Letter Sequence RAI |
---|
TAC:ME1834, Control Room Habitability (Approved, Closed) TAC:ME1836, Control Room Habitability (Approved, Closed) |
Results
Other: LR-N16-0144, Completion of Activities to Support Entry Into the Period of Extended Operation, ML092400531, ML092400532, ML092430231, ML092460442, ML092470039, ML092520185, ML092650382, ML092660174, ML092660447, ML100850459, ML102280211, ML102430586, ML11125A024
|
MONTHYEARLR-N09-0192, Information to Support NRC Staff Review of the Application for Renewed Operating License2009-08-18018 August 2009 Information to Support NRC Staff Review of the Application for Renewed Operating License Project stage: Request LR-N09-0161, PSEG Nuclear, Salem Nuclear Generating Station, Units 1 and 2, Transmittal of License Renewal Application2009-08-18018 August 2009 PSEG Nuclear, Salem Nuclear Generating Station, Units 1 and 2, Transmittal of License Renewal Application Project stage: Request ML0924005312009-08-18018 August 2009 PSEG Nuclear, Salem Nuclear Generating Station, Units 1 and 2, License Renewal Application, Volume 2 of 3 Project stage: Other ML0924302312009-08-18018 August 2009 PSEG Nuclear, Salem Nuclear Generating Station, Units 1 and 2, License Renewal Application, Volume 1 of 3 Project stage: Other ML0924005322009-08-18018 August 2009 PSEG Nuclear, Salem Nuclear Generating Station, Units 1 and 2, License Renewal Application, Volume 3 of 3 Project stage: Other ML0924604422009-09-0303 September 2009 Delaware Citizen Comment on Salem Hope Creek License Renewal Application Project stage: Other ML0924700392009-09-0404 September 2009 Comment on Salem - Hope Creek License Renewal Applications from Citizen Project stage: Other ML0926601742009-09-0707 September 2009 Comment on License Renewal for Salem and Hope Creek Power Plants - Goodman Project stage: Other ML0925201852009-09-0808 September 2009 Comments About Relicensing Salem and Hope Creek Reactors in Nj, Steven Hegedus Project stage: Other ML0926503822009-09-0808 September 2009 Citizen Comment on Salem Hope Creek License Renewal Application Project stage: Other ML0926604472009-09-23023 September 2009 Hope Creek, E-mail from Ruth Panella Comments on License Renewal Project stage: Other ML1008502062010-03-24024 March 2010 Task Order No. 004 Under Delivery Order No. NRC-DR-03-09-061 Project stage: Acceptance Review ML1008504592010-04-0606 April 2010 Project Manager Change for the License Renewal of Salem Nuclear Generating Station, Units 1 and 2 (TAC No. ME1834 and ME1836) Project stage: Other ML1007606612010-04-14014 April 2010 RAI Regarding Balance of Plant Scoping and Screening Results for the Salem Nuclear Generating Station Units 1 & 2 (Tac Nos. ME1834 and ME1836) Project stage: RAI ML1013805112010-05-24024 May 2010 Request for Additional Information for the Salem Generating Station, Units 1 and 2, License Renewal Application, Section 3.3.2 (TAC Nos ME1836 and ME1834) Project stage: RAI LR-N10-0191, Response to NRC Request for Additional Information Dated April 30, 2010, Regarding Scoping and Screening Methodology for License Renewal Application2010-05-28028 May 2010 Response to NRC Request for Additional Information Dated April 30, 2010, Regarding Scoping and Screening Methodology for License Renewal Application Project stage: Response to RAI ML1014600612010-06-0707 June 2010 Request for Additional Information for Salem Nuclear Generating Station Units 1 and 2 License Renewal Application Regarding Section 3.5 (TAC Nos. ME1834 and ME1836) Project stage: RAI ML1014400812010-06-10010 June 2010 Request for Additional Information for the Review of the Salem Generating Station, Unit 1 and Unit 2, License Renewal Application Identified During the Audit (TAC ME1836 and ME1834) Project stage: RAI ML1014600772010-06-10010 June 2010 Request for Additional Information for Salem Nuclear Generating Station Units 1 and 2 License Renewal Application (TAC ME1832 and ME1836) Project stage: RAI ML1014810092010-06-11011 June 2010 Request for Additional Information for Salem Nuclear Generating Station Units 1 and 2 License Renewal Application Project stage: RAI ML1015504712010-06-11011 June 2010 RAI for Salem Nuclear Generating Station Units 1 and 2 License Renewal Application Sections 3.1.2 and 3.3.2 (TAC No ME1834/ME1836) Project stage: RAI ML1014801892010-06-14014 June 2010 Request for Additional Information for Salem Nuclear Generating Station Units 1 and 2 License Renewal Application Regarding Sections 4.3 and 4.4 (TAC Nos. ME1834 and ME1836) Project stage: RAI ML1013905372010-06-17017 June 2010 Request for Additional Information for Salem Nuclear Generating Station Units 1 and 2 License Renewal Application(Tac Nos ME1834, ME1836) Project stage: RAI ML1016201902010-06-25025 June 2010 Request for Additional Information for Salem Nuclear Generating Station Units 1 and 2, License Renewal Application (Tac ME1834/ME1836) Project stage: RAI ML1016804022010-06-29029 June 2010 Request for Additional Information for Salem Nuclear Generating Station Units 1 and 2, License Renewal Application Regarding Subsection 3.1.2.2.14 (TAC ME1834/ME1836) Project stage: RAI ML1014807262010-06-30030 June 2010 Request for Additional Information for Salem Nuclear Generating Station Units 1 and 2 License Renewal Application Regarding Section B.3.1.1 (TAC Nos. ME1834 and ME1836) Project stage: RAI ML1017203642010-07-12012 July 2010 Request for Additional Information for Salem Nuclear Generating Station Units 1&2 LRA Regarding ASME Section XI ISI, Subsections Iwb,Iwc, and Iwd (TAC Nos. ME1834/ME1836) Project stage: RAI LR-N10-0243, Response to NRC Request for Additional Information Dated June 14, 2010, Related to Sections 4.3 and 4.4 License Renewal Application2010-07-13013 July 2010 Response to NRC Request for Additional Information Dated June 14, 2010, Related to Sections 4.3 and 4.4 License Renewal Application Project stage: Response to RAI ML1019504872010-07-19019 July 2010 Request for Additional Information for the Salem Generating Station, Unit 1 and Unit 2, License Renewal Application, Section 4.6 (TAC Nos. ME1834 and ME1836) Project stage: RAI ML1019606342010-07-23023 July 2010 Request for Additional Information for the Salem Generating Station, Unit 1 and Unit 2, License Renewal Application (TAC ME1834 and ME1836) Project stage: RAI ML1019304962010-07-30030 July 2010 Request for Additional Information for Salem Nuclear Generating Station Units 1 and 2 License Renewal Application (TAC No. ME1834 and Me 1836) Project stage: RAI ML1019504792010-08-0303 August 2010 Request for Additional Information Regarding ASME Section XI, Subsection IWE for the Salem Nuclear Generating Station Units 1 and 2 License Renewal Application (TAC Nos. ME1834 and ME1836) Project stage: RAI ML1019704742010-08-0303 August 2010 Request for Additional Information for Salem Nuclear Generating Station Units 1 and 2 License Renewal Application Regarding Bolting Integrity (TAC Nos. ME1834 and ME1836) Project stage: RAI ML1015402422010-08-0606 August 2010 Request for Additional Information for Salem Nuclear Generating Station Units 1 and 2 License Renewal Application for Buried Piping Inspection Program (TAC Nos. ME1834 and ME1836) Project stage: RAI ML1020004042010-08-0909 August 2010 Request for Additional Information for Salem Nuclear Generating Station Units 1 and 2 License Renewal Application (TAC Nos. ME1834 and ME1836) Project stage: RAI LR-N10-0295, Responses to NRC Requests for Additional Information Dated July 12, 2010, July 19, 2010 and July 23, 2010 Related to Various Sections of License Renewal Application2010-08-10010 August 2010 Responses to NRC Requests for Additional Information Dated July 12, 2010, July 19, 2010 and July 23, 2010 Related to Various Sections of License Renewal Application Project stage: Response to RAI ML1020304172010-08-19019 August 2010 RAI Regarding the Salem Nuclear Generating Station Units 1 and 2 License Renewal Application (TAC ME1834 & ME1836) Project stage: RAI ML1022802112010-08-25025 August 2010 Scoping and Screening Audit Summary Regarding the Salem Nuclear Generating Station, Units 1 and 2, License Renewal Application Project stage: Other LR-N10-0313, Responses to Request for Additional Information Dated 08/03/10, Related to Bolting Integrity and 07/30/10 to Steam Generators and Question Posed During Region 1 Inspection, Regarding License Renewal Application2010-08-26026 August 2010 Responses to Request for Additional Information Dated 08/03/10, Related to Bolting Integrity and 07/30/10 to Steam Generators and Question Posed During Region 1 Inspection, Regarding License Renewal Application Project stage: Response to RAI LR-N10-0322, Response to NRC Request for Additional Information, Dated August 6, 2010 Related to the Buried Piping Inspection Program Associated with License Renewal Application2010-09-0707 September 2010 Response to NRC Request for Additional Information, Dated August 6, 2010 Related to the Buried Piping Inspection Program Associated with License Renewal Application Project stage: Response to RAI ML1024600782010-09-29029 September 2010 RAI for Salem Nuclear Generating Station Units 1 and 2 License Renewal Application (TAC Nos. ME1834 and ME1836) Project stage: RAI ML1026003402010-10-12012 October 2010 RAI for Salem Nuclear Generating Station Units 1 and 2 License Renewal Application for Buried Piping Inspection Program (TAC No. ME1834 and ME1836) Project stage: RAI ML1029102492010-10-25025 October 2010 Request for Additional Information for Salem Nuclear Generating Station, Units 1 and 2, License Renewal Application on Structures Monitoring (TAC No. ME1834 and ME1836) Project stage: RAI ML1029300492010-11-0404 November 2010 Request for Additional Information for Salem Nuclear Generating Station, Units 1 and 2, LRA on Primary Water Stress Corrosion Cracking in Steam Generator Tube-to-Tube Sheet Welds Project stage: RAI ML1030101002010-11-0404 November 2010 Safety Evaluation Report Related to the License Renewal of Salem Nuclear Generating Station, Units 1 and 2 Project stage: Approval ML1031201722010-11-0404 November 2010 Safety Evaluation Report with Open Items Related to the License Renewal of Salem Nuclear Generating Station, Units 1 and 2 Project stage: Approval ML1024305862010-11-0909 November 2010 Audit Report Regarding the Salem Nuclear Generating Station, Units 1 and 2, License Renewal Application (TAC Nos. ME1834 and ME1836) Project stage: Other ML1028101942010-11-22022 November 2010 RAI for Salem Nuclear Generating Station Units 1 and 2 LRA for Use of Westems Program in Metal Fatigue Analysis Project stage: RAI ML1032700762010-12-10010 December 2010 RAI for Salem Nuclear Generating Station Units 1 and 2 LRA Project stage: RAI LR-N10-0414, Response to NRC Request for Additional Information, Dated October 25, 2010, Related to Structures Monitoring Associated with License Renewal Application2010-12-14014 December 2010 Response to NRC Request for Additional Information, Dated October 25, 2010, Related to Structures Monitoring Associated with License Renewal Application Project stage: Response to RAI 2010-06-11
[Table View] |
Similar Documents at Salem |
---|
Category:Letter
MONTHYEARIR 05000272/20240032024-10-30030 October 2024 Integrated Inspection Report 05000272/2024003 and 05000311/2024003 ML24296B1932024-10-23023 October 2024 Project Manager Assignment LR-N24-0068, Core Operating Limits Report - Cycle 282024-10-21021 October 2024 Core Operating Limits Report - Cycle 28 LR-N24-0063, Emergency Plan Document Revision Implemented September 18, 2024. Includes NC.EP-EP.ZZ-0903, Rev. 7, Opening of Emergency Operations Facility (EOF)2024-10-0707 October 2024 Emergency Plan Document Revision Implemented September 18, 2024. Includes NC.EP-EP.ZZ-0903, Rev. 7, Opening of Emergency Operations Facility (EOF) IR 05000272/20244032024-09-25025 September 2024 And Salem Nuclear Generating Station, Units 1 and 2, Cybersecurity Inspection Report 05000354/2024403, 05000272/2024403, and 05000311/2024403 (Cover Letter Only) ML24267A1082024-09-23023 September 2024 Submittal of the Reactor Vessel Material Surveillance Program Capsule Technical Report IR 05000272/20244022024-09-23023 September 2024 And Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2024402, 05000272/2024402, and 05000311/2024402 (Cover Letter Only) IR 05000272/20240052024-08-29029 August 2024 Updated Inspection Plan for Salem Nuclear Generating Station, Units 1 and 2 (Report 05000272/2024005 and 05000311/2024005) IR 05000272/20240022024-07-30030 July 2024 Integrated Inspection Report 05000272/2024002 and 05000311/2024002 LR-N24-0012, Application to Revise Technical Specifications and 10 CFR 50.12 Exemption Request to Implement Optimized ZIRLO Fuel Rod Cladding2024-07-24024 July 2024 Application to Revise Technical Specifications and 10 CFR 50.12 Exemption Request to Implement Optimized ZIRLO Fuel Rod Cladding ML24145A1772024-07-15015 July 2024 And Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Issuance of Amendment Nos. 236, 349, and 331 Modify Exclusion Area Boundary IR 05000272/20245012024-06-12012 June 2024 And Salem Nuclear Generating Station, Units 1 and 2 - Emergency Preparedness Biennial Exercise Inspection Report 05000354/2024501, 05000272/2024501 and 05000311/2024501 ML24099A1572024-05-29029 May 2024 Issuance of Amendment Nos. 348 and 330 Permanent Extension of Type a and Type C Containment Leak Rate Test Frequencies ML24150A0032024-05-28028 May 2024 Request for Exemptions from 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.75(h)(1)(iv) and Proposed Amendment to the Decommissioning Trust Agreement LR-N24-0041, Stations, Revisions to Emergency Plan Document Nc EP-EP-ZZ-01102, Rev. 28, Emergency Coordinator Response2024-05-22022 May 2024 Stations, Revisions to Emergency Plan Document Nc EP-EP-ZZ-01102, Rev. 28, Emergency Coordinator Response IR 05000272/20240102024-05-16016 May 2024 Fire Protection Team Inspection Report 05000272/2024010 and 05000311/2024010 05000272/LER-2024-001, Pressure Boundary Leakage Through a Reactor Coolant Pump Thermal Barrier Heat Exchanger2024-05-0909 May 2024 Pressure Boundary Leakage Through a Reactor Coolant Pump Thermal Barrier Heat Exchanger IR 05000272/20240012024-05-0707 May 2024 Integrated Inspection Report 05000272/2024001 and 05000311/2024001 LR-N24-0039, Steam Generator Tube Inspection Report - Twenty-ninth Refueling Outage2024-05-0606 May 2024 Steam Generator Tube Inspection Report - Twenty-ninth Refueling Outage LR-N24-0035, 2023 Annual Radiological Environmental Operating Report (AREOR)2024-04-30030 April 2024 2023 Annual Radiological Environmental Operating Report (AREOR) LR-N24-0034, 2023 Annual Radioactive Effluent Release Report (ARERR)2024-04-30030 April 2024 2023 Annual Radioactive Effluent Release Report (ARERR) LR-N24-0024, Response to Request for Additional Information Associated with License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary2024-04-26026 April 2024 Response to Request for Additional Information Associated with License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary LR-N24-0011, Supplemental Information to License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary2024-04-0505 April 2024 Supplemental Information to License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary IR 05000272/20240112024-04-0101 April 2024 and Salem Nuclear Generating Station, Units 1 and 2 - Plant Modification and Annual Problem Identification and Resolution Inspection Report 05000354/2024011, 05000272/2024011, and 05000311/2024011 LR-N24-0028, and Salem Generating Station - Notice of Intent to Pursue Subsequent License Renewal2024-03-28028 March 2024 and Salem Generating Station - Notice of Intent to Pursue Subsequent License Renewal LR-N24-0021, and Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums2024-03-20020 March 2024 and Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums ML24071A2132024-03-12012 March 2024 Senior Reactor and Reactor Operator Initial License Examinations LR-N24-0020, Generation Station and Salem Generating Station, Units 1 & 2 - Annual Property Insurance Status Report2024-03-0707 March 2024 Generation Station and Salem Generating Station, Units 1 & 2 - Annual Property Insurance Status Report LR-N24-0022, Spent Fuel Cask Registration2024-02-29029 February 2024 Spent Fuel Cask Registration IR 05000272/20230062024-02-28028 February 2024 Annual Assessment Letter for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2023006 and 05000311/2023006 IR 05000272/20244012024-02-26026 February 2024 and Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2024401, 05000272/2024401 and 05000311/2024401 (Cover Letter Only) LR-N24-0009, In-Service Inspection Activities2024-02-0505 February 2024 In-Service Inspection Activities IR 05000272/20230042024-02-0505 February 2024 Integrated Inspection Report 05000272/2023004 and 05000311/2023004 ML24009A1022024-01-26026 January 2024 – Exemption from Select Requirements of 10 CF Part 73 (EPID L-2023-LLE-0045 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) IR 05000272/20234012024-01-22022 January 2024 Material Control and Accounting Program Inspection Report 05000272/2023401 and 05000311/2023401 ML24004A1542024-01-0808 January 2024 Notification of Conduct of a Fire Protection Team Inspection LR-N23-0079, Special Report 23-02-00 Pursuant to the Requirements of Salem Unit 1 Technical Specification 3.3.3.7, Action 10, for the Unit 1 Main Steam Line Rad Monitor Inoperable for Greater than Seven Days2023-12-0707 December 2023 Special Report 23-02-00 Pursuant to the Requirements of Salem Unit 1 Technical Specification 3.3.3.7, Action 10, for the Unit 1 Main Steam Line Rad Monitor Inoperable for Greater than Seven Days LR-N23-0077, Loss of Coolant Accident Peak Cladding Temperature Margin Tracking - Annual Report 2023 & 30 Day Report for Salem Unit 1 Upflow Conversion2023-11-29029 November 2023 Loss of Coolant Accident Peak Cladding Temperature Margin Tracking - Annual Report 2023 & 30 Day Report for Salem Unit 1 Upflow Conversion ML23270C0072023-11-29029 November 2023 Notice of Proposed Amendment to Decommissioning Trust Agreement ML23324A3072023-11-17017 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML24250A0582023-11-14014 November 2023 PSEG to Marine Mammal Stranding Center, Salem Sea Turtle Stranding Response Services IR 05000272/20230032023-11-13013 November 2023 Integrated Inspection Report 05000272/2023003 and 05000311/2023003 LR-N23-0072, Core Operating Limits Report Cycle 302023-11-0101 November 2023 Core Operating Limits Report Cycle 30 IR 05000272/20230102023-10-12012 October 2023 Biennial Problem Identification and Resolution Inspection Report O5000272/2023010 and 05000311/2023010 IR 05000272/20234022023-10-12012 October 2023 and Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2023402, 05000272/2023402 and 05000311/2023402 (Cover Letter Only) LR-N23-0045, and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement2023-09-0808 September 2023 and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement ML23249A2612023-09-0606 September 2023 License Amendment Request to Modify the Salem and Hope Creek Exclusion Area Boundary IR 05000272/20230052023-08-31031 August 2023 Updated Inspection Plan for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2023005 and 05000311/2023005) ML23233A0762023-08-21021 August 2023 Requalification Program Inspection ML23192A8212023-08-14014 August 2023 and Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Issuance of Amendment Nos. 234, 347, and 329 Revise Technical Specifications to Delete Meteorological Tower Location 2024-09-25
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24060A0492024-02-28028 February 2024 NRR E-mail Capture - Final Exhb RAI for Hope Creek, Salem 1 and 2 Amendment to Modify Exclusion Area Boundary ML22333A9022022-11-29029 November 2022 NRR E-mail Capture - Final Iolb RAI - Salem 1 and 2 LAR to Revise TS to Extend Allowed Outage Time for Inoperable EDG ML22318A1062022-11-14014 November 2022 Information Request for Quadrennial Baseline Comprehensive Engineering Team Inspection; Notification to Perform Inspection 05000272/2023011 and 05000311/2023011 ML22290A2202022-10-17017 October 2022 NRR E-mail Capture - Final RAI - Salem 1 and 2 LAR to Revise TS to Extend Allowed Outage Time for Inoperable EDG ML22055A0702022-02-22022 February 2022 NRR E-mail Capture - Final RAI - Salem 1-Relief Request Associated with Fourth Inservice Inspection (ISI) Interval Limited Examinations (L-2021-LLR-0085) ML21256A1902021-09-10010 September 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21144A2132021-05-24024 May 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21068A4142021-03-0909 March 2021 NRR E-mail Capture - Final RAI for Salem Unit 1 LAR to Revise and Relocate Pressurizer Overpressure Protection System Limits to Pressure and Temperature Limits Report ML21043A1442021-02-11011 February 2021 NRR E-mail Capture - Salem - Final RAI Alternative for Examination of ASME Section XI, Category B-B, Item Number B2.11and B2.12 (L-2020-LRR-0103) ML21021A2592021-01-21021 January 2021 NRR E-mail Capture - Final RAI - Salem 1 - Steam Generator Tube Inspection Report ML20281A5172020-10-13013 October 2020 Notification of Conduct of a Fire Protection Team Inspection ML18267A1712018-09-21021 September 2018 NRR E-mail Capture - Final RAI from PRA Branch: Revise Technical Specifications to Increase Inverter AOT Extension (L-2018-LLA-0140) ML18264A0122018-09-20020 September 2018 NRR E-mail Capture - Final RAI from I&C Branch: Revise Technical Specifications to Increase Inverter AOT Extension (L-2018-LLA-0140) ML18250A3132018-09-0606 September 2018 NRR E-mail Capture - Final RAI: Revise Technical Specifications to Increase Inverter AOT Extension (L-2018-LLA-0140) ML18171A3212018-06-20020 June 2018 NRR E-mail Capture - Final RAI: Revise Technical Specifications to Adopt TSTF-411 and 418 (L-2017-LLA-0442) ML18094B0832018-04-0505 April 2018 Enclosurequest for Additional Information (Letter to P. Duke RAI Regarding Entergy Operations, Inc.'S Decommissioning Funding Plan Update for Salem and Hope Creek, and Peach Bottom ISFSIs Docket Nos. 72-48 and 72-29) ML18067A1482018-03-0808 March 2018 Enclosurequest for Additional Information (Letter to P. R. Simpson Request for Additional Information Regarding Exelon Generating Company, Llc'S Decommissioning Funding Plan Update for Independent Spent Fuel Storage Installation) ML17212B1152017-07-31031 July 2017 Request for Additional Information - Salem Units 1 and 2 - Containment Fan Coil Unit Allowed Outage Time Amendment Request (CACs MF9364 and MF9365) ML17199A1122017-07-18018 July 2017 Request for Additional Information - Salem Units 1 and 2 - Accident Monitoring Instrumentation License Amendment Request (CAC Nos. MF8859 & MF8860) ML17192A1672017-07-11011 July 2017 Request for Additional Information - Salem Unit 1 - Steam Generator Tube Inspection Report ML17115A4032017-05-0909 May 2017 Request for Additional Information Regarding Relief Request SC-14R-171 - Use of Code Cases N-695-1 and N-696-1 ML16321A4642016-11-21021 November 2016 and Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Request for Additional Information Regarding License Amendment Request to Remove Certain Training Requirements ML16218A0052016-08-11011 August 2016 Request for Additional Information Concerning Request for an Extension to Enforcement Guidance Memorandum 12-001 ML16195A4492016-07-14014 July 2016 Request for Additional Information Regarding Chilled Water System Modifications ML16188A4152016-07-0707 July 2016 Request for Additional Information Aging Management Program Plan for Reactor Vessel Internals ML16124A5802016-05-0303 May 2016 and Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Redacted - Request for Additional Information Review of Security Plan Revision 17 Changes ML16013A1592016-02-17017 February 2016 Request for Additional Information Regarding Chilled Water System Modifications ML15287A1412015-11-0202 November 2015 Request for Additional Information License Amendment Request Regarding Replacement of Source Range and Intermediate Range Neutron Monitoring Systems ML15287A1052015-11-0202 November 2015 Request for Additional Information License Amendment Request to Isolate Unborated Water Sources and Use Gamma-Metrics Post-Accident Neutron Monitors During Mode 6 (Refueling) (CAC Nos. MF5831 & MF5832) ML15299A3832015-10-29029 October 2015 Supplemental Information Needed for Acceptance of Requested Licensing Action Amendment Request Regarding Chilled Water System Modification ML15069A1812015-03-31031 March 2015 Request for Additional Information Aging Management Program Plan for Reactor Vessel Internals (TAC Nos. MF5149 and MF5150) ML15075A2602015-03-24024 March 2015 Request for Additional Information Spring 2014 Steam Generator Tube Inspections ML15055A3772015-03-10010 March 2015 and Salem Nuclear Generating Station, Unit Nos. 1 and 2, Request for Additional Information Request to Update Appendix B to Renewed Facility Operating License DPR-70, DPR-75 and NPF-57 ML14197A6192014-07-24024 July 2014 and Salem Nuclear Generating Station, Units 1 and 2 - Request for Additional Information Regarding Cyber Security Plan Milestone 8 Implementation Schedule (Tac Nos. MF3384, MF3385 and MF3386) ML14168A2422014-06-28028 June 2014 Request for Additional Information Regarding Flooding Hazard Reevaluation ML14135A2912014-06-0202 June 2014 RAI Regarding Request for Relief SC-I4R-140 from American Society of Mechanical Engineers Boiler & Pressure Vessel Code, Section XI Requirements Regarding the Reactor Vessel Head Flange Seal Leak Detection ML14086A6362014-04-30030 April 2014 Request for Additional Information Regarding Core Operating Limits Report ML14066A2952014-03-0606 March 2014 Licensed Operator Positive Fitness-For-Duty-Test (FY14) ML13330A5672013-11-22022 November 2013 Request for Additional Information: Salem Units 1 and 2 - Relief Request SC-14R-133 Repair of Service Water Piping (TAC MF1375 & 1376) ML13304B4182013-11-0101 November 2013 Request for Additional Information Associated with Near-Term Task Force Recommendation 2.3, Seismic Walkdowns ML13304B9362013-10-29029 October 2013 Request for Additional Information: Salem Units 1 and 2 - Relief Request SC-14R-133 Repair of Service Water Piping (TAC MF1375 & 1376) ML13270A4142013-10-17017 October 2013 Interim Staff Evaluation and Request for Additional Information Regarding the Overall Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation (TAC Nos. MF0913 and Mf ML13249A0112013-09-0505 September 2013 Weko Seal Relief Request RAI ML13196A3382013-07-15015 July 2013 2013 Decommissioning Fund Report RAI ML13192A2322013-07-11011 July 2013 Draft Request for Additional Information Overall Integrated Plan in Response to Order EA-12-051, Reliable Spent Fuel Pool Instrumentation. ML13186A1672013-07-11011 July 2013 Request for Additional Information Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) ML13179A3032013-06-28028 June 2013 RAIs for Salem Regarding Response to Order EA-12-051 (SFP Instrumentation) ML13137A4882013-06-0505 June 2013 Request for Additional Information Relief Request SC-l4R-133 ML13149A0862013-06-0505 June 2013 Request for Additional Information Decommissioning Funding Status Report ML13102A2752013-04-25025 April 2013 Request for Additional Information Change to PSEG Emergency Plan to Remove the Backup R45 Plant Vent Radiation Monitor Indications 2024-02-28
[Table view] |
Text
June 10, 2010
Mr. Thomas Joyce President and Chief Nuclear Officer PSEG Nuclear LLC P.O. Box 236 Hancocks Bridge, NJ 08038
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE SALEM NUCLEAR GENERATING STATION, UNIT 1 AND UNIT 2, LICENSE RENEWAL APPLICATION IDENTIFIED DURING THE AUDIT (TAC NOS. ME1836 AND ME1834)
Dear Mr. Joyce:
By letter dated August 18, 2009, as supplemented by letter dated January 23, 2009, Public Service Enterprise Group Nuclear, LLC, submitted an application pursuant to Title 10 of the Code of Federal Regulations Part 54 (10 CFR Part 54) for renewal of Operating Licenses Nos. DPR-70 AND DPR-75 for the Salem Nuclear Generating Station, Unit 1 and Unit 2. The staff of the U.S. Nuclear Regulatory Commission (NRC or the staff) completed its aging management program consistency audit on February 19, 2010 and has identified, in the enclosure, areas where additional information is needed to complete the review. Further requests for additional information may be issued in the future.
Items in the enclosure were discussed with John Hufnagel and other members of your staff, and a mutually agreeable date for the response is within 30 days from the date of this letter. If you have any questions, please contact me by telephone at 301-415-2981 or by e-mail at bennett.brady@nrc.gov. Sincerely, /RA/
Bennett Brady, Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation
Docket Nos. 50-272 and 50-311
Enclosure:
As stated
cc w/encl: See next page
ML101440081 OFFICE PM:DLR:RPB1 LA:DLR BC:DLR:RPB1 PM:DLR:RPB1 NAME B. Brady Y. Edmonds B. Pham B. Brady DATE 06/03/10 05/27/10 06/03/10 06/10/10 Letter to T. Joyce from B. Brady dated June 10, 2010
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE SALEM NUCLEAR GENERATING STATION, UNIT 1 AND UNIT 2, LICENSE RENEWAL APPLICATION IDENTIFIED DURING THE AUDIT (TAC NOS. ME1836 AND ME1834)
DISTRIBUTION
- HARD COPY: DLR RF E-MAIL: PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RdsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRapb Resource RidsOgcMailCenter Resource
BPham BBrady ACunanan SCuadrado CEccleston REnnis CSanders BHarris, OGC ABurritt, RI RConte, RI MModes, RI DTifft, RI NMcNamara, RI Salem Nuclear Generating Station Units 1 and 2 cc: Mr. Robert Braun Senior Vice President Nuclear PSEG Nuclear LLC One Alloway Creek Neck Road Hancocks Bridge, NJ 08038
Mr. Carl Fricker Station Vice President - Salem PSEG Nuclear LLC One Alloway Creek Neck Road Hancocks Bridge, NJ 08038 Mr. Michael Gallagher Vice President - License Renewal Projects Exelon Nuclear LLC 200 Exelon Way Kennett Square, PA 19348
Mr. Ed Eilola Plant Manager - Salem PSEG Nuclear LLC One Alloway Creek Neck Road Hancocks Bridge, NJ 08038 Mr. Brian Booth Director Nuclear Oversight PSEG Nuclear P.O. Box 236 Hancocks Bridge, NJ 08038 Mr. Jeffrie J. Keenan, Esquire Manager - Licensing PSEG Nuclear LLC One Alloway Creek Neck Road Hancocks Bridge, NJ 08038 Senior Resident Inspector Salem Nuclear Generating Station U.S. Nuclear Regulatory Commission Drawer 0509 Hancocks Bridge, NJ 08038
Mr. Ali Fakhar Manager, License Renewal PSEG Nuclear LLC One Alloway Creek Neck Road Hancocks Bridge, NJ 08038
Mr. William Mattingly Manager - Salem Regulatory Assurance PSEG Nuclear LLC One Alloway Creek Neck Road Hancocks Bridge, NJ 08038
Township Clerk Lower Alloways Creek Township Municipal Building, P.O. Box 157 Hancocks Bridge, NJ 08038
Mr. Paul Bauldauf, P.E., Asst. Director Radiation Protection Programs NJ Department of Environmental Protection and Energy, CN 415 Trenton, NJ 08625-0415
Mr. Brian Beam Board of Public Utilities 2 Gateway Center, Tenth Floor Newark, NJ 07102
Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406
Mr. Gregory Sosson Director Corporate Engineering PSEG Nuclear LLC One Alloway Creek Neck Road Hancocks Bridge, NJ 08038
Mr. Paul Davison Vice President, Operations Support PSEG Nuclear LLC One Alloway Creek Neck Road Hancocks Bridge, NJ 08038
Salem Nuclear Generating Station Units 1 and 2 cc: Ms. Christine Neely Director - Regulator Affairs PSEG Nuclear LLC One Alloway Creek Neck Road Hancocks Bridge, NJ 08038
Mr. Earl R. Gage Salem County Administrator Administration Building 94 Market Street Salem, NJ 08079 ENCLOSURE REQUEST FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE SALEM NUCLEAR GENERATING STATION, UNIT 1 AND UNIT 2, LICENSE RENEWAL APPLICATION IDENTIFIED DURING THE AUDIT (TAC NOS. ME1836 AND ME1834)
RAI B.2.1.9-01
Background
- Generic Aging Lessons Learned (GALL) aging management program (AMP) XI.M18, "Bolting Integrity," Program Element 1, "scope of program," states that the program covers bolting within the scope of license renewal, including 1) safety-related bolting, 2) bolting for nuclear steam supply system component supports, 3) bolting for other pressure retaining components, including nonsafety-related bolting, and 4) structural bolting (actual measured yield strength 150 ksi); and Program Element 2, "preventive actions," states that selection of bolting material and use of lubricants and sealants is in accordance with the guidelines of EPRI NP-5769 and the additional recommendations in NUREG-1339, and that bolting replacement activities include proper torquing and application of appropriate preload based on EPRI documents.
Both the license renewal application (LRA) and the program basis document for Salem Nuclear Generating System (SNGS) AMP B.2.1.9 indicate that aging effects for component support bolting and structural bolting are managed by AMPs different from the Bolting Integrity Program, such as the Structures Monitoring Program, the Inspection of Overhead Heavy Load and Light Load (Related to Refueling) Handling Systems Program, the ASME Section XI, Subsection IWF, Program, the External Surfaces Monitoring Program, or the Buried Piping Inspection Program.
Issue: It is not clear to the staff why the use of AMPs different from the Bolting Integrity Program for managing the aging effects of bolts in the scope of license renewal was not identified as an exception to Element 1 of the Bolting Integrity Program. Also, it is not clear how the other, credited AMPs, which are primarily inspection programs, would implement all of the elements of the Bolting Integrity Program, especially Element 2, which includes recommendations related to procurement, replacement activities, and requirements for and implementation of proper torquing, that normally are not included within the scope of an inspection program.
Requests: a) Explain why the use of other programs to manage the aging effects of component support and structural bolting was not identified as an exception to GALL AMP XI.M18, Element 1.
b) Explain how you ensure that other AMPs credited for aging management of component support and structural bolting include all recommendations for aging management of bolting in GALL AMP XI.M18. Include sufficient information for the staff to determine whether and how the preventive actions in GALL AMP XI.M18, Element 2, are included in the other credited AMPs.
RAI B.2.1.18-01
=
Background===
The applicant discussed the Fuel Oil Chemistry Program enhanced procedures for SNGS as part of the license renewal application. During the staff review of the enhanced sampling procedures for the main fuel oil storage tank, the diesel fire pump fuel oil storage tanks, and the diesel fuel oil storage tanks, it was noted that the procedures state that if a significant amount of water (greater than two ounces per gallon of fuel) is present, then a Notification per the Corrective Action Plan should be submitted.
Issue: It is not clear how the person performing the testing will be able to complete the analysis with the current level of detail provided in the procedure. For example, with the main fuel oil storage tank, it was unclear how the tester would be able to discern two ounces of water in a 10 gallon sample. With the diesel fire pump fuel oil storage tank sample, it was unclear what level of water was determined not acceptable, given that only a one liter sample was specified to be drawn. Request: Please clarify how there is reasonable assurance that the analyses requested to be performed in the enhanced procedures will be performed correctly.
RAI B.2.1.15-01
Background
- GALL AMP XI.M26, Element 4, "detection of aging effects" states:
The periodic visual inspection and function test is performed at least once every six months to examine the signs of degradation of the halon/CO 2 fire suppression system. Material conditions that may affect the performance of the system, such as corrosion, mechanical damage, or damage to dampers, are observed during these tests.
SNGS LRA Appendix B2.1.15 takes an exception to GALL AMP XI.M26, and states:
NUREG-1801 recommends visual inspection and functional testing of the Halon and Carbon Dioxide fire suppression systems at least once every six months. The Halon and Carbon Dioxide fire suppression systems currently undergo functional testing every refueling cycle (18-months).
Issue: It is not clear if the exception only applies to functional testing. Request: Clarify that the exception only applies to functional testing, and that the SNGS Fire Protection Program performs visual inspection at least once every six months to examine the signs of degradation of the halon/CO 2 fire suppression system. If the visual inspection is not performed once every six months, please justify why this is not an exception to the GALL AMP XI.M26.
RAI B.2.1.15-02
Background
- GALL AMP XI.M26, Element 4, "detection of aging effects," states:
Visual inspections of the halon/CO 2 fire suppression system detect any sign of added degradation, such as corrosion, mechanical damage, or damage to dampers. The periodic function test and inspection performed at least once every six months detects degradation of the halon/CO 2 fire suppression system before the loss of the component intended function.
GALL AMP XI.M26, Element 6, "acceptance criteria," states:
Also, any signs of corrosion and mechanical damage of the halon/CO 2 fire suppression system are not acceptable.
Program Basis Document, SH-PBD-AMP-XI.M26, under Section 3.4.f, states:
The Fire Protection Program directs halon fire suppression system surveillance that verifies storage tank weight at least every six months. The Halon fire suppression system, including associated ventilation dampers, is verified to actuate in response to a simulated test signal, every refueling cycle. During the inspections, adverse conditions are required to be reported for corrective action evaluation. Procedures S1(2).FP-SV.FS-0066 (Q) and S1(2).FP-ST.FS-0048 (Q) are referenced.
The program directs low-pressure Carbon Dioxide fire suppression system surveillance that verifies the carbon dioxide storage tank level and pressure on a weekly basis. System operability is verified at least once per refueling outage by verifying the system valves and associated ventilation dampers actuate manually and automatically in response to a simulated actuation signal. Any adverse conditions are required to be reported in the corrective action program. Procedures S1(2).FP-SV.FS-0019 (Q) and S1(2).FP-ST.FS-0048 (Q) (should be 0021) are referenced.
Issue:
Procedure S1(2).FP-ST.FS-0048 (Q) addresses functional test of the Relay Room Halon 1301 System and ensures that dampers and devices actuate properly. However, there is no visual inspection activity to check for degradation such as corrosion or mechanical damage. Acceptance criteria as identified in the procedure do not address corrosion. Procedure S1(2).FP-SV.FS-0019 (Q) verifies that the valves in the flow path of the 10 ton CO 2 system are in their correct position. However, there is no visual inspection activity to check for degradation such as corrosion or mechanical damage. Acceptance criteria as identified in the procedure do not address corrosion.
Procedure S1(2).FP-ST.FS-0021 (Q) verifies the operation of the diesel area total flooding CO 2 system. However, there is no visual inspection activity to check for degradation such as corrosion or mechanical damage. Acceptance criteria as identified in the procedure do not address corrosion.
Request: Clarify how this is considered consistent with the GALL AMP XI.M26. If it is not consistent, justify why this is not an exception or an enhancement.
RAI B.2.1.25-01
=
Background===
- GALL AMP XI.M37, "Flux Thimble Tube Inspection," Program Element 5, "monitoring and trending," states that flux thimble tube wall thickness measurements will be trended and wear rates calculated, with examination frequency based on plant-specific wear projections, and that re-baselining of the examination frequency should be justified using plant-specific wear-rate data unless prior plant-specific NRC acceptance for the re-baselining was received.
Issue: SNGS replaced its original flux thimble tubes with an improved design in 1990 and has not routinely performed flux thimble tube eddy current testing (ECT) to measure flux thimble tube wall thickness since 1993. SNGS states that it will reinstitute flux thimble tube testing in accordance with the recommendations in NRC Bulletin 88-09 during the period of extended operation. Because of the lack of on-going testing, it is not clear to the staff how SNGS will baseline the existing wall thickness of flux thimble tubes.
Requests:
a) Explain how the baseline condition of the flux thimble tube walls will be established when ECT is reinstituted during the period of extended operation.
b) Explain how plant-specific flux thimble tube wear rates will be determined and projected to ensure that acceptance criteria for flux thimble tube wall thickness continue to be met during the operating interval between subsequent flux thimble tube inspections.
RAI B.2.1.38-01
Background
- GALL AMP XI.E3, states that the program applies to inaccessible medium voltage cables that are exposed to significant moisture simultaneously with significant voltage. Significant moisture is defined as periodic exposures to moisture that last for more than a few days. GALL AMP XI.E3 also states that periodic actions are taken to prevent cables from being exposed to significant moisture. GALL AMP XI.E3 further states that inspection for water collection should be performed based on actual plant experience with water accumulation in the manhole with an inspection frequency of at least every two years.
Issue: The applicant identified operating experience and the staff confirmed through walkdowns and operating experience review, cases of inaccessible medium voltage cable exposure to significant moisture (cable submergence in manholes/vaults) and cable support structural degradation inconsistent with GALL AMP XI.E3 (i.e., periodic actions are taken to prevent cables from being exposed to significant moisture). A review of operating experience does not provide information on in-scope inaccessible medium voltage station blackout (SBO) recovery cable testing results or manhole/vault inspections. SBO cables in-scope of license renewal including direct buried portions may also be exposed to significant moisture.
Requests: a) Describe how SNGS LRA AMP B.2.1.38 meets GALL AMP XI.E3 for in-scope inaccessible medium voltage SBO recovery cables considering that operating history shows that the in-scope inaccessible medium voltage SBO recovery cables are exposed to significant moisture (i.e. exposure lasting more than a few days).
b) In addition, (i) describe how plant operating experience was incorporated into AMP B.2.1.38 to minimize exposure of in-scope inaccessible medium voltage SBO recovery cables to significant moisture during the period of extended operation, (ii) discuss any corrective actions taken that address submerged cable conditions identified through manhole/vault inspections, (iii) discuss cable testing/frequency and applicability that demonstrates that in-scope inaccessible medium voltage SBO recovery cable will continue to perform their intended function during the period of extended operation.
RAI B.2.1.38-02
=
Background===
- GALL AMP XI.E3, states that the program applies to inaccessible (e.g., in conduit, direct buried) medium-voltage cables within the scope of license renewal that are exposed to significant moisture simultaneously with significant voltage.
Issue: Program Basis Document SH-PBD-AMP-XI.E3, "Inaccessible Medium Voltage Cables Not Subject to 10 CFR 50.49 Environmental Qualification Requirements," scope of program does not identify cables that are within the scope of the program.
Request: Identify inaccessible medium voltage cables within the scope of AMP B.2.1.38 including cable ID number, insulation and jacket material.
RAI B.2.1.38-03
Background
- GALL AMP XI.E3, "Inaccessible Medium Voltage Cables Not Subject to 10 CFR 50.49 Environmental Qualification Requirements" Program Element 1, "scope of program," provides definitions for significant moisture and significant voltage. Standard Review Plan for License Renewal (SRP LR) Table 3.6-2, Final Safety Analysis Report (FSAR) Supplement for Aging Management of Electrical and Instrumentation and Control System also includes definitions for significant moisture and significant voltage.
Issue: LRA FSAR Supplement Section A.2.1.38 does not include definitions of significant moisture or significant voltage consistent with SRP LR Table 3.6-2 or GALL AMP XI.E3, "Inaccessible Medium Voltage Cables Not Subject to 10 CFR 50.49 Environmental Qualification Requirements." The lack of these definitions in combination with the applicant's stated objective of using inspections to ensure that cables are infrequently submerged may not provide consistency with GALL AMP XI.E3.
Request: Explain why LRA FSAR supplement A.2.1.38 for LRA AMP B.2.1.38 does not include the definitions of significant voltage and significant moisture consistent with GALL AMP XI.E3 and SRP LR Table 3.6-2.
RAI B.2.1.40-01
Background
- NUREG 1801, Vol. 1, Rev. 1, GALL Report states that operating experience involving the aging management program, including past corrective actions resulting in program enhancements or additional programs, should provide objective evidence to support a determination that the effects of aging will be adequately managed so that the structure and components' intended functions will be maintained during the period of extended operation. Issue: The applicant LRA and basis document provide operating experience examples that conclude that the effects of aging and aging mechanisms are being adequately managed. The applicant stated that these examples provide objective evidence that the aging management program, acceptance criterion, and the corrective action process will be effective in resolving problems prior to loss of function. However, it is not clear based on the applicant's discussion that the included examples are representative of operating experience in that the search methodology and criteria, (e.g., XI.E6 connection type, time frame, connection stressors - application, loading, locations) and aging management program components within the scope of license renewal and electrical GALL AMPs are not discussed.
Request: Provide a discussion on the evaluation methods and search criteria used to select the examples provided in LRA B.2.1.40. The discussion should demonstrate that the examples provided are representative of the operating experience for the applicable GALL AMP. See LRA Sections B.2.1.36, 37, 38, 39, 40 and B.3.1.2 and the associated program basis documents.
RAI B2.2.2-01
Background
- Plant-specific B.2.2.2 Periodic Inspection in the "detection of aging effects" program element does not describe when, where, and how program data are collected. However, Section A1.2.3 of NUREG-1800, Appendix A states that the program element should describe when, where, and how program data are collected (i.e., all aspects of activities to collect data as part of the program).
Issue:
LRA Section B.2.2.2 Periodic Inspection in the "detection of aging effects" program element description states that the parameters monitored and inspected include direct visual inspection of component surfaces and ultrasonic wall thickness measurements. It is not clear to the staff what parameter would be monitored during direct visual inspections to identify effect of aging on aluminum components, e.g., pitting and crevice corrosion (LRA Table 3.3.2-7).
Request: State what parameters would be monitored to identify the effect of aging on aluminum components, e.g., pitting and crevice corrosion (LRA Table 3.3.2-7).
RAI B2.2.2-02
Background
- Plant-specific B.2.2.2 Periodic Inspection "detection of aging effects" program element does not describe when, where, and how program data are collected. However, Section A1.2.3 of NUREG-1800, Appendix A states that the program element should describe when, where, and how program data are collected (i.e., all aspects of activities to collect data as part of the program).
Issue: LRA Section B.2.2.2 Periodic Inspection in "detection of aging effects" program element description states that visual inspections of elastomer components will detect the presence and extent of hardening and loss of strength; and visual inspection may include physical manipulation to assist in detecting hardening and degradation of elastomer components. Given that visual inspection would not always include physical manipulations, the staff is not clear on: (a) the process in determining a need for physical manipulation to assist visual inspections of elastomer components; (b) the characteristics assessed by physical manipulations; and (c) how collected information is quantified or otherwise used to assess component longevity.
Request: Clarify the process in determining a need for physical manipulation to assist visual inspections of elastomer components. Clarify characteristics assessed by physical manipulations and how collected information will be quantified or otherwise used to assess component longevity.
RAI B2.2.2-03
=
Background===
Section A1.2.3 of NUREG-1800, Appendix A states that the acceptance criteria of the program and its basis should be described.
Issue:
In element 6 of the LRA AMP it states that acceptance criteria for loss of material are based on the original equipment design wall thickness and any corrosion allowance requirements. It is not clear to the staff what the acceptance criteria for determining effects of aging on aluminum components are.
Request:
Clarify what the acceptance criteria for determining effects of aging on aluminum components are. RAI B.2.1.3-01
Background
- GALL AMP XI.M3, "Reactor Head Closure Studs," Program Element 4, "detection of aging effects," states that "Examination Category B-G-1 for pressure-retaining bolting greater than two inches diameter in reactor vessels specifies - surface and volumetric examination of studs when removed."
Issue: Based on its review of the SNGS Reactor Head Closure Studs Program, the staff has determined that only volumetric examinations are provided for studs when removed from the reactor flange.
The staff also noted that in SNGS LRA Section B.2.1.3, the "program description" states that the Reactor Head Closure Studs AMP is an existing program that provides for ASME Section XI inspections of reactor head closure studs, nuts and washers for cracking, loss of material, loss of fracture toughness and coolant leakage from reactor vessel closure stud bolting in an air environment. However, loss of fracture toughness is not an aging effect that is typically associated with reactor head closure studs.
Requests: a) Explain why this is not identified as an exception to the GALL Report's recommendations or identify it as an exception to the GALL Report.
b) Justify why volumetric examination (only) of reactor head closure studs when removed provides adequate detection of the aging effects for which the Reactor Head Closure Studs Program is credited.
c) Clarify why loss of fracture toughness is listed as an aging effect managed by the Reactor Head Closure Studs Program, and explain what mechanism causes this aging effect in these components.