IR 05000244/2006007: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:August 3, 2006Mrs. Mary Korsnick Vice President, R. E. Ginna Nuclear Power Plant R. E. Ginna Nuclear Power Plant, LLC 1503 Lake Road Ontario, New York 14519SUBJECT:GINNA NUCLEAR POWER PLANT- NRC TRIENNIAL FIRE PROTECTIONINSPECTION REPORT 05000244/2006007
{{#Wiki_filter:ust 3, 2006
 
==SUBJECT:==
GINNA NUCLEAR POWER PLANT- NRC TRIENNIAL FIRE PROTECTION INSPECTION REPORT 05000244/2006007


==Dear Mrs. Korsnick:==
==Dear Mrs. Korsnick:==
On June 23, 2006, the NRC completed a triennial fire protection team inspection at your R. E.Ginna facility. The enclosed report documents the inspection results which were discussed onJune 23, 2006, with you and other members of your staff.The inspection examined activities conducted under your license as they relate to safety andcompliance with the Commission's rules and regulations and with the conditions of your license.
On June 23, 2006, the NRC completed a triennial fire protection team inspection at your R. E.
 
Ginna facility. The enclosed report documents the inspection results which were discussed on June 23, 2006, with you and other members of your staff.
 
The inspection examined activities conducted under your license as they relate to safety and compliance with the Commissions rules and regulations and with the conditions of your license.
 
The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.
 
Based on the results of this inspection, the NRC identified one finding of very low safety significance (Green) that was a violation of NRC requirements. However, because of the very low safety significance and because it is entered into your corrective action program, the NRC is treating this finding as a non-cited violation (NCV) consistent with Section VI.A.1 of the NRC Enforcement Policy. If you contest the NCV in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001 with copies to the Regional Administrator Region I, the Director, Office of Enforcement, United States Nuclear Regulatory Commission, Washington, DC 20555-0001, and the NRC Resident Inspector at the Ginna Nuclear Power Plant.


The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.Based on the results of this inspection, the NRC identified one finding of very low safetysignificance (Green) that was a violation of NRC requirements. However, because of the verylow safety significance and because it is entered into your corrective action program, the NRC is treating this finding as a non-cited violation (NCV) consistent with Section VI.A.1 of the NRC Enforcement Policy. If you contest the NCV in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001 with copies to the Regional Administrator Region I, the Director, Office of Enforcement, United States Nuclear Regulatory Commission, Washington, DC 20555-0001, and the NRC Resi dentInspector at the Ginna Nuclear Power Plant.The enclosed report also documented two noncompliances that were identified by your staffduring the NFPA 805 transition period. The NRC is not taking any enforcement actions forthese noncompliances because the conditions for these noncompliances meet the four criteria (licensee-identified, compensatory actions have been taken, not likely to have been previously identified by routine licensee efforts, and not willful) of NRC Enforcement Policy, InterimEnforcement Policies, "Interim Enforcement Policy Regarding Enforcement Discretion for Certain Fire Protection Issues (10 CFR 50.48)", and are not associated with a finding of high safety significance.
The enclosed report also documented two noncompliances that were identified by your staff during the NFPA 805 transition period. The NRC is not taking any enforcement actions for these noncompliances because the conditions for these noncompliances meet the four criteria (licensee-identified, compensatory actions have been taken, not likely to have been previously identified by routine licensee efforts, and not willful) of NRC Enforcement Policy, Interim Enforcement Policies, Interim Enforcement Policy Regarding Enforcement Discretion for Certain Fire Protection Issues (10 CFR 50.48), and are not associated with a finding of high safety significance.


2In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, itsenclosure, and your response (if any) will be available electronically for public inspection in theNRC Public Document Room or from the Publicly Available Records (PARS) com ponent ofNRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/ADAMS.html (the Public Electronic Reading Room).
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and your response (if any) will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/ADAMS.html (the Public Electronic Reading Room).


Sincerely,
Sincerely,
/RA/John F. Rogge, ChiefEngineering Branch 3 Division of Reactor SafetyDocket Nos. 50-244License Nos. DPR-18
/RA/
John F. Rogge, Chief Engineering Branch 3 Division of Reactor Safety Docket Nos. 50-244 License Nos. DPR-18


===Enclosure:===
===Enclosure:===
NRC Inspection Report 05000244/2006007
NRC Inspection Report 05000244/2006007


REGION IDocket Nos.50-244 License Nos.DPR-18 Report No.05000244/2006007 Licensee:Constellation Energy, R. E. Ginna Nuclear Power Plant, LLC Facility:R. E. Ginna Nuclear Power PlantLocation:Ontario, New York Dates:June 5 - 23, 2006 Inspectors:L. Cheung, Senior Reactor Inspector, DRSP. Finney, Reactor Inspector, DRS K. Young, Senior Reactor Inspector, DRS A. Gaudette, Inspector Trainee, DRPApproved by:John F. Rogge, ChiefEngineering Branch 3 Division of Reactor Safety Enclosure ii
REGION I==
Docket Nos. 50-244 License Nos. DPR-18 Report No. 05000244/2006007 Licensee: Constellation Energy, R. E. Ginna Nuclear Power Plant, LLC Facility: R. E. Ginna Nuclear Power Plant Location: Ontario, New York Dates: June 5 - 23, 2006 Inspectors: L. Cheung, Senior Reactor Inspector, DRS P. Finney, Reactor Inspector, DRS K. Young, Senior Reactor Inspector, DRS A. Gaudette, Inspector Trainee, DRP Approved by: John F. Rogge, Chief Engineering Branch 3 Division of Reactor Safety Enclosure


=SUMMARY OF FINDINGS=
=SUMMARY OF FINDINGS=
IR 05000244/2006007 on 06/05 - 23/ 2006, Ginna Nuclear Power Plant; Triennial FireProtection Team Inspection, Fire Protection.This report covered a two-week triennial fire protection team inspection by three Region Ispecialist inspectors and one inspector trainee. One Green non-cited violation (NCV) was identified. The significance of most findings is indicated by their color (Green, White, Yellow,
IR 05000244/2006007 on 06/05 - 23/ 2006, Ginna Nuclear Power Plant; Triennial Fire
Red) using Inspection Manual Chapter (IMC) 0609, "Significance Determination Process" (SDP). Findings for which the SDP does not apply may be Green or be assigned a severity level after NRC management review. The NRC's program for overseeing the safe operation ofcommercial nuclear power reactors is described in NUREG-1649, "Reactor Oversight Process,"Revision 3, dated July 2000.A.
 
Protection Team Inspection, Fire Protection.
 
This report covered a two-week triennial fire protection team inspection by three Region I specialist inspectors and one inspector trainee. One Green non-cited violation (NCV) was identified. The significance of most findings is indicated by their color (Green, White, Yellow,
Red) using Inspection Manual Chapter (IMC) 0609, Significance Determination Process (SDP). Findings for which the SDP does not apply may be Green or be assigned a severity level after NRC management review. The NRCs program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649, Reactor Oversight Process,
Revision 3, dated July 2000.


===NRC-Identified Findings===
===NRC-Identified Findings===
Line 43: Line 61:
===Cornerstone: Mitigating Systems===
===Cornerstone: Mitigating Systems===
: '''Green.'''
: '''Green.'''
The team identified an NCV of license condition 2.C.3 for the failure toimplement and maintain in effect all fire protection features. Specifically, Constellation failed to provide the required quarterly training to five fire brigade members in the fourth quarter of 2005, and subsequently failed to remove those personnel from fire brigade duty during the period from January 1, 2006, to the time when those brigade membersreceived their remedial training. Site procedures require that fire brigade members attend quarterly classroom training, and that fire brigade members who fail to attend such training be removed from brigade duties until they attend remedial training. Upon identification of this finding, Constellation removed all five personnel from fire brigade duties until properly trained, initiated a prompt investigation and entered this finding intotheir corrective action program.The finding is more than minor because the finding is associated with the MitigatingSystem cornerstone attribute of protection against external factors and affected the cornerstone objective of ensuring the availability, reliability and capability of systems thatrespond to initiating events to prevent undesirable consequences. The Assumptions and Limitations of the Fire Protection Significance Determination Process (SDP), IMC 0609, Appendix F, specifically exclude fire brigade issues. As such, IMC 0612, Section 05.04.c, requires NRC management review to determine the significance of this finding.
The team identified an NCV of license condition 2.C.3 for the failure to implement and maintain in effect all fire protection features. Specifically, Constellation failed to provide the required quarterly training to five fire brigade members in the fourth quarter of 2005, and subsequently failed to remove those personnel from fire brigade duty during the period from January 1, 2006, to the time when those brigade members received their remedial training. Site procedures require that fire brigade members attend quarterly classroom training, and that fire brigade members who fail to attend such training be removed from brigade duties until they attend remedial training. Upon identification of this finding, Constellation removed all five personnel from fire brigade duties until properly trained, initiated a prompt investigation and entered this finding into their corrective action program.


NRC management determined this finding to be of very low safety significance (Green). Fire brigade performance was not significantly affected, given staffing, at times, by members that lacked a single quarter of training, because the entire brigade staff had completed the annual live-fire practice sessions. (Section 1R05.04)
The finding is more than minor because the finding is associated with the Mitigating System cornerstone attribute of protection against external factors and affected the cornerstone objective of ensuring the availability, reliability and capability of systems that respond to initiating events to prevent undesirable consequences. The Assumptions and Limitations of the Fire Protection Significance Determination Process (SDP), IMC 0609, Appendix F, specifically exclude fire brigade issues. As such, IMC 0612, Section 05.04.c, requires NRC management review to determine the significance of this finding.
 
NRC management determined this finding to be of very low safety significance (Green).
 
Fire brigade performance was not significantly affected, given staffing, at times, by members that lacked a single quarter of training, because the entire brigade staff had completed the annual live-fire practice sessions. (Section 1R05.04)
 
===Licensee-Identified Violations===


===B.Licensee-Identified Violations===
None.
None.


Enclosure
ii


=REPORT DETAILS=
=REPORT DETAILS=
BackgroundThis report presents the results of a triennial fire protection inspection conducted in accordancewith NRC Inspection Procedure (IP) 71111.05TTP, "Fire Protection.The objective of theinspection was to assess whether Constellation Energy has implemented an adequate fire protection program and that post-fire safe shutdown capabilities have been established and arebeing properly maintained at the R. E. Ginna Nuclear Power Plant facility. The following fireareas (FAs) were selected for detailed review based on risk insights from the Individual Plant Examination (IPE)/ Individual Plant Examination of External Events (IPEEE):Fire Area RRA,Fire Area CHG, Fire Area EDG1B-0, Fire Area IBS-1.The inspection team evaluated the licensee's fire protection program (FPP) against applicablerequirements which include plant Technical Specifications, Operating License Condition 2.C.3,NRC Safety Evaluations, 10 CFR 50.48 and 10 CFR 50 Appendix R. The team also reviewedrelated documents that include the Updated Final Safety Analysis Report (UFSAR) Section 9.5,the Fire Hazards Analysis (FHA) and the Post-Fire Safe Shutdown
 
Background This report presents the results of a triennial fire protection inspection conducted in accordance with NRC Inspection Procedure (IP) 71111.05TTP, Fire Protection. The objective of the inspection was to assess whether Constellation Energy has implemented an adequate fire protection program and that post-fire safe shutdown capabilities have been established and are being properly maintained at the R. E. Ginna Nuclear Power Plant facility. The following fire areas (FAs) were selected for detailed review based on risk insights from the Individual Plant Examination (IPE)/ Individual Plant Examination of External Events (IPEEE):
Fire Area RRA, Fire Area CHG, Fire Area EDG1B-0, Fire Area IBS-1.
 
The inspection team evaluated the licensees fire protection program (FPP) against applicable requirements which include plant Technical Specifications, Operating License Condition 2.C.3, NRC Safety Evaluations, 10 CFR 50.48 and 10 CFR 50 Appendix R. The team also reviewed related documents that include the Updated Final Safety Analysis Report (UFSAR) Section 9.5, the Fire Hazards Analysis (FHA) and the Post-Fire Safe Shutdown


=====Analysis.=====
=====Analysis.=====
Line 59: Line 86:


==REACTOR SAFETY==
==REACTOR SAFETY==
Cornerstones: Initiating Events, Mitigating Systems1R05Fire Protection
Cornerstones: Initiating Events, Mitigating Systems


===.01 Post-Fire Safe Shutdown From Outside Main Control Room (Alternative Shutdown) andNormal Shutdown===
{{a|1R05}}
==1R05 Fire Protection==
 
===.01 Post-Fire Safe Shutdown From Outside Main Control Room (Alternative Shutdown) and===
 
Normal Shutdown


====a. Inspection Scope====
====a. Inspection Scope====
MethodologyThe team reviewed the safe shutdown analysis, operating procedures, piping and instrumentation drawings (P&IDs), electrical drawings, the UFSAR and other supporting documents to verify that hot and cold shutdown could be achieved and maintained from outside the control room for fires that rely on shutdown from outside the control room. This review included verification that shutdown from outside the control room could be performed both with and without the availability of offsite power. Plant walkdowns werealso performed to verify that the plant configuration was consistent with that described in 2Enclosurethe safe shutdown and fire hazards analyses. These inspection activities focused onensuring the adequacy of systems selected for reactivity control, reactor coolantmakeup, reactor decay heat removal, process monitoring instrumentation and support systems functions. The team verified that the systems and components credited for useduring this shutdown method would remain free from fire damage. Similarly, for fire areas that utilize shutdown from the control room, the team alsoverified that the shutdown methodology properly identified the com ponents and systemsnecessary to achieve and maintain safe shutdown conditions. Operational ImplementationThe team verified that the training program for licensed and non-licensed operatorsincluded alternative shutdown capability. The team also verified that personnel requiredfor safe shutdown using the normal or alternative shutdown systems and procedures aretrained and available onsite at all times, exclusive of those assigned as fire brigade members.The team reviewed the adequacy of procedures utilized for post-fire shutdown andperformed an independent walk through of procedure steps to ensure the implementation and human factors adequacy of the procedures. The team also verified that the operators could be reasonably expected to perform specific actions within the time required to maintain plant parameters within specified limits. Time critical actions which were verified included restoration of AC electrical power, establishing the remote shutdown and local shutdown panels, establishing reactor coolant makeup, and establishing decay heat removal.Specific procedures reviewed for alternative shutdown, including shutdown from outsidethe control room included the following:ER-FIRE.1, Alternate Shutdown For Control Complex Fire, Revision 20FRP-4.0, Auxiliary Building Basement, Revision 5FRP-8.0, Intermediate Building Controlled Side Basement, Revision 5ER-FIRE.6, Response To Fire In D/G B Vault, Revision 2O-2.1, Normal Shutdown To Hot Shutdown, Revision 120ER-FIRE.0, CR Response To Fire Alarms and Reports, Revision 6The team reviewed manual actions to ensure that they could be implemented inaccordance with plant procedures in the time necessary to support the safe shutdown method for each fire area. The team verified that the licensee had identified operatormanual actions for post-fire safe-shutdown and had plans in place to assess them as part of the plant wide risk evaluation for transition to NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants, 2001 Edition. The team also reviewed the periodic testing of the alternative shutdown transfer capability and instrumentation and control functions to ensure the tests are adequate toensure the functionality of the alternative shutdown capability.
Methodology The team reviewed the safe shutdown analysis, operating procedures, piping and instrumentation drawings (P&IDs), electrical drawings, the UFSAR and other supporting documents to verify that hot and cold shutdown could be achieved and maintained from outside the control room for fires that rely on shutdown from outside the control room.
 
This review included verification that shutdown from outside the control room could be performed both with and without the availability of offsite power. Plant walkdowns were also performed to verify that the plant configuration was consistent with that described in the safe shutdown and fire hazards analyses. These inspection activities focused on ensuring the adequacy of systems selected for reactivity control, reactor coolant makeup, reactor decay heat removal, process monitoring instrumentation and support systems functions. The team verified that the systems and components credited for use during this shutdown method would remain free from fire damage.
 
Similarly, for fire areas that utilize shutdown from the control room, the team also verified that the shutdown methodology properly identified the components and systems necessary to achieve and maintain safe shutdown conditions.
 
Operational Implementation The team verified that the training program for licensed and non-licensed operators included alternative shutdown capability. The team also verified that personnel required for safe shutdown using the normal or alternative shutdown systems and procedures are trained and available onsite at all times, exclusive of those assigned as fire brigade members.
 
The team reviewed the adequacy of procedures utilized for post-fire shutdown and performed an independent walk through of procedure steps to ensure the implementation and human factors adequacy of the procedures. The team also verified that the operators could be reasonably expected to perform specific actions within the time required to maintain plant parameters within specified limits. Time critical actions which were verified included restoration of AC electrical power, establishing the remote shutdown and local shutdown panels, establishing reactor coolant makeup, and establishing decay heat removal.
 
Specific procedures reviewed for alternative shutdown, including shutdown from outside the control room included the following:
C      ER-FIRE.1, Alternate Shutdown For Control Complex Fire, Revision 20 C      FRP-4.0, Auxiliary Building Basement, Revision 5 C      FRP-8.0, Intermediate Building Controlled Side Basement, Revision 5 C      ER-FIRE.6, Response To Fire In D/G B Vault, Revision 2 C      O-2.1, Normal Shutdown To Hot Shutdown, Revision 120 C      ER-FIRE.0, CR Response To Fire Alarms and Reports, Revision 6 The team reviewed manual actions to ensure that they could be implemented in accordance with plant procedures in the time necessary to support the safe shutdown method for each fire area. The team verified that the licensee had identified operator manual actions for post-fire safe-shutdown and had plans in place to assess them as part of the plant wide risk evaluation for transition to NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants, 2001 Edition. The team also reviewed the periodic testing of the alternative shutdown transfer capability and instrumentation and control functions to ensure the tests are adequate to ensure the functionality of the alternative shutdown capability.


====b. Findings====
====b. Findings====
Line 72: Line 115:


====b. Inspection Scope====
====b. Inspection Scope====
The team reviewed the fire hazards analysis, safe shutdown analyses and supportingdrawings and documentation to verify that safe shutdown capabilities were properlyprotected. Under the NFPA 805 Transition Period inspection procedure, the inspection team is to validate 1 to 3 nonconformances identified in the licensee's transitional assessment of their fire areas. It is noted, as directed by and in accordance with the inspection procedure, that no fire areas have been completely assessed at the time of this inspection.The team reviewed the licensee procedures and programs for the control of ignitionsources and transient combustibles to assess their effectiveness in preventing fires and in controlling combustible loading within limits established in the FHA. A sample of hot work and transient combustible control permits were also reviewed. The team performed plant walkdowns to verify that protective features were being properly maintained and administrative controls were being implemented.The team also reviewed the licensee's design control procedures to ensure that theprocess included appropriate reviews and controls to assess plant changes for any potential adverse impact on the fire protection program and/or post-fire safe shutdown analysis and procedures.
The team reviewed the fire hazards analysis, safe shutdown analyses and supporting drawings and documentation to verify that safe shutdown capabilities were properly protected. Under the NFPA 805 Transition Period inspection procedure, the inspection team is to validate 1 to 3 nonconformances identified in the licensees transitional assessment of their fire areas. It is noted, as directed by and in accordance with the inspection procedure, that no fire areas have been completely assessed at the time of this inspection.
 
The team reviewed the licensee procedures and programs for the control of ignition sources and transient combustibles to assess their effectiveness in preventing fires and in controlling combustible loading within limits established in the FHA. A sample of hot work and transient combustible control permits were also reviewed. The team performed plant walkdowns to verify that protective features were being properly maintained and administrative controls were being implemented.
 
The team also reviewed the licensees design control procedures to ensure that the process included appropriate reviews and controls to assess plant changes for any potential adverse impact on the fire protection program and/or post-fire safe shutdown analysis and procedures.


====b. Findings====
====b. Findings====
No findings of significance were identified..03Passive Fire Protection
No findings of significance were identified.
 
===.03 Passive Fire Protection===


====a. Inspection Scope====
====a. Inspection Scope====
The team walked down accessible portions of the selected fire areas to observe materialcondition and the adequacy of design of fire area boundaries (including walls, fire doors and fire dampers) to ensure they were appropriate for the fire hazards in the area.
The team walked down accessible portions of the selected fire areas to observe material condition and the adequacy of design of fire area boundaries (including walls, fire doors and fire dampers) to ensure they were appropriate for the fire hazards in the area.


The team reviewed installation/repair and qualification records for a sample of penetration seals to ensure the fill material was of the appropriate fire rating and that theinstallation met the engineering design.
The team reviewed installation/repair and qualification records for a sample of penetration seals to ensure the fill material was of the appropriate fire rating and that the installation met the engineering design.


====b. Findings====
====b. Findings====
No findings of significance were identified.
No findings of significance were identified.
4Enclosure


===.04 Active Fire Protection===
===.04 Active Fire Protection===


====b. Inspection Scope====
====b. Inspection Scope====
The team reviewed the design, maintenance, testing and operation of the fire detectionand suppression systems in the selected plant fire areas. This included verification that the manual and automatic detection and suppression systems were installed, tested andmaintained in accordance with the NFPA code of record and that they would control and/or extinguish fires associated with the hazards in the selected areas. A review of the design capability of suppression agent delivery systems were verified to meet thecode requirements for the fire hazards involved. The team also performed a walkdown of accessible portions of the detection and suppressions systems in the selected areasas well as a walkdown of major system support equipment in other areas (e.g. fireprotection pumps, Halon and/or CO 2 storage tanks and supply system) as assess thematerial condition of the systems and components.The team reviewed electric and diesel fire pump flow and pressure tests to ensure thatthe pumps were meeting their design requirements. The team also reviewed the firemain loop flow tests to ensure that the flow distribution circuits were able to meet the design requirements. The team also assessed the fire brigade capabilities by reviewing training andqualification records, and drill critique records. The team also reviewed pre-fire plansand smoke removal plans for the selected fire areas to determine if appropriate information was provided to fire brigade members and plant operators to identify safe shutdown equipment and instrumentation, and to facilitate suppression of a fire thatcould impact post-fire safe shutdown. In addition, the team inspected the fire brigade'sprotective ensembles, self-contained breathing apparatus (SCBA), and various fire brigade equipment (including smoke removal equipment) to determine operational readiness for fire fighting.
The team reviewed the design, maintenance, testing and operation of the fire detection and suppression systems in the selected plant fire areas. This included verification that the manual and automatic detection and suppression systems were installed, tested and maintained in accordance with the NFPA code of record and that they would control and/or extinguish fires associated with the hazards in the selected areas. A review of the design capability of suppression agent delivery systems were verified to meet the code requirements for the fire hazards involved. The team also performed a walkdown of accessible portions of the detection and suppressions systems in the selected areas as well as a walkdown of major system support equipment in other areas (e.g. fire protection pumps, Halon and/or CO2 storage tanks and supply system) as assess the material condition of the systems and components.
 
The team reviewed electric and diesel fire pump flow and pressure tests to ensure that the pumps were meeting their design requirements. The team also reviewed the fire main loop flow tests to ensure that the flow distribution circuits were able to meet the design requirements.
 
The team also assessed the fire brigade capabilities by reviewing training and qualification records, and drill critique records. The team also reviewed pre-fire plans and smoke removal plans for the selected fire areas to determine if appropriate information was provided to fire brigade members and plant operators to identify safe shutdown equipment and instrumentation, and to facilitate suppression of a fire that could impact post-fire safe shutdown. In addition, the team inspected the fire brigades protective ensembles, self-contained breathing apparatus (SCBA), and various fire brigade equipment (including smoke removal equipment) to determine operational readiness for fire fighting.


====b. Findings====
====b. Findings====


=====Introduction.=====
=====Introduction.=====
The team identified a Green NCV regarding the training program for onsitefire brigade personnel under Constellation's fire protection program. Specifically, Constellation failed to provide the required quarterly training to five fire brigade members in the fourth quarter of 2005, and subsequently failed to remove those personnel from fire brigade duty during the period from January 1, 2006, to the time when those brigade members received their remedial training.Description. During the inspection, the team requested quarterly training documents forfour randomly selected fire brigade members for calendar year 2005. Ginna's fire brigade training program is executed by covering relative topics over a two-year cyclevia quarterly training sessions. Further, Constellation evaluates each fire brigade member's level of knowledge through biannual examinations in the second and fourth quarters of each calendar year. Constellation determined that one of the four randomly-5Enclosureselected fire brigade members did not receive the quarterly classroom training orevaluation in the fourth quarter of 2005. An extent of condition search resulted in the identification of four additional fire brigade members without objective quality evidence of the fourth quarter training or examinations. Therefore, as a result of the inspection, five fire brigade members were identified as having missed the fourth quarter training and examination.Site procedure ND-FPP, Fire Protection Program, Revision10, section 3.2.1, states inpart that "the protection of personnel, facilities, structures, systems, and components(SSC) at Ginna Station from hazards due to fire is planned and executed per procedures.Procedure A-202, The Fire Protection Program and Ginna Station Staff Responsibilities for Fire Protection, Revision 21, section 3.6.3, states in part that"training shall be based on NFPA Standard 27.... and conducted at least quarterly for brigade members". NFPA 27-1981, section 4-3, states in part that brigade "members should be required to complete a specified program of instruction as a condition to membership in the brigade". Procedure A-103.9, Fire Brigade Training, Revision 18, section 3.3.1, states that "an individual not attending the required quarterly training shallbe removed from brigade duty until such time that the next training session can be attended". Constellation clarified, during the inspection, that "the next training session" meant a "remedial training" which would include an examination for the second and fourth quarter training.Analysis. The failure to provide training to five fire brigade members and thesubsequent failure to remove those personnel from fire brigade duty is a performance deficiency and a finding. The licensee determined that there were three occasions where up to three of the fire brigade members who failed to received the fourth quarter training in 2005 were on brigade duty (shift) at the same time. Traditional enforcement does not apply since there were no actual safety consequences or potential for impacting the NRC's regulatory function and the finding was not the result of any willfulviolation of NRC requirements. The finding is more than minor because the finding isassociated with the Mitigating System cornerstone attribute of protection against external factors and affected the cornerstone objective of ensuring the availability,reliability and capability of systems that respond to initiating events to preventundesirable consequences.
The team identified a Green NCV regarding the training program for onsite fire brigade personnel under Constellations fire protection program. Specifically, Constellation failed to provide the required quarterly training to five fire brigade members in the fourth quarter of 2005, and subsequently failed to remove those personnel from fire brigade duty during the period from January 1, 2006, to the time when those brigade members received their remedial training.
 
=====Description.=====
During the inspection, the team requested quarterly training documents for four randomly selected fire brigade members for calendar year 2005. Ginnas fire brigade training program is executed by covering relative topics over a two-year cycle via quarterly training sessions. Further, Constellation evaluates each fire brigade members level of knowledge through biannual examinations in the second and fourth quarters of each calendar year. Constellation determined that one of the four randomly-selected fire brigade members did not receive the quarterly classroom training or evaluation in the fourth quarter of 2005. An extent of condition search resulted in the identification of four additional fire brigade members without objective quality evidence of the fourth quarter training or examinations. Therefore, as a result of the inspection, five fire brigade members were identified as having missed the fourth quarter training and examination.
 
Site procedure ND-FPP, Fire Protection Program, Revision10, section 3.2.1, states in part that the protection of personnel, facilities, structures, systems, and components (SSC) at Ginna Station from hazards due to fire is planned and executed per procedures. Procedure A-202, The Fire Protection Program and Ginna Station Staff Responsibilities for Fire Protection, Revision 21, section 3.6.3, states in part that training shall be based on NFPA Standard 27.... and conducted at least quarterly for brigade members. NFPA 27-1981, section 4-3, states in part that brigade members should be required to complete a specified program of instruction as a condition to membership in the brigade. Procedure A-103.9, Fire Brigade Training, Revision 18, section 3.3.1, states that an individual not attending the required quarterly training shall be removed from brigade duty until such time that the next training session can be attended. Constellation clarified, during the inspection, that the next training session meant a remedial training which would include an examination for the second and fourth quarter training.
 
=====Analysis.=====
The failure to provide training to five fire brigade members and the subsequent failure to remove those personnel from fire brigade duty is a performance deficiency and a finding. The licensee determined that there were three occasions where up to three of the fire brigade members who failed to received the fourth quarter training in 2005 were on brigade duty (shift) at the same time. Traditional enforcement does not apply since there were no actual safety consequences or potential for impacting the NRCs regulatory function and the finding was not the result of any willful violation of NRC requirements. The finding is more than minor because the finding is associated with the Mitigating System cornerstone attribute of protection against external factors and affected the cornerstone objective of ensuring the availability, reliability and capability of systems that respond to initiating events to prevent undesirable consequences. Additionally, the finding is similar to example 4.h of IMC 0612, Appendix E in that not all fire brigade positions were staffed with appropriately trained (qualified) members. The Assumptions and Limitations of the Fire Protection Significance Determination Process (SDP), IMC 0609, Appendix F, specifically exclude fire brigade issues. As such, IMC 0612, Section 05.04.c, requires NRC management review to determine the significance of this finding. NRC management determined this finding to be of very low safety significance (Green). Fire brigade performance was not significantly affected, given staffing, at times, by members that lacked a single quarter of training, because the entire brigade staff had completed the annual live-fire practice sessions.
 
This finding is a performance deficiency and has a human performance cross-cutting aspect, because Constellation training personnel failed to ensure that all fire brigade members were adequately trained in accordance with procedural requirements, and Constellation management subsequently failed to remove those fire fighting personnel who were not properly trained from fire brigade duty.


Additionally,  the finding is similar to example 4.h of IMC 0612, Appendix E in that not all fire brigade positions were staffed with appropriately trained (qualified) members. The Assumptions and Limitations of the Fire Protection Significance Determination Process (SDP), IMC 0609, Appendix F, specifically exclude fire brigade issues. As such, IMC 0612, Section 05.04.c, requires NRC managementreview to determine the significance of this finding. NRC management determined thisfinding to be of very low safety significance (Green). Fire brigade performance was not significantly affected, given staffing, at times, by members that lacked a single quarter of training, because the entire brigade staff had completed the annual live-fire practice sessions. This finding is a performance deficiency and has a human performance cross-cuttingaspect, because Constellation training personnel failed to ensure that all fire brigade members were adequately trained in accordance with procedural requirements, and 6EnclosureConstellation management subsequently failed to remove those fire fighting personnelwho were not properly trained from fire brigade duty.Enforcement. License condition 2.C.3 requires that Constellation implement andmaintain in effect all fire protection features as approved by the NRC's Fire ProtectionSafety Evaluation (SE) and SE supplements. Site procedure ND-FPP states in part that "the following documents... are utilized to implement the Fire Protection Programrequirements: Ginna Station Procedures.Procedure A-202 requires training be provided at least quarterly to fire brigade members and Procedure A 103.9 requires an individual not attending the required quarterly training be removed from brigade duty until such time that the next training session can be attended. Contrary to the above,Constellation failed to provide the required quarterly training to five brigade members in the fourth quarter of calendar year 2005, and subsequently failed to remove those personnel from fire brigade duty for the period of January 01, 2006, to June 19, 2006, before those brigade members received their remedial training. Upon identification of this finding, Constellation removed all five personnel from fire brigade duties, performed remedial training and evaluated them via examination prior to returning them to duty-eligible status. Further, Constellation initiated a prompt investigation and entered this finding into their corrective action program under CR 2006-2518. This violation is being treated as a Non-Cited Violation, consistent with Section VI.A.1 of the NRC EnforcementPolicy.
=====Enforcement.=====
License condition 2.C.3 requires that Constellation implement and maintain in effect all fire protection features as approved by the NRCs Fire Protection Safety Evaluation (SE) and SE supplements. Site procedure ND-FPP states in part that the following documents... are utilized to implement the Fire Protection Program requirements: Ginna Station Procedures. Procedure A-202 requires training be provided at least quarterly to fire brigade members and Procedure A 103.9 requires an individual not attending the required quarterly training be removed from brigade duty until such time that the next training session can be attended. Contrary to the above, Constellation failed to provide the required quarterly training to five brigade members in the fourth quarter of calendar year 2005, and subsequently failed to remove those personnel from fire brigade duty for the period of January 01, 2006, to June 19, 2006, before those brigade members received their remedial training. Upon identification of this finding, Constellation removed all five personnel from fire brigade duties, performed remedial training and evaluated them via examination prior to returning them to duty-eligible status. Further, Constellation initiated a prompt investigation and entered this finding into their corrective action program under CR 2006-2518. This violation is being treated as a Non-Cited Violation, consistent with Section VI.A.1 of the NRC Enforcement Policy. (NCV 05000244/2006007-01, Missed Fire Brigade Training).


(NCV 05000244/2006007-01, Missed Fire Brigade Training)..05Protection From Damage From Fire Suppression Activities
===.05 Protection From Damage From Fire Suppression Activities===


====a. Inspection Scope====
====a. Inspection Scope====
The team performed document reviews and plant walkdowns to verify that redundanttrains of systems required for hot shutdown are not subject to damage from firesuppression activities or from the rupture or inadvertent operation of fire suppression systems. Specifically, the team verified that:A fire in one of the selected fire areas would not directly, through production ofsmoke, heat or hot gases, cause activation of suppression systems that couldpotentially damage all redundant trains.A fire in one of the selected fire areas (or the inadvertent actuation or rupture ofa fire suppression system) would not directly cause damage to all redundanttrains (e.g., sprinkler caused flooding of other than the locally affected train).Adequate drainage is provided in areas protected by water suppression systems
The team performed document reviews and plant walkdowns to verify that redundant trains of systems required for hot shutdown are not subject to damage from fire suppression activities or from the rupture or inadvertent operation of fire suppression systems. Specifically, the team verified that:
C        A fire in one of the selected fire areas would not directly, through production of smoke, heat or hot gases, cause activation of suppression systems that could potentially damage all redundant trains.
 
C        A fire in one of the selected fire areas (or the inadvertent actuation or rupture of a fire suppression system) would not directly cause damage to all redundant trains (e.g., sprinkler caused flooding of other than the locally affected train).
 
C        Adequate drainage is provided in areas protected by water suppression systems


====b. Findings====
====b. Findings====
No findings of significance were identified.
No findings of significance were identified.


7Enclosure.06Alternative Shutdown Capability
===.06 Alternative Shutdown Capability===


====a. Inspection Scope====
====a. Inspection Scope====
Alternative shutdown capability for the areas selected for inspection utilizes shutdownfrom outside the control room and is discussed in Section 1R05.01 of this report..07Circuit AnalysesThis topic was not inspected for plant in NFPA 805 transition.
Alternative shutdown capability for the areas selected for inspection utilizes shutdown from outside the control room and is discussed in Section 1R05.01 of this report.
 
===.07 Circuit Analyses===
 
This topic was not inspected for plant in NFPA 805 transition.


===.08 Communications===
===.08 Communications===


====a. Inspection Scope====
====a. Inspection Scope====
The team reviewed safe shutdown procedures, the safe shutdown analysis andassociated documents to verify an adequate method of communications would be available to plant operators following a fire. During this review the team considered the effects of ambient noise levels, clarity of reception, reliability and coverage patterns. The team also inspected the designated emergency storage lockers to verify the availability of portable radios for the fire brigade and for plant operators. The inspectorsalso verified that communications equipment such as repeaters, transmitters, etc. would not be affected by a fire.
The team reviewed safe shutdown procedures, the safe shutdown analysis and associated documents to verify an adequate method of communications would be available to plant operators following a fire. During this review the team considered the effects of ambient noise levels, clarity of reception, reliability and coverage patterns.
 
The team also inspected the designated emergency storage lockers to verify the availability of portable radios for the fire brigade and for plant operators. The inspectors also verified that communications equipment such as repeaters, transmitters, etc. would not be affected by a fire.


====b. Findings====
====b. Findings====
No findings of significance were identified..09Emergency Lighting
No findings of significance were identified.
 
===.09 Emergency Lighting===


====c. Inspection Scope====
====c. Inspection Scope====
The team observed the placement and coverage area of eight-hour emergency lightsthroughout the selected fire areas to evaluate their adequacy for illuminating access andegress pathways and any equipment requiring local operation and/or instrumentationmonitoring for post-fire safe shutdown. The team also verified that the battery power supplies were rated for at least an 8 hour capacity. Preventive maintenance procedures and various documents, including the vendors manual and completed surveillance testswere reviewed to ensure adequate surveillance testing and periodic batteryreplacements were in place to ensure reliable operation of the eight-hour emergency lights and that the emergency lighting units were being maintained consistent with themanufacturer's recommendations and accepted industry practices.
The team observed the placement and coverage area of eight-hour emergency lights throughout the selected fire areas to evaluate their adequacy for illuminating access and egress pathways and any equipment requiring local operation and/or instrumentation monitoring for post-fire safe shutdown. The team also verified that the battery power supplies were rated for at least an 8 hour capacity. Preventive maintenance procedures and various documents, including the vendors manual and completed surveillance tests were reviewed to ensure adequate surveillance testing and periodic battery replacements were in place to ensure reliable operation of the eight-hour emergency lights and that the emergency lighting units were being maintained consistent with the manufacturers recommendations and accepted industry practices.


====b. Findings====
====b. Findings====
No findings of significance were identified.
No findings of significance were identified.


8Enclosure.10Cold Shutdown Repairs
===.10 Cold Shutdown Repairs===


====a. Inspection Scope====
====a. Inspection Scope====
The team verified that the licensee had dedicated repair procedures, equipment, andmaterials to accomplish repairs of components required for cold shutdown which might be damaged by the fire to ensure cold shutdown could be achieved within the time frames specified in their design and licensing bases. The inspectors verified that the repair equipment, components, tools and materials (e.g. pre-cut cables with prepared attachment lugs) were available and accessible on site.
The team verified that the licensee had dedicated repair procedures, equipment, and materials to accomplish repairs of components required for cold shutdown which might be damaged by the fire to ensure cold shutdown could be achieved within the time frames specified in their design and licensing bases. The inspectors verified that the repair equipment, components, tools and materials (e.g. pre-cut cables with prepared attachment lugs) were available and accessible on site.


====b. Findings====
====b. Findings====
No findings of significance were identified..11Compensatory Measures
No findings of significance were identified.
 
===.11 Compensatory Measures===


====a. Inspection Scope====
====a. Inspection Scope====
The team verified that compensatory measures were in place for out-of-service,degraded or inoperable fire protection and post-fire safe shutdown equipment, systems,or features (e.g., detection and suppression systems and equipment, passive firebarriers, pumps, valves or electrical devices providing safe shutdown functions or capabilities). The team also verified that the short term compensatory measurescompensated for the degraded function or feature until appropriate corrective action could be taken and that Constellation was effective in returning the equipment to service in a reasonable period of time.
The team verified that compensatory measures were in place for out-of-service, degraded or inoperable fire protection and post-fire safe shutdown equipment, systems, or features (e.g., detection and suppression systems and equipment, passive fire barriers, pumps, valves or electrical devices providing safe shutdown functions or capabilities). The team also verified that the short term compensatory measures compensated for the degraded function or feature until appropriate corrective action could be taken and that Constellation was effective in returning the equipment to service in a reasonable period of time.


====b. Findings====
====b. Findings====
No findings of significance were identified.4.OTHER ACTIVITIES4OA2Identification and Resolution of Problems.01Corrective Actions for Fire Protection Deficiencies
No findings of significance were identified.
 
==OTHER ACTIVITIES==
{{a|4OA2}}
==4OA2 Identification and Resolution of Problems==
 
===.01 Corrective Actions for Fire Protection Deficiencies===


====a. Inspection Scope====
====a. Inspection Scope====
The team verified that the licensee was identifying fire protection and post-fire safeshutdown issues at an appropriate threshold and entering them into the corrective action program. The team also reviewed a sample of selected issues to verify that the licensee had taken or planned appropriate corrective actions. In addition, the team reviewed condition report CR-2006-002099 which documented alicensee-identified design deficiency that fire induced spurious actions in the control 9Enclosurecircuitry of 480V Bus 14 undervoltage relays could cause the "A" Charging Pump circuitbreaker to be in a "tripped" condition, preventing the pump from starting when it is required to be operable for hot shutdown. Since the "A" Charging Pump is the only credited charging pump for post-fire safe shutdown outside the control room, the safeshutdown capability could be impacted. The licensee determined this to be anunanalyzed condition and made an eight-hour notification to the NRC on May 18, 2006. The licensee's preliminary evaluation indicated that this issue could cause an increase in core damage frequency of approximately 1.2E-07 per year. Subsequently, during the extent of condition investigation, the licensee also identified(documented in CR 2006-002219) that fire induced spurious actions in the control circuitry of a relay associated with the safety injection signal could also have the same result, and that these spurious actions could also cause the standby auxiliary feedwaterpumps (SAFP) to be inoperable. The SAFPs are required for safe shutdown when the auxiliary feedwater pumps or the condensate storage tank are affected by a fire. The licensee initiated the necessary compensatory actions for correcting theseproblems by adding steps to three post-fire response procedures to defeat the potential fire induced spurious actions by removing the fuses of alternate DC power supplies to the affected relay control circuits. During the inspection, the team reviewed the following three affected procedures and verified that the necessary steps were incorporated into the procedures: ER.FIRE.1Alternate Shutdown For Control Complex Fire, Revision 20ER.FIRE.4Alternate Shutdown For Battery Room A Fire, Revision 16 ER.FIRE.5Alternate Shutdown For Battery Room B Fire, Revision 18
The team verified that the licensee was identifying fire protection and post-fire safe shutdown issues at an appropriate threshold and entering them into the corrective action program. The team also reviewed a sample of selected issues to verify that the licensee had taken or planned appropriate corrective actions.
 
In addition, the team reviewed condition report CR-2006-002099 which documented a licensee-identified design deficiency that fire induced spurious actions in the control circuitry of 480V Bus 14 undervoltage relays could cause the A Charging Pump circuit breaker to be in a tripped condition, preventing the pump from starting when it is required to be operable for hot shutdown. Since the A Charging Pump is the only credited charging pump for post-fire safe shutdown outside the control room, the safe shutdown capability could be impacted. The licensee determined this to be an unanalyzed condition and made an eight-hour notification to the NRC on May 18, 2006.
 
The licensees preliminary evaluation indicated that this issue could cause an increase in core damage frequency of approximately 1.2E-07 per year.
 
Subsequently, during the extent of condition investigation, the licensee also identified (documented in CR 2006-002219) that fire induced spurious actions in the control circuitry of a relay associated with the safety injection signal could also have the same result, and that these spurious actions could also cause the standby auxiliary feedwater pumps (SAFP) to be inoperable. The SAFPs are required for safe shutdown when the auxiliary feedwater pumps or the condensate storage tank are affected by a fire.
 
The licensee initiated the necessary compensatory actions for correcting these problems by adding steps to three post-fire response procedures to defeat the potential fire induced spurious actions by removing the fuses of alternate DC power supplies to the affected relay control circuits. During the inspection, the team reviewed the following three affected procedures and verified that the necessary steps were incorporated into the procedures:
ER.FIRE.1        Alternate Shutdown For Control Complex Fire, Revision 20 ER.FIRE.4        Alternate Shutdown For Battery Room A Fire, Revision 16 ER.FIRE.5        Alternate Shutdown For Battery Room B Fire, Revision 18


====b. Findings====
====b. Findings====
No findings of significance were identified. No enforcement action is required for theabove noncompliances (10 CFR 50, Appendix R, III.G.3 for Charging Pump "A" issue,and 10 CFR 50, Appendix R, III.G.2 for the SAFPs issue) because the conditions ofthese noncompliances meet the four criteria (licensee-identified, compensatory actionshave been taken, not likely to have been previously identified by routine licensee efforts, and not willful) of NRC Enforcement Policy, Interim Enforcement Policies, "InterimEnforcement Policy Regarding Enforcement Discretion for Certain Fire Protection Issues (10 CFR 50.48)", and are not associated with a finding of high safety significance.4OA6Meetings, Including ExitExit Meeting SummaryThe team presented their preliminary inspection results to Ms. M. Korsnick, Site VicePresident, and other members of the site staff at an exit meeting on June 23, 2006. No proprietary information was included in this inspection report.
No findings of significance were identified. No enforcement action is required for the above noncompliances (10 CFR 50, Appendix R, III.G.3 for Charging Pump A issue, and 10 CFR 50, Appendix R, III.G.2 for the SAFPs issue) because the conditions of these noncompliances meet the four criteria (licensee-identified, compensatory actions have been taken, not likely to have been previously identified by routine licensee efforts, and not willful) of NRC Enforcement Policy, Interim Enforcement Policies, Interim Enforcement Policy Regarding Enforcement Discretion for Certain Fire Protection Issues (10 CFR 50.48), and are not associated with a finding of high safety significance.
 
{{a|4OA6}}
==4OA6 Meetings, Including Exit==
 
===Exit Meeting Summary===
 
The team presented their preliminary inspection results to Ms. M. Korsnick, Site Vice President, and other members of the site staff at an exit meeting on June 23, 2006. No proprietary information was included in this inspection report.


KEY POINTS OF CONTACTLicensee PersonnelS. AdamsManager of OperationsD. BisaillonReactor Operator M. EdelsteinFire Protection System Engineer R. FellowsSenior Reactor Operator M. GreenQuality Performance Assessment T. HardingLicensing Supervisor D. HolmPlant Manager D. JoslinCommunications S. KennedyEmergency Preparedness M. KorsnickVice President, Ginna T. LaursenPerformance Improvement B. LeonardTraining Manager M. LilleyGeneral Supervisor, Equipment ReliabilityM. McGrawFire Protection System Engineer T. O'ConnerFire Protection Consultant J. PacherGeneral Supervisor, System Engineering J. PierceFire Protection Consultant R. RandallLicensing Director M. RubyLicensing Engineer J. SharlowOperations Fire Protection Specialist W. ThompsonGeneral Supervisor, Chemistry R. WhalenEngineering Manager S. WihlenFire Marshall D. WilsonPrincipal Engineer, BOP Systems NRCJ. Rogge, Chief, Electrical and Fire Protection Branch, Division of Reactor SafetyK. Kolaczyk, Senior Resident Inspector, Ginna Nuclear Power PlantM. Marshfield, Resident Inspector, Ginna Nuclear Power Plant 2AttachmentLIST OF ITEMS OPENED, CLOSED, AND DISCUSSED OpenedNoneOpen and Closed05000244/2006007-01 NCVMissed Fire Brigade Training ClosedNone DiscussedNone 3Attachment LIST OF  
KEY POINTS OF CONTACT Licensee Personnel S. Adams              Manager of Operations D. Bisaillon          Reactor Operator M. Edelstein          Fire Protection System Engineer R. Fellows            Senior Reactor Operator M. Green              Quality Performance Assessment T. Harding            Licensing Supervisor D. Holm              Plant Manager D. Joslin            Communications S. Kennedy            Emergency Preparedness M. Korsnick          Vice President, Ginna T. Laursen            Performance Improvement B. Leonard            Training Manager M. Lilley            General Supervisor, Equipment Reliability M. McGraw            Fire Protection System Engineer T. OConner          Fire Protection Consultant J. Pacher            General Supervisor, System Engineering J. Pierce            Fire Protection Consultant R. Randall            Licensing Director M. Ruby              Licensing Engineer J. Sharlow            Operations Fire Protection Specialist W. Thompson          General Supervisor, Chemistry R. Whalen            Engineering Manager S. Wihlen            Fire Marshall D. Wilson            Principal Engineer, BOP Systems NRC J. Rogge, Chief, Electrical and Fire Protection Branch, Division of Reactor Safety K. Kolaczyk, Senior Resident Inspector, Ginna Nuclear Power Plant M. Marshfield, Resident Inspector, Ginna Nuclear Power Plant LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED Opened None Open and Closed 05000244/2006007-01     NCV      Missed Fire Brigade Training Closed None Discussed None LIST OF  


=DOCUMENTS REVIEWED=
=DOCUMENTS REVIEWED=
Fire Protection Licensing DocumentsFire Protection Program
 
: [[contact::R. E. Ginna Nuclear Power Plant]], Revision 3aGinna UFSAR Sections 7.4 and 9.5
Fire Protection Licensing Documents
Letter From RGE to NRCAppendix R Alternative Shutdown System  
Fire Protection Program            
: [[contact::R. G. GinnaNuclear Power Plant]], January 16, 1985Safety Evaluation Report SER For Appendix R to 10CFR Part 50, Items III.G.3 andIII.L, February 27, 1985Appendix A to BTP APCSB 9.5-1 Guidelines for Fire Protection for Nuclear Power PlantsDocketed Prior to July 1, 1976.NFPA 27-1981Private Fire Brigades
: [[contact::R. E. Ginna Nuclear Power Plant]], Revision 3a
NFPA 600-2005Standard on Industrial Fire BrigadesCalculations/Engineering Evaluation ReportsDA-EE-2000-066Appendix R Conformance Analysis, Rev. 1DA-ME-98-004Combustible Loading Analysis, Rev. 4
Ginna UFSAR                         Sections 7.4 and 9.5
DA-ME-99-009Condensate Inventory Requirements for Station Blackout Event,Rev.0DA-ME-2000-001City Yard Loop Capability to Supply Cooling Water to EDG,SAFW and Fight Screen House Fire With a Loss of Service
Letter From RGE to NRC              Appendix R Alternative Shutdown System R. G. Ginna
Water, Rev. 3DA-ME-2000-075Pressurizer Volume Control Tank and RWST Evaluations forAppendix R, Rev. 2DA-NS-2002-008Operator Action Time Requirement Evaluation, Rev. 4
Nuclear Power Plant, January 16, 1985
FTI 32-5009845-00Approval of FTI Calculation 32-5009845-00 Ginna Safe ShutdownRELEPS Analysis, September 26, 2001NSL-4976-DA002Determination of Internal Flood Zones and Sources, Rev. 0
Safety Evaluation Report             SER For Appendix R to 10CFR Part 50, Items III.G.3 and
PCR 2005-0034Fire Harden "B" S/G Level Indication (EPU), Rev.0
III.L, February 27, 1985
PCR 2005-0010ADFCS I/O Power Supply Back-Up Provision and CoolingUpgrade, Rev.0DA-ME-2003-018Replacement of Appendix R Fire Barrier in the "B" DieselGenerator Vault, Rev.1DA-ME-1998-004Combustible Loading Analysis, Rev.4
Appendix A to BTP APCSB 9.5-1       Guidelines for Fire Protection for Nuclear Power Plants
DA-ME-2000-040City Water Yard Loop X-Tie to Fire Yard Loop HydraulicCalculation, Rev.1ProceduresA-54.7:1Fire Protection TourAP-CVCS.3Loss of All Charging Flow
Docketed Prior to July 1, 1976.
AP-IA.1Loss of Instrument Air, Rev. 18
NFPA 27-1981                        Private Fire Brigades
CME-50-02-52/EG1A1Corrective Maintenance Procedure: Westinghouse 480V AirCircuit Breaker, Type DB-75 Emergency Generator Breaker A
NFPA 600-2005                        Standard on Industrial Fire Brigades
Calculations/Engineering Evaluation Reports
DA-EE-2000-066              Appendix R Conformance Analysis, Rev. 1
DA-ME-98-004                Combustible Loading Analysis, Rev. 4
DA-ME-99-009                Condensate Inventory Requirements for Station Blackout Event,
Rev.0
DA-ME-2000-001              City Yard Loop Capability to Supply Cooling Water to EDG,
SAFW and Fight Screen House Fire With a Loss of Service
Water, Rev. 3
DA-ME-2000-075              Pressurizer Volume Control Tank and RWST Evaluations for
Appendix R, Rev. 2
DA-NS-2002-008              Operator Action Time Requirement Evaluation, Rev. 4
FTI 32-5009845-00            Approval of FTI Calculation 32-5009845-00 Ginna Safe Shutdown
RELEPS Analysis, September 26, 2001
NSL-4976-DA002              Determination of Internal Flood Zones and Sources, Rev. 0
PCR 2005-0034                Fire Harden B S/G Level Indication (EPU), Rev.0
PCR 2005-0010                ADFCS I/O Power Supply Back-Up Provision and Cooling
Upgrade, Rev.0
DA-ME-2003-018              Replacement of Appendix R Fire Barrier in the B Diesel
Generator Vault, Rev.1
DA-ME-1998-004              Combustible Loading Analysis, Rev.4
DA-ME-2000-040              City Water Yard Loop X-Tie to Fire Yard Loop Hydraulic
Calculation, Rev.1
Procedures
A-54.7:1                    Fire Protection Tour
AP-CVCS.3                    Loss of All Charging Flow
AP-IA.1                      Loss of Instrument Air, Rev. 18
CME-50-02-52/EG1A1          Corrective Maintenance Procedure: Westinghouse 480V Air
Circuit Breaker, Type DB-75 Emergency Generator Breaker A
Bus 14, Position 18C, Rev. 02
Bus 14, Position 18C, Rev. 02
4AttachmentCPI-APPX-R-SR-32Calibration of Appendix R Source Range, N32REOP ATT-11.2 Attachment Diesel Air Compressor, Rev. 5
 
ER-D/G.2Alternate Cooling For Emergency D/G, Rev. 16
CPI-APPX-R-SR-32 Calibration of Appendix R Source Range, N32R
ER-FIRE.0CR Response To Fire Alarms and Reports, Rev. 6
EOP ATT-11.2     Attachment Diesel Air Compressor, Rev. 5
ER.FIRE.6Response To Fire In D/G B Vault, Rev. 2
ER-D/G.2        Alternate Cooling For Emergency D/G, Rev. 16
FRP-4.0Auxiliary Building Basement, Rev. 5
ER-FIRE.0        CR Response To Fire Alarms and Reports, Rev. 6
FRP-8.0Intermediate Building Controlled Side Basement, Rev. 5
ER.FIRE.6        Response To Fire In D/G B Vault, Rev. 2
IP-CAP-1Ginna Station Interface Procedure: Condition Reporting, Rev. 24
FRP-4.0          Auxiliary Building Basement, Rev. 5
O-2.1Normal Shutdown To Hot Shutdown, Rev. 120
FRP-8.0          Intermediate Building Controlled Side Basement, Rev. 5
O-6.11Surveillance Requirement/Routine Operations Check Sheet, Rev. 146O-9.3NRC Immediate Notification, Rev. 55
IP-CAP-1        Ginna Station Interface Procedure: Condition Reporting, Rev. 24
SC-3.15.15Emergency Fire Equipment Inventory and Inspection, Rev. 84
O-2.1            Normal Shutdown To Hot Shutdown, Rev. 120
ND-FPPFire Protection Program, Rev.10
O-6.11          Surveillance Requirement/Routine Operations Check Sheet,
2The Fire Protection Program and Ginna Station StaffResponsibilities for Fire Protection, Rev.20, Rev.21A-103.9Fire Brigade Training, Rev.18
Rev. 146
A-905Open Flame, Welding and Grinding Permit (Hot Work Permit),Rev.34FPS-16Bulk Storage of Combustible Materials and Transient Fire Loads,Rev.9O-6.11Surveillance Requirement / Routine Operations Check Sheet,Rev.144A-54.7Fire Protection Tour, Rev.29
O-9.3            NRC Immediate Notification, Rev. 55
FPS-1Fire Barrier Control Procedure, Rev.9
SC-3.15.15      Emergency Fire Equipment Inventory and Inspection, Rev. 84
FPS-2Ginna Station Fire Barrier Penetration Seal Program, Rev.4
ND-FPP          Fire Protection Program, Rev.10
FPS-2.3Temporary Fire Barrier Penetration Seals Program, Rev.4
The Fire Protection Program and Ginna Station Staff
M-56.3Permanent Fire Barrier Penetration Seal Installation / Repair,Rev.26PT-13.1Annual Fire Pump Insurance Surveillance Test, Rev.34PT-13.4.20Flood Valve Testing - Suppression System #S09 Relay Room SEManual Deluge, Rev.19PT-13.4.21Flood Valve Testing - Suppression System #S10 Relay Room WManual Deluge, Rev.21PT-13.4.22Flood Valve Testing - Suppression System #S11 Relay Room NEManual Deluge, Rev.24QCIP-44Fire Barrier Inspection (Method and Acceptance), Rev.12
Responsibilities for Fire Protection, Rev.20, Rev.21
SC-3.16.2.8Fire Signaling System Maintenance, Rev.????
A-103.9          Fire Brigade Training, Rev.18
SC-3.15.5Emergency Fire Equipment Inventory and Inspection, Rev.84
Open Flame, Welding and Grinding Permit (Hot Work Permit),
SC-3Site Contingency Plan - SC-3 Fire Emergency Plan, Rev.38
Rev.34
SC-3.1Fire Emergency General Information, Rev.20
FPS-16          Bulk Storage of Combustible Materials and Transient Fire Loads,
SC-3.1.1Fire Alarm Response (Fire Brigade Activation), Rev.17
Rev.9
SC-3.4.0Fire Assessment and Subsequent Actions, Rev.22
O-6.11          Surveillance Requirement / Routine Operations Check Sheet,
SC-3.4.1Fire Brigade Captain and Control Room PersonnelResponsibilities, Rev.37IP-RDM-3Ginna Records, Rev.13
Rev.144
5AttachmentCompleted Tests/SurveillancesO-6.11Surveillance Requirement/Routing Operations Check Sheet, Rev. 146, Completed March 2006SC-3.15.15Emergency Fire Equipment Inventory and Inspection, Rev. 84,Completed 4/10/06, 5/
A-54.7          Fire Protection Tour, Rev.29
9/06, 5/31/06 and 6/2/06FPS-2.1Control and Verification of UFSAR and/or 10CFR50 Appendix RFire Barriers, Rev.6, 09/14/05, 11/28/05FPS-7Velocity Flush of the Fire Water System, Rev.9, 05/12/06 andRev.5, 10/25/02M-56.1Establishment of Temporary Fire Seals, Rev.27, 04/21/06
FPS-1            Fire Barrier Control Procedure, Rev.9
PT-13.11Gamewell Zone Smoke Detector Testing Zones Z01 (Aux. Base.East), Rev.20, 12/15/04PT-13.11.26Testing of Smoke Detection Zone Z-44 Relay Room Annex,Rev.???, 01/10/06PT-13.11.6.1Testing of Smoke Detection Zone Z38D1 Intermediate Building -South Basement, Rev.0, 05/11/06PT-13.4.29Halon System Testing Relay Room / Computer Room (S08),Rev.24, 08/15/05PT-13.4.33Station Halon Systems Bottle Weighing and S08 (Relay Roomand Computer Room) Air Flow Test, Rev.24, 04/25/05PT-13.1Annual Fire Pump Insurance Surveillance Test, Rev.32, 12/21/05and Rev.31, 12/20/04PT-13.11.2Gamewell Zone Smoke Detector Testing Zones Z20 ("A' D/GVault), Z21 ("B" DG Vault). Rev.17, 05/17/05PT-13.10Fire System Spray Nozzle Air Flow Test for S05, S06, S09, S10,S11, S14, S17 and S29, Rev.17, 12/08/05P201504ECAD Testing on "A" EDG CablesQuality Assurance (QA) Audits and System Health ReportsFPP-05-01-GFire Protection Report Audit, August 2, 2005SA 2006-0005Fire Program, March 23, 2006
FPS-2            Ginna Station Fire Barrier Penetration Seal Program, Rev.4
Audit FPP-05-01-GFire Protection, completed 08/02/05
FPS-2.3          Temporary Fire Barrier Penetration Seals Program, Rev.4
SA 2006-0005Fire Program Assessment Report, completed 03/23/06SQUA-2004-0013-MPHSQUA-2004-0142-ENB
M-56.3          Permanent Fire Barrier Penetration Seal Installation / Repair,
Rev.26
PT-13.1          Annual Fire Pump Insurance Surveillance Test, Rev.34
PT-13.4.20      Flood Valve Testing - Suppression System #S09 Relay Room SE
Manual Deluge, Rev.19
PT-13.4.21      Flood Valve Testing - Suppression System #S10 Relay Room W
Manual Deluge, Rev.21
PT-13.4.22      Flood Valve Testing - Suppression System #S11 Relay Room NE
Manual Deluge, Rev.24
QCIP-44          Fire Barrier Inspection (Method and Acceptance), Rev.12
SC-3.16.2.8      Fire Signaling System Maintenance, Rev.????
SC-3.15.5        Emergency Fire Equipment Inventory and Inspection, Rev.84
SC-3            Site Contingency Plan - SC-3 Fire Emergency Plan, Rev.38
SC-3.1          Fire Emergency General Information, Rev.20
SC-3.1.1        Fire Alarm Response (Fire Brigade Activation), Rev.17
SC-3.4.0        Fire Assessment and Subsequent Actions, Rev.22
SC-3.4.1        Fire Brigade Captain and Control Room Personnel
Responsibilities, Rev.37
IP-RDM-3        Ginna Records, Rev.13
 
Completed Tests/Surveillances
O-6.11                      Surveillance Requirement/Routing Operations Check Sheet,
Rev. 146, Completed March 2006
SC-3.15.15                  Emergency Fire Equipment Inventory and Inspection, Rev. 84,
Completed 4/10/06, 5/9/06, 5/31/06 and 6/2/06
FPS-2.1                    Control and Verification of UFSAR and/or 10CFR50 Appendix R
Fire Barriers, Rev.6, 09/14/05, 11/28/05
FPS-7                      Velocity Flush of the Fire Water System, Rev.9, 05/12/06 and
Rev.5, 10/25/02
M-56.1                      Establishment of Temporary Fire Seals, Rev.27, 04/21/06
PT-13.11                    Gamewell Zone Smoke Detector Testing Zones Z01 (Aux. Base.
East), Rev.20, 12/15/04
PT-13.11.26                Testing of Smoke Detection Zone Z-44 Relay Room Annex,
Rev.???, 01/10/06
PT-13.11.6.1                Testing of Smoke Detection Zone Z38D1 Intermediate Building -
South Basement, Rev.0, 05/11/06
PT-13.4.29                  Halon System Testing Relay Room / Computer Room (S08),
Rev.24, 08/15/05
PT-13.4.33                  Station Halon Systems Bottle Weighing and S08 (Relay Room
and Computer Room) Air Flow Test, Rev.24, 04/25/05
PT-13.1                    Annual Fire Pump Insurance Surveillance Test, Rev.32, 12/21/05
and Rev.31, 12/20/04
PT-13.11.2                  Gamewell Zone Smoke Detector Testing Zones Z20 (A D/G
Vault), Z21 (B DG Vault). Rev.17, 05/17/05
PT-13.10                    Fire System Spray Nozzle Air Flow Test for S05, S06, S09, S10,
S11, S14, S17 and S29, Rev.17, 12/08/05
P201504                    ECAD Testing on A EDG Cables
Quality Assurance (QA) Audits and System Health Reports
FPP-05-01-G                Fire Protection Report Audit, August 2, 2005
SA 2006-0005                Fire Program, March 23, 2006
Audit FPP-05-01-G          Fire Protection, completed 08/02/05
SA 2006-0005                Fire Program Assessment Report, completed 03/23/06
SQUA-2004-0013-MPH
SQUA-2004-0142-ENB
SQUA-2005-0050-EMG
SQUA-2005-0050-EMG
6AttachmentDrawings21488-0100Fire Barrier Arrangement Sheet Fire, Smoke and Pressure BarrierPlan View El.253'6", Rev.1021488-0111Fire Barrier General Arrangement Sheet Diesel Generator RoomB West and South Walls Penetrations Location Floor El.253'6",
 
Rev.533013-2559Fire Response Plan Control Building, Rev.8
Drawings
33013-1993 Sh.2Fire Service Water Header "B", Rev.9
21488-0100      Fire Barrier Arrangement Sheet Fire, Smoke and Pressure Barrier
33013-15371B Diesel Generator Cable Vault Appendix "R" Cable Chase FireBarrier, Rev.433013-1242Fire Protection Relay and Multiplexer Rooms, Rev.5
Plan View El.253'6", Rev.10
33013-1989Fire Service Water Plant Systems, Rev.22
21488-0111      Fire Barrier General Arrangement Sheet Diesel Generator Room
2013-2539AC System Plant Load Distribution One Line Diagram, Rev.13
B West and South Walls Penetrations Location Floor El.253'6",
33013-2543Fire Response Plan Auxiliary Building Plan - Basement FloorEl.253'8", Rev.233013-2544Fire Response Plan Turbine Building Plan - Basement FloorEl.253'6", Rev.933013-2545Fire Response Plan Containment Structure & Intermediate Bldg.Plan - Intermediate Floor El. 253'3", Rev.833013-2559Fire Response Plan Control Building Plan Views, Rev.8
Rev.5
21946-0445Standby Auxiliary Feedwater Pump C Control Schematic33013-1736Diesel Generator A Control Schematic, Rev. 14
33013-2559      Fire Response Plan Control Building, Rev.8
21946-0650TDAFW Pump Steam Supply Valve MOV-3504A ControlSchematic, Rev. 821946-0651TDAFW Pump Steam Supply Valve MOV-3505A ControlSchematic, Rev. 721946-0054480V Bus 14 PT and UV Relays Control Schematic, Revision 5
33013-1993 Sh.2 Fire Service Water Header B, Rev.9
21946-0055480V Bus 16 PT and UV Relays Control Schematic, Revision 6
33013-1537      1B Diesel Generator Cable Vault Appendix R Cable Chase Fire
21946-0445Standby Auxiliary Feedwater Pump C Control Schematic,Revision 621946-0446Standby Auxiliary Feedwater Pump D Control Schematic,Revision 510909-34Bus 14 and Bus 16 Undervoltage Control, Revision 4
Barrier, Rev.4
10905-54, Sh 1Undervoltage Scheme, Bus 14 Elementary Wiring Diagram,Undervoltage Scheme Bus 14, Revision 1110905-54, Sh 2Auxiliary Relay Rack Elementary Wiring Diagram, Revision 1510905-54, Sh 3PT and UV Relays, Bus 14, Elementary Wiring Diagram, Revision
33013-1242      Fire Protection Relay and Multiplexer Rooms, Rev.5
21498-511Appendix R Instrument Panels Wiring diagram, Rev.6
33013-1989      Fire Service Water Plant Systems, Rev.22
11302-0381Steam Generator A Pressure Loop PT-482 Inst Loop WiringDiagram, Rev.111302-0382Steam Generator B Pressure Loop PT-483 Inst Loop WiringDiagram, Rev.211302-0359Steam Generator A Level Loop LT-460 Inst Loop Wiring Diagram,Rev.1
2013-2539      AC System Plant Load Distribution One Line Diagram, Rev.13
7Attachment11302-0371Steam Generator B Level Loop LT-470 Inst Loop Wiring Diagram,Rev.111302-0323Pressurizer Level Loop LT-433 Inst Loop Wiring Diagram, Rev.1
33013-2543      Fire Response Plan Auxiliary Building Plan - Basement Floor
10905-0445Standby Auxiliary Feedwater Pump C Elementary WiringDiagram, Rev. 610905-0446Standby Auxiliary Feedwater Pump D Elementary WiringDiagram, Rev. 5Pre-Fire PlansFire Response Plan FRP-4.0Auxiliary Building Basement, Rev.5Fire Response Plan FRP-8.0Intermediate Building Controlled Side Basement, Rev.5
El.253'8", Rev.2
Fire Response Plan FRP-19.0Relay Room/Multiplex Room/Annex Room, Rev.8
33013-2544      Fire Response Plan Turbine Building Plan - Basement Floor
Fire Response Plan FRP-25.0Diesel Generator Room B and Vault, Rev.6Piping and Instrumentation Diagrams (P&IDs)33013-1234Condensate Storage (CDST), Rev. 3133013-1237Auxiliary Feedwater (FW), Rev. 5233013-1238Standby Auxiliary Feedwater (FW), Rev. 2433013-1258Reactor Coolant Pressurizer (RC), Rev. 24
El.253'6", Rev.9
33013-1260Reactor Coolant (RC), Rev. 25
33013-2545      Fire Response Plan Containment Structure & Intermediate Bldg.
33013-1265, Sh. 1Chemical & Volume Control System Charging, Rev. 11
Plan - Intermediate Floor El. 253'3", Rev.8
33013-1265 Sh.2Auxiliary Building Chemical & Volume Control System Charging,Rev. 1733013-1237Auxiliary Feedwater, Revision 52Fire Brigade DocumentsFire Area/Zone Analysis for Fire Areas/Zones ABI/IBS-1, CC/RR, CHG/- and EDG1B/-
33013-2559      Fire Response Plan Control Building Plan Views, Rev.8
Fire Brigade Dr
21946-0445      Standby Auxiliary Feedwater Pump C Control Schematic
illsFire Brigade Drills for calendar years 2004, 2005 and 2006Fire Brigade TrainingFire Brigade Training documentsFire Brigade Qualification documents
33013-1736      Diesel Generator A Control Schematic, Rev. 14
nd Quarter 2006 Fire Brigade Member ExaminationsOperator Safe Shutdown TrainingAppendix R Composite Operator Time/Motion Study, May 16, 2006RER22C Site Contingencies, Appendix R - Alternative Shutdown, Rev. 8
21946-0650      TDAFW Pump Steam Supply Valve MOV-3504A Control
8AttachmentJob Performance Measures (JPMs)JC012.007Locally Trip Reactor And Turbine, Rev. 5JC039.003Locally Operate The ARVs, Rev. 9
Schematic, Rev. 8
JC061.005Reset TDAFW Pump Turbine Trip/Throttle Valve, Rev. 7
21946-0651      TDAFW Pump Steam Supply Valve MOV-3505A Control
JC079.001Startup and Align Diesel Driven Air Compressor, Rev. 8
Schematic, Rev. 7
JR004.009Take Local Manual Control of Charging Pump, Rev. 6
21946-0054      480V Bus 14 PT and UV Relays Control Schematic, Revision 5
JR039.001Locally Close MSIV's, Rev. 10
21946-0055      480V Bus 16 PT and UV Relays Control Schematic, Revision 6
JR061.008Open TDAFW Pump Supply Valves, Rev. 8
21946-0445      Standby Auxiliary Feedwater Pump C Control Schematic,
JR062.006Locally Operate 480 VAC Breakers, Rev. 9
Revision 6
JR064.004EDG Locally Per ER-FIRE.1 With No Faults, Rev. 15Hot Work and Ignition Source PermitsHWP 06-50HWP 06-51
21946-0446      Standby Auxiliary Feedwater Pump D Control Schematic,
Revision 5
10909-34        Bus 14 and Bus 16 Undervoltage Control, Revision 4
10905-54, Sh 1  Undervoltage Scheme, Bus 14 Elementary Wiring Diagram,
Undervoltage Scheme Bus 14, Revision 11
10905-54, Sh 2  Auxiliary Relay Rack Elementary Wiring Diagram, Revision 15
10905-54, Sh 3  PT and UV Relays, Bus 14, Elementary Wiring Diagram, Revision
21498-511      Appendix R Instrument Panels Wiring diagram, Rev.6
11302-0381      Steam Generator A Pressure Loop PT-482 Inst Loop Wiring
Diagram, Rev.1
11302-0382      Steam Generator B Pressure Loop PT-483 Inst Loop Wiring
Diagram, Rev.2
11302-0359      Steam Generator A Level Loop LT-460 Inst Loop Wiring Diagram,
Rev.1
 
11302-0371                    Steam Generator B Level Loop LT-470 Inst Loop Wiring Diagram,
Rev.1
11302-0323                    Pressurizer Level Loop LT-433 Inst Loop Wiring Diagram, Rev.1
10905-0445                    Standby Auxiliary Feedwater Pump C Elementary Wiring
Diagram, Rev. 6
10905-0446                    Standby Auxiliary Feedwater Pump D Elementary Wiring
Diagram, Rev. 5
Pre-Fire Plans
Fire Response Plan FRP-4.0            Auxiliary Building Basement, Rev.5
Fire Response Plan FRP-8.0            Intermediate Building Controlled Side Basement, Rev.5
Fire Response Plan FRP-19.0            Relay Room/Multiplex Room/Annex Room, Rev.8
Fire Response Plan FRP-25.0            Diesel Generator Room B and Vault, Rev.6
Piping and Instrumentation Diagrams (P&IDs)
33013-1234                    Condensate Storage (CDST), Rev. 31
33013-1237                    Auxiliary Feedwater (FW), Rev. 52
33013-1238                    Standby Auxiliary Feedwater (FW), Rev. 24
33013-1258                    Reactor Coolant Pressurizer (RC), Rev. 24
33013-1260                    Reactor Coolant (RC), Rev. 25
33013-1265, Sh. 1              Chemical & Volume Control System Charging, Rev. 11
33013-1265 Sh.2                Auxiliary Building Chemical & Volume Control System Charging,
Rev. 17
33013-1237                    Auxiliary Feedwater, Revision 52
Fire Brigade Documents
Fire Area/Zone Analysis for Fire Areas/Zones ABI/IBS-1, CC/RR, CHG/- and EDG1B/-
Fire Brigade Drills
Fire Brigade Drills for calendar years 2004, 2005 and 2006
Fire Brigade Training
Fire Brigade Training documents
Fire Brigade Qualification documents
2nd Quarter 2006 Fire Brigade Member Examinations
Operator Safe Shutdown Training
Appendix R Composite Operator Time/Motion Study, May 16, 2006
RER22C Site Contingencies, Appendix R - Alternative Shutdown, Rev. 8
 
Job Performance Measures (JPMs)
JC012.007      Locally Trip Reactor And Turbine, Rev. 5
JC039.003      Locally Operate The ARVs, Rev. 9
JC061.005      Reset TDAFW Pump Turbine Trip/Throttle Valve, Rev. 7
JC079.001      Startup and Align Diesel Driven Air Compressor, Rev. 8
JR004.009      Take Local Manual Control of Charging Pump, Rev. 6
JR039.001      Locally Close MSIVs, Rev. 10
JR061.008      Open TDAFW Pump Supply Valves, Rev. 8
JR062.006      Locally Operate 480 VAC Breakers, Rev. 9
JR064.004      EDG Locally Per ER-FIRE.1 With No Faults, Rev. 15
Hot Work and Ignition Source Permits
HWP 06-50
HWP 06-51
HWP 06-52
HWP 06-52
HWP 06-53
HWP 06-53
HWP 06-54
HWP 06-54
HWP 06-55Transient Combustible EvaluationsTCP 06-26TCP 06-27
HWP 06-55
Transient Combustible Evaluations
TCP 06-26
TCP 06-27
TCP 06-28
TCP 06-28
TCP 06-29
TCP 06-29
TCP 06-30Fire BarriersPenetration Seal DatabaseTemporary Fire Barrier I-590-P
TCP 06-30
Fire Barriers
Penetration Seal Database
Temporary Fire Barrier I-590-P
Temporary Fire Barrier D-41-P
Temporary Fire Barrier D-41-P
Fire Barrier Permit 06-03, 05/02/06
Fire Barrier Permit 06-03, 05/02/06
Fire Barrier Permit 06-13, 06/01/06
Fire Barrier Permit 06-13, 06/01/06
Spec IBD23A-703, IBD23 Style A Curtain Type Static Fire Dampers, 2003Miscellaneous DocumentsGinna Station EPU Licensing Report Fire Protection, December 2005Ginna Station EPU Licensing Report Risk Evaluation of EPU, December 2005
Spec IBD23A-703, IBD23 Style A Curtain Type Static Fire Dampers, 2003
Miscellaneous Documents
Ginna Station EPU Licensing Report Fire Protection, December 2005
Ginna Station EPU Licensing Report Risk Evaluation of EPU, December 2005
Emergency Lighting Service Manual for ALC-X Series I, AS Series I, ED Series I VTD-D1140-
Emergency Lighting Service Manual for ALC-X Series I, AS Series I, ED Series I VTD-D1140-
201 Revision 000 VM#D1140-0377 Tab 2
201 Revision 000 VM#D1140-0377 Tab 2
Line 241: Line 491:
160 BCI, 12 AS-160 BCI, 12 AS-200 BXI, GMMEL-SD4 Instructions for Installation, Operation,
160 BCI, 12 AS-160 BCI, 12 AS-200 BXI, GMMEL-SD4 Instructions for Installation, Operation,
Service
Service
9AttachmentDual-Lite Spectron Series Emergency Lighting Equipment Series: ALC-X-I, AS-BC/BX-1, AS-I,EDC-X-I, EDN-I Instructions for Installation, Operation, Maintenance
 
Equipment History Report: 52/EG1A1, 52/EG1A2, 52/EG1B1, 52/EG1A2Equipment History Report: 52/SWP1A, 52/SWP1B
Dual-Lite Spectron Series Emergency Lighting Equipment Series: ALC-X-I, AS-BC/BX-1, AS-I,
EDC-X-I, EDN-I Instructions for Installation, Operation, Maintenance
Equipment History Report: 52/EG1A1, 52/EG1A2, 52/EG1B1, 52/EG1A2
Equipment History Report: 52/SWP1A, 52/SWP1B
Equipment History Report: 52/CHP1A, 52/CHP1B
Equipment History Report: 52/CHP1A, 52/CHP1B
Equipment History Report: 52/SWP1C
Equipment History Report: 52/SWP1C
Line 252: Line 505:
Fire Protection Program Transition Plan
Fire Protection Program Transition Plan
Fire Protection Program Impairment Tracking System
Fire Protection Program Impairment Tracking System
Test Gauge Calibration Data sheet, 06/21/06Condition Reports2003-1376   2003-1478  2003-2227   2003-3333   2004-0104  2004-0190   2004-16912004-1878   2004-2663  2004-3178   2005-0712   2005-3158  2005-3179   2005-3188
Test Gauge Calibration Data sheet, 06/21/06
2005-4462   2005-4501  2005-4737   2005-4739   2005-4928  2005-5139   2005-5308
Condition Reports
2005-6217   2006-0785  2006-0891   2006-0905   2006-0941  2006-0962   2006-0956
2003-1376   2003-1478  2003-2227 2003-3333       2004-0104  2004-0190 2004-1691
2006-1040   2006-1363  2006-2368   2003-2785   2005-0682  2003-2994   2005-3190
2004-1878   2004-2663  2004-3178 2005-0712       2005-3158  2005-3179 2005-3188
2004-0010   2005-3191  2005-3190 2005-4936   2005-0616   2005-5119   2006-0883
2005-4462   2005-4501  2005-4737 2005-4739       2005-4928  2005-5139 2005-5308
2006-2375* 2006-0889   2006-2412* 2006-0941   2006-2409* 2006-0957   2006-2406*
2005-6217   2006-0785  2006-0891 2006-0905       2006-0941  2006-0962 2006-0956
2006-1618   2006-2407*  2006-2356* 2006-2366* 2006-2367*  2006-2363* 2006-2380*Work Orders
2006-1040   2006-1363  2006-2368 2003-2785       2005-0682  2003-2994 2005-3190
20002696 20505059
2004-0010   2005-3191  2005-3190 2005-4936       2005-0616       2005-5119 2006-0883
2006-2375*   2006-0889 2006-2412* 2006-0941     2006-2409*   2006-0957 2006-2406*
2006-1618   2006-2407*  2006-2356* 2006-2366*     2006-2367*  2006-2363* 2006-2380*
Work Orders
20002696
20505059
20505098
20505098
10AttachmentLIST OF ACRONYMS USEDACAlternating CurrentCFRCode of Federal Regulations
 
CO 2 Carbon DioxideCR Condition Report
LIST OF ACRONYMS USED
DCDirect Current
AC    Alternating Current
DRSDivision of Reactor Safety
CFR  Code of Federal Regulations
FAFire Area
CO2  Carbon Dioxide
FHAFire Hazards Analysis
CR    Condition Report
FPPFire Protection Program
DC    Direct Current
FZFire Zone
DRS  Division of Reactor Safety
IMCInspection Manual Chapter
FA    Fire Area
IPInspection Procedure
FHA  Fire Hazards Analysis
IPEIndividual Plant Examination
FPP  Fire Protection Program
IPEEEIndividual Plant Examination of External Events
FZ    Fire Zone
IRInspection Report
IMC  Inspection Manual Chapter
NCVNon-cited Violation
IP    Inspection Procedure
NFPANational Fire Protection Association
IPE  Individual Plant Examination
NRCNuclear Regulatory Commission
IPEEE Individual Plant Examination of External Events
PARSPublicly Available Records
IR    Inspection Report
P&IDPiping and Instrumentation Drawing
NCV  Non-cited Violation
SAFPStanby Auxiliary Feedwater PumpsSCBASelf Contained Breathing Apparatus
NFPA  National Fire Protection Association
SDPSignificance Determination Process
NRC  Nuclear Regulatory Commission
SESafety Evaluation
PARS  Publicly Available Records
SSCStructures, Systems, and Components
P&ID  Piping and Instrumentation Drawing
UFSARUpdated Final Safety Analysis Report
SAFP  Stanby Auxiliary Feedwater Pumps
SCBA  Self Contained Breathing Apparatus
SDP  Significance Determination Process
SE    Safety Evaluation
SSC  Structures, Systems, and Components
UFSAR Updated Final Safety Analysis Report
Attachment
}}
}}

Revision as of 15:34, 23 November 2019

IR 05000244-06-007; on 06/05 - 23/2006; Ginna Nuclear Power Plant; Triennial Fire Protection Team Inspection, Fire Protection
ML062150459
Person / Time
Site: Ginna Constellation icon.png
Issue date: 08/03/2006
From: Rogge J
Engineering Region 1 Branch 3
To: Korsnick M
Ginna
References
IR-06-007
Download: ML062150459 (26)


Text

ust 3, 2006

SUBJECT:

GINNA NUCLEAR POWER PLANT- NRC TRIENNIAL FIRE PROTECTION INSPECTION REPORT 05000244/2006007

Dear Mrs. Korsnick:

On June 23, 2006, the NRC completed a triennial fire protection team inspection at your R. E.

Ginna facility. The enclosed report documents the inspection results which were discussed on June 23, 2006, with you and other members of your staff.

The inspection examined activities conducted under your license as they relate to safety and compliance with the Commissions rules and regulations and with the conditions of your license.

The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.

Based on the results of this inspection, the NRC identified one finding of very low safety significance (Green) that was a violation of NRC requirements. However, because of the very low safety significance and because it is entered into your corrective action program, the NRC is treating this finding as a non-cited violation (NCV) consistent with Section VI.A.1 of the NRC Enforcement Policy. If you contest the NCV in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001 with copies to the Regional Administrator Region I, the Director, Office of Enforcement, United States Nuclear Regulatory Commission, Washington, DC 20555-0001, and the NRC Resident Inspector at the Ginna Nuclear Power Plant.

The enclosed report also documented two noncompliances that were identified by your staff during the NFPA 805 transition period. The NRC is not taking any enforcement actions for these noncompliances because the conditions for these noncompliances meet the four criteria (licensee-identified, compensatory actions have been taken, not likely to have been previously identified by routine licensee efforts, and not willful) of NRC Enforcement Policy, Interim Enforcement Policies, Interim Enforcement Policy Regarding Enforcement Discretion for Certain Fire Protection Issues (10 CFR 50.48), and are not associated with a finding of high safety significance.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and your response (if any) will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/ADAMS.html (the Public Electronic Reading Room).

Sincerely,

/RA/

John F. Rogge, Chief Engineering Branch 3 Division of Reactor Safety Docket Nos. 50-244 License Nos. DPR-18

Enclosure:

NRC Inspection Report 05000244/2006007

REGION I==

Docket Nos. 50-244 License Nos. DPR-18 Report No. 05000244/2006007 Licensee: Constellation Energy, R. E. Ginna Nuclear Power Plant, LLC Facility: R. E. Ginna Nuclear Power Plant Location: Ontario, New York Dates: June 5 - 23, 2006 Inspectors: L. Cheung, Senior Reactor Inspector, DRS P. Finney, Reactor Inspector, DRS K. Young, Senior Reactor Inspector, DRS A. Gaudette, Inspector Trainee, DRP Approved by: John F. Rogge, Chief Engineering Branch 3 Division of Reactor Safety Enclosure

SUMMARY OF FINDINGS

IR 05000244/2006007 on 06/05 - 23/ 2006, Ginna Nuclear Power Plant; Triennial Fire

Protection Team Inspection, Fire Protection.

This report covered a two-week triennial fire protection team inspection by three Region I specialist inspectors and one inspector trainee. One Green non-cited violation (NCV) was identified. The significance of most findings is indicated by their color (Green, White, Yellow,

Red) using Inspection Manual Chapter (IMC) 0609, Significance Determination Process (SDP). Findings for which the SDP does not apply may be Green or be assigned a severity level after NRC management review. The NRCs program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649, Reactor Oversight Process,

Revision 3, dated July 2000.

NRC-Identified Findings

Cornerstone: Mitigating Systems

Green.

The team identified an NCV of license condition 2.C.3 for the failure to implement and maintain in effect all fire protection features. Specifically, Constellation failed to provide the required quarterly training to five fire brigade members in the fourth quarter of 2005, and subsequently failed to remove those personnel from fire brigade duty during the period from January 1, 2006, to the time when those brigade members received their remedial training. Site procedures require that fire brigade members attend quarterly classroom training, and that fire brigade members who fail to attend such training be removed from brigade duties until they attend remedial training. Upon identification of this finding, Constellation removed all five personnel from fire brigade duties until properly trained, initiated a prompt investigation and entered this finding into their corrective action program.

The finding is more than minor because the finding is associated with the Mitigating System cornerstone attribute of protection against external factors and affected the cornerstone objective of ensuring the availability, reliability and capability of systems that respond to initiating events to prevent undesirable consequences. The Assumptions and Limitations of the Fire Protection Significance Determination Process (SDP), IMC 0609, Appendix F, specifically exclude fire brigade issues. As such, IMC 0612, Section 05.04.c, requires NRC management review to determine the significance of this finding.

NRC management determined this finding to be of very low safety significance (Green).

Fire brigade performance was not significantly affected, given staffing, at times, by members that lacked a single quarter of training, because the entire brigade staff had completed the annual live-fire practice sessions. (Section 1R05.04)

Licensee-Identified Violations

None.

ii

REPORT DETAILS

Background This report presents the results of a triennial fire protection inspection conducted in accordance with NRC Inspection Procedure (IP) 71111.05TTP, Fire Protection. The objective of the inspection was to assess whether Constellation Energy has implemented an adequate fire protection program and that post-fire safe shutdown capabilities have been established and are being properly maintained at the R. E. Ginna Nuclear Power Plant facility. The following fire areas (FAs) were selected for detailed review based on risk insights from the Individual Plant Examination (IPE)/ Individual Plant Examination of External Events (IPEEE):

Fire Area RRA, Fire Area CHG, Fire Area EDG1B-0, Fire Area IBS-1.

The inspection team evaluated the licensees fire protection program (FPP) against applicable requirements which include plant Technical Specifications, Operating License Condition 2.C.3, NRC Safety Evaluations, 10 CFR 50.48 and 10 CFR 50 Appendix R. The team also reviewed related documents that include the Updated Final Safety Analysis Report (UFSAR) Section 9.5, the Fire Hazards Analysis (FHA) and the Post-Fire Safe Shutdown

Analysis.

Specific documents reviewed by the team are listed in the attachment.

REACTOR SAFETY

Cornerstones: Initiating Events, Mitigating Systems

1R05 Fire Protection

.01 Post-Fire Safe Shutdown From Outside Main Control Room (Alternative Shutdown) and

Normal Shutdown

a. Inspection Scope

Methodology The team reviewed the safe shutdown analysis, operating procedures, piping and instrumentation drawings (P&IDs), electrical drawings, the UFSAR and other supporting documents to verify that hot and cold shutdown could be achieved and maintained from outside the control room for fires that rely on shutdown from outside the control room.

This review included verification that shutdown from outside the control room could be performed both with and without the availability of offsite power. Plant walkdowns were also performed to verify that the plant configuration was consistent with that described in the safe shutdown and fire hazards analyses. These inspection activities focused on ensuring the adequacy of systems selected for reactivity control, reactor coolant makeup, reactor decay heat removal, process monitoring instrumentation and support systems functions. The team verified that the systems and components credited for use during this shutdown method would remain free from fire damage.

Similarly, for fire areas that utilize shutdown from the control room, the team also verified that the shutdown methodology properly identified the components and systems necessary to achieve and maintain safe shutdown conditions.

Operational Implementation The team verified that the training program for licensed and non-licensed operators included alternative shutdown capability. The team also verified that personnel required for safe shutdown using the normal or alternative shutdown systems and procedures are trained and available onsite at all times, exclusive of those assigned as fire brigade members.

The team reviewed the adequacy of procedures utilized for post-fire shutdown and performed an independent walk through of procedure steps to ensure the implementation and human factors adequacy of the procedures. The team also verified that the operators could be reasonably expected to perform specific actions within the time required to maintain plant parameters within specified limits. Time critical actions which were verified included restoration of AC electrical power, establishing the remote shutdown and local shutdown panels, establishing reactor coolant makeup, and establishing decay heat removal.

Specific procedures reviewed for alternative shutdown, including shutdown from outside the control room included the following:

C ER-FIRE.1, Alternate Shutdown For Control Complex Fire, Revision 20 C FRP-4.0, Auxiliary Building Basement, Revision 5 C FRP-8.0, Intermediate Building Controlled Side Basement, Revision 5 C ER-FIRE.6, Response To Fire In D/G B Vault, Revision 2 C O-2.1, Normal Shutdown To Hot Shutdown, Revision 120 C ER-FIRE.0, CR Response To Fire Alarms and Reports, Revision 6 The team reviewed manual actions to ensure that they could be implemented in accordance with plant procedures in the time necessary to support the safe shutdown method for each fire area. The team verified that the licensee had identified operator manual actions for post-fire safe-shutdown and had plans in place to assess them as part of the plant wide risk evaluation for transition to NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants, 2001 Edition. The team also reviewed the periodic testing of the alternative shutdown transfer capability and instrumentation and control functions to ensure the tests are adequate to ensure the functionality of the alternative shutdown capability.

b. Findings

No findings of significance were identified.

.02 Protection of Safe Shutdown Capabilities

b. Inspection Scope

The team reviewed the fire hazards analysis, safe shutdown analyses and supporting drawings and documentation to verify that safe shutdown capabilities were properly protected. Under the NFPA 805 Transition Period inspection procedure, the inspection team is to validate 1 to 3 nonconformances identified in the licensees transitional assessment of their fire areas. It is noted, as directed by and in accordance with the inspection procedure, that no fire areas have been completely assessed at the time of this inspection.

The team reviewed the licensee procedures and programs for the control of ignition sources and transient combustibles to assess their effectiveness in preventing fires and in controlling combustible loading within limits established in the FHA. A sample of hot work and transient combustible control permits were also reviewed. The team performed plant walkdowns to verify that protective features were being properly maintained and administrative controls were being implemented.

The team also reviewed the licensees design control procedures to ensure that the process included appropriate reviews and controls to assess plant changes for any potential adverse impact on the fire protection program and/or post-fire safe shutdown analysis and procedures.

b. Findings

No findings of significance were identified.

.03 Passive Fire Protection

a. Inspection Scope

The team walked down accessible portions of the selected fire areas to observe material condition and the adequacy of design of fire area boundaries (including walls, fire doors and fire dampers) to ensure they were appropriate for the fire hazards in the area.

The team reviewed installation/repair and qualification records for a sample of penetration seals to ensure the fill material was of the appropriate fire rating and that the installation met the engineering design.

b. Findings

No findings of significance were identified.

.04 Active Fire Protection

b. Inspection Scope

The team reviewed the design, maintenance, testing and operation of the fire detection and suppression systems in the selected plant fire areas. This included verification that the manual and automatic detection and suppression systems were installed, tested and maintained in accordance with the NFPA code of record and that they would control and/or extinguish fires associated with the hazards in the selected areas. A review of the design capability of suppression agent delivery systems were verified to meet the code requirements for the fire hazards involved. The team also performed a walkdown of accessible portions of the detection and suppressions systems in the selected areas as well as a walkdown of major system support equipment in other areas (e.g. fire protection pumps, Halon and/or CO2 storage tanks and supply system) as assess the material condition of the systems and components.

The team reviewed electric and diesel fire pump flow and pressure tests to ensure that the pumps were meeting their design requirements. The team also reviewed the fire main loop flow tests to ensure that the flow distribution circuits were able to meet the design requirements.

The team also assessed the fire brigade capabilities by reviewing training and qualification records, and drill critique records. The team also reviewed pre-fire plans and smoke removal plans for the selected fire areas to determine if appropriate information was provided to fire brigade members and plant operators to identify safe shutdown equipment and instrumentation, and to facilitate suppression of a fire that could impact post-fire safe shutdown. In addition, the team inspected the fire brigades protective ensembles, self-contained breathing apparatus (SCBA), and various fire brigade equipment (including smoke removal equipment) to determine operational readiness for fire fighting.

b. Findings

Introduction.

The team identified a Green NCV regarding the training program for onsite fire brigade personnel under Constellations fire protection program. Specifically, Constellation failed to provide the required quarterly training to five fire brigade members in the fourth quarter of 2005, and subsequently failed to remove those personnel from fire brigade duty during the period from January 1, 2006, to the time when those brigade members received their remedial training.

Description.

During the inspection, the team requested quarterly training documents for four randomly selected fire brigade members for calendar year 2005. Ginnas fire brigade training program is executed by covering relative topics over a two-year cycle via quarterly training sessions. Further, Constellation evaluates each fire brigade members level of knowledge through biannual examinations in the second and fourth quarters of each calendar year. Constellation determined that one of the four randomly-selected fire brigade members did not receive the quarterly classroom training or evaluation in the fourth quarter of 2005. An extent of condition search resulted in the identification of four additional fire brigade members without objective quality evidence of the fourth quarter training or examinations. Therefore, as a result of the inspection, five fire brigade members were identified as having missed the fourth quarter training and examination.

Site procedure ND-FPP, Fire Protection Program, Revision10, section 3.2.1, states in part that the protection of personnel, facilities, structures, systems, and components (SSC) at Ginna Station from hazards due to fire is planned and executed per procedures. Procedure A-202, The Fire Protection Program and Ginna Station Staff Responsibilities for Fire Protection, Revision 21, section 3.6.3, states in part that training shall be based on NFPA Standard 27.... and conducted at least quarterly for brigade members. NFPA 27-1981, section 4-3, states in part that brigade members should be required to complete a specified program of instruction as a condition to membership in the brigade. Procedure A-103.9, Fire Brigade Training, Revision 18, section 3.3.1, states that an individual not attending the required quarterly training shall be removed from brigade duty until such time that the next training session can be attended. Constellation clarified, during the inspection, that the next training session meant a remedial training which would include an examination for the second and fourth quarter training.

Analysis.

The failure to provide training to five fire brigade members and the subsequent failure to remove those personnel from fire brigade duty is a performance deficiency and a finding. The licensee determined that there were three occasions where up to three of the fire brigade members who failed to received the fourth quarter training in 2005 were on brigade duty (shift) at the same time. Traditional enforcement does not apply since there were no actual safety consequences or potential for impacting the NRCs regulatory function and the finding was not the result of any willful violation of NRC requirements. The finding is more than minor because the finding is associated with the Mitigating System cornerstone attribute of protection against external factors and affected the cornerstone objective of ensuring the availability, reliability and capability of systems that respond to initiating events to prevent undesirable consequences. Additionally, the finding is similar to example 4.h of IMC 0612, Appendix E in that not all fire brigade positions were staffed with appropriately trained (qualified) members. The Assumptions and Limitations of the Fire Protection Significance Determination Process (SDP), IMC 0609, Appendix F, specifically exclude fire brigade issues. As such, IMC 0612, Section 05.04.c, requires NRC management review to determine the significance of this finding. NRC management determined this finding to be of very low safety significance (Green). Fire brigade performance was not significantly affected, given staffing, at times, by members that lacked a single quarter of training, because the entire brigade staff had completed the annual live-fire practice sessions.

This finding is a performance deficiency and has a human performance cross-cutting aspect, because Constellation training personnel failed to ensure that all fire brigade members were adequately trained in accordance with procedural requirements, and Constellation management subsequently failed to remove those fire fighting personnel who were not properly trained from fire brigade duty.

Enforcement.

License condition 2.C.3 requires that Constellation implement and maintain in effect all fire protection features as approved by the NRCs Fire Protection Safety Evaluation (SE) and SE supplements. Site procedure ND-FPP states in part that the following documents... are utilized to implement the Fire Protection Program requirements: Ginna Station Procedures. Procedure A-202 requires training be provided at least quarterly to fire brigade members and Procedure A 103.9 requires an individual not attending the required quarterly training be removed from brigade duty until such time that the next training session can be attended. Contrary to the above, Constellation failed to provide the required quarterly training to five brigade members in the fourth quarter of calendar year 2005, and subsequently failed to remove those personnel from fire brigade duty for the period of January 01, 2006, to June 19, 2006, before those brigade members received their remedial training. Upon identification of this finding, Constellation removed all five personnel from fire brigade duties, performed remedial training and evaluated them via examination prior to returning them to duty-eligible status. Further, Constellation initiated a prompt investigation and entered this finding into their corrective action program under CR 2006-2518. This violation is being treated as a Non-Cited Violation, consistent with Section VI.A.1 of the NRC Enforcement Policy. (NCV 05000244/2006007-01, Missed Fire Brigade Training).

.05 Protection From Damage From Fire Suppression Activities

a. Inspection Scope

The team performed document reviews and plant walkdowns to verify that redundant trains of systems required for hot shutdown are not subject to damage from fire suppression activities or from the rupture or inadvertent operation of fire suppression systems. Specifically, the team verified that:

C A fire in one of the selected fire areas would not directly, through production of smoke, heat or hot gases, cause activation of suppression systems that could potentially damage all redundant trains.

C A fire in one of the selected fire areas (or the inadvertent actuation or rupture of a fire suppression system) would not directly cause damage to all redundant trains (e.g., sprinkler caused flooding of other than the locally affected train).

C Adequate drainage is provided in areas protected by water suppression systems

b. Findings

No findings of significance were identified.

.06 Alternative Shutdown Capability

a. Inspection Scope

Alternative shutdown capability for the areas selected for inspection utilizes shutdown from outside the control room and is discussed in Section 1R05.01 of this report.

.07 Circuit Analyses

This topic was not inspected for plant in NFPA 805 transition.

.08 Communications

a. Inspection Scope

The team reviewed safe shutdown procedures, the safe shutdown analysis and associated documents to verify an adequate method of communications would be available to plant operators following a fire. During this review the team considered the effects of ambient noise levels, clarity of reception, reliability and coverage patterns.

The team also inspected the designated emergency storage lockers to verify the availability of portable radios for the fire brigade and for plant operators. The inspectors also verified that communications equipment such as repeaters, transmitters, etc. would not be affected by a fire.

b. Findings

No findings of significance were identified.

.09 Emergency Lighting

c. Inspection Scope

The team observed the placement and coverage area of eight-hour emergency lights throughout the selected fire areas to evaluate their adequacy for illuminating access and egress pathways and any equipment requiring local operation and/or instrumentation monitoring for post-fire safe shutdown. The team also verified that the battery power supplies were rated for at least an 8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> capacity. Preventive maintenance procedures and various documents, including the vendors manual and completed surveillance tests were reviewed to ensure adequate surveillance testing and periodic battery replacements were in place to ensure reliable operation of the eight-hour emergency lights and that the emergency lighting units were being maintained consistent with the manufacturers recommendations and accepted industry practices.

b. Findings

No findings of significance were identified.

.10 Cold Shutdown Repairs

a. Inspection Scope

The team verified that the licensee had dedicated repair procedures, equipment, and materials to accomplish repairs of components required for cold shutdown which might be damaged by the fire to ensure cold shutdown could be achieved within the time frames specified in their design and licensing bases. The inspectors verified that the repair equipment, components, tools and materials (e.g. pre-cut cables with prepared attachment lugs) were available and accessible on site.

b. Findings

No findings of significance were identified.

.11 Compensatory Measures

a. Inspection Scope

The team verified that compensatory measures were in place for out-of-service, degraded or inoperable fire protection and post-fire safe shutdown equipment, systems, or features (e.g., detection and suppression systems and equipment, passive fire barriers, pumps, valves or electrical devices providing safe shutdown functions or capabilities). The team also verified that the short term compensatory measures compensated for the degraded function or feature until appropriate corrective action could be taken and that Constellation was effective in returning the equipment to service in a reasonable period of time.

b. Findings

No findings of significance were identified.

OTHER ACTIVITIES

4OA2 Identification and Resolution of Problems

.01 Corrective Actions for Fire Protection Deficiencies

a. Inspection Scope

The team verified that the licensee was identifying fire protection and post-fire safe shutdown issues at an appropriate threshold and entering them into the corrective action program. The team also reviewed a sample of selected issues to verify that the licensee had taken or planned appropriate corrective actions.

In addition, the team reviewed condition report CR-2006-002099 which documented a licensee-identified design deficiency that fire induced spurious actions in the control circuitry of 480V Bus 14 undervoltage relays could cause the A Charging Pump circuit breaker to be in a tripped condition, preventing the pump from starting when it is required to be operable for hot shutdown. Since the A Charging Pump is the only credited charging pump for post-fire safe shutdown outside the control room, the safe shutdown capability could be impacted. The licensee determined this to be an unanalyzed condition and made an eight-hour notification to the NRC on May 18, 2006.

The licensees preliminary evaluation indicated that this issue could cause an increase in core damage frequency of approximately 1.2E-07 per year.

Subsequently, during the extent of condition investigation, the licensee also identified (documented in CR 2006-002219) that fire induced spurious actions in the control circuitry of a relay associated with the safety injection signal could also have the same result, and that these spurious actions could also cause the standby auxiliary feedwater pumps (SAFP) to be inoperable. The SAFPs are required for safe shutdown when the auxiliary feedwater pumps or the condensate storage tank are affected by a fire.

The licensee initiated the necessary compensatory actions for correcting these problems by adding steps to three post-fire response procedures to defeat the potential fire induced spurious actions by removing the fuses of alternate DC power supplies to the affected relay control circuits. During the inspection, the team reviewed the following three affected procedures and verified that the necessary steps were incorporated into the procedures:

ER.FIRE.1 Alternate Shutdown For Control Complex Fire, Revision 20 ER.FIRE.4 Alternate Shutdown For Battery Room A Fire, Revision 16 ER.FIRE.5 Alternate Shutdown For Battery Room B Fire, Revision 18

b. Findings

No findings of significance were identified. No enforcement action is required for the above noncompliances (10 CFR 50, Appendix R, III.G.3 for Charging Pump A issue, and 10 CFR 50, Appendix R, III.G.2 for the SAFPs issue) because the conditions of these noncompliances meet the four criteria (licensee-identified, compensatory actions have been taken, not likely to have been previously identified by routine licensee efforts, and not willful) of NRC Enforcement Policy, Interim Enforcement Policies, Interim Enforcement Policy Regarding Enforcement Discretion for Certain Fire Protection Issues (10 CFR 50.48), and are not associated with a finding of high safety significance.

4OA6 Meetings, Including Exit

Exit Meeting Summary

The team presented their preliminary inspection results to Ms. M. Korsnick, Site Vice President, and other members of the site staff at an exit meeting on June 23, 2006. No proprietary information was included in this inspection report.

KEY POINTS OF CONTACT Licensee Personnel S. Adams Manager of Operations D. Bisaillon Reactor Operator M. Edelstein Fire Protection System Engineer R. Fellows Senior Reactor Operator M. Green Quality Performance Assessment T. Harding Licensing Supervisor D. Holm Plant Manager D. Joslin Communications S. Kennedy Emergency Preparedness M. Korsnick Vice President, Ginna T. Laursen Performance Improvement B. Leonard Training Manager M. Lilley General Supervisor, Equipment Reliability M. McGraw Fire Protection System Engineer T. OConner Fire Protection Consultant J. Pacher General Supervisor, System Engineering J. Pierce Fire Protection Consultant R. Randall Licensing Director M. Ruby Licensing Engineer J. Sharlow Operations Fire Protection Specialist W. Thompson General Supervisor, Chemistry R. Whalen Engineering Manager S. Wihlen Fire Marshall D. Wilson Principal Engineer, BOP Systems NRC J. Rogge, Chief, Electrical and Fire Protection Branch, Division of Reactor Safety K. Kolaczyk, Senior Resident Inspector, Ginna Nuclear Power Plant M. Marshfield, Resident Inspector, Ginna Nuclear Power Plant LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED Opened None Open and Closed 05000244/2006007-01 NCV Missed Fire Brigade Training Closed None Discussed None LIST OF

DOCUMENTS REVIEWED

Fire Protection Licensing Documents

Fire Protection Program

R. E. Ginna Nuclear Power Plant, Revision 3a

Ginna UFSAR Sections 7.4 and 9.5

Letter From RGE to NRC Appendix R Alternative Shutdown System R. G. Ginna

Nuclear Power Plant, January 16, 1985

Safety Evaluation Report SER For Appendix R to 10CFR Part 50, Items III.G.3 and

III.L, February 27, 1985

Appendix A to BTP APCSB 9.5-1 Guidelines for Fire Protection for Nuclear Power Plants

Docketed Prior to July 1, 1976.

NFPA 27-1981 Private Fire Brigades

NFPA 600-2005 Standard on Industrial Fire Brigades

Calculations/Engineering Evaluation Reports

DA-EE-2000-066 Appendix R Conformance Analysis, Rev. 1

DA-ME-98-004 Combustible Loading Analysis, Rev. 4

DA-ME-99-009 Condensate Inventory Requirements for Station Blackout Event,

Rev.0

DA-ME-2000-001 City Yard Loop Capability to Supply Cooling Water to EDG,

SAFW and Fight Screen House Fire With a Loss of Service

Water, Rev. 3

DA-ME-2000-075 Pressurizer Volume Control Tank and RWST Evaluations for

Appendix R, Rev. 2

DA-NS-2002-008 Operator Action Time Requirement Evaluation, Rev. 4

FTI 32-5009845-00 Approval of FTI Calculation 32-5009845-00 Ginna Safe Shutdown

RELEPS Analysis, September 26, 2001

NSL-4976-DA002 Determination of Internal Flood Zones and Sources, Rev. 0

PCR 2005-0034 Fire Harden B S/G Level Indication (EPU), Rev.0

PCR 2005-0010 ADFCS I/O Power Supply Back-Up Provision and Cooling

Upgrade, Rev.0

DA-ME-2003-018 Replacement of Appendix R Fire Barrier in the B Diesel

Generator Vault, Rev.1

DA-ME-1998-004 Combustible Loading Analysis, Rev.4

DA-ME-2000-040 City Water Yard Loop X-Tie to Fire Yard Loop Hydraulic

Calculation, Rev.1

Procedures

A-54.7:1 Fire Protection Tour

AP-CVCS.3 Loss of All Charging Flow

AP-IA.1 Loss of Instrument Air, Rev. 18

CME-50-02-52/EG1A1 Corrective Maintenance Procedure: Westinghouse 480V Air

Circuit Breaker, Type DB-75 Emergency Generator Breaker A

Bus 14, Position 18C, Rev. 02

CPI-APPX-R-SR-32 Calibration of Appendix R Source Range, N32R

EOP ATT-11.2 Attachment Diesel Air Compressor, Rev. 5

ER-D/G.2 Alternate Cooling For Emergency D/G, Rev. 16

ER-FIRE.0 CR Response To Fire Alarms and Reports, Rev. 6

ER.FIRE.6 Response To Fire In D/G B Vault, Rev. 2

FRP-4.0 Auxiliary Building Basement, Rev. 5

FRP-8.0 Intermediate Building Controlled Side Basement, Rev. 5

IP-CAP-1 Ginna Station Interface Procedure: Condition Reporting, Rev. 24

O-2.1 Normal Shutdown To Hot Shutdown, Rev. 120

O-6.11 Surveillance Requirement/Routine Operations Check Sheet,

Rev. 146

O-9.3 NRC Immediate Notification, Rev. 55

SC-3.15.15 Emergency Fire Equipment Inventory and Inspection, Rev. 84

ND-FPP Fire Protection Program, Rev.10

The Fire Protection Program and Ginna Station Staff

Responsibilities for Fire Protection, Rev.20, Rev.21

A-103.9 Fire Brigade Training, Rev.18

Open Flame, Welding and Grinding Permit (Hot Work Permit),

Rev.34

FPS-16 Bulk Storage of Combustible Materials and Transient Fire Loads,

Rev.9

O-6.11 Surveillance Requirement / Routine Operations Check Sheet,

Rev.144

A-54.7 Fire Protection Tour, Rev.29

FPS-1 Fire Barrier Control Procedure, Rev.9

FPS-2 Ginna Station Fire Barrier Penetration Seal Program, Rev.4

FPS-2.3 Temporary Fire Barrier Penetration Seals Program, Rev.4

M-56.3 Permanent Fire Barrier Penetration Seal Installation / Repair,

Rev.26

PT-13.1 Annual Fire Pump Insurance Surveillance Test, Rev.34

PT-13.4.20 Flood Valve Testing - Suppression System #S09 Relay Room SE

Manual Deluge, Rev.19

PT-13.4.21 Flood Valve Testing - Suppression System #S10 Relay Room W

Manual Deluge, Rev.21

PT-13.4.22 Flood Valve Testing - Suppression System #S11 Relay Room NE

Manual Deluge, Rev.24

QCIP-44 Fire Barrier Inspection (Method and Acceptance), Rev.12

SC-3.16.2.8 Fire Signaling System Maintenance, Rev.????

SC-3.15.5 Emergency Fire Equipment Inventory and Inspection, Rev.84

SC-3 Site Contingency Plan - SC-3 Fire Emergency Plan, Rev.38

SC-3.1 Fire Emergency General Information, Rev.20

SC-3.1.1 Fire Alarm Response (Fire Brigade Activation), Rev.17

SC-3.4.0 Fire Assessment and Subsequent Actions, Rev.22

SC-3.4.1 Fire Brigade Captain and Control Room Personnel

Responsibilities, Rev.37

IP-RDM-3 Ginna Records, Rev.13

Completed Tests/Surveillances

O-6.11 Surveillance Requirement/Routing Operations Check Sheet,

Rev. 146, Completed March 2006

SC-3.15.15 Emergency Fire Equipment Inventory and Inspection, Rev. 84,

Completed 4/10/06, 5/9/06, 5/31/06 and 6/2/06

FPS-2.1 Control and Verification of UFSAR and/or 10CFR50 Appendix R

Fire Barriers, Rev.6, 09/14/05, 11/28/05

FPS-7 Velocity Flush of the Fire Water System, Rev.9, 05/12/06 and

Rev.5, 10/25/02

M-56.1 Establishment of Temporary Fire Seals, Rev.27, 04/21/06

PT-13.11 Gamewell Zone Smoke Detector Testing Zones Z01 (Aux. Base.

East), Rev.20, 12/15/04

PT-13.11.26 Testing of Smoke Detection Zone Z-44 Relay Room Annex,

Rev.???, 01/10/06

PT-13.11.6.1 Testing of Smoke Detection Zone Z38D1 Intermediate Building -

South Basement, Rev.0, 05/11/06

PT-13.4.29 Halon System Testing Relay Room / Computer Room (S08),

Rev.24, 08/15/05

PT-13.4.33 Station Halon Systems Bottle Weighing and S08 (Relay Room

and Computer Room) Air Flow Test, Rev.24, 04/25/05

PT-13.1 Annual Fire Pump Insurance Surveillance Test, Rev.32, 12/21/05

and Rev.31, 12/20/04

PT-13.11.2 Gamewell Zone Smoke Detector Testing Zones Z20 (A D/G

Vault), Z21 (B DG Vault). Rev.17, 05/17/05

PT-13.10 Fire System Spray Nozzle Air Flow Test for S05, S06, S09, S10,

S11, S14, S17 and S29, Rev.17, 12/08/05

P201504 ECAD Testing on A EDG Cables

Quality Assurance (QA) Audits and System Health Reports

FPP-05-01-G Fire Protection Report Audit, August 2, 2005

SA 2006-0005 Fire Program, March 23, 2006

Audit FPP-05-01-G Fire Protection, completed 08/02/05

SA 2006-0005 Fire Program Assessment Report, completed 03/23/06

SQUA-2004-0013-MPH

SQUA-2004-0142-ENB

SQUA-2005-0050-EMG

Drawings

21488-0100 Fire Barrier Arrangement Sheet Fire, Smoke and Pressure Barrier

Plan View El.253'6", Rev.10

21488-0111 Fire Barrier General Arrangement Sheet Diesel Generator Room

B West and South Walls Penetrations Location Floor El.253'6",

Rev.5

33013-2559 Fire Response Plan Control Building, Rev.8

33013-1993 Sh.2 Fire Service Water Header B, Rev.9

33013-1537 1B Diesel Generator Cable Vault Appendix R Cable Chase Fire

Barrier, Rev.4

33013-1242 Fire Protection Relay and Multiplexer Rooms, Rev.5

33013-1989 Fire Service Water Plant Systems, Rev.22

2013-2539 AC System Plant Load Distribution One Line Diagram, Rev.13

33013-2543 Fire Response Plan Auxiliary Building Plan - Basement Floor

El.253'8", Rev.2

33013-2544 Fire Response Plan Turbine Building Plan - Basement Floor

El.253'6", Rev.9

33013-2545 Fire Response Plan Containment Structure & Intermediate Bldg.

Plan - Intermediate Floor El. 253'3", Rev.8

33013-2559 Fire Response Plan Control Building Plan Views, Rev.8

21946-0445 Standby Auxiliary Feedwater Pump C Control Schematic

33013-1736 Diesel Generator A Control Schematic, Rev. 14

21946-0650 TDAFW Pump Steam Supply Valve MOV-3504A Control

Schematic, Rev. 8

21946-0651 TDAFW Pump Steam Supply Valve MOV-3505A Control

Schematic, Rev. 7

21946-0054 480V Bus 14 PT and UV Relays Control Schematic, Revision 5

21946-0055 480V Bus 16 PT and UV Relays Control Schematic, Revision 6

21946-0445 Standby Auxiliary Feedwater Pump C Control Schematic,

Revision 6

21946-0446 Standby Auxiliary Feedwater Pump D Control Schematic,

Revision 5

10909-34 Bus 14 and Bus 16 Undervoltage Control, Revision 4

10905-54, Sh 1 Undervoltage Scheme, Bus 14 Elementary Wiring Diagram,

Undervoltage Scheme Bus 14, Revision 11

10905-54, Sh 2 Auxiliary Relay Rack Elementary Wiring Diagram, Revision 15

10905-54, Sh 3 PT and UV Relays, Bus 14, Elementary Wiring Diagram, Revision

21498-511 Appendix R Instrument Panels Wiring diagram, Rev.6

11302-0381 Steam Generator A Pressure Loop PT-482 Inst Loop Wiring

Diagram, Rev.1

11302-0382 Steam Generator B Pressure Loop PT-483 Inst Loop Wiring

Diagram, Rev.2

11302-0359 Steam Generator A Level Loop LT-460 Inst Loop Wiring Diagram,

Rev.1

11302-0371 Steam Generator B Level Loop LT-470 Inst Loop Wiring Diagram,

Rev.1

11302-0323 Pressurizer Level Loop LT-433 Inst Loop Wiring Diagram, Rev.1

10905-0445 Standby Auxiliary Feedwater Pump C Elementary Wiring

Diagram, Rev. 6

10905-0446 Standby Auxiliary Feedwater Pump D Elementary Wiring

Diagram, Rev. 5

Pre-Fire Plans

Fire Response Plan FRP-4.0 Auxiliary Building Basement, Rev.5

Fire Response Plan FRP-8.0 Intermediate Building Controlled Side Basement, Rev.5

Fire Response Plan FRP-19.0 Relay Room/Multiplex Room/Annex Room, Rev.8

Fire Response Plan FRP-25.0 Diesel Generator Room B and Vault, Rev.6

Piping and Instrumentation Diagrams (P&IDs)

33013-1234 Condensate Storage (CDST), Rev. 31

33013-1237 Auxiliary Feedwater (FW), Rev. 52

33013-1238 Standby Auxiliary Feedwater (FW), Rev. 24

33013-1258 Reactor Coolant Pressurizer (RC), Rev. 24

33013-1260 Reactor Coolant (RC), Rev. 25

33013-1265, Sh. 1 Chemical & Volume Control System Charging, Rev. 11

33013-1265 Sh.2 Auxiliary Building Chemical & Volume Control System Charging,

Rev. 17

33013-1237 Auxiliary Feedwater, Revision 52

Fire Brigade Documents

Fire Area/Zone Analysis for Fire Areas/Zones ABI/IBS-1, CC/RR, CHG/- and EDG1B/-

Fire Brigade Drills

Fire Brigade Drills for calendar years 2004, 2005 and 2006

Fire Brigade Training

Fire Brigade Training documents

Fire Brigade Qualification documents

2nd Quarter 2006 Fire Brigade Member Examinations

Operator Safe Shutdown Training

Appendix R Composite Operator Time/Motion Study, May 16, 2006

RER22C Site Contingencies, Appendix R - Alternative Shutdown, Rev. 8

Job Performance Measures (JPMs)

JC012.007 Locally Trip Reactor And Turbine, Rev. 5

JC039.003 Locally Operate The ARVs, Rev. 9

JC061.005 Reset TDAFW Pump Turbine Trip/Throttle Valve, Rev. 7

JC079.001 Startup and Align Diesel Driven Air Compressor, Rev. 8

JR004.009 Take Local Manual Control of Charging Pump, Rev. 6

JR039.001 Locally Close MSIVs, Rev. 10

JR061.008 Open TDAFW Pump Supply Valves, Rev. 8

JR062.006 Locally Operate 480 VAC Breakers, Rev. 9

JR064.004 EDG Locally Per ER-FIRE.1 With No Faults, Rev. 15

Hot Work and Ignition Source Permits

HWP 06-50

HWP 06-51

HWP 06-52

HWP 06-53

HWP 06-54

HWP 06-55

Transient Combustible Evaluations

TCP 06-26

TCP 06-27

TCP 06-28

TCP 06-29

TCP 06-30

Fire Barriers

Penetration Seal Database

Temporary Fire Barrier I-590-P

Temporary Fire Barrier D-41-P

Fire Barrier Permit 06-03, 05/02/06

Fire Barrier Permit 06-13, 06/01/06

Spec IBD23A-703, IBD23 Style A Curtain Type Static Fire Dampers, 2003

Miscellaneous Documents

Ginna Station EPU Licensing Report Fire Protection, December 2005

Ginna Station EPU Licensing Report Risk Evaluation of EPU, December 2005

Emergency Lighting Service Manual for ALC-X Series I, AS Series I, ED Series I VTD-D1140-

201 Revision 000 VM#D1140-0377 Tab 2

Spectron Series AS-BC/BX Series I Self Contained Emergency Lighting Units AS-80 BCI, AS-

160 BCI, 12 AS-160 BCI, 12 AS-200 BXI, GMMEL-SD4 Instructions for Installation, Operation,

Service

Dual-Lite Spectron Series Emergency Lighting Equipment Series: ALC-X-I, AS-BC/BX-1, AS-I,

EDC-X-I, EDN-I Instructions for Installation, Operation, Maintenance

Equipment History Report: 52/EG1A1, 52/EG1A2, 52/EG1B1, 52/EG1A2

Equipment History Report: 52/SWP1A, 52/SWP1B

Equipment History Report: 52/CHP1A, 52/CHP1B

Equipment History Report: 52/SWP1C

Audit FPP-05-01-G, Fire Protection, completed 08/02/05

Self Assessment SA 2006-0005, Fire Program Assessment Report, completed 03/23/06

SQUA-2004-0013-MPH

SQUA-2004-0142-ENB

SQUA-2005-0050-EMG

Fire Protection Program Transition Plan

Fire Protection Program Impairment Tracking System

Test Gauge Calibration Data sheet, 06/21/06

Condition Reports

2003-1376 2003-1478 2003-2227 2003-3333 2004-0104 2004-0190 2004-1691

2004-1878 2004-2663 2004-3178 2005-0712 2005-3158 2005-3179 2005-3188

2005-4462 2005-4501 2005-4737 2005-4739 2005-4928 2005-5139 2005-5308

2005-6217 2006-0785 2006-0891 2006-0905 2006-0941 2006-0962 2006-0956

2006-1040 2006-1363 2006-2368 2003-2785 2005-0682 2003-2994 2005-3190

2004-0010 2005-3191 2005-3190 2005-4936 2005-0616 2005-5119 2006-0883

2006-2375* 2006-0889 2006-2412* 2006-0941 2006-2409* 2006-0957 2006-2406*

2006-1618 2006-2407* 2006-2356* 2006-2366* 2006-2367* 2006-2363* 2006-2380*

Work Orders

20002696

20505059

20505098

LIST OF ACRONYMS USED

AC Alternating Current

CFR Code of Federal Regulations

CO2 Carbon Dioxide

CR Condition Report

DC Direct Current

DRS Division of Reactor Safety

FA Fire Area

FHA Fire Hazards Analysis

FPP Fire Protection Program

FZ Fire Zone

IMC Inspection Manual Chapter

IP Inspection Procedure

IPE Individual Plant Examination

IPEEE Individual Plant Examination of External Events

IR Inspection Report

NCV Non-cited Violation

NFPA National Fire Protection Association

NRC Nuclear Regulatory Commission

PARS Publicly Available Records

P&ID Piping and Instrumentation Drawing

SAFP Stanby Auxiliary Feedwater Pumps

SCBA Self Contained Breathing Apparatus

SDP Significance Determination Process

SE Safety Evaluation

SSC Structures, Systems, and Components

UFSAR Updated Final Safety Analysis Report

Attachment