Request for Additional Information for the Salem Generating Station, Unit 1 and Unit 2, License Renewal Application, Section 4.6 (TAC Nos. ME1834 and ME1836)
ML101950487
Person / Time
Site: Salem  PSEG icon.png
Issue date: 07/19/2010
From: Bennett Brady
License Renewal Projects Branch 1
To: Joyce T
Public Service Enterprise Group
CUADRADO, SAMUEL NRR/DLR/RPB1 415-2946
References
TAC ME1834, TAC ME1836
Download: ML101950487 (4)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555*0001 July 19, 2010 Mr. Thomas Joyce President and Chief Nuclear Officer PSEG Nuclear LLC P.O. Box 236 Hancocks Bridge, NJ 08038

SUBJECT:

REQUEST FOR ADDITIONAL INFORMATION FOR THE SALEM NUCLEAR GENERATING STATION, UNIT 1 AND UNIT 2, LICENSE RENEWAL APPLICATION, SECTION 4.6 (TAC NOS. ME1834 AND ME1836)

Dear Mr. Joyce:

By letter dated August 18, 2009, as supplemented by letter dated January 23,2009, Public Service Enterprise Group Nuclear, LLC, submitted an application pursuant to Title 10 of the Code of Federal Regulations Part 54 for renewal of Operating License Nos. DPR-70 and DPR-75 for Salem Nuclear Generating Station, Units 1 and 2, respectively. The staff of the U.S.

Nuclear Regulatory Commission (NRC or the staff) is reviewing this application in accordance with the guidance in NUREG-1800, "Standard Review Plan for Review of License Renewal Applications for Nuclear Power Plants." During its review, the staff has identified areas where additional information is needed to complete the review. The staff's request for additional information is included in the Enclosure. Further requests for additional information may be issued in the future.

Items in the enclosure were provided to John Hufnagel and other members of your staff, and a mutually agreeable date for the response is within 30 days from the date of this letter. If you have any questions, please contact me by telephone at 301-415-2981 or bye-mail at bennett. brady@nrc.gov.

Sincerely, Bennett M. Brady, Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-272 and 50-311

Enclosure:

As stated cc w/encl: Distribution via Listserv

REQUEST FOR ADDITIONAL INFORMATION REGARDING SECTION 4.6 OF THE SALEM NUCLEAR GENERATING STATION, UNIT 1 AND UNIT 2, LICENSE RENEWAL APPLICATION RAI4.6-01

Background

In license renewal application (LRA) Section 2.3.3.9, "Scoping and Screening," the applicant listed a total of 33 cranes and hoists as in~scope for license renewal. Table 3.3.2-9 of the LRA requires a time-limited aging analysis (TLAA) of crane/hoist bridge/trolley girders for aging management due to cumulative fatigue damage/fatigue in accordance with GALL Report recommendations.

LRA Section 4.6 "Crane Load Cycle Limit," identified TLAA for only three cranes: "Polar Gantry Crane," "Fuel Handling Crane," and the "Cask Handling Crane." TLAA for other in~scope cranes with girders are not provided in LRA Section 4.6.

Request Explain why a TLAA for other cranes with girders is not included in the LRA. The staff needs this information to confirm that an evaluation of the fatigue of the in-scope crane girders has been performed that will remain valid for the period of extended operation as required by 10 CFR 54.21(c)(1)(i).

ENCLOSURE

ML101950487 OFFICE PM:DLR:RPB1 LA:DLR BC:DLR:RPB1 rrM:DLR:RPB1 NAME B. Brady IKing B. Pham B. Brady DATE 07/16/10 07/16/10 07/19/10 07/19/10

Letter to T. Joyce from B. Brady dated July 19, 2010

SUBJECT:

REQUEST FOR ADDITIONAL INFORMATION FOR THE SALEM NUCLEAR GENERATING STATION, UNIT 1 AND UNIT 2, LICENSE RENEWAL APPLICATION, SECTION 4.6 (TAC NOS ME1834 AND ME1836)

DISTRIBUTION:

HARD COPY:

DLR RF E-MAIL:

PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RdsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRapb Resource RidsOgcMailCenter Resource BPham BBrady ACunanan SCuadrado CEccleston REnnis CSanders BHarris, OGC ABurritt, RI RConte, RI MModes, RI DTifft, RI NMcNamara, RI