UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 May 5, 2010 LICENSEE: FPL Energy Point Beach, LLC.

FACILITY: Point Beach Nuclear Plant, Units 1 and 2

SUBJECT:

SUMMARY

OF THE APRIL 22, 2010, PUBLIC MEETING TO DISCUSS THE 2009 POINT BEACH END-OF-CYCLE PERFORMANCE ASSESSMENT On April 22, 2010, the U.S. Nuclear Regulatory Commission (NRC) held a public meeting at the Two Creeks Town Hall in Two Creeks, Wisconsin. The meeting was between NRC representatives and FPL Energy Point Beach, LLC, representatives to discuss the NRCs 2009 End-of-Cycle Assessment of the Point Beach Nuclear Plants safety performance.

The results of that assessment were discussed in a letter to the licensee dated March 3, 2010, (ADAMS ML100610484).

The NRC began the meeting with an overview of the NRC, the NRCs Reactor Oversight Process (ROP), National ROP results, and the Action Matrix. This was followed by a summary of the NRCs assessment of Point Beach performance in 2009. The NRCs meeting presentation slides can be found in ADAMS at ML101130497, and the licensees slides are at ML101130445. A list of principal meeting attendees can be found in the attached Enclosure.

Mr. Larry Meyer--the Point Beach site vice-president--and members of his staff provided the licensees perspective on the assessment and discussed some of the completed and ongoing efforts at the plant to improve and enhance performance.

After the business portion of the meeting, NRC representatives spoke with a representative of the State of Wisconsin emergency management organization on general issues of interaction between the NRC and the State.

/RA/

Michael A. Kunowski, Chief Branch 5 Division of Reactor Projects Docket Nos. 50-266; 50-301 License Nos. DPR-24; DPR-27 cc w/encl: Distribution via ListServe

PUBLIC MEETING PRINCIPAL ATTENDEES April 22, 2010 Point Beach L. Meyer, Site Vice-President T. Vehec, Plant Manager C. Trezise, Engineering Director J. Costedio, Licensing and Regulatory Affairs Manager Nuclear Regulatory Commission M. Kunowski, Branch Chief, Division of Reactor Projects J. Poole, Project Manager, Office of Nuclear Reactor Regulation S. Burton, Senior Resident Inspector M. Thorpe-Kavanaugh, Acting Resident Inspector R. Ruiz, Resident Inspector P. Cardona-Morales, Reactor Engineer A. Becker, Resident Inspector Office Assistant, Point Beach and Kewaunee P. Chandrathil, Public Affairs Officer Other Attendees B. Busch, Wisconsin Emergency Management Enclosure

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 May 5, 2010 LICENSEE: FPL Energy Point Beach, LLC.

FACILITY: Point Beach Nuclear Plant, Units 1 and 2

SUBJECT:

SUMMARY

OF THE APRIL 22, 2010, PUBLIC MEETING TO DISCUSS THE 2009 POINT BEACH END-OF-CYCLE PERFORMANCE ASSESSMENT On April 22, 2010, the U.S. Nuclear Regulatory Commission (NRC) held a public meeting at the Two Creeks Town Hall in Two Creeks, Wisconsin. The meeting was between NRC representatives and FPL Energy Point Beach, LLC, representatives to discuss the NRCs 2009 End-of-Cycle Assessment of the Point Beach Nuclear Plants safety performance.

The results of that assessment were discussed in a letter to the licensee dated March 3, 2010, (ADAMS ML100610484).

The NRC began the meeting with an overview of the NRC, the NRCs Reactor Oversight Process (ROP), National ROP results, and the Action Matrix. This was followed by a summary of the NRCs assessment of Point Beach performance in 2009. The NRCs meeting presentation slides can be found in ADAMS at ML101130497, and the licensees slides are at ML101130445. A list of principal meeting attendees can be found in the attached Enclosure.

Mr. Larry Meyer--the Point Beach site vice-president--and members of his staff provided the licensees perspective on the assessment and discussed some of the completed and ongoing efforts at the plant to improve and enhance performance.

After the business portion of the meeting, NRC representatives spoke with a representative of the State of Wisconsin emergency management organization on general issues of interaction between the NRC and the State.

/RA/

Michael A. Kunowski, Chief Branch 5 Division of Reactor Projects Docket Nos. 50-266; 50-301 License Nos. DPR-24; DPR-27 cc w/encl: Distribution via ListServe DOCUMENT NAME: G:\1-SECY\1-WORK IN PROGRESS\PTBH MTG

SUMMARY

.DOC G Publicly Available G Non-Publicly Available G Sensitive G Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII RIII RIII NAME MKunowski:cs DATE 05/05/10 OFFICIAL RECORD COPY

Letter to L. Meyer from M. Kunowski dated May 5, 2010

SUBJECT:

SUMMARY

OF THE APRIL 22, 2010, PUBLIC MEETING TO DISCUSS THE 2009 POINT BEACH END-OF-CYCLE PERFORMANCE ASSESSMENT DISTRIBUTION:

Susan Bagley RidsNrrDorlLpl3-1 Resource RidsNrrPMPointBeach RidsNrrDirsIrib Resource Cynthia Pederson Steven Orth Jared Heck Allan Barker Carole Ariano Linda Linn DRPIII DRSIII Patricia Buckley Tammy Tomczak ROPreports Resource