Perry, Unit 1 License Renewal Application (LRA)
Safety Pre-Application Meeting July 21, 2022 Vaughn Thomas Safety Project Manager License Renewal Projects Branch Division of New and Renewed Licenses Office of Nuclear Reactor Regulation
Meeting Agenda
- License Renewal Review Process + Inputs into NRC Licensing Decision
- Safety Review:
o Process Overview o Tentative Review Schedule for Perry
- NRC Contact Information
- Conclusion / Questions 2
License Renewal Review Process +
Inputs into NRC Licensing Decision Environmental Review (10 CFR 51)
NRC Renewal Decision (10 CFR 54.29)
License Renewal Application (LRA)
Accepted Safety Review (10 CFR 54)
ACRS Recommendation (10 CFR 54.25)
Hearings*
10 CFR 2 3
- If a request for Hearing is granted
Safety Review:
Process Overview Issue Safety Evaluation Report (SER)
Acceptance Review In-Office Technical Review Audit On-SiteAudit BreakoutAudit 4
Perry: Tentative Safety Review Schedule 5
Activity Estimated Date Application Submission Date July 2023 Acceptance Date (Project Start Date)
August 2023 In-Office Technical Review Audit August/September 2023 On-Site Audit September 2023 Breakout Audit October/November 2023 Safety Evaluation Report September 2024 Advisory Committee on Reactor Safeguards (ACRS) Full Committee Meeting November 2024 Licensing Decision TBD Note: The review schedule below is tentative and subject tochange.
The schedule is only finalized once the application has been accepted forreview and is docketed.
NRC Contact Information 6
Safety Project Manager Vaughn Thomas (Vaughn.Thomas@nrc.gov)
Safety Branch Chief Lauren Gibson (Lauren.Gibson@nrc.gov)
Environmental Project Manger Lance Rakovan (Lance.Rakovan@nrc.gov)
Environmental Branch Chief Ted Smith (theodore.smith@nrc.gov)
Questions?
7