License Amendment Request to Revise Point Beach Operating License to Allow Use of the EPRI Alternative Seismic Approach for 10 CFR 50.69 Risk-Informed Categorization Participants
License Amendment Request to Revise Point Beach Operating License to Allow Use of the EPRI Alternative Seismic Approach for 10 CFR 50.69 Risk-Informed Categorization Participants


Keith Vincent, Manager           -           Fleet             Reliability and Risk Manager, NextEra
Keith Vincent, Manager - Fleet Reliability and Risk Manager, NextEra


Eric Schultz, Manager -           Point Beach Regulatory Affairs
Eric Schultz, Manager - Point Beach Regulatory Affairs


Kim Locke, Principal Analyst -           Point Beach Regulatory Affairs
Kim Locke, Principal Analyst - Point Beach Regulatory Affairs


Jerry Phillabaum, Principal Engineer -           Fleet Licensing, NextEra
Jerry Phillabaum, Principal Engineer - Fleet Licensing, NextEra


Justin Wheat -           Consultant
Justin Wheat - Consultant


2 Agenda
2 Agenda
Line 42: Line 42:


Submit a LAR to revise the existing 10 CFR 50.69 License Condition:
Submit a LAR to revise the existing 10 CFR 50.69 License Condition:
* Allows use of the alternate seismic approach, as described in the LAR, for 50.69 categorization (underlined           blue text)
* Allows use of the alternate seismic approach, as described in the LAR, for 50.69 categorization (underlined blue text)


4 Scope
4 Scope
Line 51: Line 51:
5 PRA Technical Adequacy
5 PRA Technical Adequacy
* Point Beach Nuclear Plant (PBNP) internal events, including internal flooding, and fire PRA models were assessed as part of the original 10 CFR 50.69 LAR:
* Point Beach Nuclear Plant (PBNP) internal events, including internal flooding, and fire PRA models were assessed as part of the original 10 CFR 50.69 LAR:
o                           10 CFR 50.69 LAR -           ML17243A201 (August 2017) o                           NRC Amendments 262 & 265           -           ML18289A378 (November 2018)
o 10 CFR 50.69 LAR - ML17243A201 (August 2017) o NRC Amendments 262 & 265 - ML18289A378 (November 2018)
* PRA models were also assessed as part of requesting approval for the risk-informed completion time (RICT) program:
* PRA models were also assessed as part of requesting approval for the risk-informed completion time (RICT) program:
o                         RICT LAR -           ML22140A131 (May 2022) o                           Enclosure 2 of the LAR provided peer review history -           M L22140A142 o                           NRC Amendments 271 & 273 -           ML23103A133 (June 2023)
o RICT LAR - ML22140A131 (May 2022) o Enclosure 2 of the LAR provided peer review history - M L22140A142 o NRC Amendments 271 & 273 - ML23103A133 (June 2023)


6 Alternative Seismic Approach during Categorization
6 Alternative Seismic Approach during Categorization
Line 63: Line 63:
7 Point Beach is a Tier 2 Site
7 Point Beach is a Tier 2 Site
* The GMRS exceeds the SSE in a portion of the response spectrum between 1.0 Hz and 10 Hz.
* The GMRS exceeds the SSE in a portion of the response spectrum between 1.0 Hz and 10 Hz.
* PBNP did not develop an SPRA in response to the NRCs review of insights from the Fukushima Dai-ichi             accident.
* PBNP did not develop an SPRA in response to the NRCs review of insights from the Fukushima Dai-ichi accident.
* PBNP meets Tier 2 criteria per EPRI 3002017583
* PBNP meets Tier 2 criteria per EPRI 3002017583


Line 69: Line 69:
* Plan is to submit LAR on the docket in September 2024
* Plan is to submit LAR on the docket in September 2024
* Approval requested within one year after acceptance
* Approval requested within one year after acceptance
* Plan to implement the amendment within 60             days
* Plan to implement the amendment within 60 days


9 Summary and Closing Remarks
9 Summary and Closing Remarks
Line 77: Line 77:
* PBNP is considered a Tier 2 site per EPRI 3002017583.
* PBNP is considered a Tier 2 site per EPRI 3002017583.


    *LAR i                                             mplements learnings from other submittals (e.g., St. Lucie RAIs).
*LAR i mplements learnings from other submittals (e.g., St. Lucie RAIs).


10 Questions?}}
10 Questions?}}

Revision as of 07:28, 4 October 2024

NextEra - Pre-Application 10 CFR 50.69 8/28/2024 Meeting Slides
ML24227A569
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 08/31/2024
From:
Point Beach
To: Justin Poole
Plant Licensing Branch III
Wall, S P
References
EPID L-2024-LLM-0091
Download: ML24227A569 (1)


Text

August 2024

License Amendment Request to Revise Point Beach Operating License to Allow Use of the EPRI Alternative Seismic Approach for 10 CFR 50.69 Risk-Informed Categorization Participants

Keith Vincent, Manager - Fleet Reliability and Risk Manager, NextEra

Eric Schultz, Manager - Point Beach Regulatory Affairs

Kim Locke, Principal Analyst - Point Beach Regulatory Affairs

Jerry Phillabaum, Principal Engineer - Fleet Licensing, NextEra

Justin Wheat - Consultant

2 Agenda

  • Scope of Request
  • PRA Model Technical Adequacy
  • Seismic Approach & Precedent
  • Current Schedule
  • Summary & Closing Remarks

3 Scope

Submit a LAR to revise the existing 10 CFR 50.69 License Condition:

  • Allows use of the alternate seismic approach, as described in the LAR, for 50.69 categorization (underlined blue text)

4 Scope

Submit a LAR to revise the existing 10 CFR 50.69 License Condition:

  • Removes requirements to complete implementation items; all provisions have been met (stricken through red text)

5 PRA Technical Adequacy

o 10 CFR 50.69 LAR - ML17243A201 (August 2017) o NRC Amendments 262 & 265 - ML18289A378 (November 2018)

  • PRA models were also assessed as part of requesting approval for the risk-informed completion time (RICT) program:

o RICT LAR - ML22140A131 (May 2022) o Enclosure 2 of the LAR provided peer review history - M L22140A142 o NRC Amendments 271 & 273 - ML23103A133 (June 2023)

6 Alternative Seismic Approach during Categorization

  • PBNP will follow the same approach as that which was approved for LaSalle (except for site-specific information).
  • Brunswick LAR used as a model to revise the 50.69 license condition to add the alternate seismic approach while retaining SMA approach (ML23229A456 / ML24108A070).

7 Point Beach is a Tier 2 Site

  • The GMRS exceeds the SSE in a portion of the response spectrum between 1.0 Hz and 10 Hz.

88 Current Schedule

  • Plan is to submit LAR on the docket in September 2024
  • Approval requested within one year after acceptance
  • Plan to implement the amendment within 60 days

9 Summary and Closing Remarks

  • PRA models are technically adequate and have been reviewed by the NRC in previous applications.
  • LAR requests approval to adopt an alternative seismic approach during 10 CFR 50.69 risk-informed categorization, in addition to the currently licensed SMA approach.
  • LAR is consistent with precedent (Brunswick LAR, LaSalle process).
  • LAR i mplements learnings from other submittals (e.g., St. Lucie RAIs).

10 Questions?