Davis-Besse Nuclear Power Station Christopher J. Jackson General Plant Manager 5501 N. State Route 2 Oak Harbor, OH 43449

L-24-069 April 30, 2024 10 CFR 20.2206

ATTN: REIRS Project Manager Office of Nuclear Regulatory Research United States Nuclear Regulatory Commission Washington, DC 20555

Subject:

Davis-Besse Nuclear Power Station, Unit 1 Docket Number 50-346, License Number NPF-3 Occupational Radiation Exposure Report for Year 2023

On April 30th, 2024, the Davis-Besse Nuclear Power Station (DBNPS) staff electronically submitted the 774 reports showing the results of occupational radiation exposure at the DBNPS during 2023.

The Windows operating system file "NRC5.dat" was electronically submitted successfully via the Radiation Exposure and Information Reporting System (REIRS) internet webpage www.reirs.com. This submittal contained data of the reports on NRC Form 5 maintained for the individuals concerned. This information is provided in accordance with 10 CFR 20.2206(b).

There are no regulatory commitments contained in this letter. If there are any questions or if additional information is required, please contact Robert W. Oesterle, Manager, Nuclear Regulatory Compliance, at (419) 321-7462.

Sincerely, CmIB~:: n General Plant Manager, Nuclear

TNW

cc: USNRC Document Control Desk Regional Administrator, NRC Region III DB-1 NRC Senior Resident Inspector DB-1 NRC/NRR Project Manager Utility Radiological Safety Board American Nuclear Insurers