LR-N09-0161, PSEG Nuclear, Salem Nuclear Generating Station, Units 1 and 2, Transmittal of License Renewal Application
Letter Sequence Request | |
---|---|
TAC:ME1834, Control Room Habitability (Approved, Closed) TAC:ME1836, Control Room Habitability (Approved, Closed) | |
Administration Questions
Answers | |
MONTHYEARLR-N09-0192, Information to Support NRC Staff Review of the Application for Renewed Operating License2009-08-18018 August 2009
[Table View]Information to Support NRC Staff Review of the Application for Renewed Operating License Project stage: Request LR-N09-0161, PSEG Nuclear, Salem Nuclear Generating Station, Units 1 and 2, Transmittal of License Renewal Application2009-08-18018 August 2009 PSEG Nuclear, Salem Nuclear Generating Station, Units 1 and 2, Transmittal of License Renewal Application Project stage: Request ML0924005312009-08-18018 August 2009 PSEG Nuclear, Salem Nuclear Generating Station, Units 1 and 2, License Renewal Application, Volume 2 of 3 Project stage: Other ML0924302312009-08-18018 August 2009 PSEG Nuclear, Salem Nuclear Generating Station, Units 1 and 2, License Renewal Application, Volume 1 of 3 Project stage: Other ML0924005322009-08-18018 August 2009 PSEG Nuclear, Salem Nuclear Generating Station, Units 1 and 2, License Renewal Application, Volume 3 of 3 Project stage: Other ML0924604422009-09-0303 September 2009 Delaware Citizen Comment on Salem Hope Creek License Renewal Application Project stage: Other ML0924700392009-09-0404 September 2009 Comment on Salem - Hope Creek License Renewal Applications from Citizen Project stage: Other ML0926601742009-09-0707 September 2009 Comment on License Renewal for Salem and Hope Creek Power Plants - Goodman Project stage: Other ML0925201852009-09-0808 September 2009 Comments About Relicensing Salem and Hope Creek Reactors in Nj, Steven Hegedus Project stage: Other ML0926503822009-09-0808 September 2009 Citizen Comment on Salem Hope Creek License Renewal Application Project stage: Other ML0926604472009-09-23023 September 2009 Hope Creek, E-mail from Ruth Panella Comments on License Renewal Project stage: Other ML1008502062010-03-24024 March 2010 Task Order No. 004 Under Delivery Order No. NRC-DR-03-09-061 Project stage: Acceptance Review ML1008504592010-04-0606 April 2010 Project Manager Change for the License Renewal of Salem Nuclear Generating Station, Units 1 and 2 (TAC No. ME1834 and ME1836) Project stage: Other ML1007606612010-04-14014 April 2010 RAI Regarding Balance of Plant Scoping and Screening Results for the Salem Nuclear Generating Station Units 1 & 2 (Tac Nos. ME1834 and ME1836) Project stage: RAI ML1013805112010-05-24024 May 2010 Request for Additional Information for the Salem Generating Station, Units 1 and 2, License Renewal Application, Section 3.3.2 (TAC Nos ME1836 and ME1834) Project stage: RAI LR-N10-0191, Response to NRC Request for Additional Information Dated April 30, 2010, Regarding Scoping and Screening Methodology for License Renewal Application2010-05-28028 May 2010 Response to NRC Request for Additional Information Dated April 30, 2010, Regarding Scoping and Screening Methodology for License Renewal Application Project stage: Response to RAI ML1014600612010-06-0707 June 2010 Request for Additional Information for Salem Nuclear Generating Station Units 1 and 2 License Renewal Application Regarding Section 3.5 (TAC Nos. ME1834 and ME1836) Project stage: RAI ML1014400812010-06-10010 June 2010 Request for Additional Information for the Review of the Salem Generating Station, Unit 1 and Unit 2, License Renewal Application Identified During the Audit (TAC ME1836 and ME1834) Project stage: RAI ML1014600772010-06-10010 June 2010 Request for Additional Information for Salem Nuclear Generating Station Units 1 and 2 License Renewal Application (TAC ME1832 and ME1836) Project stage: RAI ML1014810092010-06-11011 June 2010 Request for Additional Information for Salem Nuclear Generating Station Units 1 and 2 License Renewal Application Project stage: RAI ML1015504712010-06-11011 June 2010 RAI for Salem Nuclear Generating Station Units 1 and 2 License Renewal Application Sections 3.1.2 and 3.3.2 (TAC No ME1834/ME1836) Project stage: RAI ML1014801892010-06-14014 June 2010 Request for Additional Information for Salem Nuclear Generating Station Units 1 and 2 License Renewal Application Regarding Sections 4.3 and 4.4 (TAC Nos. ME1834 and ME1836) Project stage: RAI ML1013905372010-06-17017 June 2010 Request for Additional Information for Salem Nuclear Generating Station Units 1 and 2 License Renewal Application(Tac Nos ME1834, ME1836) Project stage: RAI ML1016201902010-06-25025 June 2010 Request for Additional Information for Salem Nuclear Generating Station Units 1 and 2, License Renewal Application (Tac ME1834/ME1836) Project stage: RAI ML1016804022010-06-29029 June 2010 Request for Additional Information for Salem Nuclear Generating Station Units 1 and 2, License Renewal Application Regarding Subsection 3.1.2.2.14 (TAC ME1834/ME1836) Project stage: RAI ML1014807262010-06-30030 June 2010 Request for Additional Information for Salem Nuclear Generating Station Units 1 and 2 License Renewal Application Regarding Section B.3.1.1 (TAC Nos. ME1834 and ME1836) Project stage: RAI ML1017203642010-07-12012 July 2010 Request for Additional Information for Salem Nuclear Generating Station Units 1&2 LRA Regarding ASME Section XI ISI, Subsections Iwb,Iwc, and Iwd (TAC Nos. ME1834/ME1836) Project stage: RAI LR-N10-0243, Response to NRC Request for Additional Information Dated June 14, 2010, Related to Sections 4.3 and 4.4 License Renewal Application2010-07-13013 July 2010 Response to NRC Request for Additional Information Dated June 14, 2010, Related to Sections 4.3 and 4.4 License Renewal Application Project stage: Response to RAI ML1019504872010-07-19019 July 2010 Request for Additional Information for the Salem Generating Station, Unit 1 and Unit 2, License Renewal Application, Section 4.6 (TAC Nos. ME1834 and ME1836) Project stage: RAI ML1019606342010-07-23023 July 2010 Request for Additional Information for the Salem Generating Station, Unit 1 and Unit 2, License Renewal Application (TAC ME1834 and ME1836) Project stage: RAI ML1019304962010-07-30030 July 2010 Request for Additional Information for Salem Nuclear Generating Station Units 1 and 2 License Renewal Application (TAC No. ME1834 and Me 1836) Project stage: RAI ML1019504792010-08-0303 August 2010 Request for Additional Information Regarding ASME Section XI, Subsection IWE for the Salem Nuclear Generating Station Units 1 and 2 License Renewal Application (TAC Nos. ME1834 and ME1836) Project stage: RAI ML1019704742010-08-0303 August 2010 Request for Additional Information for Salem Nuclear Generating Station Units 1 and 2 License Renewal Application Regarding Bolting Integrity (TAC Nos. ME1834 and ME1836) Project stage: RAI ML1015402422010-08-0606 August 2010 Request for Additional Information for Salem Nuclear Generating Station Units 1 and 2 License Renewal Application for Buried Piping Inspection Program (TAC Nos. ME1834 and ME1836) Project stage: RAI ML1020004042010-08-0909 August 2010 Request for Additional Information for Salem Nuclear Generating Station Units 1 and 2 License Renewal Application (TAC Nos. ME1834 and ME1836) Project stage: RAI LR-N10-0295, Responses to NRC Requests for Additional Information Dated July 12, 2010, July 19, 2010 and July 23, 2010 Related to Various Sections of License Renewal Application2010-08-10010 August 2010 Responses to NRC Requests for Additional Information Dated July 12, 2010, July 19, 2010 and July 23, 2010 Related to Various Sections of License Renewal Application Project stage: Response to RAI ML1020304172010-08-19019 August 2010 RAI Regarding the Salem Nuclear Generating Station Units 1 and 2 License Renewal Application (TAC ME1834 & ME1836) Project stage: RAI ML1022802112010-08-25025 August 2010 Scoping and Screening Audit Summary Regarding the Salem Nuclear Generating Station, Units 1 and 2, License Renewal Application Project stage: Other LR-N10-0313, Responses to Request for Additional Information Dated 08/03/10, Related to Bolting Integrity and 07/30/10 to Steam Generators and Question Posed During Region 1 Inspection, Regarding License Renewal Application2010-08-26026 August 2010 Responses to Request for Additional Information Dated 08/03/10, Related to Bolting Integrity and 07/30/10 to Steam Generators and Question Posed During Region 1 Inspection, Regarding License Renewal Application Project stage: Response to RAI LR-N10-0322, Response to NRC Request for Additional Information, Dated August 6, 2010 Related to the Buried Piping Inspection Program Associated with License Renewal Application2010-09-0707 September 2010 Response to NRC Request for Additional Information, Dated August 6, 2010 Related to the Buried Piping Inspection Program Associated with License Renewal Application Project stage: Response to RAI ML1024600782010-09-29029 September 2010 RAI for Salem Nuclear Generating Station Units 1 and 2 License Renewal Application (TAC Nos. ME1834 and ME1836) Project stage: RAI ML1026003402010-10-12012 October 2010 RAI for Salem Nuclear Generating Station Units 1 and 2 License Renewal Application for Buried Piping Inspection Program (TAC No. ME1834 and ME1836) Project stage: RAI ML1029102492010-10-25025 October 2010 Request for Additional Information for Salem Nuclear Generating Station, Units 1 and 2, License Renewal Application on Structures Monitoring (TAC No. ME1834 and ME1836) Project stage: RAI ML1029300492010-11-0404 November 2010 Request for Additional Information for Salem Nuclear Generating Station, Units 1 and 2, LRA on Primary Water Stress Corrosion Cracking in Steam Generator Tube-to-Tube Sheet Welds Project stage: RAI ML1030101002010-11-0404 November 2010 Safety Evaluation Report Related to the License Renewal of Salem Nuclear Generating Station, Units 1 and 2 Project stage: Approval ML1031201722010-11-0404 November 2010 Safety Evaluation Report with Open Items Related to the License Renewal of Salem Nuclear Generating Station, Units 1 and 2 Project stage: Approval ML1024305862010-11-0909 November 2010 Audit Report Regarding the Salem Nuclear Generating Station, Units 1 and 2, License Renewal Application (TAC Nos. ME1834 and ME1836) Project stage: Other ML1028101942010-11-22022 November 2010 RAI for Salem Nuclear Generating Station Units 1 and 2 LRA for Use of Westems Program in Metal Fatigue Analysis Project stage: RAI ML1032700762010-12-10010 December 2010 RAI for Salem Nuclear Generating Station Units 1 and 2 LRA Project stage: RAI LR-N10-0414, Response to NRC Request for Additional Information, Dated October 25, 2010, Related to Structures Monitoring Associated with License Renewal Application2010-12-14014 December 2010 Response to NRC Request for Additional Information, Dated October 25, 2010, Related to Structures Monitoring Associated with License Renewal Application Project stage: Response to RAI 2010-06-11 |
ML092430230 | |
Person / Time | |
---|---|
Site: | Salem |
Issue date: | 08/18/2009 |
From: | Fricker C Public Service Enterprise Group |
To: | Document Control Desk, Division of License Renewal |
Robinson, J NRR/DLR/RPB1 415-2878 | |
Shared Package | |
ML092430232 | List: |
References | |
LR-N09-0161, TAC ME1834, TAC ME1836, FOIA/PA-2011-0113 | |
Download: ML092430230 (2) | |
Similar Documents at Salem | |
---|---|
Category:Letter type:LR
MONTHYEARLR-N23-0079, Special Report 23-02-00 Pursuant to the Requirements of Salem Unit 1 Technical Specification 3.3.3.7, Action 10, for the Unit 1 Main Steam Line Rad Monitor Inoperable for Greater than Seven Days2023-12-0707 December 2023
[Table view]Special Report 23-02-00 Pursuant to the Requirements of Salem Unit 1 Technical Specification 3.3.3.7, Action 10, for the Unit 1 Main Steam Line Rad Monitor Inoperable for Greater than Seven Days LR-N23-0077, Loss of Coolant Accident Peak Cladding Temperature Margin Tracking - Annual Report 2023 & 30 Day Report for Salem Unit 1 Upflow Conversion2023-11-29029 November 2023 Loss of Coolant Accident Peak Cladding Temperature Margin Tracking - Annual Report 2023 & 30 Day Report for Salem Unit 1 Upflow Conversion LR-N23-0072, Core Operating Limits Report Cycle 302023-11-0101 November 2023 Core Operating Limits Report Cycle 30 LR-N23-0045, and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement2023-09-0808 September 2023 and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement LR-N23-0055, Special Report 272/23-01-00, Pursuant to the Requirements of Technical Specification 3.3.3.1, Action 23, for the Vent Noble Gas Rad Monitor Inoperable for Greater than Seven Days2023-08-0303 August 2023 Special Report 272/23-01-00, Pursuant to the Requirements of Technical Specification 3.3.3.1, Action 23, for the Vent Noble Gas Rad Monitor Inoperable for Greater than Seven Days LR-N23-0054, In-Service Inspection Activities2023-07-26026 July 2023 In-Service Inspection Activities LR-N23-0046, Emergency Plan Document Revisions Implemented June 28, 20232023-07-10010 July 2023 Emergency Plan Document Revisions Implemented June 28, 2023 LR-N23-0005, License Amendment Request to Amend Technical Specifications (TS) 6.8.4.f for Permanent Extension of Type a and Type C Leak Rate Test Frequencies2023-06-23023 June 2023 License Amendment Request to Amend Technical Specifications (TS) 6.8.4.f for Permanent Extension of Type a and Type C Leak Rate Test Frequencies LR-N23-0035, 2022 Annual Radioactive Effluent Release Report (ARERR)2023-04-27027 April 2023 2022 Annual Radioactive Effluent Release Report (ARERR) LR-N23-0034, 2022 Annual Radiological Environmental Operating Report (AREOR) - Salem Nuclear Generating Station, Unit Nos. 1 and 2 and Hope Creek Generating Station2023-04-27027 April 2023 2022 Annual Radiological Environmental Operating Report (AREOR) - Salem Nuclear Generating Station, Unit Nos. 1 and 2 and Hope Creek Generating Station LR-N23-0033, Core Operating Limits Report Cycle 272023-04-26026 April 2023 Core Operating Limits Report Cycle 27 LR-N23-0010, License Amendment Request Revision of Technical Specification (TS) to Delete TS Section 5.5 - Meteorological Tower Location2023-04-21021 April 2023 License Amendment Request Revision of Technical Specification (TS) to Delete TS Section 5.5 - Meteorological Tower Location LR-N23-0006, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-24024 March 2023 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations LR-N23-0019, and Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums2023-03-21021 March 2023 and Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums LR-N23-0016, and Salem Generating Station, Units 1 and 2 - Report of Changes, Tests, and Experiments2023-02-28028 February 2023 and Salem Generating Station, Units 1 and 2 - Report of Changes, Tests, and Experiments LR-N23-0012, Annual Property Insurance Status Report2023-02-24024 February 2023 Annual Property Insurance Status Report LR-N23-0014, Stations Submittal of 2022 Annual Report of Fitness for Duty Performance Data Per 10 CFR 26.203(e) and 10 CFR 26.7172023-02-23023 February 2023 Stations Submittal of 2022 Annual Report of Fitness for Duty Performance Data Per 10 CFR 26.203(e) and 10 CFR 26.717 LR-N23-0003, Response to Requests for Additional Information Salem Unit 2 Relief Request S2-I4R-2112023-02-0101 February 2023 Response to Requests for Additional Information Salem Unit 2 Relief Request S2-I4R-211 LR-N22-0096, and Salem Generating Station, Units 1 and 2 - Request for Threshold Determination2023-01-0505 January 2023 and Salem Generating Station, Units 1 and 2 - Request for Threshold Determination LR-N22-0095, Loss of Coolant Accident Peak Cladding Temperature Margin Tracking - Annual Report 20222022-12-20020 December 2022 Loss of Coolant Accident Peak Cladding Temperature Margin Tracking - Annual Report 2022 LR-N22-0094, Emergency Plan Document Revisions Implemented November 21, 20222022-12-14014 December 2022 Emergency Plan Document Revisions Implemented November 21, 2022 LR-N22-0092, Response to Final Iolb Request for Additional Information for Salem LAR to Revise TS to Extend Allowed Outage Time for Inoperable EDG2022-12-0909 December 2022 Response to Final Iolb Request for Additional Information for Salem LAR to Revise TS to Extend Allowed Outage Time for Inoperable EDG LR-N22-0091, Independent Spent Fuel Storage Installation, Report of 10 CFR 72.48 Changes, Tests, and Experiments2022-12-0202 December 2022 Independent Spent Fuel Storage Installation, Report of 10 CFR 72.48 Changes, Tests, and Experiments LR-N22-0084, Response to Final Request for Additional Information for Salem LAR to Revise TS to Extend Allowed Outage Time for Inoperable EDG (EPID L- 2022-LLA-0095)2022-11-17017 November 2022 Response to Final Request for Additional Information for Salem LAR to Revise TS to Extend Allowed Outage Time for Inoperable EDG (EPID L- 2022-LLA-0095) LR-N22-0090, Supplement to Submittal of Salem Generating Station Updated FSAR, Revision 33, 10 CFR 71.106 Review Results and 10 CFR 54.37(b) Review Results for Salem2022-11-10010 November 2022 Supplement to Submittal of Salem Generating Station Updated FSAR, Revision 33, 10 CFR 71.106 Review Results and 10 CFR 54.37(b) Review Results for Salem LR-N22-0065, Submittal of Relief Request Associated with the Fourth Inservice Inspection (ISI) Interval Limited Examinations2022-09-27027 September 2022 Submittal of Relief Request Associated with the Fourth Inservice Inspection (ISI) Interval Limited Examinations LR-N22-0074, Emergency Plan Evacuation Time Estimate2022-09-15015 September 2022 Emergency Plan Evacuation Time Estimate LR-N22-0066, License Amendment Request (LAR) to Relocate Technical Specifications (TS) Requirements for Reactor Head Vents to the Technical Requirements Manual (TRM)2022-08-31031 August 2022 License Amendment Request (LAR) to Relocate Technical Specifications (TS) Requirements for Reactor Head Vents to the Technical Requirements Manual (TRM) LR-N22-0063, Spent Fuel Cask Registration2022-08-10010 August 2022 Spent Fuel Cask Registration LR-N22-0068, In-Service Inspection Activities - 90-Day Report2022-08-10010 August 2022 In-Service Inspection Activities - 90-Day Report LR-N22-0012, License Amendment Request to Amend the Technical Specifications to Revise and Relocate the Reactor Coolant System Pressure and Temperature Limits and Pressurizer Overpressure Protection System Limits to a Pressure and Temperature2022-08-0707 August 2022 License Amendment Request to Amend the Technical Specifications to Revise and Relocate the Reactor Coolant System Pressure and Temperature Limits and Pressurizer Overpressure Protection System Limits to a Pressure and Temperature LR-N22-0062, Spent Fuel Cask Registration2022-07-21021 July 2022 Spent Fuel Cask Registration LR-N22-0006, License Amendment Request (LAR) to Amend Salem Unit 1 and Unit 2 Technical Specifications (TS) to Extend the Allowed Outage Time for an Inoperable Emergency Diesel Generator from 72 Hours to 14 Days2022-06-29029 June 2022 License Amendment Request (LAR) to Amend Salem Unit 1 and Unit 2 Technical Specifications (TS) to Extend the Allowed Outage Time for an Inoperable Emergency Diesel Generator from 72 Hours to 14 Days LR-N22-0051, License Amendment Request to Relocate Technical Specification Facility/Unit Staff Qualification Requirements to Quality Assurance Topical Report2022-06-22022 June 2022 License Amendment Request to Relocate Technical Specification Facility/Unit Staff Qualification Requirements to Quality Assurance Topical Report LR-N22-0044, Emergency Plan Document Revisions Implemented November, 20212022-05-19019 May 2022 Emergency Plan Document Revisions Implemented November, 2021 LR-N22-0043, Core Operating Limits Report - Cycle 292022-05-0909 May 2022 Core Operating Limits Report - Cycle 29 LR-N22-0041, 2021 Annual Radioactive Effluent Release Report (Rerr)2022-04-28028 April 2022 2021 Annual Radioactive Effluent Release Report (Rerr) LR-N22-0040, 2021 Annual Radiological Environmental Operating Report2022-04-28028 April 2022 2021 Annual Radiological Environmental Operating Report LR-N22-0039, Emergency Plan Document Revisions Implemented March 24, 20222022-04-21021 April 2022 Emergency Plan Document Revisions Implemented March 24, 2022 LR-N21-0052, Request for Relief from ASME Code Defect Removal for Service Water Buried Piping2022-04-0707 April 2022 Request for Relief from ASME Code Defect Removal for Service Water Buried Piping LR-N22-0023, Guarantees of Payment of Deferred Premiums2022-03-21021 March 2022 Guarantees of Payment of Deferred Premiums LR-N22-0022, Response to Request for Additional Information Relief Request S1-14R-210, Alternative Examination of Welds2022-03-21021 March 2022 Response to Request for Additional Information Relief Request S1-14R-210, Alternative Examination of Welds LR-N22-0017, Submittal of 2021 Annual Report of Fitness for Duty (FFD) Performance Data2022-02-25025 February 2022 Submittal of 2021 Annual Report of Fitness for Duty (FFD) Performance Data LR-N22-0016, Radiological Survey of Site Property to Be Used for Offshore Wind Port Facility2022-02-24024 February 2022 Radiological Survey of Site Property to Be Used for Offshore Wind Port Facility LR-N22-0013, In-Service Inspection Activities - 90-Day Report2022-02-10010 February 2022 In-Service Inspection Activities - 90-Day Report LR-N22-0007, Request for Exemption from Specific Requirements of 10 CFR Part 26, Fitness for Duty Programs2022-01-0505 January 2022 Request for Exemption from Specific Requirements of 10 CFR Part 26, Fitness for Duty Programs LR-N21-0061, Annual Report of Specific Activity Analysis - TS 6.9.1.5c2021-12-0909 December 2021 Annual Report of Specific Activity Analysis - TS 6.9.1.5c LR-N21-0083, Loss of Coolant Accident Peak Cladding Temperature Margin Tracking - Annual Report 2021 & 30 Day Report for Salem Unit 2 Upflow Conversion2021-11-24024 November 2021 Loss of Coolant Accident Peak Cladding Temperature Margin Tracking - Annual Report 2021 & 30 Day Report for Salem Unit 2 Upflow Conversion LR-N21-0078, Hope and Creek Generating Station, Supplement to License Amendment Request to Revise Technical Specifications (TS) to Delete Definitions Found in 10 CFR Part 20 and Delete Figures of the Site and Surrounding Areas from TS2021-11-18018 November 2021 Hope and Creek Generating Station, Supplement to License Amendment Request to Revise Technical Specifications (TS) to Delete Definitions Found in 10 CFR Part 20 and Delete Figures of the Site and Surrounding Areas from TS LR-N21-0066, Submittal of Relief Request Associated with the Fourth Inservice Inspection (ISI) Interval Limited Examinations2021-11-10010 November 2021 Submittal of Relief Request Associated with the Fourth Inservice Inspection (ISI) Interval Limited Examinations 2023-09-08 |
Text
PSEG Nuclear LLC PO. Box 236,, Hancocks Bridge, NJ 08038-0236 0 PSEG NuclearL.L. C.
10 CFR 50 10 CFR 51 10 CFR 54 LR-N09-0161 August 18, 2009 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Salem Nuclear Generating Station, Unit No. 1 and Unit No. 2 Facility Operating License Nos. DPR-70 and DPR-75 NRC Docket Nos. 50-272 and 50-311
Subject:
Application for Renewed Operating Licenses - Salem Nuclear Generating Station, Unit No. 1 and Unit No. 2 Pursuant to the Code of FederalRegulations,Title 10, Parts 50, 51, and 54, PSEG Nuclear LLC hereby applies for the renewal of Salem Nuclear Generating Station (Salem), Unit No. 1 and Unit No. 2 Facility Operating Licenses, Nos. DPR-70 and DPR-75, respectively. The current Salem Unit No. 1 operating license expires at midnight on August 13, 2016, and the Salem Unit No. 2 operating license expires at midnight on April 18, 2020. PSEG Nuclear LLC seeks to extend the operating terms by 20 years beyond the current expiration dates.
The enclosed License Renewal Application (LRA) contains the information required by the License Renewal regulations set forth in 10 CFR Part 54, and meets the submittal timeliness requirements of 10 CFR 54.17(c). In addition, it satisfies the Environmental Protection regulations set forth in 10 CFR Part 51.
As required by 10 CFR 54.21(b), current licensing basis changes which have a material effect on the content of this application will be identified annually while the application is under NRC review, and at least three months prior to the scheduled completion of the NRC review.
Appendix A, Section A.5, of the Salem LRA provides a list of commitments made in this application. This list will be updated as required throughout the LRA review process.
LR-N09-0161 August 18, 2009 Page 2 Please refer any questions regarding this submittal to Mr. Ali Fakhar, PSEG Manager - License Renewal, at 856-339-1646, or Mr. Al Fulvio, Manager, Exelon License Renewal, at 610-765-5936.
I declare under penalty of perjury that the foregoing is true and correct.
Respectfully, Executed on - / - o Gý'rli.J/F ric~ke r Vice President, Operations Support PSEG Nuclear LLC
Enclosure:
License Renewal Application (paper submittal) cc: S. Collins, Regional Administrator - USNRC Region I D. Ashley, Senior Project Manager, License Renewal - USNRC J. Robinson, Environmental Project Manager, License Renewal - USNRC R. Ennis, Project Manager - USNRC NRC Senior Resident Inspector - Salem P. Mulligan, Manager IV, NJBNE L. Marabella, Corporate Commitment Tracking Coordinator Howard Berrick, Salem Commitment Tracking Coordinator