| | number = ML17082A311 | | | number = ML17082A311 |
| | issue date = 04/11/2017 | | | issue date = 04/11/2017 |
| | title = Summary of Clarification Call with Entergy Regarding Follow-Up Rais on ISG-2012-02 | | | title = Summary of Clarification Call with Entergy Regarding Follow-Up RAIs on ISG-2012-02 |
| | author name = Burton W F | | | author name = Burton W |
| | author affiliation = NRC/NRR/DLR/RSRG | | | author affiliation = NRC/NRR/DLR/RSRG |
| | addressee name = | | | addressee name = |
Line 9: |
Line 9: |
| | docket = 05000247, 05000286 | | | docket = 05000247, 05000286 |
| | license number = | | | license number = |
| | contact person = Burton W F, 415-6332 | | | contact person = Burton W, 415-6332 |
| | case reference number = CAC MD5407, CAC MD5408 | | | case reference number = CAC MD5407, CAC MD5408 |
| | document type = Meeting Summary, Memoranda | | | document type = Meeting Summary, Memoranda |
| | page count = 5 | | | page count = 5 |
| | revision = 0 | | | project = CAC:MD5407, CAC:MD5408 |
| | | stage = RAI |
| }} | | }} |
| | |
| | =Text= |
| | {{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 April 11, 2017 LICENSEE: Entergy Nuclear Operations, Inc. (Entergy) |
| | FACILITY: Indian Point Unit Nos. 2 and 3 (IP2 and IP3) |
| | |
| | ==SUBJECT:== |
| | |
| | ==SUMMARY== |
| | OF TELEPHONE CONFERENCE CALL HELD ON MARCH 15, 2017, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY CONCERNING REQUESTS FOR ADDITIONAL INFORMATION PERTAINING TO THE INDIAN POINT UNIT NOS. 2 AND 3, LICENSE RENEWAL APPLICATION (CAC. NOS. MD5407 AND MD5408) |
| | The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of Entergy held a telephone conference call on March 15, 2017, to discuss and clarify the staffs requests for additional information (RAIs) concerning the IP2 and IP3 license renewal application. The telephone conference call was useful in clarifying the intent of the staffs RAIs. provides a listing of the participants and Enclosure 2 provides a summary of the key points discussed in the conference call. The RAIs can be found in the NRCs Agencywide Documents Access and Management System (ADAMS) under Accession No. ML17046A231. |
| | The applicant had an opportunity to comment on this summary. |
| | Sincerely, |
| | /RA/ |
| | William Burton, Senior Project Manager Project Management and Guidance Branch Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-247 and 50-286 Enclosures |
| | : 1. List of Participants |
| | : 2. Summary of RAIs cc w/encls: Listserv |
| | |
| | ML17082A311 OFFICE LA:DLR PM:RPGB:DLR BC:RPGB:DLR PM:RPGB:DLR NAME YEdmonds WBurton SBloom (w/comments) WBurton DATE 3/30/17 4/10/17 4/11/17 4/11/17 TELEPHONE CONFERENCE CALL INDIAN POINT UNIT NOS 2 AND 3 LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS MARCH 15, 2017 PARTICIPANTS AFFILIATIONS William Butch Burton U.S. Nuclear Regulatory Commission (NRC) |
| | James Gavula NRC William Holston NRC Sherwin Turk NRC Paul Bessette Entergy Nuclear Operations Inc. (Entergy) |
| | Richard Burroni Entergy Charles Caputo Entergy George Dahl Entergy Kevin Elliott Entergy David Lach Entergy Thomas Orlando Entergy Mark Spinelli Entergy Michael Troy Entergy David Wootten Entergy Garry Young Entergy Enclosure 1 |
| | |
| | REQUESTS FOR ADDITIONAL INFORMATION LICENSE RENEWAL APPLICATION MARCH 15, 2017 |
| | |
| | ===Background=== |
| | On July 25, 2016, the NRC staff issued RAI SET 2016-01 in NRC Agencywide Documents Access and Management System (ADAMS Accession No. ML16138A194), requesting additional information pertaining to License Renewal Interim Staff Guidance, LR-ISG-2012-02, Aging Management of Internal Surfaces, Fire Water Systems, Atmospheric Storage Tanks, and Corrosion Under Insulation. By letter dated December 2, 2016, Entergy responded to RAI SET 2016-01 (ADAMS Accession No. ML16350A005). Based on its review of the information contained in Entergys letter, the NRC staff issued follow-up RAIs by letter dated March 8, 2017 (ADAMS Accession No. ML17046A231). On March 15, 2017, NRC and Entergy staff held a clarification call to ensure that Entergy clearly understood what the staff was requesting in the follow-up RAIs. |
| | The follow-up RAIs are listed below and can be found in the ADAMS under Accession No. ML17046A231. |
| | RAIs RAI 3.0.3-9a RAI 3.0.3-9b RAI 3.0.3-10-1a RAI 3.0.3-10-2a RAI 3.0.3-10-6a RAI 3.0.3-10-7a RAI Discussion RAIs 3.0.3-9a and 3.0.3-9b Subsequent to the applicant stating that they had no follow-up questions on RAI 3.0.3-9a and 3.0.3-9b, the staff emphasized the following points: (a) the basis of RAI 3.0.3-9a is that the staff believes that for the leak that had available wall thickness measurements, it would appear that structural integrity requirements could have been met on the day of the leak; (b) the thrust of request (1) is confirmation of this assumption or obtaining enough information to demonstrate that structural integrity would not have been met; (c) if structural integrity would have been met, then structural integrity should not be used as an acceptance criteria for wall thickness measurements; and (d) staff does not have a concern with the number of periodic inspections, periodicity, and the number of augmented inspections if adverse results are encountered. |
| | The applicant indicated that the question is clear. |
| | RAI 3.0.3-10-1a The applicant asked to discuss the level of detail that the staff expected for the requested changes to the service water integrity program. The applicant had limited its previous responses to those that required the program document itself to be modified. The staff discussed the circumstances surrounding the relief request cited in the RAI to provide context Enclosure 2 |
| | |
| | for issues related to the potential need for improvements in nondestructive examination techniques or service life predictive methodology. The applicant stated that they had previously considered those types of changes as individual corrective actions as opposed to changes to the program, but with that clarification they understood the level of detail that the staff was expecting. The applicant did not ask the staff to make any changes to the RAI wording. |
| | RAI 3.0.3-10-2a The applicant stated, with the clarification discussed for the previous RAI regarding the level of detail, that they did not need any further discussion. The applicant did not ask the staff to make any changes to the RAI wording. |
| | RAI 3.0.3-10-6a The applicant stated that they did not need any further discussion for this RAI, and they did not ask the staff to make any changes to the RAI wording. |
| | RAI 3.0.3-10-7a This RAI was not discussed during the call. |
| | RAI Response Date The letter that contained these follow-up RAIs requested a response from Entergy no later than 30 days from the date of the letter (i.e., response by April 8, 2017). During the call, Entergy requested 60 days to respond to the follow-up RAIs. The basis for the request is due to the applicant having entered an outage at Indian Point 3 outage on 3/13/17. The Subject Matter Expert (SME) is focusing on outage tasks and is working night shift, focusing on service water piping inspections (Visual and non-destructive examination (NDE)), service water heat exchanger inspections, including Containment Fan Cooler Units (FCU), eddy current inspections of Balance of Plant systems, structures, and components (SSCs) & FCUs, Main Condenser inspections, and engineering field support. The SME is needed to participate in both the outage and RAI response preparation and review. He has the detailed knowledge of the involved systems and the data to ensure the response is of high quality and validated. |
| | The Director of the Division of License Renewal reviewed and approved Entergys request for a 60-day response. |
| | Commitment Table By letter dated January 17, 2017 (ADAMS Accession No. ML17023A209), Entergy submitted an update to the list of commitments associated with the Indian Point license renewal review. The staff discussed the list with Entergy to ensure that the implementation dates were still appropriate in light of the recent agreement to shorten the period of extended operation for the units. All agreed that no change to the implementation dates was needed at this time.}} |
Letter Sequence RAI |
---|
|
Initiation
- Request, Request, Request
- Acceptance, Acceptance, Acceptance, Acceptance
- Supplement, Supplement, Supplement, Supplement, Supplement, Supplement
Results
Other: ML15327A213, ML16133A459, ML16133A499, ML17101A697, ML17207A165, ML17256A286, ML18212A032, ML18212A185, NL-16-138, Amendment 18 to License Renewal Application, NL-17-005, Actions Concerning License Renewal Commitments 41 and 42 in Response to LR-ISG-2016-01, Changes to Aging Management Guidance for Various Steam Generator Components., NL-17-019, Amendment to License Renewal Application - Reflecting Shortened License Renewal Terms, NL-17-157, Amendment 19 to License Renewal Application (LRA)
|
MONTHYEARML15344A4362015-12-10010 December 2015 Lr Hearing - (External_Sender) Draft Audit Plan Edits Project stage: Request ML15327A2132015-12-21021 December 2015 Plan for the Regulatory Audit of the Service Water Integrity and Fire Water System Aging Management Programs Pertaining to the Indian Point Nuclear Generating Unit Nos. 2 and 3 LRA Project stage: Other ML15351A2032015-12-30030 December 2015 Summary of Conference Call Held on December 9, 2015, Between the NRC and Entergy Nuclear Operations, Inc. Concerning the Draft Audit Plan for the Service Water Integrity and Fire Water System Aging Management Programs Project stage: Draft Other ML16133A4592016-06-15015 June 2016 Service Water and Fire Water Systems Aging Management Programs Audit Report for the Indian Point Nuclear Generating Unit Nos. 2 and 3 License Renewal Application Project stage: Other ML16133A4992016-06-21021 June 2016 Summary of Telephone Conference Call Held Between NRC and Entergy Concerning the Indian Point LRA Safety Review Project stage: Other ML16138A1942016-07-25025 July 2016 Request for Additional Information for the Review of License Renewal Application, Set 2016-01 Project stage: RAI ML16208A2772016-07-26026 July 2016 Lr Hearing - RAI Set 2016-01 Project stage: Request NL-16-122, Reply to Request for Additional Information for the Review of License Renewal Application, Set 2016-01 (CAC Nos. MD5407 and MD5408)2016-12-0202 December 2016 Reply to Request for Additional Information for the Review of License Renewal Application, Set 2016-01 (CAC Nos. MD5407 and MD5408) Project stage: Response to RAI NL-16-138, Amendment 18 to License Renewal Application2016-12-15015 December 2016 Amendment 18 to License Renewal Application Project stage: Other NL-17-005, Actions Concerning License Renewal Commitments 41 and 42 in Response to LR-ISG-2016-01, Changes to Aging Management Guidance for Various Steam Generator Components.2017-01-17017 January 2017 Actions Concerning License Renewal Commitments 41 and 42 in Response to LR-ISG-2016-01, Changes to Aging Management Guidance for Various Steam Generator Components. Project stage: Other NL-17-019, Amendment to License Renewal Application - Reflecting Shortened License Renewal Terms2017-02-0808 February 2017 Amendment to License Renewal Application - Reflecting Shortened License Renewal Terms Project stage: Other ML17046A2312017-03-0808 March 2017 Request for Additional Information for the Review of the Indian Point License Renewal - Set 2017-01 Project stage: RAI ML17082A3112017-04-11011 April 2017 Summary of Clarification Call with Entergy Regarding Follow-Up RAIs on ISG-2012-02 Project stage: RAI ML17088A3272017-04-19019 April 2017 Requests for Additional Information for the Review of the Indian Point License Renewal Application RAI Set 2017-02 (CAC Nos. MD5407 and MD5408) Project stage: RAI ML17088A4052017-04-20020 April 2017 Requests for Additional Information for the Review of the Indian Point License Renewal Application RAI Set 2017-3 (CAC Nos. MD5407 and MD5408) Project stage: RAI ML17101A6972017-04-25025 April 2017 License Renewal Clarification Call on Baffle Bolt Rai'S Project stage: Other NL-17-052, Reply to Request for Additional Information for the Review of the License Renewal Application, Set 2017-012017-05-0808 May 2017 Reply to Request for Additional Information for the Review of the License Renewal Application, Set 2017-01 Project stage: Response to RAI NL-17-053, Reply to Request for Additional Information for the Review of the Indian Point License Renewal Application RAI Set 2017-03 (CAC Nos. MD5407 and MD5408)2017-05-18018 May 2017 Reply to Request for Additional Information for the Review of the Indian Point License Renewal Application RAI Set 2017-03 (CAC Nos. MD5407 and MD5408) Project stage: Response to RAI NL-17-060, Reply to Requests for Additional Information for the Review of the Indian Point License Renewal Application RAI Set 2017-02 (CAC Nos. MD5407 and MD5408)2017-05-19019 May 2017 Reply to Requests for Additional Information for the Review of the Indian Point License Renewal Application RAI Set 2017-02 (CAC Nos. MD5407 and MD5408) Project stage: Response to RAI ML17128A3352017-05-23023 May 2017 Summary of Telephone Conference Call Between the NRC and Entergy Concerning RAIs Pertaining to IP2 and IP3 Project stage: RAI NL-17-061, Reply to Requests for Additional Information for the Review of the License Renewal Application RAI Set 2017-042017-05-24024 May 2017 Reply to Requests for Additional Information for the Review of the License Renewal Application RAI Set 2017-04 Project stage: Response to RAI NL-17-069, Reply to Requests for Additional Information for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3, License Renewal Application RAI Set 2017-05 (CAC Nos. MD5407 and MD5408)2017-06-0808 June 2017 Reply to Requests for Additional Information for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3, License Renewal Application RAI Set 2017-05 (CAC Nos. MD5407 and MD5408) Project stage: Response to RAI NL-17-074, Supplemental Information Regarding Reply to Request for Additional Information Set 2017-01 for the Review of the License Renewal Application (LRA)2017-06-27027 June 2017 Supplemental Information Regarding Reply to Request for Additional Information Set 2017-01 for the Review of the License Renewal Application (LRA) Project stage: Response to RAI ML17170A2862017-06-27027 June 2017 RAI Set 2017-06 Project stage: RAI ML17160A1652017-06-27027 June 2017 Summary of Telephone Conference Call Held on May 31,2017, Between the NRC and Entergy Nuclear Operations Inc. Concerning Requests for Additional Information Pertaining to the Indian Point, License Renewal Application (TAC Nos. MD5407/MD5408 Project stage: RAI NL-17-084, Reply to Requests for Additional Information for the Review of the License Renewal Application. Re RAI Set 2017-062017-07-27027 July 2017 Reply to Requests for Additional Information for the Review of the License Renewal Application. Re RAI Set 2017-06 Project stage: Response to RAI NL-17-092, Amended Response to Request for Additional Information Question RAI 3.3.2-17-IP3-1 Re License Renewal Application RAI Set 2017-052017-07-27027 July 2017 Amended Response to Request for Additional Information Question RAI 3.3.2-17-IP3-1 Re License Renewal Application RAI Set 2017-05 Project stage: Response to RAI ML17207A1652017-09-0101 September 2017 License Renewal Audit Plan Regarding the Service Water Integrity Program Project stage: Other ML17250A2442017-09-20020 September 2017 Audit Report for IP Swi - Aug 2017 Project stage: Acceptance Review ML17191A4562017-09-20020 September 2017 06/08/2017 Telecon Summary Related to Indian Point License Renewal RAIs Associated with ISG-2016-01 Project stage: RAI ML17180A5032017-09-21021 September 2017 04/19/2017 Summary of Teleconference with Entergy Nuclear Operations, Inc., Concerning Request for Additional Information Pertaining to the Indian Point Unit Nos. 2 and 3 License Renewal Application Project stage: RAI ML17256A2862017-09-25025 September 2017 Summary of Telephone Call on 09/06/17, Between NRC and Entergy Concerning Next Steps from the Site Audit on 08/1-3/17 Project stage: Other NL-17-127, Supplemental Information Regarding the Service Water Integrity Aging Management Program for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3 License Renewal Application (LRA) (CAC Nos. MD5407 and MD5408)2017-11-0808 November 2017 Supplemental Information Regarding the Service Water Integrity Aging Management Program for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3 License Renewal Application (LRA) (CAC Nos. MD5407 and MD5408) Project stage: Supplement NL-17-155, Re-Submittal of Supplemental Information Regarding the Service Water Integrity Aging Management Program for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3 License Renewal Application (LRA)2017-12-14014 December 2017 Re-Submittal of Supplemental Information Regarding the Service Water Integrity Aging Management Program for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3 License Renewal Application (LRA) Project stage: Supplement NL-17-157, Amendment 19 to License Renewal Application (LRA)2017-12-14014 December 2017 Amendment 19 to License Renewal Application (LRA) Project stage: Other NL-17-161, Supplemental Information Regarding the Service Water Integrity Aging Management Program for the Review of the Indian Point Nuclear Generating Units 2 and 3 License Renewal Application (LRA) (CAC Nos. MD5407 and MD5408)2017-12-21021 December 2017 Supplemental Information Regarding the Service Water Integrity Aging Management Program for the Review of the Indian Point Nuclear Generating Units 2 and 3 License Renewal Application (LRA) (CAC Nos. MD5407 and MD5408) Project stage: Supplement NL-18-010, Supplemental Information Regarding the Review of the License Renewal Application2018-02-26026 February 2018 Supplemental Information Regarding the Review of the License Renewal Application Project stage: Supplement ML18107A7592018-04-30030 April 2018 NUREG-1437, Suppl. 38, Vol. 5, Generic Environmental Impact Statement for License Renewal of Nuclear Plants Supplement 38 Regarding Indian Port Nuclear Generating Unit Nos. 2 and 3 Final. Project stage: Acceptance Review NL-18-030, Supplemental Information Associated with Amendment 19 to the License Renewal Application (LRA)2018-05-0808 May 2018 Supplemental Information Associated with Amendment 19 to the License Renewal Application (LRA) Project stage: Supplement NL-18-044, Supplemental Information Regarding the Review of the License Renewal Application2018-06-25025 June 2018 Supplemental Information Regarding the Review of the License Renewal Application Project stage: Supplement ML18200A3332018-08-0101 August 2018 NUREG-1930, Supp 3, Safety Evaluation Report Related to the License Renewal of Indian Point Nuclear Generating Plant, Units 2 and 3. Project stage: Approval ML18211A4842018-08-0707 August 2018 to NUREG-1930, Safety Evaluation Report Related to the License Renewal of Indian Point Nuclear Generating Plant, Units 2 and 3. Project stage: Approval ML18211A5842018-09-17017 September 2018 Issuance of Renewed Facility Operating License Nos. DPR 26 and DPR-64 for Indian Point Nuclear Generating Unit Nos. 2 and 3 (CAC Nos. MD5407 and MD5408) Project stage: Request ML18212A1882018-09-17017 September 2018 Renewed License Appendix C Project stage: Acceptance Review ML18212A1852018-09-17017 September 2018 Renewed Facility Operating License DPR-26, Technical Specifications, Appendix B Project stage: Other ML18212A1812018-09-17017 September 2018 Renewed Facility Operating License DPR-26, Technical Specifications, Appendix a Project stage: Acceptance Review ML18212A0322018-09-17017 September 2018 Records of Decision for the Indian Point Renewed Licenses Project stage: Other ML18211A5962018-09-17017 September 2018 Transmittal Letter - Issuance of Renewed Facility Operating License Nos. DPR-26 and DPR-64 for Indian Point Nuclear Generating Unit Nos. 2 and 3 (CAC Nos. MD5407 and MD5408) Project stage: Approval ML18211A5782018-09-17017 September 2018 Federal Register Notice - Announcing the Issuance of the Indian Point Renewed Licenses Project stage: Approval ML18213A1142018-09-17017 September 2018 Renewed Facility Operating License Project stage: Other 2017-04-25
[Table View] |
|
---|
Category:Meeting Summary
MONTHYEARML22309A0062022-12-12012 December 2022 Public Non-Sensitive Meeting Summary on Clarification Call with Holtec Regarding Request for Additional Information for Indian Point Unit 2 Master Decommissioning Trust Agreement as Per Indian Point Nuclear Generating Facility Unit 1 and 2 ML21342A1402021-12-0909 December 2021 Summary of Public Meeting in Tarrytown, Ny, to Discuss Indian Point Units 1, 2, and 3 (IPEC) Post-shutdown Decommissioning Activities Report ML21055A9122021-02-24024 February 2021 (E-mail Dated 2/24/2021) Summary of Feb 8, 2021, Pre-submittal Meeting for Relief Request No. IP3-ISI-RR-16, Code Case N-513-4 Periodic Inspection Frequency Extension ML20321A0002020-11-17017 November 2020 Summary of 9/30/20 Pre-Submittal Meeting with Entergy to Discuss Proposed One-Time Exemption Request - Biennial Emergency Preparedness Onsite Evaluated Exercise Requirements ML20289A7322020-10-15015 October 2020 2020 Annual Assessment Meeting for Indian Point - Meeting Summary ML20083F5962020-03-23023 March 2020 Summary of Teleconference with the National Marine Fisheries Service for Indian Point Biological Opinion ML20059P1292020-03-0303 March 2020 Summary of Partially Closed Pre-submittal Public Meeting with Entergy Nuclear Operations, Inc. to Discuss the Proposed License Amendment Request to Replace the Indian Point Unit No. 3 Crane with a New Holtec High-Lift Crane (EPID L:2019-LRM ML19330F5182019-11-29029 November 2019 Summary of Public Meeting Between the NRC and Entergy Regarding Pre-Submittal of a License Transfer Application to Holtec International for Indian Point Energy Center ML19319A0242019-10-0202 October 2019 NEIMA Meeting - Courtney Williams Comments ML19319A0282019-10-0202 October 2019 NEIMA Meeting - Marilyn Elie Comments ML19319A0272019-10-0202 October 2019 NEIMA Meeting - Linda Puglisi Comments ML19319A0252019-10-0202 October 2019 NEIMA Meeting - Jenean Eichenholtz Comments ML19198A2392019-07-17017 July 2019 Annual Assessment Meeting for Indian Point Energy Center - Meeting Summary ML18200A2722018-07-19019 July 2018 Summary of Annual Assessment Meeting for Indian Point Energy Center ML18131A0572018-05-11011 May 2018 Summary of 04/12/2018 Meeting with the State of New York Regarding the Indian Point Generating Unit No. 2 Reactor Pressure Vessel Head Penetration Alternative Weld Repair ML18117A3162018-04-30030 April 2018 Summary of 04/03/2018 Meeting with Entergy on Planned Submittal of Propose Alternative for Reactor Pressure Vessel Head Nozzle Weld Repair ML18107A4972018-04-27027 April 2018 April 10, 2017, Summary of Public Meeting with Entergy Nuclear Operations, Inc. Regarding Upcoming License Amendment Request to Add Setpoint Verification Requirement to Technical Specification Surveillance Requirements ML18099A0712018-04-16016 April 2018 March 20, 2018, Summary of Meeting with the Nuclear Energy Institute and Other Industry Representatives Regarding the Surveillance Frequency Control Program ML18002A2562018-01-30030 January 2018 11/30/2017 and 12/19/2017 Summary Telephone Conference Calls with Entergy Nuclear Operations, Inc., Concerning Request for Additional Information Pertaining to the Indian Point License Renewal Application ML17256A2862017-09-25025 September 2017 Summary of Telephone Call on 09/06/17, Between NRC and Entergy Concerning Next Steps from the Site Audit on 08/1-3/17 ML17180A5032017-09-21021 September 2017 04/19/2017 Summary of Teleconference with Entergy Nuclear Operations, Inc., Concerning Request for Additional Information Pertaining to the Indian Point Unit Nos. 2 and 3 License Renewal Application ML17237A2132017-08-25025 August 2017 Memo E-mail to File -Summary of July 26, 2017, Meeting with Entergy to Discuss Proposed License Amendment Request, New Criticality Safety Analysis ML17173A7672017-07-28028 July 2017 Summary of 6/20/2017 Meeting with Entergy to Discuss Plan for Decommissioning Licensing Actions of Palisades, Pilgrim, Indian Point, Units 2 and 3, and Vermont Yankee ML17160A1652017-06-27027 June 2017 Summary of Telephone Conference Call Held on May 31,2017, Between the NRC and Entergy Nuclear Operations Inc. Concerning Requests for Additional Information Pertaining to the Indian Point, License Renewal Application (TAC Nos. MD5407/MD5408 ML17172A1972017-06-20020 June 2017 Summary of Annual Assessment Meeting for Indian Point Units 2 and 3 ML17157B5422017-06-20020 June 2017 Conference Call on 2nd Round RAIs - Final ML17082A3112017-04-11011 April 2017 Summary of Clarification Call with Entergy Regarding Follow-Up RAIs on ISG-2012-02 ML16281A2162016-10-25025 October 2016 10/04/2016,Summary of Public Meeting with Entergy Nuclear Operations, Inc. Regarding Proposed Changes to the Service Water Integrity Program for the Indian Point Nuclear Generating, Units 2 and 3 (IP2 and IP3) License Renewal Application (LRA) ML16209A3712016-08-17017 August 2016 July 21, 2016, Summary of Conference Call Held Between NRC and Entergy Nuclear Operations, Inc. Concerning the Draft RAI for the Review of the Indian Point, Units 2 & 3, License Renewal Application, Set 2016-01 (TAC Nos. MD5407 & MD5408) ML16188A0202016-07-0505 July 2016 Summary of Annual Assessment Meeting for Indian Point Units 2 and 3 ML16133A4992016-06-21021 June 2016 Summary of Telephone Conference Call Held Between NRC and Entergy Concerning the Indian Point LRA Safety Review ML16035A4802016-02-12012 February 2016 Jsc Meeting Summary Attachment ML15351A2032015-12-30030 December 2015 Summary of Conference Call Held on December 9, 2015, Between the NRC and Entergy Nuclear Operations, Inc. Concerning the Draft Audit Plan for the Service Water Integrity and Fire Water System Aging Management Programs ML15190A2912015-07-22022 July 2015 070115, Summary of Telephone Conference Call Held Between NRC and Entergy Concerning the RAIs Pertaining to the Indian Point LRA Safety Review ML15152A0762015-05-29029 May 2015 Summary of Annual Assessment Meeting for Indian Point Units 2 and 3 on 5/20/2015 ML15120A6442015-05-0606 May 2015 Summary of Telephone Conference Call Held Between NRC and Entergy Concerning the RAIs Pertaining to the Indian Point LRA Safety Review ML15107A1752015-04-28028 April 2015 041615, Summary of Telephone Conference Call Held Between NRC and Entergy Concerning the RAIs Pertaining to the Indian Point LRA Environmental Review ML15093A5052015-04-14014 April 2015 Summary of Telephone Conference Call Held Between NRC and Entergy Concerning the Indian Point LRA Environmental Review ML15051A5022015-03-10010 March 2015 Summary of Telephone Conference Call Held Between NRC and Entergy Concerning the RAIs Pertaining to the Indian Point LRA Environmental Review ML15022A1602015-02-11011 February 2015 and 01/13/15, Summary of Telephone Conference Call Held Between NRC and Entergy Concerning the RAIs Pertaining to the Indian Point LRA Environmental Review ML14197A5832014-09-18018 September 2014 Summary of the June 19, 2014, Category 1 Public Meeting with Entergy to Discuss Seismic Hazard Reevaluations Associated with Implementation of Japan Lessons-Learned Near-Tear Task Force Recommendation 2.1 ML14260A4312014-09-17017 September 2014 Revised Summary of Annual Assessment Meeting for Indian Point Energy Center on 6/4/2014 ML14238A7262014-09-10010 September 2014 Summary of Conference Call Held on July 30, 2014, Between the U.S. Nuclear Regulatory Commission and Entergy Nuclear Operations Inc., Regarding a Draft Request for Additional Information on Removal of Certain Aging Management Review Items ML14219A6742014-08-14014 August 2014 July 15, 2014 Summary of Telephone Conference Call Held Between U.S. Nuclear Regulatory Commission and Entergy Nuclear Operations, Inc., Concerning the Environmental Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3, License R ML14206B1282014-08-0101 August 2014 June 19, 2014 & July 16, 2014 Summary of Conference Calls Held Between the U.S. Nuclear Regulatory Commission and Entergy Nuclear Operations, Inc., Regarding Entergy Response to a Request for Additional Information ML14178A8682014-06-25025 June 2014 Summary of Annual Assessment Meeting for Indian Point Energy Center on 6/4/2014 ML14136A0052014-05-27027 May 2014 Summary of Phone Call Between New York State Department of State and U.S. Nuclear Regulatory Commission on May 7, 2014, Regarding the Coastal Zone Management Act Consistency Review ML14105A3542014-04-24024 April 2014 Summary of Conference Call Held on March 26, 2014, Between the U.S. Nuclear Regulatory Commission and Entergy Nuclear Operations, Inc., Concerning a Draft Request for Additional Information on the Reactor Vessel Internals Program ML14078A3992014-03-21021 March 2014 Summary of Conference Call Held on February 20, 2014, Between the U.S. Nuclear Regulatory Commission and Entergy Nuclear Operations, Inc., Concerning a Draft Request for Additional Information on LR-ISG-2012-02 and Draft LR-ISG-2013-01 ML13256A0862013-09-24024 September 2013 Summary of Meeting with Entergy Nuclear Operations, Inc. and Netco on Indian Point Unit 2 Spent Fuel Pool Management 2022-12-12
[Table view] Category:Memoranda
MONTHYEARML23356A0212023-12-0101 December 2023 American Nuclear Insurers, Secondary Financial Protection (SFP) Program ML23103A2742023-04-25025 April 2023 04-25-23 - Letter to the Honorable Charles Schumer, Et Al., Responds to Concerns Regarding Holtec Decommissioning International'S Plans to Release Effluents at the Indian Point Energy Center ML21232A2342021-08-20020 August 2021 Memo - Revised Transcript for Public Meeting Held on July 29, 2021, in Tarrytown, Ny, Re IP Energy Center Post-Shutdown Decommissioning Activities Report ML21056A0772021-04-0707 April 2021 Memo to File: Final Environmental Assessment and Finding of No Significant Impact for Initial and Updated Decommissioning Funding Plans for Indian Point ISFSI (Docket: 72-51) ML20104A3882020-04-13013 April 2020 Tasking in Response to the Concerns Pertaining to Gas Transmission Lines at the Indian Point Nuclear Power Plant Follow Up Activities Agency Level ML20104A7232020-04-13013 April 2020 Tasking in Response to the Concerns Pertaining to Gas Transmission Lines at the Indian Point Nuclear Power Plant; Follow Up Activities; Office Level ML20099F7752020-04-0909 April 2020 Report Transmittal Memo to the Commissioners, from: Margaret M. Doane ML20058E3542020-02-27027 February 2020 Tasking Memo to Dskeen Re Concerns Identifed in Report Pertaining to Gas Transmission Lines ML20056F0952020-02-13013 February 2020 Concerns Pertaining to Gas Transmission Lines at the Indian Point Nuclear Power Plant ML18046B4412018-02-23023 February 2018 Review of Updated Final Safety Analysis Report, Revision 7 ML17271A0532017-09-29029 September 2017 2017 Summary of Annual Decommissioning Funding Status Reports for Reactors in Decommissioning ML17180A5032017-09-21021 September 2017 04/19/2017 Summary of Teleconference with Entergy Nuclear Operations, Inc., Concerning Request for Additional Information Pertaining to the Indian Point Unit Nos. 2 and 3 License Renewal Application ML17157B5422017-06-20020 June 2017 Conference Call on 2nd Round RAIs - Final ML17128A3352017-05-23023 May 2017 Summary of Telephone Conference Call Between the NRC and Entergy Concerning RAIs Pertaining to IP2 and IP3 ML17060A6602017-04-12012 April 2017 Potentially Cost-Beneficial SAMAs ML17082A3112017-04-11011 April 2017 Summary of Clarification Call with Entergy Regarding Follow-Up RAIs on ISG-2012-02 ML16336A4992017-01-18018 January 2017 Notice of Significant Licensing Action ML17052A3002017-01-11011 January 2017 Security Exclusion Zone Acoustic Tag Detection Study, 9 November 2016 ML17052A3092017-01-11011 January 2017 Atlantic Sturgeon Distribution Memo ML16088A2042016-03-28028 March 2016 Memo T Bowers from s Ruffin, Technical Assistance Requests - Review 2015 Tri-Annual Decommissioning Funding Plans for Multiple Independent Spent Fuel Storage Installations W/ Encl 2 (Template) ML16088A2052016-03-28028 March 2016 Enclosure 1 - (72.30 DFP Reviews to Be Completed 2015) - Memo T Bowers from s Ruffin, Technial Assistance Requests - Review 2015 Tri-Annual Decommissioning Funding Plans for Multiple Independent Spent Fuel Storage Installations ML15190A2912015-07-22022 July 2015 070115, Summary of Telephone Conference Call Held Between NRC and Entergy Concerning the RAIs Pertaining to the Indian Point LRA Safety Review ML15139A1952015-05-19019 May 2015 Special Inspection Team Charter - Indian Point Nuclear Generating Unit 3 - Water Accumulation in Safety-Related Switchgear Room Following Deluge of Main Transformer Fire ML15107A1752015-04-28028 April 2015 041615, Summary of Telephone Conference Call Held Between NRC and Entergy Concerning the RAIs Pertaining to the Indian Point LRA Environmental Review ML15091A0972015-04-0101 April 2015 Figures from Indian Point Quarter 3 2014 Groundwater Monitoring Report - Part 4 ML14344A9652014-12-18018 December 2014 Summary of Telephone Conference Call Held Between NRC and Entergy Concerning the RAIs Pertaining to the Indian Point LRA Environmental Review ML14269A1972014-10-0303 October 2014 LTR-14-0463-1 - Proposed Comments to the Federal Energy Regulatory Commission'S Draft Environmental Impact Statement Algonquin Incremental Market Project (Docket No. CP14-96-000) ML13256A0432013-09-10010 September 2013 Request for Additional Information to Entergy Nuclear Northeast, Indian Point Units 2 and 3, Regarding NTTF Recommendation 9.3 Phase 1 Staffing Assessments Submittal ML13218A0862013-08-0808 August 2013 Notice of Forthcoming Meeting with Entergy Nuclear Operations, Inc. and Netco to Discuss the Goals and Objectives of the Long-Term Spent Fuel Pool Improvement Program for Indian Point Unit 2 and 3 ML13102A1242013-04-15015 April 2013 Summary of April 11, 2013, Telephone Conference Call Between NRC and Entergy Entry of Indian Point Nuclear Generating Unit No. 2 Into the Period of Timely Renewal ML12361A1552012-12-26026 December 2012 Summary of Entergy Drop-In on December 19, 2012 ML12296A9292012-10-23023 October 2012 Memo Draft Request for Additional Information for Indian Point Units 1 and 2 Memo ML12215A2482012-09-17017 September 2012 Summary of Conference Call Held on June 4, 2012, Between the U.S. Nuclear Regulatory Commission and Entergy Nuclear Operations, Inc., Concerning the Reactor Vessel Internals Program at Indian Point Nuclear Generating Station, Units 2 and 3 ML12213A0612012-08-0101 August 2012 8/16/12 Forthcoming Conference Call with NextEra Energy and Florida Power & Light Concerning Generic Letter 2004-02 and Request for NRC Staff Review of Draft Proposed Guideline for Strainer Fiber Bypass Test Protocol ML13196A2202012-06-0606 June 2012 Memo from B. Balsam, NRR and D. Logan, NRR to J. Susco, NRR on Summary of Section 7 Consultation Activities Related to the National Marine Fisheries Service'S Final Rule to List the Atlantic Sturgeon ML12137A0602012-05-29029 May 2012 Nuclear Regulatory Commission'S Analysis of Entergy Nuclear Operations, Inc. Decommissioning Funding Status Report for Indian Point Nuclear Generating Station, Units 1, 2 & 3; and Pilgrim Nuclear Power Station ML1122701452011-08-30030 August 2011 Summary of Conference Call Between NRC and Entergy Nuclear Operations, Regarding Non-EQ Inaccessible Medium-Voltage Cable Program for Indian Point Units 2 & 3 ML11201A3062011-07-29029 July 2011 Summary of Telephone Conference Calls Held on June 20, June 22, and June 29, 2011, Regarding the Ongoing Endangered Species Act Consultation for the Proposed Indian Point Nuclear Generating Unit Nos. 2 and 3 License Renewal NL-11-093, Clean Water Act Section 401 Water Quality Certification Waiver2011-07-29029 July 2011 Clean Water Act Section 401 Water Quality Certification Waiver ML1118703442011-07-0606 July 2011 Memorandum and Order (Ruling on Pending Motions for Leave to File New and Amended Contentions) ML1115704052011-06-0606 June 2011 Notice of Meeting with Entergy Operations, Inc., to Discuss Implementation of Quality Oversight and Verification Programs at Entergy Sites Including Actions Being Taken to Enhance Effectiveness ML11102A0062011-05-0909 May 2011 01/12/11 Summary of Telephone Conference Call Between Nuclear Regulatory Commission and Entergy Nuclear Operations, Inc., Concerning the Final SEIS for the Proposed License Renewal of Indian Point, Units 2 and 3 ML1110909492011-04-25025 April 2011 Notice of Meeting G20110221/EDATS:OEDO-2011-0226- with the State of New York Attorney General'S Office (the Petitioner) Requesting Action Under 10 CFR 2.206 Regarding Fire Protection at Indian Point ML1110909052011-04-22022 April 2011 NRC and Entergy Nuclear Operations, Inc. Held a Category 1 Public Meeting on April 18, 2011, to Discuss the Shortnose Sturgeon ML1110103962011-04-11011 April 2011 Notice of Forthcoming Meeting with Entergy Nuclear Operations, Inc. to Discuss the License Amendment Requests to Permit the Transfer of Spent Fuel from the Indian Point Unit 3 Spent Fuel Pool to the Unit 2 Spent Fuel Pool ML1109803932011-04-0808 April 2011 Forthcoming Meeting with NRC and Entergy Operations, Inc ML11223A0412011-03-23023 March 2011 Memorandum from J. Boska, NRR to T. Quay, NRR on Review of 10 CFR 2.206 Petition on Gas Pipelines Near the Indian Point Reactors ML1107504052011-03-21021 March 2011 Notice of Meeting with Entergy Operations, Inc., to Discuss Fleetwide Submittal for Proposed Technical Specification and Quality Assurance Program Manual Changes Related to Unit Staff Qualification Requirements ML1029106182010-10-14014 October 2010 Documentation of Telephone Conversation Between Mr. David Lochbaum Regarding Follow-Up Questions Related to NRC Letter Dated July 28, 2010 (ML102040807) ML0931701682009-11-17017 November 2009 Summary of Teleconference Call Held on 11/3/09 Between the U.S. NRC and Entergy Nuclear Operations, Inc., Concerning Meteorological Data Used for the Severe Accident Mitigation Alternative Analyses 2023-04-25
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 April 11, 2017 LICENSEE: Entergy Nuclear Operations, Inc. (Entergy)
FACILITY: Indian Point Unit Nos. 2 and 3 (IP2 and IP3)
SUBJECT:
SUMMARY
OF TELEPHONE CONFERENCE CALL HELD ON MARCH 15, 2017, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY CONCERNING REQUESTS FOR ADDITIONAL INFORMATION PERTAINING TO THE INDIAN POINT UNIT NOS. 2 AND 3, LICENSE RENEWAL APPLICATION (CAC. NOS. MD5407 AND MD5408)
The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of Entergy held a telephone conference call on March 15, 2017, to discuss and clarify the staffs requests for additional information (RAIs) concerning the IP2 and IP3 license renewal application. The telephone conference call was useful in clarifying the intent of the staffs RAIs. provides a listing of the participants and Enclosure 2 provides a summary of the key points discussed in the conference call. The RAIs can be found in the NRCs Agencywide Documents Access and Management System (ADAMS) under Accession No. ML17046A231.
The applicant had an opportunity to comment on this summary.
Sincerely,
/RA/
William Burton, Senior Project Manager Project Management and Guidance Branch Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-247 and 50-286 Enclosures
- 1. List of Participants
- 2. Summary of RAIs cc w/encls: Listserv
ML17082A311 OFFICE LA:DLR PM:RPGB:DLR BC:RPGB:DLR PM:RPGB:DLR NAME YEdmonds WBurton SBloom (w/comments) WBurton DATE 3/30/17 4/10/17 4/11/17 4/11/17 TELEPHONE CONFERENCE CALL INDIAN POINT UNIT NOS 2 AND 3 LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS MARCH 15, 2017 PARTICIPANTS AFFILIATIONS William Butch Burton U.S. Nuclear Regulatory Commission (NRC)
James Gavula NRC William Holston NRC Sherwin Turk NRC Paul Bessette Entergy Nuclear Operations Inc. (Entergy)
Richard Burroni Entergy Charles Caputo Entergy George Dahl Entergy Kevin Elliott Entergy David Lach Entergy Thomas Orlando Entergy Mark Spinelli Entergy Michael Troy Entergy David Wootten Entergy Garry Young Entergy Enclosure 1
REQUESTS FOR ADDITIONAL INFORMATION LICENSE RENEWAL APPLICATION MARCH 15, 2017
Background
On July 25, 2016, the NRC staff issued RAI SET 2016-01 in NRC Agencywide Documents Access and Management System (ADAMS Accession No. ML16138A194), requesting additional information pertaining to License Renewal Interim Staff Guidance, LR-ISG-2012-02, Aging Management of Internal Surfaces, Fire Water Systems, Atmospheric Storage Tanks, and Corrosion Under Insulation. By letter dated December 2, 2016, Entergy responded to RAI SET 2016-01 (ADAMS Accession No. ML16350A005). Based on its review of the information contained in Entergys letter, the NRC staff issued follow-up RAIs by letter dated March 8, 2017 (ADAMS Accession No. ML17046A231). On March 15, 2017, NRC and Entergy staff held a clarification call to ensure that Entergy clearly understood what the staff was requesting in the follow-up RAIs.
The follow-up RAIs are listed below and can be found in the ADAMS under Accession No. ML17046A231.
RAIs RAI 3.0.3-9a RAI 3.0.3-9b RAI 3.0.3-10-1a RAI 3.0.3-10-2a RAI 3.0.3-10-6a RAI 3.0.3-10-7a RAI Discussion RAIs 3.0.3-9a and 3.0.3-9b Subsequent to the applicant stating that they had no follow-up questions on RAI 3.0.3-9a and 3.0.3-9b, the staff emphasized the following points: (a) the basis of RAI 3.0.3-9a is that the staff believes that for the leak that had available wall thickness measurements, it would appear that structural integrity requirements could have been met on the day of the leak; (b) the thrust of request (1) is confirmation of this assumption or obtaining enough information to demonstrate that structural integrity would not have been met; (c) if structural integrity would have been met, then structural integrity should not be used as an acceptance criteria for wall thickness measurements; and (d) staff does not have a concern with the number of periodic inspections, periodicity, and the number of augmented inspections if adverse results are encountered.
The applicant indicated that the question is clear.
RAI 3.0.3-10-1a The applicant asked to discuss the level of detail that the staff expected for the requested changes to the service water integrity program. The applicant had limited its previous responses to those that required the program document itself to be modified. The staff discussed the circumstances surrounding the relief request cited in the RAI to provide context Enclosure 2
for issues related to the potential need for improvements in nondestructive examination techniques or service life predictive methodology. The applicant stated that they had previously considered those types of changes as individual corrective actions as opposed to changes to the program, but with that clarification they understood the level of detail that the staff was expecting. The applicant did not ask the staff to make any changes to the RAI wording.
RAI 3.0.3-10-2a The applicant stated, with the clarification discussed for the previous RAI regarding the level of detail, that they did not need any further discussion. The applicant did not ask the staff to make any changes to the RAI wording.
RAI 3.0.3-10-6a The applicant stated that they did not need any further discussion for this RAI, and they did not ask the staff to make any changes to the RAI wording.
RAI 3.0.3-10-7a This RAI was not discussed during the call.
RAI Response Date The letter that contained these follow-up RAIs requested a response from Entergy no later than 30 days from the date of the letter (i.e., response by April 8, 2017). During the call, Entergy requested 60 days to respond to the follow-up RAIs. The basis for the request is due to the applicant having entered an outage at Indian Point 3 outage on 3/13/17. The Subject Matter Expert (SME) is focusing on outage tasks and is working night shift, focusing on service water piping inspections (Visual and non-destructive examination (NDE)), service water heat exchanger inspections, including Containment Fan Cooler Units (FCU), eddy current inspections of Balance of Plant systems, structures, and components (SSCs) & FCUs, Main Condenser inspections, and engineering field support. The SME is needed to participate in both the outage and RAI response preparation and review. He has the detailed knowledge of the involved systems and the data to ensure the response is of high quality and validated.
The Director of the Division of License Renewal reviewed and approved Entergys request for a 60-day response.
Commitment Table By letter dated January 17, 2017 (ADAMS Accession No. ML17023A209), Entergy submitted an update to the list of commitments associated with the Indian Point license renewal review. The staff discussed the list with Entergy to ensure that the implementation dates were still appropriate in light of the recent agreement to shorten the period of extended operation for the units. All agreed that no change to the implementation dates was needed at this time.