ML21340A221: Difference between revisions
StriderTol (talk | contribs) (StriderTol Bot change) |
StriderTol (talk | contribs) (StriderTol Bot change) |
||
Line 18: | Line 18: | ||
=Text= | =Text= | ||
{{#Wiki_filter: | {{#Wiki_filter:EA-21-155 | ||
EA-21-155 | |||
Mr. Terry Brown | Mr. Terry Brown | ||
Site Vice President | Site Vice President | ||
Line 25: | Line 24: | ||
Davis-Besse Nuclear Power Station | Davis-Besse Nuclear Power Station | ||
5501 N. State Rte. 2, Mail Stop A-DB-3080 | 5501 N. State Rte. 2, Mail Stop A-DB-3080 | ||
Oak Harbor, OH 43449-9760 | Oak Harbor, OH 43449-9760 | ||
SUBJECT: | SUBJECT: DAVIS-BESSE - NRC INSPECTION REPORT (05000346/2021090); | ||
PRELIMINARY WHITE FINDING | |||
Dear Mr. Brown: | Dear Mr. Brown: | ||
This letter transmits the NRCs preliminary detailed risk evaluation of the safety significance of | This letter transmits the NRCs preliminary detailed risk evaluation of the safety significance of | ||
an inspection finding described in NRC inspection report 05000246/2021050. The finding has | an inspection finding described in NRC inspection report 05000246/2021050. The finding has | ||
preliminarily been determined to be of low to moderate increased safety significance | preliminarily been determined to be of low to moderate increased safety significance | ||
(i.e., White) that may require additional NRC inspections. As described in the previous | (i.e., White) that may require additional NRC inspections. As described in the previous | ||
inspection report, the finding involved the failure to select a suitable replacement part for the | inspection report, the finding involved the failure to select a suitable replacement part for the | ||
emergency diesel generator (EDG) speed switch. The speed switch design was not compatible | emergency diesel generator (EDG) speed switch. The speed switch design was not compatible | ||
with the stations 125/250 Volts direct current (Vdc) battery system. The switch design | with the stations 125/250 Volts direct current (Vdc) battery system. The switch design | ||
contained a subcomponent that was rated for 170 Vdc but was exposed to a voltage potential of | contained a subcomponent that was rated for 170 Vdc but was exposed to a voltage potential of | ||
201 Vdc. The long-term exposure to this voltage potential caused the switch subcomponent to | 201 Vdc. The long-term exposure to this voltage potential caused the switch subcomponent to | ||
fail and, combined with another unrelated ground on the 125/250 Vdc system, resulted in failure | fail and, combined with another unrelated ground on the 125/250 Vdc system, resulted in failure | ||
of the switch. The failure of the switch resulted in the failure of the EDG to start during testing | of the switch. The failure of the switch resulted in the failure of the EDG to start during testing | ||
on September 4, 2020. This finding was assessed based on the best available information, | on September 4, 2020. This finding was assessed based on the best available information, | ||
using the applicable Significance Determination Process (SDP). The final resolution of this | using the applicable Significance Determination Process (SDP). The final resolution of this | ||
finding will be conveyed in separate correspondence. | finding will be conveyed in separate correspondence. | ||
The basis for the staffs significance determination is provided in the enclosure. This finding | The basis for the staffs significance determination is provided in the enclosure. This finding | ||
does not represent a current safety concern because the speed switches on both EDGs have | does not represent a current safety concern because the speed switches on both EDGs have | ||
been replaced and interim measures have been put in place until a new design is procured. | been replaced and interim measures have been put in place until a new design is procured. | ||
However, the finding is also an apparent violation of NRC requirements and is being considered | However, the finding is also an apparent violation of NRC requirements and is being considered | ||
for escalated enforcement action in accordance with the Enforcement Policy, which can be | for escalated enforcement action in accordance with the Enforcement Policy, which can be | ||
found on the NRCs Web site at http://www.nrc.gov/about-nrc/regulatory/enforcement/enforce- | found on the NRCs Web site at http://www.nrc.gov/about-nrc/regulatory/enforcement/enforce- | ||
pol.html. | pol.html. | ||
In accordance with NRC Inspection Manual Chapter 0609, we intend to complete our evaluation | In accordance with NRC Inspection Manual Chapter 0609, we intend to complete our evaluation | ||
using the best available information and issue our final determination of safety significance | using the best available information and issue our final determination of safety significance | ||
within 90 days of November 19, 2021, the date of the issuance of the special inspection report | within 90 days of November 19, 2021, the date of the issuance of the special inspection report | ||
that initially documented the finding. The SDP encourages an open dialogue between the NRC | that initially documented the finding. The SDP encourages an open dialogue between the NRC | ||
staff and the licensee; however, the dialogue should not impact the timeliness of the staffs final | staff and the licensee; however, the dialogue should not impact the timeliness of the staffs final | ||
determination. | determination.December 9, 2021 | ||
T.Brown 2 | |||
Before we make a final decision on this matter, we are providing you with an opportunity to | Before we make a final decision on this matter, we are providing you with an opportunity to | ||
(1) attend a Regulatory Conference where you can present to the NRC your perspective on the | (1) attend a Regulatory Conference where you can present to the NRC your perspective on the | ||
facts and assumptions the NRC used to arrive at the finding and assess its significance, | facts and assumptions the NRC used to arrive at the finding and assess its significance, | ||
(2) submit your position on the finding to the NRC in writing, or (3) accept the finding as | (2) submit your position on the finding to the NRC in writing, or (3) accept the finding as | ||
documented in the enclosure. If you request a Regulatory Conference, it should be held within | documented in the enclosure. If you request a Regulatory Conference, it should be held within | ||
40 days of the receipt of this letter, and we encourage you to submit supporting documentation | 40 days of the receipt of this letter, and we encourage you to submit supporting documentation | ||
at least one week prior to the conference in an effort to make the conference more efficient and | at least one week prior to the conference in an effort to make the conference more efficient and | ||
effective. The focus of the Regulatory Conference is to discuss the significance of the finding | effective. The focus of the Regulatory Conference is to discuss the significance of the finding | ||
and not necessarily the root cause(s) or corrective action(s) associated with the finding. If a | and not necessarily the root cause(s) or corrective action(s) associated with the finding. If a | ||
Regulatory Conference is held, it will be open for public observation. If you decide to submit | Regulatory Conference is held, it will be open for public observation. If you decide to submit | ||
only a written response, such submittal should be sent to the NRC within 40 days of your receipt | only a written response, such submittal should be sent to the NRC within 40 days of your receipt | ||
of this letter. If you decline to request a Regulatory Conference or to submit a written response, | of this letter. If you decline to request a Regulatory Conference or to submit a written response, | ||
you relinquish your right to appeal the final SDP determination, in that by not doing either, you | you relinquish your right to appeal the final SDP determination, in that by not doing either, you | ||
fail to meet the appeal requirements stated in the Prerequisite and Limitation sections of | fail to meet the appeal requirements stated in the Prerequisite and Limitation sections of | ||
Attachment 2 of NRC Inspection Manual Chapter 0609. | Attachment 2 of NRC Inspection Manual Chapter 0609. | ||
If you choose to send a response, it should be clearly marked as a "Response to An Apparent | If you choose to send a response, it should be clearly marked as a "Response to An Apparent | ||
Violation; (EA-21-155)" and should include for the apparent violation: (1) the reason for the | Violation; (EA-21-155)" and should include for the apparent violation: (1) the reason for the | ||
apparent violation or, if contested, the basis for disputing the apparent violation; (2) the | apparent violation or, if contested, the basis for disputing the apparent violation; (2) the | ||
corrective steps that have been taken and the results achieved; (3) the corrective steps that will | corrective steps that have been taken and the results achieved; (3) the corrective steps that will | ||
be taken; and (4) the date when full compliance will be achieved. Your response should be | be taken; and (4) the date when full compliance will be achieved. Your response should be | ||
submitted under oath or affirmation and may reference or include previously docketed | submitted under oath or affirmation and may reference or include previously docketed | ||
correspondence, if the correspondence adequately addresses the required response. | correspondence, if the correspondence adequately addresses the required response. | ||
Line 83: | Line 84: | ||
ATTN: Document Control Center, Washington, DC 20555-0001 with a copy to Laura Kozak, | ATTN: Document Control Center, Washington, DC 20555-0001 with a copy to Laura Kozak, | ||
acting Branch Chief, U.S. Nuclear Regulatory Commission, Region III, 2443 Warrenville Road, | acting Branch Chief, U.S. Nuclear Regulatory Commission, Region III, 2443 Warrenville Road, | ||
Suite 210, Lisle, IL 60532, within 40 days of the date of this letter. If an adequate response is | Suite 210, Lisle, IL 60532, within 40 days of the date of this letter. If an adequate response is | ||
not received within the time specified or an extension of time has not been granted by the NRC, | not received within the time specified or an extension of time has not been granted by the NRC, | ||
the NRC will proceed with its enforcement decision or schedule a Regulatory Conference. | the NRC will proceed with its enforcement decision or schedule a Regulatory Conference. | ||
Please contact Laura Kozak at 630-829-9604 and in writing within 10 days from the issue date | Please contact Laura Kozak at 630-829-9604 and in writing within 10 days from the issue date | ||
of this letter to notify the NRC of your intentions. If we have not heard from you within 10 days, | of this letter to notify the NRC of your intentions. If we have not heard from you within 10 days, | ||
we will continue with our significance determination and enforcement decision. The final | we will continue with our significance determination and enforcement decision. The final | ||
resolution of this matter will be conveyed in separate correspondence. | resolution of this matter will be conveyed in separate correspondence. | ||
Because the NRC has not made a final determination in this matter, no Notice of Violation is | Because the NRC has not made a final determination in this matter, no Notice of Violation is | ||
being issued for these inspection findings at this time. In addition, please be advised that the | being issued for these inspection findings at this time. In addition, please be advised that the | ||
characterization of the apparent violation described in the enclosed inspection report may | characterization of the apparent violation described in the enclosed inspection report may | ||
change as a result of further NRC review. | change as a result of further NRC review. | ||
T. Brown 3 | |||
T. Brown | In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its | ||
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its | enclosure will be made available electronically for public inspection in the NRC Public | ||
enclosure will be made available electronically for public inspection in the NRC Public | Document Room and in the NRCs Agencywide Documents Access and Management System | ||
Document Room and in the NRCs Agencywide Documents Access and Management System | |||
(ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html. | (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html. | ||
Sincerely, | |||
Michelle Hayes, Acting Deputy Director | |||
Division of Reactor Safety | |||
Docket No. 05000346 | |||
License No. NPF-3 | |||
Docket No. 05000346 | |||
License No. NPF-3 | |||
Enclosure: | Enclosure: | ||
As stated | As stated | ||
cc: Distribution via LISTSERV | cc: Distribution via LISTSERV | ||
Signed by Hayes, Michelle | |||
on 12/09/21 | |||
T. Brown 4 | |||
Letter to Terry Brown from Michelle Hayes dated December 9, 2021. | Letter to Terry Brown from Michelle Hayes dated December 9, 2021. | ||
SUBJECT: | |||
SUBJECT: DAVIS-BESSE - NRC INSPECTION REPORT (05000346/2021090); | |||
PRELIMINARY WHITE FINDING | |||
DISTRIBUTION: | DISTRIBUTION: | ||
Jessie Quichocho | Jessie Quichocho | ||
Line 129: | Line 134: | ||
DRSIII | DRSIII | ||
ROPassessment.Resource@nrc.gov | ROPassessment.Resource@nrc.gov | ||
Summary of the Detailed Risk Evaluation for the Davis-Besse Speed Switch Finding and | |||
ADAMS Accession Number: ML21340A221 | |||
Publicly Available Non-Publicly Available Sensitive Non-Sensitive | |||
OFFICE RIII RIII RIII RIII | |||
NAME JHanna:mb LKozak JCameron MHayes | |||
DATE 12/08/2021 12/08/2021 12/09/2021 12/09/2021 | |||
OFFICIAL RECORD COPY | |||
Summary of the Detailed Risk Evaluation for the Davis-Besse Speed Switch Finding and | |||
Basis for Preliminary Significance Determination | |||
Exposure Time - From late August 28 or early August 29, 2020, until September 7, 2020, | Exposure Time - From late August 28 or early August 29, 2020, until September 7, 2020, | ||
Emergency Diesel Generator-2 (EDG) was unavailable; a time window of 9 days. This was | Emergency Diesel Generator-2 (EDG) was unavailable; a time window of 9 days. This was | ||
when the engine was reasonably known to be in a failed condition. A factor of | when the engine was reasonably known to be in a failed condition. A factor of | ||
9 days/365 days/year, or 0.0246 was applied to the annualized results. | 9 days/365 days/year, or 0.0246 was applied to the annualized results. | ||
Failure Mechanism - The failure of EDG-2, during a hypothetical demand, would be in the first | Failure Mechanism - The failure of EDG-2, during a hypothetical demand, would be in the first | ||
few seconds of an attempted start of the engine. Consequently, the basic event in the | few seconds of an attempted start of the engine. Consequently, the basic event in the | ||
Davis-Besse Standardized Plant Analysis Risk (SPAR) model basic event Diesel Generator 1-2 | Davis-Besse Standardized Plant Analysis Risk (SPAR) model basic event Diesel Generator 1-2 | ||
Fails to Start was set to True. All other basic events were left at their nominal failure | Fails to Start was set to True. All other basic events were left at their nominal failure | ||
probabilities, except for the Mitigating Strategies equipment, which is discussed below. | probabilities, except for the Mitigating Strategies equipment, which is discussed below. | ||
Common Cause Implications - The two safety-related EDGs at Davis-Besse are similar in all | Common Cause Implications - The two safety-related EDGs at Davis-Besse are similar in all | ||
respects, and the performance deficiency affected both engines. The potential for common | respects, and the performance deficiency affected both engines. The potential for common | ||
cause failure was used in the NRCs evaluation. However, it is important to note that the | cause failure was used in the NRCs evaluation. However, it is important to note that the | ||
Davis-Besse Station Blackout EDG was sufficiently different in design, vintage, and other | Davis-Besse Station Blackout EDG was sufficiently different in design, vintage, and other | ||
material properties such that it was not part of the Common Cause Component Group with the | material properties such that it was not part of the Common Cause Component Group with the | ||
two safety-related engines in the SPAR model. | two safety-related engines in the SPAR model. | ||
Mitigating Strategies - The Mitigating Strategies equipment and response procedures | Mitigating Strategies - The Mitigating Strategies equipment and response procedures | ||
(commonly and collectively known as FLEX) were credited in this analysis. Given that the | (commonly and collectively known as FLEX) were credited in this analysis. Given that the | ||
performance deficiency affected the safety-related EDGs, and the accident sequences of | performance deficiency affected the safety-related EDGs, and the accident sequences of | ||
concern were station blackout sequences that become extended losses of AC power scenarios, | concern were station blackout sequences that become extended losses of AC power scenarios, | ||
FLEX was included in the internal and external events analysis. However, the analyst adjusted | FLEX was included in the internal and external events analysis. However, the analyst adjusted | ||
the failure probabilities in the SPAR model for the FLEX basic events using a 3x multiplier to | the failure probabilities in the SPAR model for the FLEX basic events using a 3x multiplier to | ||
more accurately reflect the higher unreliability of portable equipment. The analyst also | more accurately reflect the higher unreliability of portable equipment. The analyst also | ||
compared the FLEX unavailability/unreliability values used in the licensee Probabilistic risk | compared the FLEX unavailability/unreliability values used in the licensee Probabilistic risk | ||
assessment (PRA) model with the NRC SPAR model (using the 3x multiplier). No significant | assessment (PRA) model with the NRC SPAR model (using the 3x multiplier). No significant | ||
differences were identified. | differences were identified. | ||
Repair/Recovery of Failed Components - The diagnosis and replacement of the failed speed | Repair/Recovery of Failed Components - The diagnosis and replacement of the failed speed | ||
switch following the surveillance testing failure was three days in duration. The analyst | switch following the surveillance testing failure was three days in duration. The analyst | ||
concluded that the recovery of the failed speed switch during a postulated event, i.e., during a | concluded that the recovery of the failed speed switch during a postulated event, i.e., during a | ||
loss of offsite power that progresses to a station blackout for the non-conforming case was not | loss of offsite power that progresses to a station blackout for the non-conforming case was not | ||
credible. | credible. | ||
Internal Events Risk - The dominant internal event accident sequence is a weather-related | Internal Events Risk - The dominant internal event accident sequence is a weather-related | ||
loss of offsite power sequence and contributes 46% of the total internal events risk. However, | loss of offsite power sequence and contributes 46% of the total internal events risk. However, | ||
the overall results were dominated by fire and internal events only represented 12% of the total. | the overall results were dominated by fire and internal events only represented 12% of the total. | ||
External Events Risk - | External Events Risk - | ||
Fire - Fire was the dominant contributor to the overall change in core damage frequency | |||
(CDF) result and was included quantitatively using the licensees all hazard model. The | |||
dominant fire sequence are large damaging fires, or high energy arc faults, which cause | |||
a loss of offsite power (LOOP) with a subsequent loss of decay heat removal via the | |||
once-through steam generators with subsequent failure of makeup/high pressure | |||
injection (HPI) cooling. These scenarios contribute 54% of the fire risk. FLEX | |||
Enclosure | |||
equipment/strategies were credited in both the base and non-conforming cases. The | |||
analyst sampled the top 20 dominant cutsets and verified that bounding and/or | |||
unrealistic assumptions were not being used, however, further reviews or discussions | |||
with Energy Harbor staff may be needed to either confirm or refute this assumption. | |||
Tornados/High Winds and External Flooding - External flooding or tornados leading to a | |||
LOOP, though credible, was determined to be several orders of magnitude less frequent | |||
than the LOOP values used in the internal events model. No further analysis was | |||
performed. | |||
Seismic - Seismic-induced events were quantified using the licensees all hazard model, | |||
though they were not a significant contributor to the overall result. | |||
Uncertainty - With all risk evaluations, there are both aleatory (randomness) and epistemic | Uncertainty - With all risk evaluations, there are both aleatory (randomness) and epistemic | ||
(lack of knowledge) uncertainties. The aleatory uncertainty was assessed using the | (lack of knowledge) uncertainties. The aleatory uncertainty was assessed using the | ||
Davis-Besse SPAR model. The 5% and 95% values for the consolidated results (both internal | Davis-Besse SPAR model. The 5% and 95% values for the consolidated results (both internal | ||
and external events) were 9E-7/year to 4E-6/year. The remaining epistemic uncertainties with | and external events) were 9E-7/year to 4E-6/year. The remaining epistemic uncertainties with | ||
the results were centered on the fire results generated from the licensees model. Specifically, it | the results were centered on the fire results generated from the licensees model. Specifically, it | ||
was unknown at the time of completion of the risk analysis whether substantial conservatism | was unknown at the time of completion of the risk analysis whether substantial conservatism | ||
were present in the fire model, though some efforts had been taken to address this question as | were present in the fire model, though some efforts had been taken to address this question as | ||
described above. | described above. | ||
Item of Merit - The risk contribution for the two most commonly used items of merit, delta-CDF | Item of Merit - The risk contribution for the two most commonly used items of merit, delta-CDF | ||
and delta large early release frequency (LERF), were quantified in the analysis. Delta-CDF | and delta large early release frequency (LERF), were quantified in the analysis. Delta-CDF | ||
remained the item of merit. | remained the item of merit. | ||
Consolidated Results - | Consolidated Results - | ||
Base Non-Conforming Delta Risk | |||
Case Case (change in CDF) | |||
Internal Events (NRC Results) 1.3E-7 3.6E-7 2.2E-7 | |||
Seismic (Licensee Results) 3.1E-7 3.4E-7 3.2E-8 | |||
Fire (Licensee Results) 1.3E-6 2.9E-6 1.6E-6 | |||
Total = 1.7E-6 3.6E-6 1.9E-6 | |||
The quantitative and qualitative inputs described above support the treatment of this finding as | The quantitative and qualitative inputs described above support the treatment of this finding as | ||
low to moderate safety significance (i.e., White). | low to moderate safety significance (i.e., White). | ||
2 | |||
}} | }} |
Latest revision as of 03:43, 19 November 2024
ML21340A221 | |
Person / Time | |
---|---|
Site: | Davis Besse |
Issue date: | 12/09/2021 |
From: | Hayes M Division of Reactor Safety III |
To: | Tony Brown Energy Harbor Nuclear Corp |
References | |
EA-21-155 IR 2021090 | |
Download: ML21340A221 (6) | |
See also: IR 05000346/2021090
Text
Mr. Terry Brown
Site Vice President
Energy Harbor Nuclear Corp.
Davis-Besse Nuclear Power Station
5501 N. State Rte. 2, Mail Stop A-DB-3080
Oak Harbor, OH 43449-9760
SUBJECT: DAVIS-BESSE - NRC INSPECTION REPORT (05000346/2021090);
Dear Mr. Brown:
This letter transmits the NRCs preliminary detailed risk evaluation of the safety significance of
an inspection finding described in NRC inspection report 05000246/2021050. The finding has
preliminarily been determined to be of low to moderate increased safety significance
(i.e., White) that may require additional NRC inspections. As described in the previous
inspection report, the finding involved the failure to select a suitable replacement part for the
emergency diesel generator (EDG) speed switch. The speed switch design was not compatible
with the stations 125/250 Volts direct current (Vdc) battery system. The switch design
contained a subcomponent that was rated for 170 Vdc but was exposed to a voltage potential of
201 Vdc. The long-term exposure to this voltage potential caused the switch subcomponent to
fail and, combined with another unrelated ground on the 125/250 Vdc system, resulted in failure
of the switch. The failure of the switch resulted in the failure of the EDG to start during testing
on September 4, 2020. This finding was assessed based on the best available information,
using the applicable Significance Determination Process (SDP). The final resolution of this
finding will be conveyed in separate correspondence.
The basis for the staffs significance determination is provided in the enclosure. This finding
does not represent a current safety concern because the speed switches on both EDGs have
been replaced and interim measures have been put in place until a new design is procured.
However, the finding is also an apparent violation of NRC requirements and is being considered
for escalated enforcement action in accordance with the Enforcement Policy, which can be
found on the NRCs Web site at http://www.nrc.gov/about-nrc/regulatory/enforcement/enforce-
pol.html.
In accordance with NRC Inspection Manual Chapter 0609, we intend to complete our evaluation
using the best available information and issue our final determination of safety significance
within 90 days of November 19, 2021, the date of the issuance of the special inspection report
that initially documented the finding. The SDP encourages an open dialogue between the NRC
staff and the licensee; however, the dialogue should not impact the timeliness of the staffs final
determination.December 9, 2021
T.Brown 2
Before we make a final decision on this matter, we are providing you with an opportunity to
(1) attend a Regulatory Conference where you can present to the NRC your perspective on the
facts and assumptions the NRC used to arrive at the finding and assess its significance,
(2) submit your position on the finding to the NRC in writing, or (3) accept the finding as
documented in the enclosure. If you request a Regulatory Conference, it should be held within
40 days of the receipt of this letter, and we encourage you to submit supporting documentation
at least one week prior to the conference in an effort to make the conference more efficient and
effective. The focus of the Regulatory Conference is to discuss the significance of the finding
and not necessarily the root cause(s) or corrective action(s) associated with the finding. If a
Regulatory Conference is held, it will be open for public observation. If you decide to submit
only a written response, such submittal should be sent to the NRC within 40 days of your receipt
of this letter. If you decline to request a Regulatory Conference or to submit a written response,
you relinquish your right to appeal the final SDP determination, in that by not doing either, you
fail to meet the appeal requirements stated in the Prerequisite and Limitation sections of
Attachment 2 of NRC Inspection Manual Chapter 0609.
If you choose to send a response, it should be clearly marked as a "Response to An Apparent
Violation; (EA-21-155)" and should include for the apparent violation: (1) the reason for the
apparent violation or, if contested, the basis for disputing the apparent violation; (2) the
corrective steps that have been taken and the results achieved; (3) the corrective steps that will
be taken; and (4) the date when full compliance will be achieved. Your response should be
submitted under oath or affirmation and may reference or include previously docketed
correspondence, if the correspondence adequately addresses the required response.
Additionally, your response should be sent to the U.S. Nuclear Regulatory Commission,
ATTN: Document Control Center, Washington, DC 20555-0001 with a copy to Laura Kozak,
acting Branch Chief, U.S. Nuclear Regulatory Commission, Region III, 2443 Warrenville Road,
Suite 210, Lisle, IL 60532, within 40 days of the date of this letter. If an adequate response is
not received within the time specified or an extension of time has not been granted by the NRC,
the NRC will proceed with its enforcement decision or schedule a Regulatory Conference.
Please contact Laura Kozak at 630-829-9604 and in writing within 10 days from the issue date
of this letter to notify the NRC of your intentions. If we have not heard from you within 10 days,
we will continue with our significance determination and enforcement decision. The final
resolution of this matter will be conveyed in separate correspondence.
Because the NRC has not made a final determination in this matter, no Notice of Violation is
being issued for these inspection findings at this time. In addition, please be advised that the
characterization of the apparent violation described in the enclosed inspection report may
change as a result of further NRC review.
T. Brown 3
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its
enclosure will be made available electronically for public inspection in the NRC Public
Document Room and in the NRCs Agencywide Documents Access and Management System
(ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html.
Sincerely,
Michelle Hayes, Acting Deputy Director
Division of Reactor Safety
Docket No. 05000346
License No. NPF-3
Enclosure:
As stated
cc: Distribution via LISTSERV
Signed by Hayes, Michelle
on 12/09/21
T. Brown 4
Letter to Terry Brown from Michelle Hayes dated December 9, 2021.
SUBJECT: DAVIS-BESSE - NRC INSPECTION REPORT (05000346/2021090);
DISTRIBUTION:
RidsNrrDorlLpl3
RidsNrrPMDavisBesse Resource
RidsNrrDroIrib Resource
DRPIII
DRSIII
ROPassessment.Resource@nrc.gov
ADAMS Accession Number: ML21340A221
Publicly Available Non-Publicly Available Sensitive Non-Sensitive
OFFICE RIII RIII RIII RIII
NAME JHanna:mb LKozak JCameron MHayes
DATE 12/08/2021 12/08/2021 12/09/2021 12/09/2021
OFFICIAL RECORD COPY
Summary of the Detailed Risk Evaluation for the Davis-Besse Speed Switch Finding and
Basis for Preliminary Significance Determination
Exposure Time - From late August 28 or early August 29, 2020, until September 7, 2020,
Emergency Diesel Generator-2 (EDG) was unavailable; a time window of 9 days. This was
when the engine was reasonably known to be in a failed condition. A factor of
9 days/365 days/year, or 0.0246 was applied to the annualized results.
Failure Mechanism - The failure of EDG-2, during a hypothetical demand, would be in the first
few seconds of an attempted start of the engine. Consequently, the basic event in the
Davis-Besse Standardized Plant Analysis Risk (SPAR) model basic event Diesel Generator 1-2
Fails to Start was set to True. All other basic events were left at their nominal failure
probabilities, except for the Mitigating Strategies equipment, which is discussed below.
Common Cause Implications - The two safety-related EDGs at Davis-Besse are similar in all
respects, and the performance deficiency affected both engines. The potential for common
cause failure was used in the NRCs evaluation. However, it is important to note that the
Davis-Besse Station Blackout EDG was sufficiently different in design, vintage, and other
material properties such that it was not part of the Common Cause Component Group with the
two safety-related engines in the SPAR model.
Mitigating Strategies - The Mitigating Strategies equipment and response procedures
(commonly and collectively known as FLEX) were credited in this analysis. Given that the
performance deficiency affected the safety-related EDGs, and the accident sequences of
concern were station blackout sequences that become extended losses of AC power scenarios,
FLEX was included in the internal and external events analysis. However, the analyst adjusted
the failure probabilities in the SPAR model for the FLEX basic events using a 3x multiplier to
more accurately reflect the higher unreliability of portable equipment. The analyst also
compared the FLEX unavailability/unreliability values used in the licensee Probabilistic risk
assessment (PRA) model with the NRC SPAR model (using the 3x multiplier). No significant
differences were identified.
Repair/Recovery of Failed Components - The diagnosis and replacement of the failed speed
switch following the surveillance testing failure was three days in duration. The analyst
concluded that the recovery of the failed speed switch during a postulated event, i.e., during a
loss of offsite power that progresses to a station blackout for the non-conforming case was not
credible.
Internal Events Risk - The dominant internal event accident sequence is a weather-related
loss of offsite power sequence and contributes 46% of the total internal events risk. However,
the overall results were dominated by fire and internal events only represented 12% of the total.
External Events Risk -
Fire - Fire was the dominant contributor to the overall change in core damage frequency
(CDF) result and was included quantitatively using the licensees all hazard model. The
dominant fire sequence are large damaging fires, or high energy arc faults, which cause
a loss of offsite power (LOOP) with a subsequent loss of decay heat removal via the
once-through steam generators with subsequent failure of makeup/high pressure
injection (HPI) cooling. These scenarios contribute 54% of the fire risk. FLEX
Enclosure
equipment/strategies were credited in both the base and non-conforming cases. The
analyst sampled the top 20 dominant cutsets and verified that bounding and/or
unrealistic assumptions were not being used, however, further reviews or discussions
with Energy Harbor staff may be needed to either confirm or refute this assumption.
Tornados/High Winds and External Flooding - External flooding or tornados leading to a
LOOP, though credible, was determined to be several orders of magnitude less frequent
than the LOOP values used in the internal events model. No further analysis was
performed.
Seismic - Seismic-induced events were quantified using the licensees all hazard model,
though they were not a significant contributor to the overall result.
Uncertainty - With all risk evaluations, there are both aleatory (randomness) and epistemic
(lack of knowledge) uncertainties. The aleatory uncertainty was assessed using the
Davis-Besse SPAR model. The 5% and 95% values for the consolidated results (both internal
and external events) were 9E-7/year to 4E-6/year. The remaining epistemic uncertainties with
the results were centered on the fire results generated from the licensees model. Specifically, it
was unknown at the time of completion of the risk analysis whether substantial conservatism
were present in the fire model, though some efforts had been taken to address this question as
described above.
Item of Merit - The risk contribution for the two most commonly used items of merit, delta-CDF
and delta large early release frequency (LERF), were quantified in the analysis. Delta-CDF
remained the item of merit.
Consolidated Results -
Base Non-Conforming Delta Risk
Case Case (change in CDF)
Internal Events (NRC Results) 1.3E-7 3.6E-7 2.2E-7
Seismic (Licensee Results) 3.1E-7 3.4E-7 3.2E-8
Fire (Licensee Results) 1.3E-6 2.9E-6 1.6E-6
Total = 1.7E-6 3.6E-6 1.9E-6
The quantitative and qualitative inputs described above support the treatment of this finding as
low to moderate safety significance (i.e., White).
2