R. E. Ginna Nuclear Power Plant, LLC - Request for Information for a Biennial Problem Identification and Resolution Inspection; Inspection Report 05000244/2022010
ML22160A396
Person / Time
Site: Ginna Constellation icon.png
Issue date: 06/09/2022
From: Erin Carfang
Division of Operating Reactors
To: Rhoades D
Constellation Energy Generation, Constellation Nuclear
Carfang E
References
IR 2022010
Download: ML22160A396 (6)


See also: IR 05000244/2022010

Text

June 9, 2022

Mr. David P. Rhoades

Senior Vice President

Constellation Energy Generation, LLC

President and Chief Nuclear Officer (CNO)

Constellation Nuclear

4300 Winfield Road

Warrenville, IL 60555

SUBJECT:

R.E. GINNA NUCLEAR POWER PLANT, LLC - REQUEST FOR

INFORMATION FOR A BIENNIAL PROBLEM IDENTIFICATION AND

RESOLUTION INSPECTION; INSPECTION REPORT 05000244/2022010

Dear Mr. Rhoades:

The purpose of this letter is to notify you that the U.S. Nuclear Regulatory Commission (NRC)

Region I staff will conduct a biennial problem identification and resolution inspection at

R.E. Ginna Nuclear Power Plant, LLC. Niklas Floyd, a Senior Reactor Inspector from the NRCs

Region I office, will lead the inspection team. The inspection will be conducted in accordance

with Inspection Procedure 71152, Problem Identification and Resolution, dated December 14,

2021 (ADAMS Accession No. ML21281A181).

The inspection will assess the effectiveness of your problem identification and resolution (PI&R)

program in identifying, prioritizing, evaluating, and correcting problems, including the use of

operating experience, assessments, and audits. This inspection will also assess your program

for raising concerns under the established safety conscious work environment.

The onsite inspection is scheduled for the weeks of July 25 and August 8, 2022.

In order to minimize the inspection impact on the site and to ensure a productive inspection for

both parties, we have enclosed a request for information needed for the inspection. It is

important that all of these documents are up-to-date and complete in order to minimize the

number of additional documents requested during the preparation and/or the onsite portions of

the inspection. Insofar as possible, this information should be provided electronically to the lead

inspector by July 7, 2022.

If there are any questions about the inspection or the material requested in the enclosure,

please contact the lead inspector at 610-337-5282 or via e-mail at Niklas.Floyd@nrc.gov.

This letter does not contain new or amended information collection requirements subject to the

Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection

requirements were approved by the Office of Management and Budget, Control Number 3150-

0011. The NRC may not conduct or sponsor, and a person is not required to respond to,

D. Rhoades

2

a request for information or an information collection requirement unless the requesting

document displays a currently valid Office of Management and Budget Control Number.

This letter and its enclosure will be made available for public inspection and copying at

http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in

accordance with Title 10 of the Code of Federal Regulations, Part 2.390, Public Inspections,

Exemptions, Requests for Withholding.

Sincerely,

Erin E. Carfang, Chief

Projects Branch 1

Division of Operating Reactor Safety

Docket No. 50-244

License No. DPR-18

Enclosure:

Request for Information for Biennial

Problem Identification and Resolution

cc: Distribution via ListServ

Erin E.

Carfang

Digitally signed by Erin E.

Carfang

Date: 2022.06.09 12:13:22

-04'00'

ML22160A396

x

SUNSI Review

x

Non-Sensitive

Sensitive

x

Publicly Available

Non-Publicly Available

OFFICE

RI/DORS

RI/DORS

NAME

NFloyd

ECarfang

DATE

6/9/22

6/9/22

REQUEST FOR INFORMATION

BIENNIAL PROBLEM IDENTIFICATION AND RESOLUTION

Enclosure

Inspection Report: 05000244/2022010

Onsite Inspection Dates:

July 25, through July 29, 2022; and

August 8, through August 12, 2022

Inspection Procedure:

71152, Problem Identification and Resolution,

dated December 14, 2021

Lead Inspector:

Niklas Floyd, Senior Reactor Inspector

610-337-5282

Niklas.Floyd@nrc.gov

The following information is requested by July 7, 2022, or sooner, to facilitate inspection

preparation. The requested information is for the period from March 5, 2020 through July 25,

2022 (Present), which covers the timeframe since the previous problem identification and

resolution (PI&R) inspection. The inspection procedure also specifies a five-year review for a

subset of selected program, system, or component issues. The selected samples for this

five-year review will be provided at a future date.

A bagman trip is currently scheduled for July 11 and 12, 2022. The purpose of this trip is for the

team lead to familiarize their self with the site organization including meetings with department

managers and overview of the corrective action program and to finalize remaining administrative

arrangements for the inspection.

Feel free to contact the lead inspector as soon as possible if you have any questions regarding

this information request. Please provide the information electronically in pdf files, Excel, or

other searchable formats, preferably on an internet database system (e.g., OneDrive) or

portable electronic media (e.g., CD-ROM, DVD, etc.). The files should contain descriptive

names, be indexed, and hyperlinked to facilitate ease of use. Information in lists should

contain enough information to be easily understood by someone who has knowledge of light

water reactor technology.

I.

General

1. Organization charts, phone list, and list of system engineers

2. List of system numbers/designations and a list of system engineers assigned to those

systems.

3. Access to a hardcopy set of system prints (P&IDs) and operator training manuals for the

team room. These will be returned at the end of the inspection.

4. Final Safety Analysis Report (FSAR), Technical Specifications (TS), and Technical

Requirements Manual (TRM) including the bases. Please provide electronically, with

one consolidated file for each of the FSAR, TS, and TRM.

5. Copy of the Quality Assurance Manual and Quality Assurance Topical Report.

6. A schedule of the date/time/location of meetings associated with implementation of the

correction action program such as Plan-of-the-Day, Station Ownership Committee

(SOC), Management Review Committee (MRC), etc.

REQUEST FOR INFORMATION

BIENNIAL PROBLEM IDENTIFICATION AND RESOLUTION

2

7. PRA risk-ranking of systems, including a chart with highest risk systems/components.

II.

Corrective Actions

1. Copy of procedures related to the corrective action program, including issue

identification, cause evaluations, corrective actions, trending, self-assessments, audits,

operability determinations, work management, operating experience, etc.

2. List of all corrective action program deficiency reports (IRs, ARs, etc.) initiated after

March 5, 2020 (last PI&R inspection) - in electronic spreadsheet format - include the

following (as applicable): system number/designation, date initiated, significance level,

status (open or closed), title/short description, department, date closed or due, and if

possible, the number of due date extensions.

3. Separate list of all corrective action program documents (IRs, ARs, etc.) initiated before

March 5, 2020 (last PI&R inspection) that remain open - in electronic spreadsheet

format - include the following (as applicable): system number/designation, date initiated,

significance level, status (open or closed), title/short description, department, date

closed or due, and if possible, the number of due date extensions.

4. List of all root cause evaluations (RCE), apparent cause evaluations (ACE), common

cause evaluations (CCE), and work group evaluations (WGE), performed after March 5,

2020 (last PI&R inspection) - include number, title, eval type, and date completed.

5. Matrix of the total number of condition report IRs generated annually and monthly for all

of 2020 and 2021, and to date for 2022 by department.

6. For all notice of violations (NOVs), non-cited violations (NCVs), and findings (FIN) issued

since March 5, 2020 (last PI&R inspection) - provide copies of the associated IRs

including all supporting information such as closeout documentation.

7. For all licensee event reports (LERs) issued since March 5, 2020 (last PI&R inspection)

- provide copies of the associated IRs including all supporting information such as

closeout documentation.

8. List of open temporary modifications, operability determinations, control room

deficiencies and operator workarounds\\challenges, and adverse condition monitoring

plans - in electronic spreadsheet format - include tracking no., system id., title/short

description, date initiated, and date corrective action(s) due / work order(s) scheduled.

9. List of rework and repeat maintenance items, and a list of maintenance performance

metrics including the backlog of corrective and elective maintenance issues - include

tracking no., unit/system id, work order no., title/short description, date initiated, date

corrective action(s) due / work order(s) scheduled, and department.

10. Copies of the system health reports for all (a)(1) systems and all systems pending

maintenance rule expert panel review for (a)(1) status determination.

11. List of all maintenance rule systems, include risk significance of system (high or low) and

whether the system is considered an (a)(1) or (a)(2). The list should indicate the trend in

overall system performance since the last PI&R inspection. For all (a)(1) systems,

please include a copy of the Action Plan and expert panel minutes.

III.

Operating Experience

1. List of operating experience reviews, including Part 21s and NRC generic

communications (i.e. Information Notices, Generic Letters, Bulletins) initiated since the

REQUEST FOR INFORMATION

BIENNIAL PROBLEM IDENTIFICATION AND RESOLUTION

3

last PI&R inspection. Provide tracking number, title/short description, date initiated, date

due or closer, significance level, evaluation class/type, status, department, and, if

possible, the number of due date extensions.

2. List of industry operating experience issues (NSSS vendor reports, EPRI Reports, and

OPEX reports from other facilities) entered into the corrective action program for review

since the last PI&R Inspection. Provide tracking number, title/short description, date

initiated, date due or closer, significance level, evaluation class/type, status, department,

and, if possible, the number of due date extensions.

3. Provide list of correction action program tracking items generated as a result of issues

identified during the OE reviews and assessment. Provide tracking number, title/short

description, date initiated, date due or closer, significance level, evaluation class/type,

status, department, and, if possible, the number of due date extensions.

IV.

Audits and Assessments

1. Copy of all QA reviews (audits, assessments, etc.) and self-assessments of the

corrective action program performed since the last PI&R inspection.

2. List of all QA reviews, self-assessments and safety culture reviews since last PI&R

inspection.

3. Copy of the corrective action program trend reports and performance indicators used by

management since the last PI&R inspection.

4. A list of IRs generated as a result of identified trends (either by station or department)

initiated since the last PI&R inspection. Provide IR number, title, and open/closed

status.

5. List of reports or specific issues identified by safety review committees (such as PORC,

NSRB, etc.) or other management oversight mechanisms since the last PI&R inspection.

Indicate whether these items are being tracked in the corrective action program or other

means.

6. Most recent PI&R functional area self-assessment (FASA) that was performed in

preparation for the upcoming PI&R inspection.

7. Hard-copy of last completed INPO evaluation and assistance report. (Will be reviewed

onsite to maintain confidentiality)

V.

Safety Conscious Work Environment and ECP

1. Procedures related to the Employee Concerns Program (ECP).

2. Procedures related to the Safety Conscious Work Environment and the stations

management of related issues.

3. Access to a list of all ECP cases and contacts initiated since the last PI&R inspection.

Include a list of IRs generated as a result of these reviews. (Will be reviewed onsite to

maintain confidentiality)

4. A copy of all safety culture reviews (audits, assessments, surveys, trend review, etc.)

initiated since the last PI&R inspection. Include a list of any NOTFs generated as a