S/G Nozzle Dam Removal Pre-job Brief Agenda
- 1. Introduction -Sr Manager (Jim Schweitzer)
- a. Scope of Job
- b. Lessons Learned/OE
- 2. Radiological Conditions/ Precautions - RP (Carberry/ReifffPeroutka)
- 3. Work Order/ Procedure Summary - Contract Liaison (Kiesper)
- 4. Energy Sources/ Danger Tagging Contract Liaison (Klesper)
- 5. Communications Protocol (Hennessy)
- 6. Safety/Hazards/Permits (Hennessy/Sipiorski)
- 7. Identify Critical Steps/ Error Likely Situations/Defense Barriers (Hennessy)
- 8. Other (Hennessy)
NOTE: If anyone during in the brief makes the statement: "I think" or "I believe,"
challenge their assumptions before their inaccurate mental model creates a problem on the job. Use Qualification, Validation, and Verification (QV&V) to eliminate assumptions.
Note: Verify correct revision of attached PBF 1148, Infrequently Performed Tests or Evolutions Job Brief Checklist and PBF 9205, High Risk Work Pre-Job Briefing Checklist prior to beginning brief.