ML24089A258

From kanterella
Jump to navigation Jump to search
Request for Information for the NRC Quuadrennial Comprehensive Engineering Team Inspection: Inspection Report 05000346/2024010
ML24089A258
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 04/01/2024
From: Jorge Corujo-Sandin
NRC/RGN-III/DORS/EB2
To: Tony Brown
Energy Harbor Nuclear Corp
References
IR 2024010
Download: ML24089A258 (1)


See also: IR 05000346/2024010

Text

Terry Brown

Site Vice President

Energy Harbor Nuclear Corp.

Davis-Besse Nuclear Power Station

5501 N. State Rte. 2, Mail Stop A-DB-3080

Oak Harbor, OH 43449-9760

SUBJECT: DAVIS-BESSE NUCLEAR POWER STATION - REQUEST FOR INFORMATION

FOR THE NRC QUADRENNIAL COMPREHENSIVE ENGINEERING TEAM

INSPECTION: INSPECTION REPORT 05000346/2024010

Dear Terry Brown:

On September 9, 2024, the U.S. Nuclear Regulatory Commission (NRC) will begin a quadrennial

baseline Comprehensive Engineering Team Inspection (CETI) at Davis-Besse Nuclear Power

Station. This inspection will be performed in accordance with NRC Inspection Procedure

71111.21M.

The CETI focuses on the design, maintenance, and operation of risk significant components

with low margin, or associated with an accident scenario, or a specific system. The inspection

also monitors the implementation of changes to structures, systems, and components as

modifications to one system may also affect the design bases and functioning of interfacing

systems as well as introduce the potential for common cause failures. The components,

modifications, 50.59 Evaluations, 50.59 Screenings and Operating Experiences to be reviewed

during this baseline inspection will be identified as part of the preparation for the inspection and

finalized during the first onsite inspection week. Additionally, the inspection team may request

scenarios to be performed on the simulator. This request would require support from your

simulator staff to validate scenarios, simulator time, and a crew to perform the actions which

would most likely occur during the second onsite week. The team will work closely with your

staff early on during the inspection process to ensure this activity can be accomplished with

minimal impact.

The inspection will include two weeks onsite. The inspection team will consist of seven NRC

inspectors who will focus on engineering/maintenance/operations of the selected components,

modifications, 50.59 Evaluations, 50.59 Screenings, and Operating Experiences. The current

inspection schedule is as follows:

  • Preparation week: September 2 - 6, 2024
  • Onsite weeks: Week 1: September 9 - 13, 2024

Week 2: September 23 - 27, 2024April 1, 2024

T. Brown 2

Experience with previous baseline design/modification inspections of similar depth and length

has shown that this type of inspection is extremely resource intensive, both for the NRC

inspectors and the licensee staff. To minimize the inspection impact on the site and to ensure a

productive inspection for both parties, we have enclosed a request for information.

It is important that all these documents are up-to-date and complete to minimize the number of

additional documents requested during the preparation and/or the onsite portions of the

inspection. Insofar as possible, this information should be provided electronically to the lead

inspector. The information request has been divided into four groups, with their respective due

dates:

  • May 14, 2024 - The first group lists information necessary for our initial inspection

scoping activities (preliminary sample selections).

  • July 15, 2024 - The lead inspector will communicate the preliminary

samples selected. This will include Components, Modifications, 50.59

Evaluations and 50.59 Screenings.

  • August 21, 2024 - The second group of documents requested are those items needed

to support our in-office preparation activities. During the in-office preparation activities,

the team may identify additional information needed to support the inspection.

  • September 9, 2024 - The third group includes the additional information identified during

the in-office preparation as well as plant-specific reference material. This information

should be available to the team onsite.

  • After September 9, 2024 - The fourth group includes supporting information to be

provided throughout the inspection. Specifically, corrective action documents and

answers to questions developed during the inspection are requested to be provided as

the documents are generated.

In addition, the enclosure includes information and requests addressing inspection logistics.

The lead inspector for this inspection is Jorge Corujo-Sandin. We understand that our licensing

contact for this inspection is Gerry Wolf of your organization. If there are any questions about

the inspection or the material requested in the enclosure, please contact the lead inspector at

630-829-9741 or via email at Jorge.Corujo-Sandin@nrc.gov.

This letter does not contain new or amended information collection requirements subject to the

Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection

requirements were approved by the Office of Management and Budget, Control Number

3150-0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a

request for information or an information collection requirement unless the requesting document

displays a currently valid Office of Management and Budget Control Number.

T. Brown 3

This letter and its enclosure will be made available for public inspection and copying at

http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in

accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

Jorge Corujo-Sandin

Senior Reactor Inspector

Engineering Branch 1

Division of Operating Reactor Safety

Docket No. 05000346

License No. NPF-3

Enclosure:

Comprehensive Engineering Team

Inspection - Request for Information

cc w/ encl: Distribution via LISTSERV

Rodriguez, Lionel signing on behalf

of Corujo-Sandin, Jorge

on 04/01/24

T. Brown 4

Letter to Terry Brown from Jorge Corujo-Sandin dated April 1, 2024.

SUBJECT: DAVIS-BESSE NUCLEAR POWER STATION - REQUEST FOR INFORMATION

FOR THE NRC QUADRENNIAL COMPREHENSIVE ENGINEERING TEAM

INSPECTION: INSPECTION REPORT 05000346/2024010

DISTRIBUTION:

Farrah Gaskins

RidsNrrPMDavisBesse Resource

RidsNrrDorlLpl3

RidsNrrDroIrib Resource

John Giessner

Mohammed Shuaibi

Diana Betancourt-Roldan

Allan Barker

David Curtis

Karla Stoedter

R3-DORS

ADAMS Accession Number: ML24089A258

Publicly Available Non-Publicly Available Sensitive Non-Sensitive

OFFICE RIII RIII

NAME LRodriguez for

JCorujo-Sandin:gmp

DATE 04/01/2024

OFFICIAL RECORD COPY

COMPREHENSIVE ENGINEERING TEAM INSPECTION

REQUEST FOR INFORMATION

I. ADMINISTRATIVE INSPECTION INFORMATION

Inspection Report Number: 05000346/2024010

Onsite Inspection Dates: September 9 - 13, 2024 and September 23 - 27, 2024

Inspection Procedure: IP 71111.21M, Comprehensive Engineering Team Inspection

Jorge Corujo-Sandin, Senior Reactor Inspector

Lead Inspector: RIII/DORS/EB1

630-829-9741

Jorge.Corujo-Sandin@nrc.gov

Benny Jose, Senior Reactor Inspector, RIII/DORS/EB2

Ijaz Jesse Hafeez, Senior Reactor Inspector, RIII/DORS/EB2

Teammates: Kevin Barclay, Senior Reactor Inspector, RIII/DORS/EB1

Lionel Rodriguez, Senior Reactor Inspector, RIII/DORS/EB1

Edison Fernandez, Senior Reactor Inspector, RIII/DORS/ERPB

Thomas Briley, Senior Project Engineer, RIII/DORS/TSS

Elba Sanchez Santiago, Senior Project Engineer, RIII/DORS/TSS

Observers: Anthony Valiaveedu, Reactor Inspector, RIII/DORS/EB2

Stephanie Liska, Reactor Inspector, RIII/DORS/EB2

II. INSPECTION LOGISTICS

Email the following inspection logistics to the lead inspector by August 12, 2024, or sooner:

1. Inspection room name/number, and phone number. If possible, also provide an interview

room name/number;

2. Response team contact information (names and phone numbers), team roles (e.g.,

management sponsor, lead, inspector counterpart), and normal working hours;

3. Any site access/badging and dosimetry actions needed for each inspector/observer;

4. Entrance meeting time and location;

5. Confirmation that the team will have Wi-Fi access, and access to a licensee computer

with a nearby printer;

6. Cafeteria location and hours (if any);

7. Any potential resource conflicts during the inspection (e.g., emergency drills and all-staff

meetings); and

8. Available times, during the Monday and Tuesday of the second onsite week, to use the

simulator to run scenarios. An operations crew to support this effort will also be required.

9. Current management and engineering organizational chart.

Enclosure

III. INFORMATION REQUEST

Contact the lead inspector as soon as possible if you have any questions regarding this

information request. Provide the information electronically in pdf files, Excel, or other

searchable formats, preferably via an electronic sharing service (CERTREC, ShareFile, Box,

etc.). Specific Excel formats for various enclosure items may be requested to assist in

inspection sample selection. If you do not have access to any of these services or similar,

we can provide you access to Box, which can be used to upload/download and share

documents. The files should contain descriptive names and be indexed and hyperlinked to

facilitate ease of use. Information in lists should contain enough information to be easily

understood by someone who has knowledge of light water reactor technology.

1. Information Requested for Preliminary Selection of Samples

The following information is requested by May 14, 2024, or sooner, to facilitate the initial

sample selection.

Note: If you are unable to provide the items below as requested, please reach out to the

Team Lead as soon as possible.

1.1. Risk-Ranking of the top 250 components from your site-specific probabilistic safety

analysis (PSA) sorted by Birnbaum Worth. Include values for Risk Achievement

Worth, Risk-Reduction Worth, and Fussell-Veseley. Please provide the ranking in

an excel spreadsheet that contains the importance measures and the description

of the basic event (e.g., not just the basic event designator).

1.2. Risk-ranking of the top 250 components (i.e., Large Early Release Frequency

(LERF)) from your site-specific PSA similar to the request in item 1.1. (Provide in

Excel format.)

1.3. Provide a list of the top 250 cut-sets from your PSA. Provide the descriptions of the

basic events in the list of cut-sets. (Provide in Excel format.)

1.4. Provide a list of the top 100 cut-sets for each initiator modeled in the PSA that

contributes more than 5 percent to the baseline plant core damage frequency.

(Provide in Excel format.)

1.5. Copies of PSA system notebooks, Human Error Reliability Analysis Notebook,

Internal Flood scenario notebook and latest internal event PSA summary

document.

1.6. List of systems, system numbers/designators, and corresponding system names.

1.7. List of high-risk Maintenance Rule systems/components based on engineering or

expert panel judgment (i.e., those systems/components not identified high-risk in

the PSA).

1.8. Electronic copies of simplified plant drawings (if available). Note: these may be

uncontrolled documents such as big notes, training diagrams, etc.

2

1.9. Electronic copies of updated final safety analysis report (UFSAR), Technical

Specifications, Technical Specifications Bases, and Technical Requirements

Manual.

1.10. Provide copies of the emergency operating procedures and abnormal operating

procedures.

1.11. Provide the in-service testing (IST) program document. Include the IST Program

Basis document, or equivalent (if any).

1.12. Copies of procedures addressing the following: modifications, design changes, set

point changes, equivalency evaluations or suitability analyses, post-modification

testing, 10 CFR 50.59 evaluations and screenings, and UFSAR updates.

1.13. Structures, systems, and components (SSCs) in the Maintenance Rule (a)(1)

category for the last 4 years.

1.14. A list of operating experience evaluations for the last 4 years.

1.15. Information of any common cause failure of components experienced in the last

4 years at your facility.

1.16. List of Root Cause Evaluations associated with component failures or design

issues initiated/completed in the last 4 years.

1.17. List of open operability evaluations.

1.18. Procedures addressing time critical and/or risk significant operator actions. If not

part of the procedure, include a list of all time critical and/or risk significant operator

actions. Identify those actions that do not have job performance measures.

1.19. List of permanent plant modifications to SSCs that are field work complete. Do

not include canceled or still in process modifications. For the purpose of this

inspection, permanent plant modifications include permanent:

1.19.1 Plant changes, design changes, set point changes, completed in the last

4 years;

1.19.2 Equivalency evaluations, and suitability analyses completed in the last

4 years;

1.19.3 Procedure changes for Emergency Operating Procedures (EOPs),

Abnormal Operating Procedures (AOPs), surveillances, and test

procedures in the last 4 years; and

1.19.4 Calculation changes that have been issued for use in the last 4 years.

1.20. A list of corrective action documents (open and closed) in the last 4 years that

address permanent plant modifications issues, concerns, or processes. These

documents should also include the corrective action documents associated with

the modification implementation.

3

1.21. List of all 10 CFR 50.59 completed evaluations involving (a) calculations,

(b) procedure revisions, (c) changes to the facility (modifications), (d) non-routine

operating configurations, or (e) departures in methods of analyses. The list should

NOT include any evaluations which concluded a license amendment was required.

Include evaluations performed over the last 4 years. This list should include 50.59

evaluations for the following:

1.21.1 Changes that have been made under the provisions of 10 CFR 50.59 that

have been updated in accordance with 10 CFR 50.71(e)(4);

1.21.2 Modifications that are field work complete; and

1.21.3 Changes to calculations (or initiation of new calculations) that have been

issued. The list should contain the number and title of each document, a

brief description of the change, and the corresponding number and type of

the affected document (i.e., the modification or procedure to which the

evaluation applies).

1.22. A list of all 10 CFR 50.59 changes that have been screened out as not requiring a

full evaluation involving (i.e., just a 50.59 Screening): (a) calculations; (b)

procedure revisions; (c) changes to the facility (modifications); (d) non-routine

operating configurations; or (e) departures in methods of analyses.

The list should contain the number and title of each document, a brief description

of the change, and the corresponding number and type of the affected document

(i.e., the modification or procedure to which the evaluation applies.)

1.23. A list of any modifications, procedure revisions, or the UFSAR changes where it

was determined that 10 CFR 50.59 did not apply.

1.24. A list of corrective action documents (open and closed) that address 10 CFR 50.59

issues, concerns, or processes. These documents should also include the

associated corrective action documents and the 50.59 change implementation.

The list should contain the number, title, and revision (or date) of each document,

the affected system and corresponding documentation (if applicable).

1.25. UFSAR updates submitted in accordance with 10 CFR 50.71(e)(4). Provide copies

of the complete submittal.

1.26. Copy of the UFSAR change log or a synopsis of the changes. This should include

all of the changes made to the UFSAR that were incorporated in the last

10 CFR 50.71(e)(4) submittal.

4

2. Information Requested for the Preliminary Selected Samples to be Available by

August 21, 2024

This information should be separated for each selected sample, especially if provided

electronically (e.g., folder with component or modification name that includes calculations,

condition reports, maintenance history, etc.).

2.1. Corrective Action Program procedures, including the operability/functionality

determination procedure.

2.2. Quality Assurance Program document/procedure.

2.3. A copy of any internal/external self-assessments and associated corrective action

documents generated in preparation for the inspection.

2.4. A copy of engineering/operations related audits completed in the last 2 years.

For the selected Components:

2.5. System Health Reports, System Descriptions, Design Basis Documents, and/or

Training Lesson Plans associated with each of the selected components.

2.6. List of condition reports (corrective action documents) associated with each of the

selected components for the last 4 years. (Excel format preferred.)

2.7. For each selected component list of the maintenance history (corrective,

preventive, and elective) over the last 10 years. Identify frequency of preventive

maintenance activities.

2.8. Aging Management Program documents applicable to each selected component.

2.9. Provide an all-inclusive list of calculation revisions in effect associated with each

of the selected components. Include document number, title, and revision number.

2.10. Copies of calculations associated with each of the selected components, excluding

data files. If number of applicable responses under this request, for a specific

component, is excessive (e.g., more than 10 calculations), you may reach out to

the Team Lead to for an alternative. [Pipe stress calculations excluded from this

request.]

2.11. Electronic copies of electrical drawings (ac and dc) and key diagrams.

2.12. Electronic copy of Piping and Instrumentation Drawings (P&IDs) (if available).

2.13. Copies of operability evaluations (open/closed for last 4 years) associated with

each of the selected components and plans for restoring operability, if applicable.

2.14. Copies of operator work-around evaluations associated with each of the selected

components and plans for resolution, if applicable.

5

2.15. Copies of any open temporary modifications associated with each of the selected

components, if applicable.

2.16. Trend data on the selected electrical/mechanical components performance for

last 4 years. (For example, pumps performance including in-service testing, other

vibration monitoring, oil sample results, etc., for valves: stroke time and leak rate

results, diagnostic trend data, etc.)

2.17. Provide copies of the normal and alarm response procedures associated with the

selected components and selected scenarios (if any).

2.18. If available electronically, provide the vendor manual. Otherwise refer to section 4

of this RFI.

2.19. Completed tests and surveillances for each selected component performed during

the last 3 years. For those tests and surveillances performed at a periodicity of

greater than 3 years, provide the latest two performed. Include the associated

acceptance criteria basis calculations. For those specific tests or surveillances

performed at a periodicity resulting in excessive responses to this request, you

may reach out to the Team Lead for an alternative.

For the selected Modifications, 50.59 Evaluations and 50.59 Screenings:

2.20. For each of the selected modifications, provide the engineering change package.

Include any associated 50.59 Screening and/or 50.59 Evaluation.

2.21. Provide a copy of each selected 50.59 Evaluation.

2.22. Provide copies of the selected 50.59 Screenings.

2.23. The selected Modifications, 50.59 Evaluations and 50.59 Screenings will be

further filtered by the inspectors until the final samples are selected. Once these

are selected (during the preparation week and the first on-site week) the site

should be prepared to provide other supporting documents for the selected item.

Examples of supporting documents include:

  • Design drawings supporting the change
  • Procedures, calculations, etc. affected by the change
  • Post-modification test packages
  • UFSAR change papers generated (e.g., marked off pages)

6

3. Additional Information to be Provided on September 9, 2024, When the Team is

Onsite

3.1. During the in-office preparation activities, the team will be making final selections

and may identify additional information needed to support the inspection.

3.2. Schedule of any testing/maintenance activities to be conducted on the selected

components or installed modifications during the two onsite inspection weeks.

4. Information Requested to be Provided Throughout the Inspection

4.1. Any corrective action documents generated as a result of the teams questions

during this inspection as the documents are generated.

4.2. List of questions and/or document requests submitted by the team and their status

(e.g., open, closed) sorted by inspector. Provide daily by 2:00 p.m., plant local

time, to each inspector. It is recommended to provide the team leader with a

master list sorted by inspector and each inspector with a list containing only the

items originated by that inspector.

4.3. If available in hardcopy form, one complete set of P&IDs and simplified drawings

(e.g., training schematics). If any of these documents is not available in hardcopy

form, contact the lead inspector.

4.4. Please ensure that other supporting documents for the selected items have been

located and are readily retrievable as the inspection team will likely be requesting

these documents during the inspection. Examples of supporting documents are:

4.4.1 Individual Plant Examination/Probabilistic Risk Assessment report;

4.4.2 Procurement documents for components and modifications selected (verify

retrievable);

4.4.3 Plant procedures (normal, abnormal, emergency, surveillance, etc.);

4.4.4 Vendor manuals;

4.4.5 Historical revisions of the Final Safety Analysis Report (FSAR), including

the Original FSAR and Original Safety Evaluation Report; and

4.4.6 Copy of electrical drawings, key diagrams, and isometrics (paper copies).

If you have questions regarding the information requested, please contact the lead inspector.

7