 2006 March 14 Public Meeting Annual Assessment Final Slides 2023-02-16
[Table view] |
Text
FENOC - NRC Pre-Submittal Meeting Request for Licensing Action October 15, 2013 Perry Nuclear Power Plant
FENOC Representatives Doug Reeves, Director - Site Engineering Robb Borland, Director - Nuclear Fuel & Analysis Ben Huck, Manager - Design Engineering Tom Lentz, Manager - Fleet Licensing Paul Gilles, Supervisor - Core Design Phil Lashley, Supervisor - Fleet Licensing Al Widmer, Nuclear Engineering Analysis Brad Ferrell, Licensing Engineer Nicole Schlichting, Core Design Engineer Tom Tomlinson, Project Manager Marvin Morris, Enercon 2
Requested Licensing Action Proposed Licensing Action Scope Full implementation of alternative accident source term (AST) for PNPP design basis accident analyses, using RADTRAD and GNF2 fuel source term Updated Safety Analysis Report (USAR) changes included for NRC review/approval One Technical Specification change (I-131)
Requested for spring 2015 refueling outage 3
Current Design Basis Accident Analysis Amendment 103 (March 1999) was a pilot plant application of an alternative AST for a Loss Of Coolant Accident (LOCA)
Amendment 112 (June 2000 power uprate) looked at four of the design basis events, and scaled prior dose calculation results in order to bound the uprate Amendment 122 (March 2003) analyzed the Fuel Handling Accident using an alternative AST and RADTRAD 4
Regulatory Requirement Governing Submittal 10 CFR 50.59 requires reviews of changes including items such as departures from a method of evaluation previously used in the safety analyses 10 CFR 50.67(b)(1) requires licensees who seek to revise their current accident source term in design basis radiological consequence analyses to apply for a license amendment per 10 CFR 50.90, including an evaluation of the consequences of applicable design basis accidents previously analyzed in the safety analysis report 5
LOCA Calculation Polestar Applied Technology methodology is replaced with RADTRAD Current core source term is updated for GNF2 Expanded guidance in Regulatory Guide 1.183 is used 6
LOCA Calculation Results Current Revised Acceptance Location Analysis Analysis Criteria (rem TEDE) (rem TEDE) (rem TEDE)
EAB 21.2 21.2 25 LPZ 10.1 6.5 25 Control Room 4.3 2.8 5 7
LOCA Dose Calculation Key Input Changes Isotopes Gap Release Pressure Reduction at 24 Hours Control Room Filtration Aerosol Removal in Containment Dose Conversion Factors Containment Spray Initiation 8
Control Rod Drop Accident Calculation Revised calculation uses Regulatory Guide 1.183 Revised calculation uses RADTRAD TID 14844 source term is updated to GNF2 source term Current TID 14844 whole body and thyroid doses converted to a TEDE dose for comparison purposes on next slide 9
CRDA Calculation Results Converted TEDE Revised Acceptance Location Dose (rem) Analysis Criteria (rem TEDE) (rem TEDE)
EAB 0.07206 0.161 6.3 LPZ 0.3896 0.162 6.3 Control Room Not Previously 0.263 5 Required 10
Main Steam Line Break Calculation Current TID 14844 source term is updated to Regulatory Guide 1.183 source term Revised calculation uses Regulatory Guide 1.183 Revised calculation uses RADTRAD Current TID 14844 whole body and thyroid dose converted to TEDE dose for comparison 11
MSLB OC Calculation Results (4 Ci/g)
Converted TEDE Revised Acceptance Location Dose (rem) Analysis Criteria (rem TEDE) (rem TEDE)
EAB 3.597 1.17 25 LPZ 0.458 0.131 25 Control Room Not Previously 0.622 5 Required 12
Dose Calculation Results Summary All revised calculations conform to the methodology in Regulatory Guide 1.183, including the use of RADTRAD All calculated doses meet Regulatory Guide 1.183 acceptance criteria No calculated doses increase by more than 10% of the margin to the regulatory limit 13
Regulatory Evaluation 10 CFR 50.90 application submitted in accordance with 10 CFR 50.59 and 10 CFR 50.67 No significant hazards No change to the site Environmental Plan No impact on the environment 14
Requested Licensing Action Next Steps:
Submittal planned for November 2013 NRC review requested to support spring 2015 refueling outage 15