IR 05000244/2022012

From kanterella
Jump to navigation Jump to search
LLC - Design Basis Assurance Inspection (Teams) Inspection Report 05000244/2022012
ML23012A127
Person / Time
Site: Ginna Constellation icon.png
Issue date: 01/12/2023
From: Mel Gray
NRC/RGN-I/DORS
To: Rhoades D
Constellation Energy Generation, Constellation Nuclear
References
IR 2022012
Preceding documents:
Download: ML23012A127 (1)


Text

January 12, 2023

SUBJECT:

R.E. GINNA NUCLEAR POWER PLANT, LLC - DESIGN BASIS ASSURANCE INSPECTION (TEAMS) INSPECTION REPORT 05000244/2022012

Dear David Rhoades:

On December 1, 2022, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at R.E. Ginna Nuclear Power Plant, LLC. On January 6, 2023, the NRC inspectors discussed the results of this inspection with Daren Blankenship, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.

One finding of very low safety significance (Green) is documented in this report. This finding involved a violation of NRC requirements. We are treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violation or the significance or severity of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region I; the Director, Office of Enforcement; and the NRC Resident Inspector at R.E. Ginna Nuclear Power Plant, LLC.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region I; and the NRC Resident Inspector at R.E. Ginna Nuclear Power Plant, LLC. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Mel Gray, Chief Engineering Branch 1 Division of Operating Reactor Safety

Docket No. 05000244 License No. DPR-18

Enclosure:

As stated

Inspection Report

Docket Number:

05000244

License Number:

DPR-18

Report Number:

05000244/2022012

Enterprise Identifier: I-2022-012-0009

Licensee:

Constellation Energy Generation, LLC

Facility:

R.E. Ginna Nuclear Power Plant, LLC

Location:

Ontario, New York

Inspection Dates:

November 14, 2022 to December 1, 2022

Inspectors:

N. Floyd, Senior Reactor Inspector

D. Kern, Senior Reactor Inspector

J. Kulp, Senior Reactor Inspector

N. Mentzer, Resident Inspector

J. Schoppy, Senior Reactor Inspector

D. Tifft, Regional State Liaison Officer

Approved By:

Mel Gray, Chief

Engineering Branch 1

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a design basis assurance inspection (teams) at R.E. Ginna Nuclear Power Plant, LLC, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Failure to Evaluate Water Leakage during Modification of Circulating Water Pump Automatic Trip Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000244/2022012-01 Open/Closed

[H.6] - Design Margins 71111.21M The NRC inspectors identified a Green finding and associated Non-cited Violation (NCV) of 10 CFR 50, Appendix B, Criterion III, Design Control when the licensee performed a plant modification to remove the automatic trip of the circulating water pumps after a flood is detected in the turbine building. Specifically, the licensee did not evaluate the impact of water leakage into the emergency diesel generator (EDG) and battery rooms during the analyzed internal flooding event.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

===71111.21M - Design Bases Assurance Inspection

The inspectors evaluated the following components and listed applicable attributes, permanent modifications, and operating experience:

Design Review - Risk-Significant/Low Design Margin Components (IP Section 02.02)

=

The inspectors used the event scenario-based approach described in IP Section 03.01.c to select components for the design review. The high-risk event scenarios utilized by the team included initiating events from

(i) a house heating steam leak in the screen house and
(ii) a 200 gallon per minute flood in the relay room.
(1) 'C' Standby Auxiliary Feedwater Pump
  • Material condition and installed configuration (e.g., visual inspection/walkdown)
  • Normal, abnormal, and emergency operating procedures
  • Consistency among design and licensing bases and other documents/procedures
  • System health report, maintenance effectiveness and records, and corrective action history
  • Design calculations
  • Surveillance testing and recent test results
  • System and component level performance monitoring
  • Equipment protection from fire, flood, and water intrusion or spray
  • Operator actions
  • Heat removal cooling water and ventilation

The team used Appendix B guidance for Valves, Pumps, Instrumentation, and As-Built System.

(2)480V Bus 14

  • Material condition and installed configuration (e.g., visual inspection/walkdown)
  • Consistency among design and licensing bases and other documents/procedures
  • Maintenance records and corrective action history
  • Adequacy of design (calculations and modifications)
  • Surveillance testing and recent test results
  • System and component level performance monitoring
  • Control logic
  • Component adequacy for minimum voltage
  • Protection coordination (load in-rush and full load current)
  • Energy source availability (electricity)
  • Equipment qualification suitable for the environment expected under all conditions

The team used Appendix B guidance for Instrumentation, Circuit Breakers and Fuses, Cables, Electric Loads, and As-Built System.

(3) Standby Auxiliary Feedwater Diesel Generator - KDG08
  • Material condition and installed configuration (e.g., visual inspection/walkdown)
  • Normal, abnormal, and emergency operating procedures
  • Consistency among design and licensing bases and other documents/procedures
  • System health report, maintenance effectiveness and records, and corrective action history
  • Design calculations
  • Surveillance testing and recent test results
  • System and component level performance monitoring
  • Equipment protection from fire, flood, and water intrusion or spray
  • Operator actions
  • Heat removal cooling water and ventilation

The team used Appendix B guidance for Valves, Pumps, Instrumentation, and As-Built System.

(4) A Emergency Diesel Generator - KDG01
  • Material condition and configuration (e.g., visual inspection/walkdown)
  • Normal, abnormal, and emergency operating procedures
  • Consistency among design and licensing bases and other documents/procedures
  • System health report, maintenance effectiveness and records, and corrective action history
  • Adequacy of design (calculations and modifications)
  • Surveillance testing procedures and recent test results

The team used Appendix B guidance for Valves, Instrumentation, Circuit Breakers, Electrical Loads, and As-built System.

Design Review - Large Early Release Frequency (LERFs) (IP Section 02.02) (1 Sample)

(1) Atmospheric Relief Valve 3410
  • Material condition and installed configuration (e.g., visual inspection/walkdown)
  • Normal, abnormal, and emergency operating procedures
  • Consistency among design and licensing bases and other documents/procedures
  • Maintenance records and corrective action history
  • Equipment/environmental controls and qualification
  • Adequacy of design (calculations and modifications)
  • Surveillance testing and recent test results
  • Component degradation and performance monitoring
  • Operator actions

The team used Appendix B guidance for Valves, Pumps, Instrumentation, and As-Built System.

Modification Review - Permanent Mods (IP Section 02.03) (6 Samples)

(1) ECP-18-000455: ESR-18-0152 - 'B' Battery Room Cable Vault Level Alarm
(2) ECP-19-000306: ESR-19-0067 - Modify MOV-700 to Prevent Pressure Locking
(3) ECP-19-000482: Install Spring-Loaded Check Valve in Emergency Diesel Generator Lube Oil Supply Line to Turbo
(4) ECP-21-000008: Reduce Fouling Upstream of Service Water Strainers for A & B Auxiliary Feedwater Pumps by Increasing Size of Tubing, Valves, and Strainers
(5) ECP-21-000049: Eliminate Circulating Water Pump Flood Switch Trip in Screenhouse and Turbine Building
(6) ECP-21-000202: Reconfigure MOV 4615 to Use Torque / Limit Control

Review of Operating Experience Issues (IP Section 02.06) (3 Samples)

(1) NRC Information Notice 2019-01: Inadequate Evaluation of Temporary Alterations, dated March 12, 2019
(2) NRC Information Notice 2020-02: Flex Diesel Generator Operational Challenges, dated September 15, 2020
(3) NRC Operating Experience Smart Sample OpESS 2007/02: Analysis of Flooding Vulnerabilities, dated September 11,

INSPECTION RESULTS

Failure to Evaluate Water Leakage during Modification of Circulating Water Pump Automatic Trip Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems

Green NCV 05000244/2022012-01 Open/Closed

[H.6] - Design Margins 71111.21M The NRC inspectors identified a Green finding and associated Non-cited Violation (NCV) of 10 CFR 50, Appendix B, Criterion III, Design Control when the licensee performed a plant modification to remove the automatic trip of the circulating water pumps after a flood is detected in the turbine building. Specifically, the licensee did not evaluate the impact of water leakage into the emergency diesel generator (EDG) and battery rooms during the analyzed internal flooding event.

Description:

In April 2021, licensee staff performed a plant modification under ECP-21-000049 to disable the automatic trip function of the circulating water pumps when a flood is detected in the screenhouse or the turbine building lower elevation (pit beneath the turbine condenser). The flood switches were left in-place to provide alarm functions in the control room, but the automatic pump trip function was removed. The primary scenario affected was postulated internal flooding due to ruptured rubber expansion boots between the circulating water inlet piping to the turbine condenser inlet head. The licensee determined that by removing the automatic trip of the circulating water pumps, that the final steady-state flood water height inside the turbine building basement increased to 4.8 feet from the previous height of 9 inches and was limited to 4.8 feet by the failure of the rollup door TB-10 due to pressure effects of the flood water. The two EDG rooms and two vital battery rooms are both located in the turbine basement. While the EDG room doors are at the same elevation as the turbine building basement, the battery room doors are on top of an 18-inch wall which is a physical barrier between the battery room floor and the turbine basement floor. These rooms need to be protected from the effects of flooding as they house safety-related equipment that provides electrical power for various safety related components and instruments that mitigate the effects of design basis accidents.

The inspectors reviewed the design change package for the modification and performed a walk down of the turbine building focusing on the configuration of the EDG and battery room doors. The inspectors noted that the licensee assumed the flood doors were essentially watertight in their analysis and did not account for any flood water leakage into the rooms. The doors were procured and installed as airtight to mitigate a high-energy line break in the turbine building. Rubber flap seals were installed between the door and the door jambs to cover the gap between the two components. They were subsequently dedicated as "flood doors" with a modification to the flap seals which increased the width of the seal from 1.5 inches to 2 inches, adding an additional half inch of seal to cover the gap. The inspectors observed that the doors are not the traditional watertight door which use a knife edge, elastomer seal and door latches to provide a compression seal. The inspectors questioned the assumption of watertightness for the existing doors based on the air leakage allowance in the door procurement specification as well as design documentation submitted to the NRC in 2014 for external flooding hazard re-analysis that calculated a leak rate (i.e., water-resistant)to qualify the doors. The inspectors also questioned the qualification of the flood doors since the licensee did not consider differences between the design drawings and as-found configuration of the doors (i.e., gap between the flap seals and doors) and because there was no analyses or calculations of water leakage at the qualified flood heights described in the plant design basis documents.

The inspectors observed that the licensee did not determine the change in leakage rate due to the increase flood height nor evaluate the effects of the additional leakage over the undefined timeline for the safety related equipment in the EDG or the battery rooms. While the licensee had an alarm response procedure for when the turbine building high-level flood detectors indicated in the control room, they did not credit or evaluate any operator actions in the analysis for the modification to mitigate the effects of this internal flood.

Corrective Actions: The licensee staff entered the issue into their corrective action program and performed a calculation of water leakage in the EDG and battery rooms at the new flood height. The licensee plans to update their design basis documentation, including the door drawings and seal inspection criteria.

Corrective Action References: IR 04541356 and IR 04546969

Performance Assessment:

Performance Deficiency: The licensee did not evaluate the impact of increased flood water leakage into the EDG and battery rooms when they made a plant modification to disable the automatic circulating water pump trip. Specifically, the modification increased the flood height in the turbine building from 9 inches to 4.8 feet, and the licensee did not evaluate the water leakage at this new height.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Design Control attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, plant modification ECP-21-000049 affected the availability and reliability of the safety-related components in the EDG and battery rooms due to increased water leakage during a postulated internal flooding event. The inspectors considered this is similar to IMC 0612, Appendix E, example 3.a because there was a reasonable doubt about the amount of flood water that would leak into the rooms for a flood occurring over an indefinite period of time.

Significance: The inspectors assessed the significance of the finding using IMC 0609 Appendix A, The Significance Determination Process (SDP) for Findings At-Power. Using IMC 0609, Appendix A, Exhibit 2, Mitigating System Screening Questions, the inspectors determined the finding to be of very low safety significance (Green) because the systems and components in the impacted rooms would maintain their operability during the internal flooding event. This was based on the inspectors independent assessment of design-specification door seal performance and reasonable operator actions for the postulated internal flooding event of concern at the revised flood height of 4.8 feet. Specifically, the inspectors determined, based upon licensee staff calculations completed in response to this issue, operators would receive an alarm in the control room, follow the steps in the alarm response procedure to investigate the source of the flood, and would have sufficient time to trip the circulating water pumps and mitigate the event before the affected safety systems of concern were rendered inoperable or non-functional.

Cross-Cutting Aspect: H.6 - Design Margins: The organization operates and maintains equipment within design margins. Margins are carefully guarded and changed only through a systematic and rigorous process. Special attention is placed on maintaining fission product barriers, defense-in-depth, and safety related equipment. Specifically, the licensee made a design change that significantly increased the flood height during a postulated internal flood event and did not carefully evaluate the impact of that change to guard the design margin.

Enforcement:

Violation: 10 CFR 50, Appendix B, Criterion III, Design Control, states in part that measures shall be established to assure that applicable regulatory requirements and the design basis for those structures, systems, and components are correctly translated into specifications, drawings, procedures, and instructions, and that design control measures shall provide for verifying or checking the adequacy of design, such as by the performance of design reviews, by the use of alternate or simplified calculational methods, or by the performance of a suitable testing program.

Contrary to the above, from April 2021 to present, the licensee failed to verify the adequacy the of the design for an analyzed internal flooding event. Specifically, the licensee performed a plant modification to remove the automatic trip of the circulating water pumps when a flood is detected in the turbine building and did not evaluate the impact of increased water leakage into the EDG and battery rooms.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On December 1, 2022, the inspectors presented the preliminary inspection results to Doug Hild, Plant Manager, and other members of the licensee staff.
  • On January 6, 2023, the inspectors presented the design basis assurance inspection (teams) inspection results to Daren Blankenship, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21M Calculations

9001-05050056.0

Alternate Test Media Correlation for Pressure Relief Valves

5959 & 5960

71111.21M Calculations

CALC-2010-0018

Time to Locally Open ARV 3410/3411

71111.21M Calculations

DA-EE-92-098-01 Diesel Generator A Steady-State Loading Analysis

71111.21M Calculations

DA-EE-92-111-01 Diesel Generator A Dynamic Loading Analysis

71111.21M Calculations

DA-EE-93-006-08 Instrument Performance Evaluation and Setpoint Verification

Undervoltage Relays and Voltmeters on 480V Safeguards

Busses

71111.21M Calculations

DA-EE-93-104-07 480V Coordination and Circuit Protection Study

71111.21M Calculations

DA-EE-95-146

Evaluate Concurrent Routing of Cable

71111.21M Calculations

DA-EE-98-089

Emergency Diesel Generator Overcurrent Protection

71111.21M Calculations

DA-ME-12-005

SAFW Hydraulic Model

71111.21M Calculations

DA-ME-13-012

Seismic Design of SAFW Diesel Generator and Associated

Electrical Equipment

71111.21M Calculations

DA-ME-2001-053

Minimum Engineering Limit for Differential Pressure for

Preferred and Standby Auxiliary Feedwater Pumps During

Periodic Testing

71111.21M Calculations

GC-20226

RG&E Ginna Superwall Check for Water Pressure due to

Flooding

03/23/1983

71111.21M Corrective Action

Documents

CR-2010-006914

2568045

03995521

04004226

04036374

04149657

04169669

04171248

04194833

230952

271817

278201

04321584

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

04333162

04342146

04363839

04364457

04364913

04368000

04383941

04383962

04402989

04424057

04428133

04446627

04449563

04450886

04453318

04459583

04461152

04471260

04476764

04492882

04494013

04510333

04510507

04516938

04533848

04535292

04535442

04535937

04538765

71111.21M Corrective Action

Documents

Resulting from

Inspection

04529821

04535218

04536858

04536930

04536954

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

04537064

04537165

04537450

04537613

04537638

04537846

04537935

04539568

04539589

04539598

04539610

04539641

04539667

04539682

04539821

04539861

04539930

04539940

04539943

04539944

04540133

04540175

04540202

71111.21M Drawings

10905-0067

Auxiliary Building Service Water Isolation Valve MOV-4615

Elementary Wiring Diagram

71111.21M Drawings

11310-0199

MOV-4615 Auxiliary Building Service Water Isolation Valve

Connection Diagram

71111.21M Drawings

33013-1238

Standby Auxiliary Feedwater (FW) P&ID

71111.21M Drawings

33013-1239,

Sheet 1

Diesel Generator - A (DG) P&ID

71111.21M Drawings

33013-1239,

Sheet 2

Diesel Generator - B (DG) P&ID

71111.21M Drawings

33013-1250,

Sheet 2

Station Service Cooling Water Safety Related (SW) P&ID

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21M Drawings

33013-1606,

Sheet 1

Miscellaneous Relay Rack M1

71111.21M Drawings

33013-2539

AC System Plant Load Distribution One Line Diagram

71111.21M Drawings

D5 File 7477

Overly Manufacturing Door Design for Robert E. Ginna

Nuclear Station

71111.21M Engineering

Changes

ECN 4136-1

A D.G. ELCP Mod

01/23/1986

71111.21M Engineering

Changes

ECP-14-000571

Flood Barrier Qualification Summary

71111.21M Engineering

Changes

ECP-16-000445

Ginna Design Basis Flood Re-evaluation

71111.21M Engineering

Changes

ESR-11-0362

Evaluate Enhancements for Diesel Generator Margin

71111.21M Engineering

Changes

EWR 3990-CE1

Design Analysis Ginna Station DGB Modifications

71111.21M Engineering

Changes

PMA-21-132507

Revise Frequencies of PMs Not Completed in RFP 2021

03/01/2022

71111.21M Engineering

Changes

PMC-21-131112

Change Frequency of P200123 Perform PM Inspection on

2/PHCG Pressurizer Heater Control to 9 Years

10/13/2021

71111.21M Engineering

Changes

PMC-21-131563

Extend Breaker 52/MCC1C (MCC C Supply Breaker) PM

P200124

10/14/2021

71111.21M Miscellaneous

RS-17-026

Exelon Generation Company, LLC Response to March 12,

2012, Request for Information Enclosure 2,

Recommendation 2.1, Flooding, Required Response 3,

Flooding Focused Evaluation Summary Submittal

(ML17069A004)

03/10/2017

71111.21M Miscellaneous

TS-203-044594-

G5

Technical Specifications for Doors and Door Frames Ginna

Station

05/24/1978

71111.21M Procedures

AR-DG-A-3

Primary Fuel Filter Hi DP

71111.21M Procedures

AR-L-12

Condenser Pit or Screen House Hi Level 6.5

71111.21M Procedures

ER-AFW.1

Alternate Water Supply to the AFW Pumps

71111.21M Procedures

ER-D/G.1

Restoring D/Gs

71111.21M Procedures

ER-SH.1

Response to Loss of Screenhouse

71111.21M Procedures

GC-76.8

Installation and Inspection of Tubing and

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Instrumentation/Tubing Supports

71111.21M Procedures

GME-50-02-

DB50

Westinghouse 480V Air Circuit Breaker Type DB-50

Maintenance

71111.21M Procedures

IP-CON-9

Plant Barrier Control Program Implementation

71111.21M Procedures

MMP-GM008-

00003

A or B Diesel Generator Primary and Secondary Fuel Oil

Filter Minor Inspection and Maintenance

71111.21M Procedures

OP-AA-102-106

Operator Response Time Program

71111.21M Procedures

OP-GI-102-106

Operator Response Time Program at Ginna Station

71111.21M Procedures

SC-3.17.1

SAFW Annex Flood Barrier Installation/Removal/Inspection

71111.21M Procedures

STP-O-12.1

Emergency Diesel Generator A

71111.21M Procedures

STP-O-30.11

Emergency Diesel Generator B Pre-Startup Alignment

71111.21M Procedures

T-44.2

Standby Auxiliary Feedwater (SAFW) System Alignment for

Normal Operation

71111.21M Procedures

WC-AA-120

Preventive Maintenance Database Revision Requirements

71111.21M Work Orders

C90638092

C90638094

C90638095

C90960720

C91453936

C92100746

C92592215

C93060937

C93612036

C93636558

C93687220

C93692742

C93699259

C93719524

C93723304

C93723305

C93737945

C93757543

C93759291

C93772303

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

C93772719

C93775060

C93775878

C93775879

C93782279

C93790219

C93794156

C93794370

C93794825

C93794825

C93802841

C93804275

C93804679

C93807963