Issue date | Title | Topic | |
---|---|---|---|
ML22333A902 | 29 November 2022 | NRR E-mail Capture - Final Iolb RAI - Salem 1 and 2 LAR to Revise TS to Extend Allowed Outage Time for Inoperable EDG | Probabilistic Risk Assessment |
ML22318A106 | 14 November 2022 | Information Request for Quadrennial Baseline Comprehensive Engineering Team Inspection; Notification to Perform Inspection 05000272/2023011 and 05000311/2023011 | Ultimate heat sink Commercial Grade Dedication Probabilistic Risk Assessment Temporary Modification Aging Management |
ML22290A220 | 17 October 2022 | NRR E-mail Capture - Final RAI - Salem 1 and 2 LAR to Revise TS to Extend Allowed Outage Time for Inoperable EDG | Probabilistic Risk Assessment |
ML22055A070 | 22 February 2022 | NRR E-mail Capture - Final RAI - Salem 1-Relief Request Associated with Fourth Inservice Inspection (ISI) Interval Limited Examinations (L-2021-LLR-0085) | |
ML21256A190 | 10 September 2021 | NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application | |
ML21144A213 | 24 May 2021 | NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application | |
ML21068A414 | 9 March 2021 | NRR E-mail Capture - Final RAI for Salem Unit 1 LAR to Revise and Relocate Pressurizer Overpressure Protection System Limits to Pressure and Temperature Limits Report | Anticipated operational occurrence Hydrostatic Pressure and Temperature Limits Report |
ML21043A144 | 11 February 2021 | NRR E-mail Capture - Salem - Final RAI Alternative for Examination of ASME Section XI, Category B-B, Item Number B2.11and B2.12 (L-2020-LRR-0103) | Hydrostatic Incorporated by reference |
ML21021A259 | 21 January 2021 | NRR E-mail Capture - Final RAI - Salem 1 - Steam Generator Tube Inspection Report | Foreign Material Exclusion |
ML20281A517 | 13 October 2020 | Notification of Conduct of a Fire Protection Team Inspection | Safe Shutdown Probabilistic Risk Assessment Temporary Modification Time Critical Operator Action Fire Protection Program |
ML18267A171 | 21 September 2018 | NRR E-mail Capture - Final RAI from PRA Branch: Revise Technical Specifications to Increase Inverter AOT Extension (L-2018-LLA-0140) | Probabilistic Risk Assessment Large early release frequency |
ML18264A012 | 20 September 2018 | NRR E-mail Capture - Final RAI from I&C Branch: Revise Technical Specifications to Increase Inverter AOT Extension (L-2018-LLA-0140) | |
ML18250A313 | 6 September 2018 | NRR E-mail Capture - Final RAI: Revise Technical Specifications to Increase Inverter AOT Extension (L-2018-LLA-0140) | Anticipated operational occurrence |
ML18171A321 | 20 June 2018 | NRR E-mail Capture - Final RAI: Revise Technical Specifications to Adopt TSTF-411 and 418 (L-2017-LLA-0442) | Mission time Probabilistic Risk Assessment |
ML18094B083 | 5 April 2018 | Enclosurequest for Additional Information (Letter to P. Duke RAI Regarding Entergy Operations, Inc.'S Decommissioning Funding Plan Update for Salem and Hope Creek, and Peach Bottom ISFSIs Docket Nos. 72-48 and 72-29) | Decommissioning Funding Plan Authorized possession limits |
ML18067A148 | 8 March 2018 | Enclosurequest for Additional Information (Letter to P. R. Simpson Request for Additional Information Regarding Exelon Generating Company, Llc'S Decommissioning Funding Plan Update for Independent Spent Fuel Storage Installation) | Decommissioning Funding Plan Authorized possession limits |
ML17212B115 | 31 July 2017 | Request for Additional Information - Salem Units 1 and 2 - Containment Fan Coil Unit Allowed Outage Time Amendment Request (CACs MF9364 and MF9365) | Probabilistic Risk Assessment Large early release frequency |
ML17199A112 | 18 July 2017 | Request for Additional Information - Salem Units 1 and 2 - Accident Monitoring Instrumentation License Amendment Request (CAC Nos. MF8859 & MF8860) | Probabilistic Risk Assessment |
ML17192A167 | 11 July 2017 | Request for Additional Information - Salem Unit 1 - Steam Generator Tube Inspection Report | |
ML17115A403 | 9 May 2017 | Request for Additional Information Regarding Relief Request SC-14R-171 - Use of Code Cases N-695-1 and N-696-1 | Dissimilar Metal Weld |
ML16321A464 | 21 November 2016 | and Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Request for Additional Information Regarding License Amendment Request to Remove Certain Training Requirements | |
ML16218A005 | 11 August 2016 | Request for Additional Information Concerning Request for an Extension to Enforcement Guidance Memorandum 12-001 | Enforcement Discretion |
ML16195A449 | 14 July 2016 | Request for Additional Information Regarding Chilled Water System Modifications | Probabilistic Risk Assessment |
ML16188A415 | 7 July 2016 | Request for Additional Information Aging Management Program Plan for Reactor Vessel Internals | Aging Management |
ML16124A580 | 3 May 2016 | and Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Redacted - Request for Additional Information Review of Security Plan Revision 17 Changes | |
ML16013A159 | 17 February 2016 | Request for Additional Information Regarding Chilled Water System Modifications | Ultimate heat sink Large early release frequency Maintenance Rule Program |
ML15287A141 | 2 November 2015 | Request for Additional Information License Amendment Request Regarding Replacement of Source Range and Intermediate Range Neutron Monitoring Systems | Earthquake |
ML15287A105 | 2 November 2015 | Request for Additional Information License Amendment Request to Isolate Unborated Water Sources and Use Gamma-Metrics Post-Accident Neutron Monitors During Mode 6 (Refueling) (CAC Nos. MF5831 & MF5832) | Surveillance Frequency Control Program |
ML15299A383 | 29 October 2015 | Supplemental Information Needed for Acceptance of Requested Licensing Action Amendment Request Regarding Chilled Water System Modification | |
ML15069A181 | 31 March 2015 | Request for Additional Information Aging Management Program Plan for Reactor Vessel Internals (TAC Nos. MF5149 and MF5150) | Aging Management Power change |
ML15075A260 | 24 March 2015 | Request for Additional Information Spring 2014 Steam Generator Tube Inspections | |
ML15055A377 | 10 March 2015 | and Salem Nuclear Generating Station, Unit Nos. 1 and 2, Request for Additional Information Request to Update Appendix B to Renewed Facility Operating License DPR-70, DPR-75 and NPF-57 | NJPDES |
ML14197A619 | 24 July 2014 | and Salem Nuclear Generating Station, Units 1 and 2 - Request for Additional Information Regarding Cyber Security Plan Milestone 8 Implementation Schedule (Tac Nos. MF3384, MF3385 and MF3386) | Cyber Security |
ML14168A242 | 28 June 2014 | Request for Additional Information Regarding Flooding Hazard Reevaluation | |
ML14135A291 | 2 June 2014 | RAI Regarding Request for Relief SC-I4R-140 from American Society of Mechanical Engineers Boiler & Pressure Vessel Code, Section XI Requirements Regarding the Reactor Vessel Head Flange Seal Leak Detection | VT-2 Through Wall Leak |
ML14086A636 | 30 April 2014 | Request for Additional Information Regarding Core Operating Limits Report | |
ML14066A295 | 6 March 2014 | Licensed Operator Positive Fitness-For-Duty-Test (FY14) | |
ML13330A567 | 22 November 2013 | Request for Additional Information: Salem Units 1 and 2 - Relief Request SC-14R-133 Repair of Service Water Piping (TAC MF1375 & 1376) | |
ML13304B418 | 1 November 2013 | Request for Additional Information Associated with Near-Term Task Force Recommendation 2.3, Seismic Walkdowns | |
ML13304B936 | 29 October 2013 | Request for Additional Information: Salem Units 1 and 2 - Relief Request SC-14R-133 Repair of Service Water Piping (TAC MF1375 & 1376) | |
ML13270A414 | 17 October 2013 | Interim Staff Evaluation and Request for Additional Information Regarding the Overall Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation (TAC Nos. MF0913 and Mf | High Radiation Area FLEX Spent Fuel Pool Instrumentation Fire Protection Program |
ML13249A011 | 5 September 2013 | Weko Seal Relief Request RAI | |
ML13196A338 | 15 July 2013 | 2013 Decommissioning Fund Report RAI | |
ML13192A232 | 11 July 2013 | Draft Request for Additional Information Overall Integrated Plan in Response to Order EA-12-051, Reliable Spent Fuel Pool Instrumentation. | FLEX Spent Fuel Pool Instrumentation |
ML13186A167 | 11 July 2013 | Request for Additional Information Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) | FLEX Spent Fuel Pool Instrumentation |
ML13179A303 | 28 June 2013 | RAIs for Salem Regarding Response to Order EA-12-051 (SFP Instrumentation) | FLEX Spent Fuel Pool Instrumentation |
ML13137A488 | 5 June 2013 | Request for Additional Information Relief Request SC-l4R-133 | Nondestructive Examination VT-2 |
ML13149A086 | 5 June 2013 | Request for Additional Information Decommissioning Funding Status Report | |
ML13102A275 | 25 April 2013 | Request for Additional Information Change to PSEG Emergency Plan to Remove the Backup R45 Plant Vent Radiation Monitor Indications | Grab sample |
ML13063A717 | 11 March 2013 | Second Request for Additional Information Deletion of Condition for Inoperable Control Area Air Condition System/Control Room Emergency Air Conditioning System Isolation Dampers |