License Renewal Application - Safety Pre-Application Meeting July 21, 2022 (NRC Slides)
ML22201A005
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 07/19/2022
From: Vaughn Thomas
Office of Nuclear Reactor Regulation
To:
Thomas V
References
Download: ML22201A005 (7)


Text

Perry, Unit 1 License Renewal Application (LRA)

Safety Pre-Application Meeting July 21, 2022 Vaughn Thomas Safety Project Manager License Renewal Projects Branch Division of New and Renewed Licenses Office of Nuclear Reactor Regulation

Meeting Agenda

  • Safety Review:

o Process Overview o Tentative Review Schedule for Perry

  • NRC Contact Information
  • Conclusion / Questions 2

License Renewal Review Process +

Inputs into NRC Licensing Decision Environmental Review (10 CFR 51)

License Renewal NRC Renewal Application (LRA) Hearings* Decision Accepted 10 CFR 2 (10 CFR 54.29)

Safety ACRS Review Recommendation (10 CFR 54) (10 CFR 54.25)

  • If a request for Hearing is granted 3

Safety Review:

Process Overview Acceptance Review In-Office Technical Review On-Site Audit Breakout Audit Audit Issue Safety Evaluation Report (SER) 4

Perry: Tentative Safety Review Schedule Note: The review schedule below is tentative and subject to change.

The schedule is only finalized once the application has been accepted forreview and is docketed.

Activity Estimated Date Application Submission Date July 2023 Acceptance Date (Project Start Date) August 2023 In-Office Technical Review Audit August/September 2023 On-Site Audit September 2023 Breakout Audit October/November 2023 Safety Evaluation Report September 2024 Advisory Committee on Reactor November 2024 Safeguards (ACRS) Full Committee Meeting Licensing Decision TBD 5

NRC Contact Information Safety Project Manager

Safety Branch Chief

Environmental Project Manger

Environmental Branch Chief

Questions?