Letter Sequence RAI |
---|
|
Results
Other: LR-N09-0162, PSEG Nuclear, Hope Creek Generating Station, Transmittal Letter, License Renewal Application, LR-N10-0234, 10 CFR 54.21(b) Review to Identify Any Current Licensing Basis (CLB) Changes Made Since Submittal of the License Renewal Application (LRA), ML092430373, ML092430374, ML092430384, ML092430386, ML092430387, ML092430388, ML092430389, ML092430390, ML092430484, ML092460442, ML092520185, ML092650382, ML092660174, ML092660447, ML100850462, ML101660452, ML102100544, ML111090416
|
MONTHYEARML0924303742009-08-18018 August 2009 PSEG Nuclear, Hope Creek Generating Station, License Renewal Application, Volume 2 of 3 Project stage: Other ML0924303892009-08-18018 August 2009 PSEG Nuclear, Hope Creek Generating Station, License Renewal Application, Volume 3, Appendix E Project stage: Other ML0924303842009-08-18018 August 2009 PSEG Nuclear, Hope Creek Generating Station, License Renewal Application, Volume 3 Through Appendix a Project stage: Other ML0924303862009-08-18018 August 2009 PSEG Nuclear, Hope Creek Generating Station, License Renewal Application, Volume 3, Appendix B Project stage: Other ML0924303872009-08-18018 August 2009 PSEG Nuclear, Hope Creek Generating Station, License Renewal Application, Volume 3, Appendix C Project stage: Other ML0924303902009-08-18018 August 2009 PSEG Nuclear, Hope Creek Generating Station, License Renewal Application, Volume 3, Appendix F Project stage: Other ML0924304842009-08-18018 August 2009 PSEG Nuclear, Hope Creek Generating Station, License Renewal Application, Volume 3 of 3 Project stage: Other ML0924303882009-08-18018 August 2009 PSEG Nuclear, Hope Creek Generating Station, License Renewal Application, Volume 3, Appendix D Project stage: Other LR-N09-0162, PSEG Nuclear, Hope Creek Generating Station, Transmittal Letter, License Renewal Application2009-08-18018 August 2009 PSEG Nuclear, Hope Creek Generating Station, Transmittal Letter, License Renewal Application Project stage: Other ML0924303732009-08-18018 August 2009 PSEG Nuclear, Hope Creek Generating Station, License Renewal Application, Volume 1 of 3 Project stage: Other LR-N09-0191, Information to Support NRC Staff Review of the Application for Renewed Operating License2009-08-18018 August 2009 Information to Support NRC Staff Review of the Application for Renewed Operating License Project stage: Request ML0924005312009-08-18018 August 2009 PSEG Nuclear, Salem Nuclear Generating Station, Units 1 and 2, License Renewal Application, Volume 2 of 3 Project stage: Other ML0924005322009-08-18018 August 2009 PSEG Nuclear, Salem Nuclear Generating Station, Units 1 and 2, License Renewal Application, Volume 3 of 3 Project stage: Other ML0924302312009-08-18018 August 2009 PSEG Nuclear, Salem Nuclear Generating Station, Units 1 and 2, License Renewal Application, Volume 1 of 3 Project stage: Other LR-N09-0161, PSEG Nuclear, Salem Nuclear Generating Station, Units 1 and 2, Transmittal of License Renewal Application2009-08-18018 August 2009 PSEG Nuclear, Salem Nuclear Generating Station, Units 1 and 2, Transmittal of License Renewal Application Project stage: Request LR-N09-0192, Information to Support NRC Staff Review of the Application for Renewed Operating License2009-08-18018 August 2009 Information to Support NRC Staff Review of the Application for Renewed Operating License Project stage: Request ML0924604422009-09-0303 September 2009 Delaware Citizen Comment on Salem Hope Creek License Renewal Application Project stage: Other ML0924700392009-09-0404 September 2009 Comment on Salem - Hope Creek License Renewal Applications from Citizen Project stage: Other ML0926601742009-09-0707 September 2009 Comment on License Renewal for Salem and Hope Creek Power Plants - Goodman Project stage: Other ML0925201852009-09-0808 September 2009 Comments About Relicensing Salem and Hope Creek Reactors in Nj, Steven Hegedus Project stage: Other ML0926503822009-09-0808 September 2009 Citizen Comment on Salem Hope Creek License Renewal Application Project stage: Other ML0926604472009-09-23023 September 2009 Hope Creek, E-mail from Ruth Panella Comments on License Renewal Project stage: Other ML1007704192010-03-17017 March 2010 Task Order No. 005 Under Delivery Order No. NRC-DR-03-09-061 Project stage: Acceptance Review ML1008502062010-03-24024 March 2010 Task Order No. 004 Under Delivery Order No. NRC-DR-03-09-061 Project stage: Acceptance Review ML1008504622010-04-0606 April 2010 Project Manager Change for the License Renewal of Hope Creek Generating Station Project stage: Other ML1008504592010-04-0606 April 2010 Project Manager Change for the License Renewal of Salem Nuclear Generating Station, Units 1 and 2 (TAC No. ME1834 and ME1836) Project stage: Other ML1009703502010-04-14014 April 2010 License Renewal Application - Request for Additional Information for Section 2.2.5, Boral Monitoring Program Project stage: RAI ML1007606612010-04-14014 April 2010 RAI Regarding Balance of Plant Scoping and Screening Results for the Salem Nuclear Generating Station Units 1 & 2 (Tac Nos. ME1834 and ME1836) Project stage: RAI ML1007503312010-04-15015 April 2010 Request for Additional Information Regarding Scoping and Screening Results for the Hope Creek Generating Station (Tac ME1832) Project stage: RAI ML1010205112010-04-27027 April 2010 License Renewal Application - Request for Additional Information for Section 2.1, Scoping and Screening Methodology Project stage: RAI ML1010601552010-05-14014 May 2010 Request for Additional Information for the Review of the Hope Creek Generating Station License Renewal Application Identified During the Audit Project stage: RAI ML1013805112010-05-24024 May 2010 Request for Additional Information for the Salem Generating Station, Units 1 and 2, License Renewal Application, Section 3.3.2 (TAC Nos ME1836 and ME1834) Project stage: RAI LR-N10-0191, Response to NRC Request for Additional Information Dated April 30, 2010, Regarding Scoping and Screening Methodology for License Renewal Application2010-05-28028 May 2010 Response to NRC Request for Additional Information Dated April 30, 2010, Regarding Scoping and Screening Methodology for License Renewal Application Project stage: Response to RAI ML1013806202010-06-0101 June 2010 Request for Additional Information Regarding Sections 4.6 and 4.7 of the Hope Creek Generating Station License Renewal Application Project stage: RAI ML1013803162010-06-0101 June 2010 Request for Additional Information for the Review of the Hope Creek Generating Station License Renewal Application Section 3.3.2 Project stage: RAI ML1014501792010-06-0303 June 2010 Letter Request for Additional Information for the Review of the Hope Creek Generating Station License Renewal Application Project stage: RAI ML1013801492010-06-0707 June 2010 Request for Additional Information for the Review of the Hope Creek Generating Station License Renewal Application for Section 3.5 Project stage: RAI ML1014600612010-06-0707 June 2010 Request for Additional Information for Salem Nuclear Generating Station Units 1 and 2 License Renewal Application Regarding Section 3.5 (TAC Nos. ME1834 and ME1836) Project stage: RAI ML1013705592010-06-0909 June 2010 Request for Additional Information for the Review of the Hope Creek Generating Station License Review Application Project stage: RAI ML1014600772010-06-10010 June 2010 Request for Additional Information for Salem Nuclear Generating Station Units 1 and 2 License Renewal Application (TAC ME1832 and ME1836) Project stage: RAI ML1014400812010-06-10010 June 2010 Request for Additional Information for the Review of the Salem Generating Station, Unit 1 and Unit 2, License Renewal Application Identified During the Audit (TAC ME1836 and ME1834) Project stage: RAI ML1015504712010-06-11011 June 2010 RAI for Salem Nuclear Generating Station Units 1 and 2 License Renewal Application Sections 3.1.2 and 3.3.2 (TAC No ME1834/ME1836) Project stage: RAI ML1014810092010-06-11011 June 2010 Request for Additional Information for Salem Nuclear Generating Station Units 1 and 2 License Renewal Application Project stage: RAI ML1013707612010-06-14014 June 2010 Request for Additional Information for the Review of the Hope Creek Generating Station License Renewal Application Project stage: RAI ML1014801892010-06-14014 June 2010 Request for Additional Information for Salem Nuclear Generating Station Units 1 and 2 License Renewal Application Regarding Sections 4.3 and 4.4 (TAC Nos. ME1834 and ME1836) Project stage: RAI ML1013905372010-06-17017 June 2010 Request for Additional Information for Salem Nuclear Generating Station Units 1 and 2 License Renewal Application(Tac Nos ME1834, ME1836) Project stage: RAI ML1016104482010-06-22022 June 2010 RAI for the Review of the Hope Creek Generating Station License Renewal Application for Fire Protection Project stage: RAI LR-N10-0234, 10 CFR 54.21(b) Review to Identify Any Current Licensing Basis (CLB) Changes Made Since Submittal of the License Renewal Application (LRA)2010-06-24024 June 2010 10 CFR 54.21(b) Review to Identify Any Current Licensing Basis (CLB) Changes Made Since Submittal of the License Renewal Application (LRA) Project stage: Other ML1016601502010-06-25025 June 2010 Request for Additional Information for the Review of the Hope Creek Generating Station License Renewal Application for Open Cycle Cooling Water System Program and Structures Project stage: RAI ML1015906752010-06-25025 June 2010 Request for Additional Information for the Review of the Hope Creek Generating Station License Renewal Application for Section 4.3 Project stage: RAI 2010-05-14
[Table View] |
Similar Documents at Salem |
---|
Category:Letter
MONTHYEARIR 05000272/20230042024-02-0505 February 2024 Integrated Inspection Report 05000272/2023004 and 05000311/2023004 ML24009A1022024-01-26026 January 2024 Exemption from Select Requirements of 10 CF Part 73 (EPID L-2023-LLE-0045 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) IR 05000272/20234012024-01-22022 January 2024 Material Control and Accounting Program Inspection Report 05000272/2023401 and 05000311/2023401 ML24004A1542024-01-0808 January 2024 Notification of Conduct of a Fire Protection Team Inspection LR-N23-0079, Special Report 23-02-00 Pursuant to the Requirements of Salem Unit 1 Technical Specification 3.3.3.7, Action 10, for the Unit 1 Main Steam Line Rad Monitor Inoperable for Greater than Seven Days2023-12-0707 December 2023 Special Report 23-02-00 Pursuant to the Requirements of Salem Unit 1 Technical Specification 3.3.3.7, Action 10, for the Unit 1 Main Steam Line Rad Monitor Inoperable for Greater than Seven Days ML23270C0072023-11-29029 November 2023 Notice of Proposed Amendment to Decommissioning Trust Agreement LR-N23-0077, Loss of Coolant Accident Peak Cladding Temperature Margin Tracking - Annual Report 2023 & 30 Day Report for Salem Unit 1 Upflow Conversion2023-11-29029 November 2023 Loss of Coolant Accident Peak Cladding Temperature Margin Tracking - Annual Report 2023 & 30 Day Report for Salem Unit 1 Upflow Conversion ML23324A3072023-11-17017 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000272/20230032023-11-13013 November 2023 Integrated Inspection Report 05000272/2023003 and 05000311/2023003 LR-N23-0072, Core Operating Limits Report Cycle 302023-11-0101 November 2023 Core Operating Limits Report Cycle 30 IR 05000272/20230102023-10-12012 October 2023 Biennial Problem Identification and Resolution Inspection Report O5000272/2023010 and 05000311/2023010 IR 05000272/20234022023-10-12012 October 2023 and Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2023402, 05000272/2023402 and 05000311/2023402 (Cover Letter Only) LR-N23-0045, and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement2023-09-0808 September 2023 and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement ML23249A2612023-09-0606 September 2023 License Amendment Request to Modify the Salem and Hope Creek Exclusion Area Boundary IR 05000272/20230052023-08-31031 August 2023 Updated Inspection Plan for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2023005 and 05000311/2023005) ML23233A0762023-08-21021 August 2023 Requalification Program Inspection ML23192A8212023-08-14014 August 2023 and Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Issuance of Amendment Nos. 234, 347, and 329 Revise Technical Specifications to Delete Meteorological Tower Location IR 05000272/20230022023-08-0909 August 2023 Integrated Inspection Report 05000272/2023002 and 05000311/2023002 LR-N23-0055, Special Report 272/23-01-00, Pursuant to the Requirements of Technical Specification 3.3.3.1, Action 23, for the Vent Noble Gas Rad Monitor Inoperable for Greater than Seven Days2023-08-0303 August 2023 Special Report 272/23-01-00, Pursuant to the Requirements of Technical Specification 3.3.3.1, Action 23, for the Vent Noble Gas Rad Monitor Inoperable for Greater than Seven Days IR 05000354/20230022023-08-0303 August 2023 Integrated Inspection Report 05000354/2023002 and Independent Spent Fuel Storage Installation Inspection Report 07200048/2023001 LR-N23-0054, In-Service Inspection Activities2023-07-26026 July 2023 In-Service Inspection Activities LR-N23-0046, Emergency Plan Document Revisions Implemented June 28, 20232023-07-10010 July 2023 Emergency Plan Document Revisions Implemented June 28, 2023 LR-N23-0005, License Amendment Request to Amend Technical Specifications (TS) 6.8.4.f for Permanent Extension of Type a and Type C Leak Rate Test Frequencies2023-06-23023 June 2023 License Amendment Request to Amend Technical Specifications (TS) 6.8.4.f for Permanent Extension of Type a and Type C Leak Rate Test Frequencies ML23139A1472023-06-0505 June 2023 Relief Request Associated with Fourth Interval In-service Inspection Limited Examinations of Weld Coverage ML23096A1842023-05-0909 May 2023 Issuance of Amendment No. 328 Revise and Relocate Reactor Coolant System Pressure and Temperature Limits and Pressurizer Overpressure Protection System Limits to Pressure and Temperature Limits Report IR 05000272/20230012023-05-0303 May 2023 Integrated Inspection Report 05000272/2023001 and 05000311/2023001 ML23081A4662023-05-0202 May 2023 Issuance of Amendment Nos. 346 and 327 Revise Technical Specifications to Extend Allowable Outage Time for Inoperable Emergency Diesel Generator IR 05000272/20233012023-05-0101 May 2023 Initial Operator Licensing Examination Report 05000272/2023301 and 05000311/2023301 LR-N23-0034, 2022 Annual Radiological Environmental Operating Report (AREOR) - Salem Nuclear Generating Station, Unit Nos. 1 and 2 and Hope Creek Generating Station2023-04-27027 April 2023 2022 Annual Radiological Environmental Operating Report (AREOR) - Salem Nuclear Generating Station, Unit Nos. 1 and 2 and Hope Creek Generating Station LR-N23-0035, 2022 Annual Radioactive Effluent Release Report (ARERR)2023-04-27027 April 2023 2022 Annual Radioactive Effluent Release Report (ARERR) LR-N23-0033, Core Operating Limits Report Cycle 272023-04-26026 April 2023 Core Operating Limits Report Cycle 27 LR-N23-0010, License Amendment Request Revision of Technical Specification (TS) to Delete TS Section 5.5 - Meteorological Tower Location2023-04-21021 April 2023 License Amendment Request Revision of Technical Specification (TS) to Delete TS Section 5.5 - Meteorological Tower Location ML23089A0942023-04-17017 April 2023 NRC to PSEG Hope Creek, Transmittal of the National Marine Fisheries Service'S March 24, 2023, Biological Opinion GAR-2020-02842 Concerning Salem and Hope Creek ML23087A1492023-04-17017 April 2023 NRC to PSEG Salem, Transmittal of the National Marine Fisheries Service'S March 24, 2023, Biological Opinion GAR-2020-02842 Concerning Salem and Hope Creek ML23103A3232023-04-13013 April 2023 Submittal of Updated Final Safety Analysis Report, Rev. 26, Summary of Revised Regulatory Commitments for Hope Creek, Summary of Changes to PSEG Nuclear LLC, Quality Assurance Topical Report, NO-AA-10, Rev. 89 ML23095A3682023-04-12012 April 2023 and Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Threshold Determination for Proposed Transfer of Land Ownership LR-N23-0006, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-24024 March 2023 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations ML23086A0912023-03-24024 March 2023 NMFS to NRC, Transmittal of Biological Opinion for Continued Operations of Salem and Hope Creek Nuclear Generating Stations RS-23-049, Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-23023 March 2023 Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations LR-N23-0019, and Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums2023-03-21021 March 2023 and Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums ML23044A1052023-03-13013 March 2023 Issuance of Amendment Nos. 345 and 326 Relocate Technical Specifications Requirements for Reactor Head Vents to Technical Requirements Manual ML23037A9712023-03-0909 March 2023 and Salem Nuclear, Unit Nos. 1 and 2 Issuance of Amendment Nos. 233, 344, and 325 Relocate Technical Specification Staff Qualification Requirements to the PSEG Quality Assurance Topical Report IR 05000272/20230112023-03-0707 March 2023 Comprehensive Engineering Team Inspection Report 05000272/2023011 and 05000311/2023011 IR 05000272/20220062023-03-0101 March 2023 Annual Assessment Letter for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2022006 and 05000311/2022006) LR-N23-0016, and Salem Generating Station, Units 1 and 2 - Report of Changes, Tests, and Experiments2023-02-28028 February 2023 and Salem Generating Station, Units 1 and 2 - Report of Changes, Tests, and Experiments LR-N23-0012, Annual Property Insurance Status Report2023-02-24024 February 2023 Annual Property Insurance Status Report LR-N23-0014, Stations Submittal of 2022 Annual Report of Fitness for Duty Performance Data Per 10 CFR 26.203(e) and 10 CFR 26.7172023-02-23023 February 2023 Stations Submittal of 2022 Annual Report of Fitness for Duty Performance Data Per 10 CFR 26.203(e) and 10 CFR 26.717 ML23034A1532023-02-0909 February 2023 Operator Licensing Examination Approval ML23019A3482023-02-0202 February 2023 Issuance of Relief Request No. SC-I5R-221 for the Alternative Repair for Service Water System Piping LR-N23-0003, Response to Requests for Additional Information Salem Unit 2 Relief Request S2-I4R-2112023-02-0101 February 2023 Response to Requests for Additional Information Salem Unit 2 Relief Request S2-I4R-211 2024-02-05
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML22333A9022022-11-29029 November 2022 NRR E-mail Capture - Final Iolb RAI - Salem 1 and 2 LAR to Revise TS to Extend Allowed Outage Time for Inoperable EDG ML22318A1062022-11-14014 November 2022 Information Request for Quadrennial Baseline Comprehensive Engineering Team Inspection; Notification to Perform Inspection 05000272/2023011 and 05000311/2023011 ML22290A2202022-10-17017 October 2022 NRR E-mail Capture - Final RAI - Salem 1 and 2 LAR to Revise TS to Extend Allowed Outage Time for Inoperable EDG ML22055A0702022-02-22022 February 2022 NRR E-mail Capture - Final RAI - Salem 1-Relief Request Associated with Fourth Inservice Inspection (ISI) Interval Limited Examinations (L-2021-LLR-0085) ML21256A1902021-09-10010 September 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21144A2132021-05-24024 May 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21068A4142021-03-0909 March 2021 NRR E-mail Capture - Final RAI for Salem Unit 1 LAR to Revise and Relocate Pressurizer Overpressure Protection System Limits to Pressure and Temperature Limits Report ML21043A1442021-02-11011 February 2021 NRR E-mail Capture - Salem - Final RAI Alternative for Examination of ASME Section XI, Category B-B, Item Number B2.11and B2.12 (L-2020-LRR-0103) ML21021A2592021-01-21021 January 2021 NRR E-mail Capture - Final RAI - Salem 1 - Steam Generator Tube Inspection Report ML20281A5172020-10-13013 October 2020 Notification of Conduct of a Fire Protection Team Inspection ML18267A1712018-09-21021 September 2018 NRR E-mail Capture - Final RAI from PRA Branch: Revise Technical Specifications to Increase Inverter AOT Extension (L-2018-LLA-0140) ML18264A0122018-09-20020 September 2018 NRR E-mail Capture - Final RAI from I&C Branch: Revise Technical Specifications to Increase Inverter AOT Extension (L-2018-LLA-0140) ML18250A3132018-09-0606 September 2018 NRR E-mail Capture - Final RAI: Revise Technical Specifications to Increase Inverter AOT Extension (L-2018-LLA-0140) ML18171A3212018-06-20020 June 2018 NRR E-mail Capture - Final RAI: Revise Technical Specifications to Adopt TSTF-411 and 418 (L-2017-LLA-0442) ML18094B0832018-04-0505 April 2018 Enclosurequest for Additional Information (Letter to P. Duke RAI Regarding Entergy Operations, Inc.'S Decommissioning Funding Plan Update for Salem and Hope Creek, and Peach Bottom ISFSIs Docket Nos. 72-48 and 72-29) ML18067A1482018-03-0808 March 2018 Enclosurequest for Additional Information (Letter to P. R. Simpson Request for Additional Information Regarding Exelon Generating Company, Llc'S Decommissioning Funding Plan Update for Independent Spent Fuel Storage Installation) ML17212B1152017-07-31031 July 2017 Request for Additional Information - Salem Units 1 and 2 - Containment Fan Coil Unit Allowed Outage Time Amendment Request (CACs MF9364 and MF9365) ML17199A1122017-07-18018 July 2017 Request for Additional Information - Salem Units 1 and 2 - Accident Monitoring Instrumentation License Amendment Request (CAC Nos. MF8859 & MF8860) ML17192A1672017-07-11011 July 2017 Request for Additional Information - Salem Unit 1 - Steam Generator Tube Inspection Report ML17115A4032017-05-0909 May 2017 Request for Additional Information Regarding Relief Request SC-14R-171 - Use of Code Cases N-695-1 and N-696-1 ML16321A4642016-11-21021 November 2016 and Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Request for Additional Information Regarding License Amendment Request to Remove Certain Training Requirements ML16218A0052016-08-11011 August 2016 Request for Additional Information Concerning Request for an Extension to Enforcement Guidance Memorandum 12-001 ML16195A4492016-07-14014 July 2016 Request for Additional Information Regarding Chilled Water System Modifications ML16188A4152016-07-0707 July 2016 Request for Additional Information Aging Management Program Plan for Reactor Vessel Internals ML16124A5802016-05-0303 May 2016 and Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Redacted - Request for Additional Information Review of Security Plan Revision 17 Changes ML16013A1592016-02-17017 February 2016 Request for Additional Information Regarding Chilled Water System Modifications ML15287A1412015-11-0202 November 2015 Request for Additional Information License Amendment Request Regarding Replacement of Source Range and Intermediate Range Neutron Monitoring Systems ML15287A1052015-11-0202 November 2015 Request for Additional Information License Amendment Request to Isolate Unborated Water Sources and Use Gamma-Metrics Post-Accident Neutron Monitors During Mode 6 (Refueling) (CAC Nos. MF5831 & MF5832) ML15299A3832015-10-29029 October 2015 Supplemental Information Needed for Acceptance of Requested Licensing Action Amendment Request Regarding Chilled Water System Modification ML15069A1812015-03-31031 March 2015 Request for Additional Information Aging Management Program Plan for Reactor Vessel Internals (TAC Nos. MF5149 and MF5150) ML15075A2602015-03-24024 March 2015 Request for Additional Information Spring 2014 Steam Generator Tube Inspections ML15055A3772015-03-10010 March 2015 and Salem Nuclear Generating Station, Unit Nos. 1 and 2, Request for Additional Information Request to Update Appendix B to Renewed Facility Operating License DPR-70, DPR-75 and NPF-57 ML14197A6192014-07-24024 July 2014 and Salem Nuclear Generating Station, Units 1 and 2 - Request for Additional Information Regarding Cyber Security Plan Milestone 8 Implementation Schedule (Tac Nos. MF3384, MF3385 and MF3386) ML14168A2422014-06-28028 June 2014 Request for Additional Information Regarding Flooding Hazard Reevaluation ML14135A2912014-06-0202 June 2014 RAI Regarding Request for Relief SC-I4R-140 from American Society of Mechanical Engineers Boiler & Pressure Vessel Code, Section XI Requirements Regarding the Reactor Vessel Head Flange Seal Leak Detection ML14086A6362014-04-30030 April 2014 Request for Additional Information Regarding Core Operating Limits Report ML14066A2952014-03-0606 March 2014 Licensed Operator Positive Fitness-For-Duty-Test (FY14) ML13330A5672013-11-22022 November 2013 Request for Additional Information: Salem Units 1 and 2 - Relief Request SC-14R-133 Repair of Service Water Piping (TAC MF1375 & 1376) ML13304B4182013-11-0101 November 2013 Request for Additional Information Associated with Near-Term Task Force Recommendation 2.3, Seismic Walkdowns ML13304B9362013-10-29029 October 2013 Request for Additional Information: Salem Units 1 and 2 - Relief Request SC-14R-133 Repair of Service Water Piping (TAC MF1375 & 1376) ML13270A4142013-10-17017 October 2013 Interim Staff Evaluation and Request for Additional Information Regarding the Overall Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation (TAC Nos. MF0913 and Mf ML13249A0112013-09-0505 September 2013 Weko Seal Relief Request RAI ML13196A3382013-07-15015 July 2013 2013 Decommissioning Fund Report RAI ML13192A2322013-07-11011 July 2013 Draft Request for Additional Information Overall Integrated Plan in Response to Order EA-12-051, Reliable Spent Fuel Pool Instrumentation. ML13186A1672013-07-11011 July 2013 Request for Additional Information Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) ML13179A3032013-06-28028 June 2013 RAIs for Salem Regarding Response to Order EA-12-051 (SFP Instrumentation) ML13137A4882013-06-0505 June 2013 Request for Additional Information Relief Request SC-l4R-133 ML13149A0862013-06-0505 June 2013 Request for Additional Information Decommissioning Funding Status Report ML13102A2752013-04-25025 April 2013 Request for Additional Information Change to PSEG Emergency Plan to Remove the Backup R45 Plant Vent Radiation Monitor Indications ML13063A7172013-03-11011 March 2013 Second Request for Additional Information Deletion of Condition for Inoperable Control Area Air Condition System/Control Room Emergency Air Conditioning System Isolation Dampers 2022-02-22
[Table view] |
Text
June 10, 2010 Mr. Thomas Joyce President and Chief Nuclear Officer PSEG Nuclear LLC P.O. Box 236 Hancocks Bridge, NJ 08038
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION FOR SALEM NUCLEAR GENERATING STATION UNITS 1 AND 2 LICENSE RENEWAL APPLICATION (TAC NOS. ME1834 AND ME1836)
Dear Mr. Joyce:
By letter dated August 18, 2009, as supplemented by letter dated January 23, 2009, Public Service Enterprise Group Nuclear, LLC, submitted an application pursuant to Title 10 of the Code of Federal Regulations Part 54 for renewal of Operating License Nos. DPR-70 and DPR-75 for Salem Nuclear Generating Station Units 1 and 2, respectively. The staff of the U.S.
Nuclear Regulatory Commission (NRC or the staff) is reviewing this application in accordance with the guidance in NUREG-1800, Standard Review Plan for Review of License Renewal Applications for Nuclear Power Plants. During its review, the staff has identified areas where additional information is needed to complete the review. The staffs request for additional information is included in the Enclosure. Further requests for additional information may be issued in the future.
Items in the enclosure were provided to John Hufnagel and other members of your staff, and a mutually agreeable date for the response is within 30 days from the date of this letter. If you have any questions, please contact me by telephone at 301-415-2981 or by e-mail at bennett.brady@nrc.gov.
Sincerely,
/RA/
Bennett M. Brady, Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-272 and 50-311
Enclosure:
As stated cc w/encl: See next page
ML101460077 OFFICE PM:DLR:RPB1 LA:DLR BC:DLR:RPB1 PM:DLR:RPB1 NAME B. Brady S. Figueroa B. Pham B. Brady DATE 6/9/10 6/1/10 6/9/10 6/10/10
Letter to T. Joyce from B. Brady dated June 10, 2010
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION FOR SALEM NUCLEAR GENERATING STATION UNITS 1 AND 2 LICENSE RENEWAL APPLICATION (TAC NOS. ME1834 AND ME1836)
DISTRIBUTION:
HARD COPY:
DLR RF E-MAIL:
PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RdsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRapb Resource RidsOgcMailCenter Resource
BPham BBrady ACunanan SCuadrado CEccleston REnnis CSanders BHarris, OGC ABurritt, RI RConte, RI MModes, RI DTifft, RI NMcNamara, RI
Salem Nuclear Generating Station, Units 1 and 2 cc:
Mr. Robert Braun Mr. Michael Gaffney Senior Vice President Nuclear Manager - Hope Creek Regulatory PSEG Nuclear LLC Assurance One Alloway Creek Neck Road PSEG Nuclear LLC Hancocks Bridge, NJ 08038 One Alloway Creek Neck Road Hancocks Bridge, NJ 08038 Mr. Brian Booth Director Nuclear Oversight Mr. Ali Fakhar PSEG Nuclear Manager, License Renewal P.O. Box 236 PSEG Nuclear LLC Hancocks Bridge, NJ 08038 One Alloway Creek Neck Road Hancocks Bridge, NJ 08038 Mr. John Perry Station Vice President - Hope Creek Township Clerk PSEG Nuclear Lower Alloways Creek Township P.O. Box 236 Municipal Building, P.O. Box 157 Hancocks Bridge, NJ 08038 Hancocks Bridge, NJ 08038 Mr. Larry Wagner Mr. Paul Bauldauf, P.E., Asst. Director Plant Manager - Hope Creek Radiation Protection Programs PSEG Nuclear LLC NJ Department of Environmental One Alloway Creek Neck Road Protection and Energy, CN 415 Hancocks Bridge, NJ 08038 Trenton, NJ 08625-0415 Mr. Michael Gallagher Mr. Brian Beam Vice President - License Renewal Projects Board of Public Utilities Exelon Nuclear LLC 2 Gateway Center, Tenth Floor 200 Exelon Way Newark, NJ 07102 Kennett Square, PA 19348 Regional Administrator, Region I Mr. Jeffrie J. Keenan, Esquire U.S. Nuclear Regulatory Commission Manager - Licensing 475 Allendale Road PSEG Nuclear LLC King of Prussia, PA 19406 One Alloway Creek Neck Road Hancocks Bridge, NJ 08038 Mr. Paul Davison Vice President, Operations Support Mr. Gregory Sosson PSEG Nuclear LLC Director Corporate Engineering One Alloway Creek Neck Road PSEG Nuclear LLC Hancocks Bridge, NJ 08038 One Alloway Creek Neck Road Hancocks Bridge, NJ 08038
Salem Nuclear Generating Station, Units 1 and 2 cc:
Ms. Christine Neely Director - Regulator Affairs PSEG Nuclear LLC One Alloway Creek Neck Road Hancocks Bridge, NJ 08038 Senior Resident Inspector Hope Creek Generating Station U.S. Nuclear Regulatory Commission Drawer 0509 Hancocks Bridge, NJ 08038 Mr. Earl R. Gage Salem County Administrator Administration Building 94 Market Street Salem, NJ 08079
REQUEST FOR ADDITIONAL INFORMATION FOR SALEM NUCLEAR GENERATING STATION (SNGS) UNITS 1 AND 2 LICENSE RENEWAL APPLICATION (LRA)
(TAC NOS. ME1834 AND ME1836)
RAI B.2.1.7-01
Background:
Based on a review of GALL Report Table 1, line item 80, for cast austenitic stainless steel (CASS) reactor vessel internal components, the GALL recommends use of the GALL AMP XI.M13, Thermal Aging and Neutron Irradiation Embrittlement of Cast Austenitic Stainless Steel (CASS) Program to manage the aging effect of loss of fracture toughness/thermal aging embrittlement. The GALL Report does not have an aging effect of cracking, stress-corrosion cracking (SCC), irradiation-assisted stress-corrosion cracking (IASCC), void swelling, or changes in dimension line item with CASS as the material.
Issue:
Several line items in LRA Table 3.1.2-3, assigned generic note C, have an aging effect of cracking, SCC, IASCC, changes in dimension and void swelling with CASS material components. These line items credit the LRA pressurized-water reactor (PWR) Vessel Internals AMP. These line items reference GALL Report NUREG-1801 Volume 2 line items which list stainless steel instead of CASS as the material. Additionally, one LRA Table 3.1.2-3 line item associated with a loss of fracture toughness/neutron irradiation embrittlement, and void swelling credits the PWR Vessel Internals Program and assigns this line item generic note E. Although there is no specific GALL line item for an aging effect of cracking, SCC, IASCC, changes in dimension and void swelling with CASS material components, the staff questions why the LRA does not credit GALL AMP XI.M13, Thermal Aging and Neutron Irradiation Embrittlement of Cast Austenitic Stainless Steel (CASS) Program to manage these aging effects.
Request:
Provide a justification for using the PWR Vessels Internals AMP instead of GALL AMP XI.M13, Thermal Aging and Neutron Irradiation Embrittlement of Cast Austenitic Stainless Steel (CASS).
RAI B.2.1.23-01
Background:
GALL AMP XI.M35, Element 4 detection of aging effects, states that inspections of ASME Code Class 1 small-bore piping should be volumetric.
Issue:
The LRA Sections B.2.1.23 and A.2.1.23 state socket welds that fall within the weld examination sample will be examined using visual examination (VT-2). The staff notes that the proposed inspection methodology is not consistent with GALL.
ENCLOSURE
Request:
Please provide technical basis how VT-2 can adequately manage aging in ASME Code Class 1 socket welds.
RAI B.2.2.2-03
Background:
Section A1.2.3 of NUREG-1800, Appendix A states that the acceptance criteria of the program and its basis should be described.
Issue:
In element 6 of the LRA AMP it states that acceptance criteria for loss of material are based on the original equipment design wall thickness and any corrosion allowance requirements. It is not clear to the staff what the acceptance criteria for determining effects of aging on aluminum components are.
Request:
Clarify what the acceptance criteria for determining effects of aging on aluminum components are.
RAI 3.1.1-01
Background:
Standard Review Plan-License Renewal (SRP-LR) Section 3.1.2.2.13 identifies that cracking due to primary water stress-corrosion cracking (PWSCC) could occur in PWR components made of nickel alloy and steel with nickel alloy cladding, including reactor coolant pressure boundary components and penetrations inside the reactor coolant system (RCS) such as pressurizer heater sheathes and sleeves, nozzles, and other internal components. GALL Report Volume 2 Item IV.D1-06 recommends Chapter XI.M2, Water Chemistry, for PWR primary water for managing the aging effect of cracking in the nickel alloy steam generator (SG) divider plate exposed to reactor coolant.
In LRA Table 3.1.1, Item 81, the applicant credits its Water Chemistry Program to manage cracking due to stress corrosion cracking in nickel alloy steam generator (SG) primary channel head divider plate exposed to reactor coolant in the steam generators.
In UFSAR Section 5.5.2.2.1, the applicant describes that the divider plate is made with Inconel 690 for Unit 2 replacement steam generators. The staff notes that the use of this nickel alloy 690 should prevent the aging effect of PWSCC.
However, there is no information about the construction material of the divider plate for Unit 1 steam generators.
Issue:
From recent operating experience in steam generators with a similar design to that of Salem Unit 1 steam generators, extensive cracking due to PWSCC has been identified in SG divider plates made with nickel alloy 600, even with proper primary water chemistry. Specifically, cracks have been detected in the stub runner, very close to the tubesheet/stub runner weld and with depths of almost a third of the divider plate thickness. Therefore, the staff notes that the Water Chemistry Program alone may not be effective in managing the aging effect of cracking due to PWSCC in SG divider plates.
Such cracks could impact adjacent items, such as the tubesheet and the channel head, if they propagate to the boundary with these items. For the tubesheet, PWSCC cracks in the divider plate could propagate to the tubesheet cladding with possible consequences to the integrity of the tube/tubesheet welds. For the channel head, the PWSCC cracks in the divider plate could propagate to the SG triple point and potentially affect the pressure boundary of the SG channel head.
Request:
Please discuss the materials of construction of your Unit 1 SG divider plate assembly. If these materials are susceptible to cracking (e.g., nickel alloy 600 or the associated nickel alloy 600 weld materials), please discuss the potential for cracking in the divider plate to propagate into other components (e.g., tubesheet cladding).
If propagation into these other components cannot be ruled out, please describe an inspection program (examination technique and frequency) to ensure that there are no cracks propagating into other items (e.g., tubesheet and channel head) that could challenge the integrity of other adjacent items.